Requirements Structure and Status for NCFE
Aurelien PontonEdgar Sargsyan
NCFE Interface Workshop, 23-24 April 2015, ESS, Lund
Product Breakdown structure (PBS) Levels L1 – L4 for the ESS Accelerator
L1
L2
L3
L4
ESS SYSTEMS ‘PROJECTS’
LINAC SECTIONS
DISCIPLINE SYSTEMS (Mapping to WBS
Work Packages shown)
ESS FACILITY
ICS – INTEGRATED CONTROL SYSTEMS‘CONTROLS’
SI – SITE INFRASTRUCTURE‘CONVENTIONAL FACILITIES’
NSS‘INSTRUMENTS’
ACC – LINEAR ACCELERATOR (LINAC)‘ACCSYS’
TS – TARGET STATION‘TARGET’
ISrc LEBT RFQ MEBTDTL
(DTL tanks)SPK
(LWUs, CMs)
DmpL(inc. beam
dump)
BMDBeam Magnets &, Deflectors (BM*)
RFSRadio Frequency
Systems
EMREM Resonators
(Bunchers, RFQ, DTL tanks, CMs)
PBIProton Beam
Instrumentation
CRYOCryo Plant (ACCP) & Distribution (CDS*)
VACVacuum
WTRCWater Cooling
CNPW*Conventional Power
SUPPLIED BY WP 2, 3, 6, 17
SUPPLIED BY WP 3,4,5 SUPPLIED BY WP 7
SUPPLIED BY WP 8 SUPPLIED BY WP 12 SUPPLIED BY WP 11 SUPPLIED BY WP 16 SUPPLIED BY WP 15 SUPPLIED BY WP 13
Safety
MBL(LWUs, CMs)
HBL(LWUs, CMs)
*PBS definitionCM =CryoModuleHEBT=High Energy Beam TransportLWU=Linac Warm Unit
HEBT*
CRYOGENICS DISTRIBUTION
Beam to Target
ISS*Ion Source Specialties
SUPPLIED BY WP 3
A2T
RMHF – RADIOACTIVE MATERIALS HANDLING FACILITY
To Be Determined or
To Be Agreed Upon
SUPPLIED BY WP 6, 17
PWRC*PS*, HV Power
Convertors*
Date: 27-Feb-2015Prepared by: E.Tanke, ESS-ACCSYSCHESS#: ESS-0008904 R4
Product Breakdown structure (PBS) Levels L4 - L5 for the ESS Accelerator
L4
L5
DISCIPLINE SYSTEMS (Mapping to WBS Work
Packages shown)
‘COMPONENTS’(includes WP
contracted products & services)
BMDBeam Magnets &, Deflectors (BM*)
EMREM Resonators
(Bunchers, RFQ, DTL tanks, CMs)
PBIProton Beam
InstrumentationSUPPLIED BY WP 2, 3, 6, 17 SUPPLIED BY WP 3,4,5 SUPPLIED BY WP 7
LLRFWP8
RFRLWP8
CICWP8
ISS*Ion Source Specialties
SUPPLIED BY WP 3SUPPLIED BY WP 6, 17
PWRC*Power Convertors*
RFMOWP8
AMPLWP8
AMPHWP8
Technical Labs
Mechanical Supports
L4
DISCIPLINE SYSTEMS (Mapping to WBS
Work Packages shown)
RFSRadio Frequency
Systems
CRYOCryo Plant (ACCP) & Distribution (CDS*)
VACVacuum
WTRCWater Cooling
CNPW*Conventional Power
SUPPLIED BY WP 8 SUPPLIED BY WP 12 SUPPLIED BY WP 11 SUPPLIED BY WP 16 SUPPLIED BY WP 15
L5
‘COMPONENTS’(includes WP contracted
products & services)
PSWP 6, 17
HVPCWP17
Mechanical Supports
Technical Labs
Mechanical Supports
Technical Labs
Mechanical Supports
Technical Labs
BCM BLM
SC CavitiesSPK
Technical Labs
RFDSWP8
Technical Labs
FE CollimatorsWP3
Linac DumpWP??
EM BPM
BSM
NPM(non-invas.)
PM (invasiv
e)
FC
Technical Labs
TD(Target Diagn.)
ID(Insertable Dump)
*PBS definitionCM =CryoModuleHEBT=High Energy Beam TransportLWU=Linac Warm Unit
Beam Pipes
Collimators & Gamma Blockers
SUPPLIED BY WP 6
SC CavitiesMBL
SC CavitiesHBL
Date: 27-Feb-2015Prepared by: E.Tanke, ESS-ACCSYSCHESS#: ESS-0008904 R4
L5 requirements are specification documents and are not stored in DOORS
4
Responsibility for Authoring of Requirements
• Top-down:– Accelerator Integration Group (AIG)
• i.e., the Lead Engineers
• Interface:– The interfacing Work Packages– In the case of IKC, this means the contracted institution
• Thus:– Top-down requirements will be authored by ESS
• For delivery to WP3
– Interface requirements will be authored by WP3 and respective WPs• For delivery to ESS AIG
NCFE Interface Workshop, 23-24 April 2015, ESS, Lund
5
Requirements in DOORS
NCFE Interface Workshop, 23-24 April 2015, ESS, Lund
Top-down requirements written by Lead Engineers
Linac section
L3-System
L4-ISS
L4-PBI
L4-BMD
L4-EMR
L4-RFS
Ion Source
✔ ✔ ✔ n/a n/a n/a
LEBT ✔ n/a ✔ to do n/a n/a
RFQ ✔ n/a ✔ n/a ✔ ✔
MEBT ✔ n/a to do ✔ ✔ ✔
DTL ✔ n/a to do ✔ ✔ ✔
Interface requirements written by interfacing WPs (Interface A – Interface B) in a common
agreement
Examples: EMR (WP3) – WTRC (WP16)BMD (WP3) – PWRC (WP17)