C ITY OF N EW O RLEANS Reporting Period: November 15 – December 15 Office of Performance & Accountability ReqtoCheckSTAT

Transcript of ReqToCheckStat 12.15.2011

Page 1: ReqToCheckStat 12.15.2011

CITY OF NEW ORLEANS

Reporting Period: November 15 – December 15

Office of Performance & Accountability

ReqtoCheckSTAT

Page 2: ReqToCheckStat 12.15.2011

Context In order to deliver critical services for its citizens—such as constructing roads, rehabilitating homes, or picking up trash—the City often engages with private companies with specialized expertise. Because these and other services are so critical, Mayor Landrieu has made it a priority for vendors to be selected fairly, for contracts to be negotiated expeditiously and in the best interests of New Orleanians, and for vendors to be paid in a timely manner. What is ReqtoCheckStat? In order to improve the performance, accountability, and transparency of the City’s contracting system, Mayor Landrieu asked the Office of Performance and Accountability to design a performance management program for the entire process of contracting out services—from the requisition of budgeted funds to the issuance of check for services rendered. The result is ReqtoCheckStat, a performance management system where key City officials review data to assess how the City is meetings its goals and to hold departments accountable for their results. ReqtoCheckStat, which takes place monthly, are working meetings, intended to provoke constructive dialogue on what is working, what is not, and what the City needs to do to improve. Can I participate? This meetings are open to the public. Members of the public are invited to submit questions, which will be addressed by City officials.

2

Page 3: ReqToCheckStat 12.15.2011

Procurement Process Overview*

Requisition

•Department identifies need, and creates a requisition

•Requisition to use budgeted funds is approved by different offices

Procurement / DBE

•Approved requisition is reviewed by the Bureau of Purchasing

•Requisition is converted to Purchase Order (PO), Bid or Request for Proposal (RFP), depending upon scope of work and dollar amount

Contract Creation and

Routing

• Department routes contract materials through the system in order to obtain a contract

Contract Processing

and Approval

•Contract is reviewed for form, legality by Law Department

•CAO, City Attorney, Executive Counsel, Mayor/ Council review and approve contract

Payment

•Department reviews invoice and submits payment voucher to Accounts Payable (AP) to process payment

•Accounts Payable processes requests and makes payment

*See a more detailed process map on slide 33

3

Page 4: ReqToCheckStat 12.15.2011

Requisition Approval

4

• Approval Time of Requisitions

• Requisition Approved and Processed per Period

• Requisition Approval Queue by Approval Level

Requisition Procurement

/ DBE

Contract Creation and

Routing

Contract Processing

and Approval Payment

Page 5: ReqToCheckStat 12.15.2011

Source : Obtained from BuySpeed System and evaluated by the Office of Performance and Accountability 12.15.2011

5

Requisition Procurement / DBE Contract Creation and Routing Contract Processing and Approval Payment

Approval queue for requisitions remains practically unchanged from the prior period

62 153 214 213 92

882 791 696 635 667 668 673 794

EndingApproval Q 8/15/2011

NewRequisitions

Created8.16 - 9.15

RequisitionsApproved8.16 -9.15

EndingApproval Q 9/15/2011

NewRequisitions

Created9.16 - 10.15

RequisitionsApproved

9.16 - 10.15

EndingApproval Q10/15/2011

NewRequisitions

Created10.16 - 11.15

RequisitionsApproved

10.16 - 11.15

EndingApproval Q11/15/2011

NewRequisitions

Created11.16 - 12.15

RequisitionsApproved

11.16 - 12.15

EndingApproval Q12/15/2011

Requisition Approval Queue General Fund for Period Ending 12.15.2011

58 43 35 49 54 36

19 19

116

159 158

56

6 1

77 62

153

214 213

92

0

50

100

150

200

250

7.15.2011 8.15.2011 9.15.2011 10.15.2011 11.15.2011 12.15.2012

Finance

Budget

Director

Requisitions in Q to be Approved by Period

Page 6: ReqToCheckStat 12.15.2011

Source : Obtained from BuySpeed System and evaluated by the Office of Performance and Accountability 12.15.2011 6

Requisition Procurement / DBE Contract Creation and Routing Contract Processing and Approval Payment

Delay is driven by longer approval times by the Budget Office due to city wide spending controls

