REPUBLIC OF IRAQ - World Bank€¦ · 14/03/2016  · According to the hydro-geological...

121
1 REPUBLIC OF IRAQ Ministry of Construction, Housing, Municipalities & Public Works Emergency Operation Development Projects (EODP) (P155732) Environmental and Social Management Plan (ESMP) For the AL-AWJA - OWAINAT WATER TREATMENT PLANT IN SALAH AL- DIN GOVERNORATE February, 12, 2017 SFG2336 V6 Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized

Transcript of REPUBLIC OF IRAQ - World Bank€¦ · 14/03/2016  · According to the hydro-geological...

  • 1

    REPUBLIC OF IRAQ

    Ministry of Construction, Housing, Municipalities & Public Works

    Emergency Operation Development Projects (EODP)

    (P155732)

    Environmental and Social Management Plan (ESMP)

    For the

    AL-AWJA - OWAINAT WATER TREATMENT PLANT IN SALAH AL-

    DIN GOVERNORATE

    February, 12, 2017

    SFG2336 V6P

    ublic

    Dis

    clos

    ure

    Aut

    horiz

    edP

    ublic

    Dis

    clos

    ure

    Aut

    horiz

    edP

    ublic

    Dis

    clos

    ure

    Aut

    horiz

    edP

    ublic

    Dis

    clos

    ure

    Aut

    horiz

    ed

  • 2

    Revision History

    Version Revision

    Date

    Description or

    Reason for Change

    Discipline

    Review

    Director

    Review Approval

    Prepared by: Tatyana Gorskaya

    Contributors:

  • 3

    EXECUTIVE SUMMARY

    Introduction

    This Environmental and Social Management Plan (ESMP) is prepared in accordance to the

    Terms of Reference for Al-Awja - Owainat Water Treatment Plant, Salah Al-Din

    Governorate within the framework of Emergency Operation for Development Project

    (EODP) (P155732) (IBRD Loan No.: 8520). According to the World Bank environmental

    safeguards the project is categorized as Category B.

    Project Description

    The project is located in the city of Tikrit, Salah Al-Din Governorate, approximately 140

    km north of Baghdad.

    Figure 1: Administrative Project Location

    Output of the water treatment plant in 2200 m3/day for 22 hour operation per day; 1000

    m3/hr.

  • 4

    The project consists of the following components:

    Intake stricture.

    Low lift pumps.

    Sedimentation tank (2).

    Filter tanks (6)

    Alum system

    Chemical building

    Chlorine system

    High lift pump station

    Motor Control Center (MCC) building

    Ground reservoir

    Supervisory control and data acquisition (SCADA) system.

    At present, the facilities are destroyed conditions and in completely non-operational

    condition.

    Figure 2: Present Condition of the Facilities

    The area have received clearance from the Iraqi Armed Forces for the absence of

    UXO/REW, however, accidental discovery is still possible. In case of the discovery, the

    personnel should be immediately evacuated and armed forces contacted. The works could

    be resumed only after removal of the munitions.

  • 5

    The project will require a Main Camp, the operational center, with prefabricated offices

    and parking areas for administration and technical staff. This will also include areas for

    materials testing and storage, and equipment cleaning and maintenance. The need for

    residential accommodation is likely to be relatively minor. The accommodation at the camp

    will be required for the security guards, 2 persons. The construction camp should have

    independent sources of water and electricity, and the septic tank for the residential effluent

    disposal. The construction camp will be located on the state-owned land within the

    perimeter of the existing water pumping station.

    The personnel requirements for the project are 47 persons including administrative staff,

    technical staff, qualified construction crew and unskilled labor. All workers will be locally

    hired.

    The project comprises the rehabilitation of the existing facilities with no additional

    structures or pipelines to be constructed. Therefore, the project will not require any

    permanent or temporary land acquisition. As a result OP 4.12 will not be applied.

    The total project duration is 6 months. The main goal of the project is the rehabilitation of

    facilities for the provision of the potable water. The project is expected to provide drinking

    water to approximately 35000 local residents and IDPs. At present, the residents rely

    almost exclusively on the water delivered by water tankers for drinking purposes which

    poses additional financial burden on household.

    Work consists of a simple civil works such as cleaning work and raise dirt debris resulting

    from combat operations and rehabilitation of all the damaged civil buildings such as Intake,

    Sedimentation Tank, Filtration Building, Storage Tank, MCC Building and services

    buildings and repainting buildings and replace and renovating pipes, bathrooms, doors,

    windows and re-paving of internal roads and treatment of cracks in the sedimentation tank

    and Storage Tank.

  • 6

    Most of the works in this project are the electrical and mechanical works include supply,

    installation, and operation of the pumps, electric transformers, electric generator and the

    replacement of cables and outdoor lightings.

