2All rights reserved. Proprietary and confidential.
Endeca Development Methodology
• Define Armstrong Goals and Objectives
• Introduction to Endeca
• Prioritize User Stories and map to Endeca functionality
• Plan first iteration’s goals
Endeca Discovery Workshop
• Finalize Ramp Up & Staffing
• Discovery Prep Homework
• Data
• Tech Arch Review
• Setup Dev Environment
• Discovery Homework Review
• POC
Kickoff
Deliverable
3All rights reserved. Proprietary and confidential.
Dimensions vs. Dimension Values
Think of a dimension as a column header in a spreadsheet, and dimension values as the values that appear in the cells beneath.
Dimensions
DimensionValues
COLOR
Apple
Green
Black
Pool
PRICE
Less than $200
$200-$400
$400-$600
More than $600
4All rights reserved. Proprietary and confidential.
Endeca Architecture
User Web Browser
InternetLoad Balancer
Load Balancer
Web Application Server
Web Application Server
Endeca Server
Endeca Server
Editable Text
5All rights reserved. Proprietary and confidential.
Dimension Hierarchy
Hierarchical DimensionDimension values in a hierarchical dimension can have one “parent” and many “child” dimension values.
Flat DimensionDimensions with only one level of hierarchy are referred to as “flat” dimensions.
General Software
Operating System
Security
Screen Capture
Linux
Windows
McAffee
Norton
SnagIt
Captivate
Manufacturer
Microsoft
Toshiba
Sun
7All rights reserved. Proprietary and confidential.
Sample Search Interface
Search
Guided Navigation
Search within
Snippeting
Spell Correction
Stemming
Search messaging
8All rights reserved. Proprietary and confidential.
AreaPrior Week
Current Week Description
BudgetRequire Change Order to be approved to finish project. Endeca change order submitted to THD for approval. 32% of SOW10 budget remaining.
Scope
Agreed to proceed with reduced scope for March 1 deadline (delay Web Studio, High Interactivity mouse-overs, lookahead, guided nav sliders/checkboxes until March 14).
Schedule Delay in accessing development environment totaled 17 days.
Staffing Endeca UI developer on site at THD. No foreseen staffing problems.
On TargetNeeds
AttentionAt RiskStatus
Key
Project Summary
9
Text Tagger Overview #3
Text Tagger
Loading Data
Caching & Joining Data
Manipulating DataDimension Mapping
The Endeca pipeline
“Whitelist” of terms
OR
Endeca Relationship
Discovery
The end result is an Endeca index which possesses enriched source data and enhanced search and Guided Navigation capabilities
All rights reserved. Proprietary and confidential.
10All rights reserved. Proprietary and confidential.
The scope and functionality of the development iterations will be mutually agreed upon by Endeca and <CLIENT> during the first project phase. At the end of each iteration, there will be a “show me” checkpoint to demonstrate the functionality developed.
Estimated Project Schedule & Cost
Project Phase WK 1 WK 2 WK 3 WK 4 WK 5 WK 6 WK 7 WK 8 WK 9 WK 10
Discovery & Planning
Design & Dev
Iteration 1
Iteration 2
Iteration 3
Iteration 4
Testing & Deployment
= “Show Me” iteration checkpoint
= Project Phase Transition
= Go Live
Project Phase Est. Duration Est. Work Effort (days)
Est. Cost
Discovery & Planning 5 days 15 $23,280
Design & Dev 35 days 69 $108,000
Testing & Deployment 10 days 17 $26,200
Estimated Total 50 days 101 days $157,480
Note: Schedule is illustrative and subject to change.