Days to Approve 8.15.2011 9.15.2011 10.15.2012 11.15.2011 12.15.2012

1 or less 100% 100% 100% 99% 99%

2 Days 0% 0% 0% 1% 0%

3-5 Days 0% 0% 0% 0% 1%

6-10 Days 0% 0% 0% 0% 0%

11-15 Days 0% 0% 0% 0% 0%

Over 15 Days 0% 0% 0% 0% 0%

FinanceApproval Distribution by Period

Days to Approve 8.15.2011 9.15.2011 10.15.2012 11.15.2011 12.15.2012

2 or less 91% 72% 68% 69% 61%

3 Days 5% 2% 5% 4% 6%

4-5 Days 4% 8% 10% 8% 12%

6-10 Days 0% 12% 12% 7% 17%

11-15 Days 0% 5% 3% 7% 4%

Over 15 Days 0% 1% 2% 5% 0%

Approval Distribution by Period

Budget

3.9

0.8 0.9

3 3.0 3.4 3.0

0.7

0.3 0.1

0.2 0.5 0.6

0.7

4.6

1.1 1.00

3.2 3.5 4 3.7

0

1

2

3

4

5

May 16 -Jun 15

June 15 -July 15

July 16 -August 15

August 16 -September 15

September 16 -October 15

October 16 -November 15

November 16 -December 15

Average Number of Days to Approve Requisitions by Reporting Period (Budget Office and Department of Finance)

Finance(1 Working DayTarget)

Budget(2 Working DayTarget)

3 Working Day Target

Page 7: ReqToCheckStat 12.15.2011

Requisition to Procurement

7

• Processing of Requisition by Bureau of Purchasing

• Status of Requisitions Awaiting Buyer Response

• Time to Convert Requisition to PO

• Status of Requests for Proposals

• Status of Bids

• DBE Compliance (Preliminary Data)

Requisition Procurement

/ DBE

Contract Creation and

Routing

Contract Processing

and Approval Payment

Page 8: ReqToCheckStat 12.15.2011

Source : Obtained from BuySpeed System and Bureau of Purchasing 12.15.2011 and the Bureau of Purchasing 1.4.2012 8

Requisition Procurement / DBE Contract Creation and Routing Contract Processing and Approval Payment

The number of requisitions in queue waiting to be processed by the Bureau of Purchasing increased by 24 despite the significant increase in volume

136 124 130 148 172

791 803 635 629 668 650

794 770

Awaiting BuyerQ

8.15.2011

NewRequisitions

Created8.16 - 9.15

RequisitionsApproved8.16 -9.15

Awaiting BuyerQ

9.15.2011

NewRequisitions

Created9.16 - 10.15

RequisitionsApproved

9.16 -10.15

Awaiting BuyerQ

10.15.2011

NewRequisitions

Created10.16 - 11.15

RequisitionsApproved

10.16 - 11.15

EndingApproval Q11/15/2011

NewRequisitions

Created11.16 - 12.15

RequisitionsApproved

11.16 - 12.15

EndingApproval Q12/15/2011

Requisition Awaiting Buyer Processing for Period Ending 12.15.2011

Status Count

Completed 1/4/2012 110

Contract Being Processed 39

In Process Bureau of Purchasing 18

Waiting for Support 5

Grand Total 172

Status of Reqs Awaiting Buyer Processing

12.15.2011

91% 87% 91% 92%

3% 6% 5% 7% 6% 7% 4% 1%

0%

20%

40%

60%

80%

100%

August 16-September 15

September 16-October 15

October 16 -November 15

November 16 -December 15

7 Days and Over 3-6 Days 0-3 Days * Target

The Bureau of Purchasing converts requisitions to POs in four days of less 90% of the time (Average 550 POs per month)

Page 9: ReqToCheckStat 12.15.2011

Source : Bureau of Purchasing 12.20.2011

9

Requisition Procurement / DBE Contract Creation and Routing Contract Processing and Approval Payment

5

13 13 8

7 4

3

7 3

7

Ending Bid Q10.15.2011

New Bid RequestsReceived

10.16 - 11.15

Bid ProceduresCompleted

10.16 -11.15

Ending Bid Q11.15.2011

New Bid RequestsReceived

11.16 - 10.15

Bid ProceduresCompleted

11.16 -12.15

Ending Bid Q12.15.2011

The number of Bids in process increased from 16 to 20 as of 12.15.2011

Waiting Opening Date

Waiting Information From Department

Total 13 Total 16

Total 20

56% 56% 52% 50%

44% 44% 45% 47%

3% 3%

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

8.15.11 - 9.15.11 Cumulative (8.15.11-10.15.11 )

