E. M. Hanna; 7/31/03 DXI Management Consulting 1 Resource Leveling.
Resource Leveling Technique
-
Upload
yogacruise -
Category
Documents
-
view
219 -
download
0
Transcript of Resource Leveling Technique
-
7/28/2019 Resource Leveling Technique
1/11
Resource leveling technique, how often you are using it and is it common practice?
9 days ago
Like CommentFollow Flag More
Ahmad Shihadeh, Osama Abdelmalik Arafat, PMP Certifeid, Primavera P6 like this
37 comments Jump to most recent comments
Follow Jan
Jan van den Berg Yes, i use resource leveling technique regularly and i consider this common
practice.
Regards Jan
7 days ago Like
Follow Andreas
Andreas Andersson Do you mean the automatic leveling function in Primavera or the process of
and in it's self.
in terms of the built in function i haven't met anyone who uses it. Most planners, including me, do it
old school style. Ie. manually.
7 days ago Like
Follow Joe
Joe Barros i don't use it,i try once never again it short the durations and on other activities
increases to be able to level the resources,it is a mess
7 days ago Like1
Follow Lorenzo
Lorenzo Lopez Fernandez I agree with previous comments.
Resource leveling is inevitable do it to avoid overloading the resources and schedules.
-
7/28/2019 Resource Leveling Technique
2/11
But I do not advise to do it automatically, or Primavera or Project, or any other program.
It is preferable to see the curves resource use and go leveling them.
7 days ago Like4
Follow Anthony
Anthony Myers We use the automatic resource leveling function in Primavera on all of our refinery
turnaround projects prior to start of execution and at least once at every update. We use 2 activity
codes per activity and total float to prioritize our activities.
We have been using this process for 6 years at 7 refineries and have found it to be very beneficial.
6 days ago Like2
Follow Saju
Saju Samuel when you load resource , cost , manpower, etc, it is based on your productivity and
cost strategy based on BOQ. It is optimum and no need to level it again.
It want to level, I suggest you to do it manually other than automatic leveling
6 days ago Like
Follow Lambert
Lambert S. Saju - Do you have unlimited manpower per discipline? How can you level it manually if
there are thousands of activities?
6 days ago Like
Follow Nicola
Nicola Preto Interesting point of view Mr. Lambert, I'm working now in Algeri, for a important
project.
I have the same problem, i can't do it manually..
how i can define a correct procedure in primavera p6?
-
7/28/2019 Resource Leveling Technique
3/11
(i'd like to study better this program because i really want to work in USA one day. My actual level
are good for italian planner, but if i compare myself with all of you i'm a very basic planner. Any
suggest for a great book for improve my level?)
Best regards
Nicola
6 days ago Like
Follow Saju
Saju Samuel @Lambert, you have unlimited man power it doesn't mean that you have to put all
company manpower in a particular project, Man power is based on the amount of work in that
project /duration and the productivity of the company. Before loading manpower you must have
some idea about manpower and productivity of each an every labor based on activity.
" your duration and manpower is related'
Take only overloaded activities that showing above in histogram, correct it Manually
6 days ago Like2
Follow Lorenzo
Lorenzo Lopez Fernandez It is clear that there is no single answer.
Each type of project requires a different use.
In general I do not like to use any automatic system.
But I understand that when there are many activities no choice.
My use of the manual leveling to large construction projects.
I do not know its use in oil or gas.
6 days ago Like
Follow Mimoune
-
7/28/2019 Resource Leveling Technique
4/11
Mimoune Djouallah Anthony : Could you please explain more your methodology, how do you deal
with soft links, do you use them at all, I read one of your contribution ( i can't remember which
forum) that for resource leveling you use other software beside P6 ?
6 days ago Like
Follow Lambert
Lambert S. @Saju - Maybe we are not in the same boat.... If you have available 100 welders in your
pool, Then your schedule histogram shown an overloaded of 120 welders. Are you going to reduce it
one by one even if there are thousands of activities? How many types of resources you are using?
Friendly advice, Don't work with the computer let the computer works for you.
