1
The Retrofitting Programme
>> Cotentin-Falguière Residence
2
Reminder of the retrofitting stakes
� Patrimonial stakes
- bring the building to current safety and comfort standards
- improve the building’s thermal performance and limit consumption
- highlight the building’s strengths
- adjust the housing supply to the needs of SNCF staff
� Tenant stakes
- improve the comfort and living standard of dwellings
- limiting expenses related to energy consumption
3
The project in figures
� Number of dwellings: 86 before, 82 after retrofitting
� Estimated duration of work: 18 months
� Total cost of work: about € 6 million (excl. European subsidy)
� Cost of work per dwelling: € 70 000 (excl. European subsidy)
� No rent increase after the works
� A 50% share of the cost savings achieved between landlord and
tenant (MOLLE Act of 2009)
4
A European project
BEEM-UP: a European Union initiative
� 3 pilot sites: Alingsas (Sweden), Delft (Netherlands) and Paris (France)
� Exchange of practices and ideas among donors, builders, consulting firms,
manufacturers and universities from many countries
� A subsidy for energy saving works
Multiple common objectives
� Energy consumption reduced by 75%
� Use of innovative technical solutions
� Special attention to the support of tenants
� An long-term approach (performance and consumption monitoring)
5
Tenant support
� Relocations of tenants of the apartments converted
into duplexes
� Development of buffer apartments to provide rest
areas during the works
� Support for the relocation of tenants who are
permanently leaving their homes
� Support before and during the works
� “Outer spaces” workshops: “Zen“atmosphere, more
room for bikes
� “Energy saving” workshop: a charter of "green
behaviour" in preparation
� Consultation with tenants: the result
6
The detailed work programme
� The building envelope
• Thermal insulation
• Façade restoration
• Roof and terraces
• Replacement of windows
� Outdoor areas
• Courtyards and parking lots
� Common areas
• Lobbies, hallways and technical rooms
� Common amenities
• Ventilation
• Collective heating and hot water
� Housing units
• The restructured dwellings
• Heating and sanitary equipments
• Electricity
Presentation by D. LE FERRAND, Georges ROUX architect firm
7
The building envelope
� External thermal insulation (ETI)
of façades
� Roof insulation
� Insulation of ceilings of common
areas
� Thermal insulation
Thickness of the
outer insulation:
20 cm
8
The building envelope
� Smoothed coating on the running
parts of the facades, white tone
� Façade refurbishment
� Ground floor: stone
cladding
� Slab cladding with
natural stone effect on
metal framing,
invisible mounting
brackets
� Very high resistance to
shock and vandalism
Appearance: matt,
glossy or granite-like
� Last level: zinc
metal siding
9
The building envelope
� Roof and terraces
� Roofs:
� Thermal insulation and re-sealing
� Installation of a safety railing on street
side
� Private terraces:
� Replacement of railings
� Replacement of terrace pavement by
wooden floor tiles on studs
� Transformation of 10 balconies (at the
intersection of the two streets) in bay
windows, for a gain of living space
10
� Complete removal of the old frame
� Windows offset outwards, offering a small shelf
space
� Replacement of the outer window lining
� PVC frame
� Maintenance of double glazing
� The replacement of the windows
The building’s envelope
Result: better thermal and
noise insulation and a slight
increase in glass area
11
� Common courtyards
Outdoor areas
� Reorganisation of the green
spaces
� Renovation of the parking
area for two-wheelers
� Garage with green roof,
securing of the terrace
� Transparency between the
street and the courtyard
(portals)
12
� Parking space on cour Falguière
Outdoor areas
Abris vélo 18 places
� Installation of a wooden
bike shelter with 18
spaces
� Replacement of the porch
gate
� Upgrade of footpaths
(asphalt)
� Reorganisation of green
spaces
Motorbike
parking for the
entire residence
(14 spaces)
Bicycle parking
(28 spaces)
13
Outdoor areas
� Separation of bicycles and
motorcycles
� Direct access between
porch and bike parking
� Replacement of the porch
gate
� Upgrade of footpaths
(asphalt)
� Reorganisation of green
spaces
� Parking space on cour Cotentin
14
Common areas
� Replacement of the building’s
access doors
� Rehabilitation of access control
/ intercom
� Refurbishment of the keeper’s
lodge
� Mailboxes
� Embellishments of the halls
� Painting of the hallways and
stairwells
� Compliance of common
electrical, lighting
� Conformance of electrical and
lighting infrastructures
� Lobbies, hallways and stairwells
15
Common areas
� Technical rooms
� Renovation of premises for strollers
and garbage room
� Evacuation of containers via the
courtyards
� Development of a maintenance room
� Compliance with fire safety
requirements (garbage room,
smoke extraction)
� Closing of galley waste discharge
chutes
Common amenities
16
� Controlled mechanical ventilation (CMV)
� Installation of engines on the roof
� Recovery of existing vertical ducts
� Installation of a conduct dressed in the false ceilings of kitchens in T2
apartments
� Air vents in the kitchen, bathroom and WC
� Planing of interior doors
Constant renewal of indoor
air based on moisture levels.