Cumulative (8.15.11-11.15.11 )

Cumulative (8.15.11-12.15.11 )

10 andAbove

4 to 9

3 and below

Number of Proposals Received for Bids completed (8.15.2011 - 12..15.2011)

Aviation Board Fire Alarm

Aviation Board Airport Waste Removal

Aviation Board High Speed Runway Sweeper Vehicle

Aviation Board High Pleasure Water Paint

Capital Projects NOFD Engine 10

Capital Projects Joe Brown Center

Fire Spectrophotometer

EMD CBRN Vehicle

NOPD Robot

NOPD Light Towers

DPW Asphalt Pavement Services

DPW Concrete Pavement

DPW Press Drive

12.15.2011

Waiting on Support / Response from Departments

Page 10: ReqToCheckStat 12.15.2011

Source : Bureau of Purchasing 12.20.2011 10

Requisition Procurement / DBE Contract Creation and Routing Contract Processing and Approval Payment

25%

46% 38% 38%

38%

31% 31%

38%

38% 23%

31% 24%

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

8.15.2011 -9.15.2011

Cumulative (8.15.2011-10.15.2011 )

Cumulative (8.15.2011-11.15.2011 )

Cumulative (8.15.2011-12.15.2011 )

10 andAbove

4 to 9

3 andbelow

Number of Proposals Received for RFPs completed (8.15.2011 - 12.15.2011)

Department RFP Opened Description

Economic Development 10/31/2011New Orleans East Redevelopment

Opportunity

Economic Development 11/4/2011Economic Development Fund (EDF)

Administrative Services

EMD 6/10/2011 Fleet Management: On Hold

Aviation 9/16/2011 Financial Consulting Services

Awaiting Committee Meeting

Department

Finance

Finance

Aviation Board

Aviation Board

Aviation Board

Aviation Board

Aviation Board

DPW

DPW

ITI

Economic Development

Law Department

Payroll, Time & Attendance, and Human Resource Hosted Software Services

Online Auction Services - New Orleans East Redevelopment

Assorted Professional Legal Services

Terminal Mgmt Financial Feasibility

Waiting For Department Specifications or Support

Collection of Sanitation Fees

Property Land Use

Environmental Study

Design Services for Long Term Airport Development

Healthcare Revenue Maximizing Services

BRAC Community Based Usage

Curbside Management Enforcement

Project Management Services for Long Term Airport Development

Description

6 2

6

7

7 3

10

9 5

4

1 6 12

Ending RFP Q10.15.2011

New RFP RequestsReceived

10.16 - 11.15

RFP ProceduresCompleted

10.16 -11.15

Ending RFP Q11.15.2011

New RFP RequestsReceived

11.16 - 12.15

RFP ProceduresCompleted

11.16 -12.15

Ending RFP Q12.15.2011

The number of RFPS in process increased to 22 as 12.15.2011

Waiting Committee Meeting

Waiting Opening Date

Total 14

Total 18 Waiting Information From Department

Total 22

Page 11: ReqToCheckStat 12.15.2011

11

Requisition Procurement / DBE Contract Creation and Routing Contract Processing and Approval Payment

Source : Office of Supplier Diversity 1/17/2012

The cumulative percentage of DBE award value continues to climb, but is slightly shy of the 35% goal (Preliminary Data)

Note: Information herein is preliminary. The Office of Supplier Diversity is currently working on finish gathering this data.

68,621,515

16% 15% 28% 28% 28% 26% 23% 22% 22% 25%

29%

32%

-

10,000,000

20,000,000

30,000,000

40,000,000

50,000,000

60,000,000

70,000,000

80,000,000

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

35% Target

DBE Award for Bids and RFP opened in 2011. Cumulative DBE Percentage by Period Per Estimated Contract Value

Page 12: ReqToCheckStat 12.15.2011

Contract Package Routing

12

• Average Contract Routing Time

Requisition Procurement /

DBE Contract Creation

and Routing

Contract Processing and

Approval Payment

Page 13: ReqToCheckStat 12.15.2011

Source : ECMS 12.15.2011

13

Requisition Procurement / DBE Contract Creation and Routing Contract Processing and Approval Payment

