Request for Inspection (RFI) Form 1

2
INSPECTION REQUEST TO: SUPERVISOR INSPECTION UNIT ENGINEERING DIVISION FROM: Tel.: ____________ Fax.: ___________ Request No.: ________________ Request Date: _______________ This is to inform you that the following job is scheduled to start as detailed below. Please provide the required inspection coverage. Work Description: (Include Plant No., Location of work, etc.) Start Date: ___ / ___ / ______ Time: ________ Completion Date: ___ / ___ / ______ Time:_______ Inspection Required: ________ Pre – T&I ________ Pre – T&I ________ None T&I Mechanical Welding Electrical Paints & Coating Cath. Protection Relief Valves Engineering Package: (Repairs / Modifications / Maintenance Projects) Available Under Preparation Not Required Inspection Worksheet: Available IWS #: IU- ________ Required Not Required Saudi Aramco: Company General Use

description

hh

Transcript of Request for Inspection (RFI) Form 1

Page 1: Request for Inspection (RFI) Form 1

INSPECTION REQUEST

TO: SUPERVISORINSPECTION UNITENGINEERING DIVISION

FROM:

Tel.: ____________ Fax.: ___________

Request No.: ________________

Request Date: _______________

This is to inform you that the following job is scheduled to start as detailed below. Please provide the required inspection coverage.

Work Description: (Include Plant No., Location of work, etc.)

Start Date: ___ / ___ / ______ Time: ________

Completion Date: ___ / ___ / ______ Time:_______

Inspection Required: ________ Pre – T&I ________ Pre – T&I ________ None T&I

Mechanical Welding Electrical Paints & Coating Cath. Protection Relief Valves

Engineering Package: (Repairs / Modifications / Maintenance Projects)

Available Under Preparation Not Required

Inspection Worksheet:

Available IWS #: IU- ________

Required Not Required

Comments:

______________________ Area Rep. Sign

For Inspection Unit Use Only

Assigned Inspector: _____________________Inspection Supvr. Instructions: __________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

cc: Supt. ED Supvr. OEU _____________________ Supvr. MSU Inspection Unit Sup. Operations Forman