5 days ago Like2
Follow Muhanad
Muhanad Fakhri, MSc, MBA @ Lambert:- You need to re-prioritize your activities to maintain your
100 welders peak, by shifting some activities and watching the accumulative hours at each point. Or,
you could negotiate with the management to deploy more people, it happened to me in my current
shutdown job where we required more scaffolders, 230 compared to 150 scaffolders in peak, and so
we managed to get nearly 240 by requesting from other ongoing projects.
5 days ago Like2
Follow Lambert
Lambert S. Muhanad please check the topic, we are discussing resource leveling
5 days ago Like
Follow Anthony
Anthony Myers Mimoune:
Most of the execution phase work in turnarounds and outages can be broken down into 3 phase.
1. Disassembly
2. Inspect and repair
3. Reassembly
-
7/28/2019 Resource Leveling Technique
5/11
We create 2 global activity codes
1. Activity Priority with values 1 - 9
2. Equipment Priority with values AA - ZZ
All disassembly activities have an Activity Priority less than 5.
All inspect and repair activities have an Activity Priority of 5.
All reassembly activities have an Activity Priority greater than 5.
Jobs with know repairs would have a 1 for disassembly, 5 for inspect and repair and 9 for
reassembly. The repair activities get as much float as possible.
Jobs with no known repairs would have a 4 for disassembly, 5 for inspect and repair and 6 for
reassembly.
We only use true logic. A must happen before B. Usually only 1 constraint date which is pull feed.
If we have several similar jobs that we need to sequence. Job 1 would receive the Equipment Priority
AA. Job 2 AB, 3 AC etc.
If all else is equal we tell Primavera to then look at total float. The less float the higher the priority.
First criteria is Activity Priority, second is Equipment Priority and last is total float. We level within
float.
Set your resource limit to allow for 25% overage, but when leveling try to keep most of the hours
below the limit line. A small spike here are there should not be an issue. Large on long duration
overallocation must be avoided.
Use you histogram to when leveling set at the smallest time scale you use. For turnarounds we use
hours, for capital projects days.
-
7/28/2019 Resource Leveling Technique
6/11
When I review a schedule I teach to only have 1 activity without a predecessor and 1 without a
successor. If there is more than 1 constraint data the reason must be noted in the activity note tab.
NO SOFT LINKS. EVER. TRUE LOGIC TIES ONLY. Soft links will override any benefits you would gain
from leveling.
5 days ago Like5
Follow Jan
Jan van den Berg Further to my initial post regarding resource leveling, and reading the
contributions of other members of the group I would like to expand on resource leveling either
manual or automatic by the software. As said before I use automatic resource leveling frequently, by
every weekly update on all project in the portfolio. On the other hand I use inherently leveling
planning technique, by using cascading tasks approach. Furthermore all the schedules need to by
resourced by similar resources, properly prioritized, absolutely no loose ends are allowed and the
labor estimate shall not be more out the say 5 10% otherwise the results are untrustworthy and
hence useless. On authors website I have 2 articles on resource leveling. One on the basis of
automatic leveling for resources and one other article on automatic resource leveling on limited
floor space. The website is http://plannenvoornietplanners.net/
5 days ago Like
Follow Anthony
Anthony Myers As Jan van den Berg described, we too use leveling when we are resource
constrained due to logistics, resource availablity or safety. Using these features gives us a more
predictable turnover date.
5 days ago Like
Follow Mimoune
Mimoune Djouallah I appreciate your detailed answers, i tried the automatic leveling but with a
limited success, usually our main resources constraints is the availability of accommodation in
remote areas, P6 will let you level using only one maximum value, or in our case the availability is
not fixed, you may have 200 bed the first month then 250 the next one.
-
7/28/2019 Resource Leveling Technique
7/11
it would have been useful, if P6 have the options to set the limit using roles, and and the options to
assign activities the split or non split attribute.
but the main reason that I use manual leveling is that going the automatic way will impose a wholedifferent approach how you develop the schedule in the first place, like using only hard logic, I don't
want really to step outside my comfort zone.