Average time to approve contracts being routed almost doubled from the previous period. Still, average time remains below target

0.6 0.6 0.50 0.22

1.95 0.8 0.2 0.20

0.22

0.63

0.2

0.5 0.60 1.3

0.69

1.1

0.5 0.75

0.27

0.70

2.7

1.75 2.05 2.01

3.97

0

1

2

3

4

5

8/15/2011 9/15/2011 10/15/2011 11/15/2011 12/15/2011

Average Approval Time of Contracts by Approval Level in Days (by period) CAO (1 daytarget)

Civil Service (1day target)

Finance (1 daytarget)

Bureau ofPurchasing (1day target)

4 day agregate target

Days to Approve 8.15.2011 9.15.2011 10.15.2011 11.15.2011 12.15.2012

0-1 Days 83% 91% 79% 94% 88%

2- 3 Days 7% 7% 15% 6% 2%

4-7 Days 8% 0% 6% 0% 10%

Over 8 Days 2% 2% 0% 0% 0%

Days to Approve 8.15.2011 9.15.2011 10.15.2011 11.15.2011 12.15.2012

0-1 Days 90% 95% 100% 98% 98%

2- 3 Days 8% 4% 0% 2% 2%

4-7 Days 2% 1% 0% 0% 0%

Over 8 Days 0% 0% 0% 0% 0%

Finance Distribution Approval

CAO Distribution Approval

Days to Approve 8.15.2011 9.15.2011 10.15.2011 11.15.2012 12.15.2011

0-1 Days 93% 89% 97% 73% 83%

2- 3 Days 7% 10% 3% 26% 17%

4-7 Days 0% 1% 0% 1% 0%

Over 8 Days 0% 0% 0% 0% 0%

Days to Approve 8.15.2011 9.15.2011 10.15.2011 11.15.2012 12.15.2011

0-1 Days 93% 86% 94% 96% 69%

2- 3 Days 5% 13% 5% 4% 9%

4-7 Days 2% 1% 1% 0% 17%

Over 8 Days 0% 0% 0% 0% 5%

Civil Service Distribution Approval

Bureau of Purchasing Distribution Approval

Page 14: ReqToCheckStat 12.15.2011

Contract Approval Process

14

• Contract Rejections

• Contract Processing and Approval

Requisition Procurement /

DBE Contract Creation

and Routing

Contract Processing and

Approval Payment

Page 15: ReqToCheckStat 12.15.2011

15

Requisition Procurement / DBE Contract Creation and Routing Contract Processing and Approval Payment

Source : Law Department 12.15.2011 and ECMS System

Number of contracts rejected/returned during the period remain under 10

Note: 9 items were rejected during the period. However, the rejections were the result of multiple reasons.

18

9

31

8 9 9

0

10

20

30

40

7.15.2011 8.15.2011 9.15.2011 10.15.2011 11.15.2012 12.15.2013

Contracts Returned / Rejected by Approval Level or Law Department by Period (in units)

5

2 3 3

0

1

2

3

4

5

6

TaxClearance

CorporateResolution

DBE Form ExpiredContract

CorporateResolution

RequisitionProblem

Vendor ID Missing Supportand Other

Reasons for Contracts Returned or Rejected by Either Approval Level or Law Department 11.15.2011 - 12.15.2011

Department Total

Blight / Code Enforcement 2

Finance 3

Library 1

NORD 1

Property Management 1

Neighborhood Rev. 1

Grand Total 9

12.15.2011

Page 16: ReqToCheckStat 12.15.2011

16

Requisition Procurement / DBE Contract Creation and Routing Contract Processing and Approval Payment

Contracts: All Contracts in Process as of 12.15.2011 (Legal Review, CAO, Vendor Signature, City Attorney, Executive Council, Mayor/City Council)

Source : Law Department 12.15.2011 and ECMS System

161 154 151 133

109

40 47

90 93 81 99

39 63

0

50

100

150

200

250

300

8.15.2011 NewContractsReceived

ContractsCompleted

9.15.2011 NewContractsReceived

ContractsCompleted

10.15.2011 NewContractsReceived

ContractsCompleted

11.15.2011 NewContractsReceived

ContractsCompleted

12.15.2011

All Contracts Processed, Received and in Q at the End of the Reporting Period as of 12.15.2011 (in units)

