Reserve Proposals
description
Transcript of Reserve Proposals
Reserve Proposals
David LaPlante, Vice President, Markets
DevelopmentMarch 14, 2001
Summary of Presentation
Describe Objectives of New Reserve Proposal presented to PC on 2/15
Describe How the Proposal would work
Compare it to current initiatives Present a progress report on unit
commitment and uplift reduction Recommendation
Proposal Objectives
1. Assure that reserve requirements are met with the lowest possible production loss.
2. Provide incentive for flexible units and flexible bidding of all units .
3. Reduce Uplift as much as possible4. Include replacement reserves in reserve
markets.5. Cascade prices in reserve markets.
Alternative Approaches
Participant Committee Proposal described by Jeff Tranen on 2/15 (PC Proposal)
Demand curve for reserves Other Initiatives:
Three part bidding Net Commitment Period
Compensation
Motivation for PC Proposal
To assure that energy and reserves are met with most efficient combination of energy and fast start resources
Minimize use of inflexible steam units providing reserve, consistent with minimizing total production costs
PC Proposal DescriptionBusiness Process
Commit units to provide energy only to determine most efficient energy units
Determine if this commitment yields adequate reserves. If so, stop
If not, back down fast start resources to provide reserves
Hold units at backed down level and run new commitment to provide sufficient energy and reserves
Proposal Description Reserve Market Pricing
Calculate Lost Opportunity Cost of units backed down to provide reserves in real-time (Real-Time ECP - bid)
Use this bid to price reserves Note: Units would be held back in
energy market to provide reserves but price of reserves not calculated until real time based on actual ECP
Analysis of PC Proposal Unit Commitment Objective Function.
Minimize energy production costs to meet:
Energy Requirement Ten-Minute Spin Requirements Ten-Minute Non-Spin Requirements Thirty-Minute Requirement
Commitment then checked to see if replacement reserve is met
In recent months no adjustment to commitment needed for replacement reserves
Analysis of PC Proposal
Current commitment objective function meets proposal objective of best use of resources (and as bid characteristics) to provide energy and reserves
Energy and reserves of fast start optimized by unit characteristics
Current Initiatives
Several Initiatives underway to meet same objectives as PC proposal Net Commitment Period
Compensation Three-Part Bidding Demand Curve for Reserves
Comparison of PC Proposal and Current Initiatives
Objective 1: Meet energy and reserve requirements at minimum product costs Current unit commitment procedures
do this. It co-optimizes energy and reserve requirements (without an accounting for reserve bid prices)
No need to change commitment process as described in PC Proposal
Comparison of PC Proposal and Current Initiatives
Objective 2: Provide Incentives for Flexible Resources and Flexible Bidding Both proposals seek to increase revenues
in the reserve market Magnitude of revenues increase in either
proposal is uncertain Current initiatives with NCPC and 3-Part
Bidding, incent shorter run times and lower low limits
Comparison of PC Proposal and Current Initiatives
• Objective 4 -- Reduce Uplift• The amount of uplift reduction that
occurs depends on how successful the proposals are with incenting more flexible unit characteristics.
• Other Important Efforts to reduce uplift are underway and have had some success
Comparison of PC Proposal and Current Initiatives
Objective 4: Include Replacement Reserve in 30 Minute Market New proposal does this by explicitly
increasing amount cleared in market Current initiatives does this by increasing
an amount cleared but with a demand curve
New proposal seems more market driven but could increase use of reserve price cap
Comparison of PC Proposal and Current Initiatives
Objective 5: Cascade Prices New proposal does this fully Current initiatives limited cascading.
Full cascading could be incorporated
Progress Report on Reducing Unit Commitment and Uplift
Steve Whitley has taken several steps to improve commitment and meet proposal objectives:
September 15, 2000: reduction of capacity margin from 1500 MW to 1350 MW
February 2, 2001: New York reserve sharing 1350 MW to 1050 MW
Increased internal focus on uplift reduction Improved transmission outage scheduling Improved satellite coordination of security
Progress Report -Replacement Reserves, met without Additional
Commitment Lower Requirement means fewer
units needed so additional commitment not needed
Units committed economically or via self-schedules provide needed reserves
This has resulted in lower uplift Following charts show reduction in
uplift. Analysis of available capacity over peak is underway
Recently Declining Uplift
Daily Energy Uplift, Rolling 7 Day Average, Since Start of 2001
$0
$200,000
$400,000
$600,000
$800,000
$1,000,000
$1,200,000
12/3
1/00
01/0
7/01
01/1
4/01
01/2
1/01
01/2
8/01
02/0
4/01
02/1
1/01
02/1
8/01
02/2
5/01
03/0
4/01
03/1
1/01
2/2/01: start of reserve sharing
Uplift Since Start of MarketsDaily Energy Uplift, Rolling 7 Day Average,
Since Start of Markets
$0
$200,000
$400,000
$600,000
$800,000
$1,000,000
$1,200,000
5/1/
99
6/1/
99
7/1/
99
8/1/
99
9/1/
99
10/1
/99
11/1
/99
12/1
/99
1/1/
00
2/1/
00
3/1/
00
4/1/
00
5/1/
00
6/1/
00
7/1/
00
8/1/
00
9/1/
00
10/1
/00
11/1
/00
12/1
/00
1/1/
01
2/1/
01
3/1/
01
Implementation
PC proposal - To fully implement concept in PC proposal of a day ahead selection of units in reserves requires a day ahead market of some kind. This would take several months to design and several months to implement
Current Initiatives - 3 to 6 months
Recommendation
Continue with Current Initiatives Continue work on improving
reserve markets Day-Ahead Concept. Unit Commitment Demand Curve