5 days ago Like
Follow Engr.Faiz
Engr.Faiz Rasul (PMP) can anyone who ever talked about mannual levelling explain that are the
main steps for mannual levelling?
5 days ago Like
Follow Muhanad
Muhanad Fakhri, MSc, MBA @ Lambert: I understood the subject matter and I was talking about
either manually leveling the resources (prioritizing and shifting activities) to maintain my peak
manpower histogram, or negotiating my management to increase resource in case the situation is
inevitable ...
5 days ago Like
Follow Muhanad
Muhanad Fakhri, MSc, MBA @ Faiz: The way I used to follow in manual leveling is by watching my
manpower mobilization plan, once we got the job we will prepare the schedule considering many
factors, one of them is the manpower and equipment required to accomplish a certain amount of
work, this has to be discussed with the management in light of the current manpower utilizationacross the projects portfolio and the possibility to recruit more in the long run in addition to the
peak manpower requirements such as accommodation and logistics and space constraints. Once the
manpower mobilization histogram is agreed then this has to be our guidelines in adjusting the
schedule prior final submission for client approval. So we need to ensure that individual resources
are not exceeding the required peak and hence the accumulative resources are not exceeding the
total manpower peak. Manually i believe its hectic and time consuming but with experience and
dedication the stress would be..somehow...affordable. :)
5 days ago Like1
-
7/28/2019 Resource Leveling Technique
8/11
Follow Engr.Faiz
Engr.Faiz Rasul (PMP) Muhanad Fakhri,Suppose I am getting Overallocation in "Month X" so I shall
filter Out the Activities of "MOnth X" and shift some of them to other months or increase durations
to decrease the resource usage.Is this the approach when we talk about mannual levelling?
4 days ago Like1
Follow Lambert
Lambert S. Good Question!
4 days ago Like
Follow Dave
Dave Caldwell Faiz: Look at the histogram at the bottom of the page and then manually move or
adjust durations so that your hours come down to an acceptable level. Anthony: That is a great
explanation, thanks.
4 days ago Like
Follow Lambert
Lambert S. @Dave - Considering restrictions for each relationship of every activity and talking
thousands of activities especially critical items. I don't think your idea is advisable. It is possible if the
over allocation is very minimal and considered hours only instead of detailed manpower with few
activities only.
4 days ago Like
Follow Dave
Dave Caldwell @Lambert - I am sure that you are right in your projects. I work typically on new
facilities and I may have 50 to one hundred activities with the same resource working at any one
time. The issue that I found were priorities change over the life cycle of a project. This made us go
through and modifying the plan after an update and realistically after the initial resource leveling
session the changes were minimal.
4 days ago Like
Follow Anthony
-
7/28/2019 Resource Leveling Technique
9/11
Anthony Myers Each project type has its own idiosyncrasies. What works well in one environment
may not work at all in another. Projects that I work with range in size from 2,000 to 40,000 activities.
Time increments are in hours. We try to keep the execution phase of our project below 45 days
working 7 days per week 24 hours per day. The nature of our beast mandates we utilize the power
of the computer as much as possible. Prioritized leveling works well for us, but could well be overkill
for projects under 100 activities with longer durations. The beauty of todays software is that it can
be configured for different needs within the same organization. The only requirement is that the end
user know how and when to take advantage of this power.
3 days ago Like
Follow Jan
Jan van den Berg Mimoune
I understand that you have tried and that automatic leveling has limited success. You noted that the
the number of bed may are different every month. Note that you can specify the limit of number of
resources, of any way you want in time and availability. So suggest to proceed as follows. Make an
resource called. BEDS specify the number as 20000% for 200 beds in the time period. Then assign
this resource to all activities. Go to the leveling tab and set only the resource BEDS for leveling . The
activities shall now be leveled. Next step is to priorities the activities.
Regards Jan
3 days ago Like
Follow Anthony
Anthony Myers I do something similar, but would assign 1 bed per resource to each activity.
You would then need to turn off level within float or you could have overallocations.