216 Contracts

as 3.15.2011

Page 17: ReqToCheckStat 12.15.2011

17

Requisition Procurement / DBE Contract Creation and Routing Contract Processing and Approval Payment

Contracts : All Contracts in Process as of 12.15.2011 (Legal Review, CAO, City Attorney, Executive Counsel, Mayor/Council Approval)

Source : Law Department 12.15.2011 and ECMS System

81 71 37

74 69 43

32 59

64 14 26

25

17 13

37 41 12

13

14 7 8 16 12

6

13 11 8 6

14 22*

0

50

100

150

200

250

300

7.15.2011 8.15.2011 9.15.2011 10.15.2011 11.15.2011 12.15.2012

Over 120 Days

91 - 120 Days

61 - 90 Days

31- 60 Days

0 - 30 Days

The average age of contracts awaiting processing increased to 64 days

Total 157 Average Days 53

Total 161 Average Days 46

Total 154 Average Days 55

Total 151 Average Days 50

216 Contracts 64 Average

Days 3.15.2011

Total 133 Average Days 46

Total 109 Average Days 64

*2 of the 22 contracts in the over 120 category were submitted for processing before 4.12.2011

57 57 54 45

60

39

- 10 20 30 40 50 60 70

7.15.2011 8.15.2011 9.15.2011 10.15.2011 11.15.2012 12.15.2013

The average time to close contracts during the period has been reduced from 66 as of 3.15.2011 to 39 days as of 12.15.2011 (in days)

66 Days 3.15.2011

Page 18: ReqToCheckStat 12.15.2011

18

Requisition Procurement / DBE Contract Creation and Routing Contract Processing and Approval Payment

Source : ECMS System 12.15.2011

36 ECMS contracts are awaiting vendor signature as of as of 12.15.2011 and have been waiting an average of 22 days since they arrived to this stage

1

23

2

36

15

0 Days 27 Days

0 Days 22 Days 17 Days

0

5

10

15

20

25

30

0

5

10

15

20

25

30

35

40

Law Approval Attorney Deputy CityAttorney

CAO Vendor Signature Executive Counsel

Un

its

Un

its

Avg Age at this stage

Contracts in Queue and Average Age of Contracts Since Arriving to Each Level as of 12.15.2011

* Total of 77 herein only relates to contracts routed using ECMS (Electronic Routing System).

Page 19: ReqToCheckStat 12.15.2011

19

Source : Law Department 12.15.2011 and ECMS System

Requisition Procurement / DBE Contract Creation and Routing Contract Processing and Approval Payment

Contracts : All Contracts Closed between 11.16.2011 and 12.15.2011 (Legal Review, CAO, City Attorney, Executive Counsel, Mayor/Council Approval)

(69) (61)

(81) (67)

(57) (70)

(59)

31 39

19 33

43 30

41

(100)

(80)

(60)

(40)

(20)

-

20

40

60

3.15.2011 7.15.2011 8.15.2011 9.15.2011 10.15.2011 11.15.2012 12.15.2013

Completed in 30 days Completed after 30 days

41% of all contracts closed during the period were completed in 30 days or less, compared to 30% in the prior period

%

41% of all contracts closed during the period were completed in 30 days or less, compared to 30% in the prior period

Page 20: ReqToCheckStat 12.15.2011

The check: Accounts payable

20

• General Fund Payments

• Processing by Accounts Payable

• Payment from Invoice Date

• Capital and Grants Expenditure Payments

• Processing by Accounts Payable

• Payment from Invoice Date

• Detail Review (invoices in the pipeline)

• CDBG Invoice Payments

• DPW Payments

• DPW Revolver Payments

• Capital Projects Payments

• Capital Projects Revolver Payments

Requisition Procurement Contract Creation

and Routing

Contract Processing and

Approval Payment

Page 21: ReqToCheckStat 12.15.2011

21

Requisition Procurement / DBE Contract Creation and Routing Contract Processing and Approval Payment

Source :Accounts Payable and Office of Performance and Accountability. Collected 11.20.2011

The percentage of General Fund (and agency) payments processed in 7 days or less decreased to 37%.

