Republic of the PhilippinesDepartment of Agriculture
PROPOSED BREAKWATER PROJECT
ILOILO FISH PORT COMPLEX
ILOILO RIVER
ILOILO STRAIT
QUAYSIDE
BREAKWATER, 470 m
DAMAGED REVETMENT
WAVE DIRECTION BROUGHT BY SOUTHWEST MONSOON & INCLEMENT WEATHER
EXISTING BREAKWATER
386 m
250
m
WAVE DIRECTION BROUGHT BY SOUTHWEST MONSOON & INCLEMENT WEATHER
130 m
PROPOSED CONSTRUCTION OF NEW BREAKWATER
65 m.
86 m.
250 m.
350 m.
130 m.
ILOILO
FISHPO
RT C
OM
PLEX
PROPOSED BREAKWATER
(PHASE I)SITE DEVELOPMENT PLAN
EXISTING BREAKWATER
PROPOSED CONTRUCTION OF IFPC BREAKWATER (PHASE I)
100
m.
99 m.
PROJECT : CONSTRUCTION OF BREAKWATER AT ILOILO FISH PORT COMPLEX (PHASE 1 )
LOCATION: BRGY TANZA, ILOILO CITY
TYPE : CONCRETE BLOCKSSCOPE OF WORKS ESTIMATED COST
1. CONSTRUCTION OF BREAKWATER 35,456,310.68
ESTIMATED DIRECT COST PHP 37,044,939.71
PLUS :
MARK-UP ................................... 17% 6,297,639.75
VAT ........................................... 12% 5,201,109.54
TOTAL CONSTRUCTION COST PHP 48,543,689.00
PLUS :
ADMINISTRATIVE/ENG’G SERVICES..... 1% 485,436.89
BUDGET CONTINGENCY...................... 2% 970,873.78
TOTAL PROJECT COST PHP 50,000,000.00
TOTAL LENGHT IN METER 98.73
COST PER LINEAR METER PHP 506,428.98
PRE-CONSTRUCTION IMPLEMENTATION SCHEDULE
PROJECT BUDGETARY COST CONTRACT DURATION1. Construction of IFPC Breakwater (Phase I) PHP 50.00 M. 300 Calendar Days
ACTIVITY PERIOD1. Pre-Procurement Conference May 2, 2012
2. Publication/Posting of Invitation to Bid/Letter of Intent May 14 – 18 , 2012
3. Issuance of Bid Documents May 14 – 25 , 2012
4. Pre-bid Conference May 29, 2012
5. Submission/Bid Opening June 11, 2012
6. Evaluation of Bids June 13 – 20 , 2012
7. Post -qualification June 21 - 29 , 2012
8. Recommend Award to the PFDA Board of Directors 1st week of July 2012
9. Approval of Resolution/ Issuance of Notice of Award July
10. Contract Preparation and Signing July
11. Issuance of Notice to Proceed July
12. Construction Period August 2012 to May 2013
IFPC HARBOR BASIN TAKEN SEPT. 28, 2011
EXISTING BREAKWATER