3 days ago Like
Follow Jan
Jan van den Berg Anthony
Yes, there are many other items to consider during leveling. Hope to have a reaction of Mimoune or
any other members of the group. Feedback is also important. Regards Jan
3 days ago Like
Follow Mimoune
-
7/28/2019 Resource Leveling Technique
10/11
Mimoune Djouallah thanks, P6 let you define resource availability by period, that's good, but for
leveling it use only one value, which is useless in my case.
3 days ago Like
Follow Muhanad
Muhanad Fakhri, MSc, MBA Faiz you will have different combination of resources building up your
histogram, not only one, you can use automatic leveling but you might have issues in overall
duration and hence you might miss some milestones, If my resources are over allocated then I have
two solutions, either to re-prioritize my activities and shift them, or discuss with my management to
increase the pre-set peak. As we know, for example, excavating a trench using JCB with a prescribed
productivity, assuming only 2 JCBs are available can not be challenged, when I update my schedule
the balance work has to be done with available resources, i normally update the schedule and
present the actual scenario to my management with delays expected and ways to recover including
increment of resources or using the available float to re-prioritize, in severe cases a complete delay
analysis and a recovery plan will follow when we exceed 5% slippage.
2 days ago Like
Follow Stijn
Stijn Van de Vonder It's good to read that resource leveling functionality is used by some of you.
But by all means, it is NOT common practice at all to level automatically. Very few of our clients use
this functionality. Whether it is best practice is an other discussion. There exists a lot of academic
research on what they call the RCPSP (resource constraint project scheduling problem). The
algorithms in this research are far more powerful than the simple priority list-based heuristics in P6
and MSP. But the bottom line is that every algorithm struggles to model human decisions / priorities
(there are just too many factors that impact decisions). For that reason, automatic leveling is a
bridge too far for most people.
2 days ago Like
Follow David
David Hulett, Ph.D. I review a lot of schedules for best practices, which includes not overloading
limited resources. Even if resources are entered, i see no evidence that the automatic leveling
capability of the scheduling software has been used. Most contractors say they address resource
management in some other software, but then the question is: "How can we be sure that the
schedule reflects what you had to do to manage resources?" I suspect that resource management is
the reason I see so many Start-not-earlier-than constraints, since resource leveling is usually
resource shifting.
-
7/28/2019 Resource Leveling Technique
11/11
Where I need to use the automatic resource leveling algorithms in the scheduling software is when I
conduct a Monte Carlo simulation on the schedule, using risk drivers or 3-point estimates. There is
just not enough time to level each of 3,000 iterations manually. Since manual leveling is usually
more efficient than the algorithms, I believe that (1) at least the iterations are not violating resource
constraints and (2) the simulation results may be more conservative than necessary.
1 day ago Like
Follow Osama Abdelmalik
Osama Abdelmalik Arafat, PMP Certifeid, Primavera P6 I think at early stages of the project,
automatic resources leveling is more efficient that manual, while at advanced stages of the project,
manual leveling is more efficient.
1 day ago Like
Follow Jaco
Jaco Stadler It would be interesting to see how does resource leveling add up in a Contract, most
contract I have seen talks about Critical path (Logic and task) = EOT as such I believe the scehdule
should tell you in order to achieve your early schedule you need x amount of resources, in Order to
achive your late curve you need Y resources, I normally try to add in Lags and Increase duraton tolevel my early required resources. The reason EOT claim is impact is never based on a Contract that
states reqource leveling, it always states CPM method.
10 hours ago Like Reply privately Flag as inappropriate
Follow Joe
Joe Barros i agree with Muhana Fakhri,the resource are allocated according to the scope of
work,hours required to complete the project,priorities,commission dates or key dates,once this hasbeen ascertain the program can be drawn the same as you build a house brick by brick,resources are
allocated as required task by task taking into consideration that you program is not start steep and
with over resourcing up front,if automatic resourcing is applied the program will increase or
decrease task duration to level the resources,
many times once the S curve has been drawn it is required to go back and readjust the plan to
accommodate certain gapes but this has to be done the the project requirements in mind.
therefore automatic resource leveling in my opinion is not a good option as the package does not
know the project requirements