90% 83% 87%

63% 67% 56%

37%

10% 17% 13%

34% 32%

23% 40%

1%

11% 23%

3% 8%

0%

20%

40%

60%

80%

100%

6/15/2011 7/15/2011 8/15/2011 9/15/2011 10/15/2011 11/15/2011 12/15/2011

Working Days to Process General Funds and Agencies Check Payments by A/P Office for periods ending 6.15.2011 to 12.15.2011 (in %)

Sample 270 selections 95% confidence level +-5

Over 30 Days

16 - 30 Days

8-15 Days

7 Days or less

4 5 5

7 6

11 11

0

2

4

6

8

10

12

6.15 7.15 8.15 9.15 10.15 11.15 12.15

Average Number of Days to Process Invoices by A/P Department (GF Expenditures)

Page 22: ReqToCheckStat 12.15.2011

22

Requisition Procurement / DBE Contract Creation and Routing Contract Processing and Approval Payment

Source :Accounts Payable and Office of Performance and Accountability. Collected 12.20.2011

The percentage of General Fund (and agency) payments in 30 days or less decreased to 46% in the current period

64% 57% 57% 58% 60% 50% 46%

18% 26% 26% 25% 27% 28% 36%

10% 9% 10% 13% 7% 17% 10%

8% 8% 7% 4% 6% 5% 9%

0%

20%

40%

60%

80%

100%

6/15/2011 7/15/2011 8/15/2011 9/15/2011 10/15/2011 11/15/2011 12/15/2011

Percentage of Payments in Days From Invoice Date to Payment for General Fund (or Agency) Expenditures for Periods Ending

6.15.2011 to 12.15.2011 (in %) Sample 270 selections 95% confidence level +-5

Over 121 Days

61 - 120 Days

31 to 60 Days

30 Days or Less

40 41 39 40 39 45 48

0

20

40

60

6.15 7.15 8.15 9.15 10.15 11.15 12.15

Average Number of Days to Pay Invoices From Invoice Date (GF Expenditures)

Target 30 Days

Page 23: ReqToCheckStat 12.15.2011

23

Requisition Procurement / DBE Contract Creation and Routing Contract Processing and Approval Payment

Source :Accounts Payable and Office of Performance and Accountability. Collected between 12.15.2011 and 1.10.2012

General Fund and Agencies: Multiple reasons appear to be the cause of invoices being paid in more than 60 days from invoice date (findings from sample (270) selection made during the current reporting period)

Department Dispute with the

vendor

Goods were received later /

Services were not rendered /

Invoice not received timely

Invoice was not processed

timely /Invoice was

misplaced

Contract was being

processed Other (Explain)

Total From

Sample

Aviation 1 4 5

Library 1 1 1 3

NORDC 1 3 4

Safety and Permits 1 2 1(*) 4

Sanitation 1 4 5

Total 3 3 14 0 1 21

(*) Vendor did not received payment. A new check had to be issued.

Over 60 days From Invoice Date Payments from Sample

Page 24: ReqToCheckStat 12.15.2011

The percentage of capital and grant payments processed in 7 days or less remains at over 95%

24

Requisition Procurement / DBE Contract Creation and Routing Contract Processing and Approval Payment

Source :Accounts Payable and Office of Performance and Accountability. Collected 11.20.2011

96% 89% 96% 99% 97% 98% 97%

4% 7% 1%

1% 2% 3% 4%

1% 2%

3%

0%

20%

40%

60%

80%

100%

6/15/2011 7/15/2011 8/15/2011 9/15/2011 10/15/2011 11/15/2011 12/15/2011

Working Days to Process Capital Expenditures and Grants Check Payments by A/P Office for periods ending 6.15.2011 to 12.15.2011 (in %)

Sample 100 selections 90% confidence level +--10

Over 30 Days

16 - 30 Days

8-15 Days

7 Days or less

2

4 3

1 2 2 2

0

2

4

6

6.15 7.15 8.15 9.15 10.15 11.15 12.15

Average Number of Days to Process Invoices by A/P Department (Capital and Grant Expenditures)

Page 25: ReqToCheckStat 12.15.2011

25

Requisition Procurement / DBE Contract Creation and Routing Contract Processing and Approval Payment

The Percentage of capital and grant payments made in 30 days or less from invoice date decreased to 49 % from 53% in the prior period

Source :Accounts Payable and Office of Performance and Accountability. Collected 11.20.2011