Common amenities
17
� Heating
� Replacement of old boilers by collective high-efficiency boilers
� Compliance with fire safety requirements for boiler room in basement
� Common hot water: the Biofluids process
� Heat recovery of wastewater to preheat the common hot water
� Demolition of six cellars and transfer for the creation of the storage room for
hot water tanks
� Retrofitting of wastewater drainage networks, requiring access to certain
private cellars
Common areas
18
� Intervention in basements
� The insulation and replacement of drains will require access to
numerous cellars
� The affected tenants will be contacted directly in order to find a
solution adapter to their needs
Dwellings
19
� Restructuring of dwellings
� Creation of 6 duplex apartments on the two upper levels
� Separation between the keeper’s lodge and apartment
� Extension of T4 living rooms (transition to T3bis) subject to agreement
� Soundproofing of the party wall in the sleeping room of T2s
20
Dwellings
� Replacement of sanitary fixtures according to their obsolescence level
� Replacement of hip baths by enamelled steel bathtubs
� Upgrade of wall tiles when replacing a bathtub or installing a shower, including painting of
degraded walls
� Replacement of kitchen sinks and wash basins according to their state
� Replacement of toilets with 3/6 liter tank toilets
� Replace of faucets by mixer faucets fitted with aerators
21
Dwellings
� Heating networks
� Installation of steel radiators in all
rooms except toilet rooms
� Horizontal format under
windows
� Vertical format alongside
French windows
� Installation of towel rails in
bathrooms
� Installation of thermostatic valve
(with integrated temperature
sensor)
� Installation of an atmosphere
thermostat for energy savings
22
T4 type apartment – project
Current state
� Heating network and sanitary equipment
radiators
pipes
23
T3 type apartment – project
Current state
radiators
pipes
� Heating network and sanitary equipment
24
T2 type appartment – project
Current state
radiators
pipes
� Heating network and sanitary equipment
25
Dwellings
� Electricity
� three scenarios are possible:
� Facilities are new and undamaged: no work needed
� Facilities are old, but still usable: targeted interventions
� Electrical facilities are old, composed of obsolete materials and equipments
(ceramic or metal switches, insufficient safeguards on the switchboard, fabric
wiring): bringing into full compliance of facilities
� Securing the facilities
� Replacement of
switchboards
� Replacement of original or
degraded equipments and
materials
� Electrical outlet
complements, especially in
the kitchen and living room
(if full compliance)
26
Tentative general schedule of works
27
Interventions inside dwellings: estimated duration of actions
General works
� Replacement of the chassis and dressings of interior panels 3-4 d
� Replacement of entrance doors and planing of interior doors 1 d
� Installation of radiators and power outlets 2-3 d
� Electricity 1-3 d
� Controlled mechanical ventilation, valves and ducts 1-2 d
� Passing of mounting columns 2 d
� Plumbing works 3 d
Removal of the hot water tanks and patching
Connection to the collective network
New faucets and flushes
� Painting (wall of the hot water tank and ventilation ducts) 2 d
Special works
� T4 : extension of living room (demolition, electricity, painting, floor) 5 d
� T2 : doubling of the bedroom wall (+ electricity, painting) 3 d
The building refurbishment programme
28
Still under investigation:
� The overall asbestos diagnosis before start of general works on
building (in progress)
� Assessment of energy savings (consumption measurements
and remote meter reading in progress)
� During the site preparation in the presence of the construction
company
Next meeting
29
Next steps
Support for the relocation of tenants affected by the duplexesJuly 2011 through June
2012
Asbestos diagnosis before the start of works (entire residence) May 2012
Consultation of contracting firms June / July 2012
3rd tenant meeting: preparation of works
Visits before worksSeptember / October 2012
Works October 2012 through April
2014
Support of tenants during the worksOctober 2012 through April
2014
30