58% 62% 45%

60% 67% 53% 49%

16% 24%

26% 23% 12%

25% 29%

14% 4%

22% 10% 15% 14% 8%

12% 10% 7% 7% 6% 8% 15%

0%

20%

40%

60%

80%

100%

6/15/2011 7/15/2011 8/15/2011 9/15/2011 10/15/2011 11/15/2011 12/15/2011

Percentage of Payments in Days From Invoice Date to Payment for Capital and Grant Expenditures for Periods Ending

6.15.2011 to 12.15.2011 (in %) Sample 100 selections 90% confidence level +-10

Over 121 Days

61 - 120 Days

31 to 60 Days

30 Days or Less

59

38

47 50

40

50 57

0

10

20

30

40

50

60

70

6.15 7.15 8.15 9.15 10.15 11.15 12.15

Average Number of Days to Pay Invoices From Invoice Date (Capital and Grant Expenditures)

Target 30 Days

Page 26: ReqToCheckStat 12.15.2011

26

Requisition Procurement / DBE Contract Creation and Routing Contract Processing and Approval Payment

Source :Accounts Payable and Office of Performance and Accountability. Collected between 12.15.2011 and 1.10.2012

Capital and Grant Expenditures : Multiple reasons appear to be the cause of invoices being paid in more than 60 days from invoice date (findings from sample (100) selection made during the current reporting period)

Department Dispute with the

vendor

Goods were received later /

Services were not rendered /

Invoice not received timely

Invoice was not processed

timely /Invoice was

misplaced

Contract was being

processed Other (Explain)

Total From

Sample

DPW 3 2 (**) 5

Health 2 (****) 2

Homeland Security 3(***) 3

Mosquito 1 5 1(*) 7

OCD 5 2 7

Total 6 7 3 8 24

(*) Mosquito cut from general budget and had to wait until access was reestablished

(**) CDBG disallowed expenditures included in invoice. Have to wait until problem was resolved

(***) Funding from GOHSEP not received which delayed the payments

(****) Vendor send invoice to the wrong location. Invoice exceeded requisition amount and a new PO had to be created to authorize payment

Over 60 days From Invoice Date Payments from Sample

Page 27: ReqToCheckStat 12.15.2011

A number of old CDBG invoices remain unpaid because of contracts currently being processed

Information obtained from Quickbase maintained by Hagerty Consulting 12.15.2011 27

Requisition Procurement / DBE Contract Creation and Routing Contract Processing and Approval Payment

Over 60

days

Over 30

days

Process Before June June July August September October November December

PM to Owning Department 1 1 3 1 1

Owning Dep. Review and Approval 1 1

Owning Dep. To Accounting 1 1 2

Approved by Accounting 1

Accounting to OCD Fiscal Unit

OCD Fiscal to State Consultant 1

State Consultant to State DRU

State DRU to State Finance 3 16 11

State Finance to City's Account 11 26 1

Payment Clears City Bank 3 1

Reasons for Delay

Dispute with the vendor 1

Invoice was misplaced/Not

processed timely

Waiting on Acct. to release funds 5 8 3

Contract/Amendment being

processed 2 1 1 3 1 1 1

Awaiting Reimbursement from State 3 28 10

Paid 10 6 3

Location of Invoices that Remain Outstanding

100% 98% 98% 96%

76%

38%

0%

June July August September October November December

Invoices Paid as a % of Invoices Received per Month as of 12.15.2011

(invoices received during the month) Avg 84 invoices per Mon

Page 28: ReqToCheckStat 12.15.2011

28

Requisition Procurement / DBE Contract Creation and Routing Contract Processing and Approval Payment

Information obtained from Quickbase (DPW Department) 12.15.2011

Over 60 days

Over 30 days

A significant number of DPW (City) invoices received over 60 days ago remain unpaid. Most of these exceptions are the result of contracts currently being processed

* Does not include operational invoices

Process Before June June July August September October November December

DPW to PM

PM to Approve 9 1 2 3 2 1 2 1

PM Approval to DPW Fiscal 1

DPW Fiscal to Create Receiver 2 1 2 1 3 5 3

Receiver Creation to Finance

City to Cut Check 1 2

City Check to be Release

Reasons for Delay Dispute with the vendorGoods Received at a Later date later / Services were

not rendered

Invoice was misplaced / Not processed timely Contract being processed 12 2 4 3 2 1

Other Plan Change Needed 1 2

Paid 1

Location of Invoices that Remain Outstanding

93%

78% 82% 85% 81%

67%

25%

June July August September October November December

Invoices Paid as a % of Invoices Received per Month as of 12.15.2011(invoices received during the month) Avg 20 invoices per Mon

Page 29: ReqToCheckStat 12.15.2011

Information obtained from Quickbase (DPW Department) 12.19.2011 29

Requisition Procurement / DBE Contract Creation and Routing Contract Processing and Approval Payment

Over 60 days

*Project cost overruns have surpassed the FEMA obligated amount. DPW is working with FEMA to increase the PW obligated amount in order to process these payments. **Additional projects with outstanding invoices to be added to next ReqtoCheck

A significant number of DPW (revolver) invoices received over 60 days ago remain unpaid. Some of the problems relate to cost overruns surpassing FEMAS obligated amount

Over 30 days

64%

0% 0%

38%

0% N/A 0%

June July August September October November December

Invoices Paid as a % of Invoices Received per Month as of 12.15.2011 (invoices received during the month) Avg 11invoices per Mon

Process Before June June July August September October November December

DRC Receipt to Transmittal to DPW 1

Transmittal to DPW to Receipt in DPW

Receipt in DPW to Project Manager

PM to Approve

PM to Approve to DPW Fiscal 3 3 12 5 3

DPW Fiscal to Create Receiver 2 1

Receiver Creation to DPW Approval

DPW Approval to Finance

Finance to Receive

Finance to Send to State

State to Send to Hancock Bank

Hancock Bank to Send Check Copy

Reasons for Delay

Dispute with the vendorGoods Received at a Later date later / Services were

not rendered

Invoice was misplaced / Not processed timely

Contract being processed 1

Other* 2 3 3 12 5 3

Paid

Location of Invoices that Remain Outstanding

64%

0% 0%

38%

0% N/A 0%

June July August September October November December

Invoices Paid as a % of Invoices Received per Month as of 12.15.2011(invoices received during the month) Avg 11invoices per Mon

Page 30: ReqToCheckStat 12.15.2011

Capital Projects maintains good track record of paying invoices on time.

30

Requisition Procurement / DBE Contract Creation and Routing Contract Processing and Approval Payment

Information obtained from Quickbase (Capital Projects Department ) 12.15.2011

Over 60

days

Over 30

days

Process Step Before June June July August September October November December

PM To Approve

CPA to Create Receiver 1

CPA to Finance 1 1

Finance to Receive 3

City to Cut Check 1 4 3

City Check Cut to Release 3

Reasons for Delay

Dispute with the vendor

Goods Received at a Later date

later / Services were not rendered

Invoice was misplaced / Not

processed timely

Contract being processed

Other 1(*) 1(**)

Paid 1 4 10

(*) Problem AFIN Address did not match Invoice. Could not process

(**) Technical problem using the system from the vendor

Location of Invoices that Remain Outstanding

100% 100% 100% 95%83%

71%

100%

June July August September October November December

Invoices Paid as a % of Invoices Received per Month as of 12.15.2011(invoices received during the month) Avg 28 invoices Mon.

Page 31: ReqToCheckStat 12.15.2011

Capital Projects invoices paid through the revolver have been paid on time with the exception of a few outliers due to disputes with the vendor

Information obtained from Quickbase (Capital Projects Department ) 12.15.2011

31

Requisition Procurement / DBE Contract Creation and Routing Contract Processing and Approval Payment

Over 60

days

Over 30

days

Process Before May June July August September October November December

PM To Approve 3

CPA to Create Receiver

CPA to Finance 1 1

Finance to Receive 1

Finance to Send State

State to Send to Hancock Bank 3 5 8

Hancock Bank to Send Check Copy

Reasons for Delay

Dispute with the vendor 4

Goods Received at a Later date

later / Services were not rendered

Invoice was misplaced / Not

processed timely

Contract being processed

Other 1(*)

Paid 3 5

(*) Problem AFIN Address did not match Invoice. Could not process

Location of Invoices that Remain Outstanding

100% 100% 100% 97%89% 81%

0%

June July August September October November December

Invoices Paid as a % of Invoices Received per Month as of 12.15.2011(invoices received during the month) Avg 31 invoices per Mon

Page 32: ReqToCheckStat 12.15.2011

Procurement Requisition

Contract Creation

and Routing

Contract

Processing

and Approval

Payment

Supplemental

Procurement

32

Page 33: ReqToCheckStat 12.15.2011

33