    The intake structure shall be constructed from reinforced concrete. The pump sump

    (Basement) shall be designed as a water tight structure in two compartments for

    independent operation during maintenance with bypass arrangement controlled by a 2 Nos.

    sluice valves. The floor of the (Basement) shall be sloped to one corner with a sump to

    pump accumulated settled sludge to the river using duplicated submersible pumps. The

    Basement shall have access ladder and lighting. The channel from river to the intake

    Basement shall be constructed according to the drawing from reinforced concrete the

    contractor is responsible to make a full hydraulic study to design the final shape of the

    channel. Rip-raping along the shoulder of the river for a distance of 50m from each side of

    the channel to protect the structure and to direct the water to the channels. The necessary

    arrangements are to be made to minimize the problem of settling of the suspended matter

    at the channel bar during high turbidity seasons by using submerged scraping device.

    The breakdown of duration of project activities is presented in the Table below:

    Table 1: Duration of Construction Activities

    # Activity Duration (man days)

    1 Cleaning post-combat debris 75

    2 Construction of the intake structure 75

    3 Rehabilitation of Intake Structure 60

    4 Rehabilitation of sedimentation tank 60

    5 Rehabilitation of filtration facilities 60

    6 Rehabilitation of storage tank 60

    7 Rehabilitation of MCC building 60

    8 Rehabilitation of service building 60

    9 Replacing of pipes 35

    10 Repair and paving of roads within the facility 14

    11 Installation of doors and windows 28

    11 Painting 38

  • 7

    # Activity Duration (man days)

    12 Electrical and mechanical works 42

    Baseline Conditions

    The project is located in the city of Tikrit, Salah Al-Din Governorate, Iraq. The project

    location is approximately 140km north of capital city of Baghdad. The project is located

    directly on the bank of the Tigris River. The area is void of residential settlements,

    industrial facilities and predominantly used for livestock grazing and limited rain-fed crop

    cultivation during rainy periods.

    Regional Geology, Topography and Seismic Activity

    Stratigraphically, the project area is dominated by geological formations ranging from

    Middle Miocene to Quaternary. In the project location the geological formation is

    composed of thin-bedded, black bituminous limestone, dolomitic limestone and black

    papery shale with streaks of thin black chert. The terrain is characterized as flat to gently

    rolling plains, hills, and mountains. In the project area the elevations are ranging between

    300-550 m asl. The maximum elevation is 543.5 m asl and the minimum elevation is 313.9

    m asl.

    The project area is located in the minor damage zone with the seismic activity of I-II on

    MM scale.

    Water Resources

    According to the hydro-geological classification of Iraq, the project area is located in the

    Low Fold hydro-geological zone. The Low Fold zone is filled by sedimentary formations

    that range in age from Late Miocene to Recent: Fatha, Injana, Mukdadiyah and Bai Hassan,

    and Quaternary cover. These formations represent the main aquifers in this zone. The

    general trend of the groundwater movement is mainly from north and northwest towards

    south and southeast.

    The groundwater quality in the project area is slightly brackish with the salinity of 1000-

    3000 ppm. The groundwater depth in the project area ranges from 10-20 m below surface.

  • 8

    The area consists of potentially fertile soils characterized as heavy alluvial soils, with some

    organic content and a high proportion of clays. The soil classification is 68.4% silty loam,

    20.9% silty clay loam and 10.7% is clay soil. The river bed is composed of fine sand, silt

    and clays with rather high sedimentation load.

    Climate

    The climate in the project area is characterized as Mid-steppe and desert climate. The

    average temperature is 22.2°C. The warmest month, on average, is July with an average

    temperature of 35°C. The coolest month on average is January, with an average

    temperature of 9.4°C. The average amount of precipitation per year is 348 mm per year.

    The predominant wind direction is Northeast in the months November through to April,

    and predominantly north-west in the months May-October. The mean average wind speed

    is 10-12 km/h with the wind gusts reaching up to 26-28 km/h.

    Ambient Air Quality and Noise

    At present, there is no information on ambient air quality in the project area; no

    measurements on air quality were performed previously. The roads in the area are mostly

    rural unpaved roads and roads in rather bad conditions partially destroyed due to the war

    conditions in recent years. The main source of pollution is dust generated through the

    agricultural activities and use of the rural roads in addition to the dust generated by windy

    conditions during dry periods. Potentially, there might be the additional air pollution from

    the operating oil fields and/or refineries.

    Similarly, no information on noise levels is available for the project area. However, the

    noise level in the rural area with limited vehicle movement and limited agricultural

    activities is not a significant issue.

    Biological Environment

    The project area is located in the Mesopotamian shrub desert terrestrial eco-region

    considered as a transitional zone between the Syrian Desert and steppe region further north.

    This terrestrial eco-zone is categorized as vulnerable and due to the security concerns have

    received little focused study.

  • 9

    Vegetation reflects the Mesopotamian province of the Irano-Turanian eco-region and is

    characterized by the dominance of the drought-tolerant low shrubs with a variety of grasses

    and legumes.

    The area of the project is located in a general area identified as a fly-way route for

    migratory birds from Eastern Europe and West Siberia to Mesopotamia and Africa.

    The riparian vegetation predominantly comprises reeds and rushes that grow in the wetland

    areas and poplars, willows and tamarisk trees along river channels, banks, and beside

    irrigation ditches throughout the country. The freshwater habitats of the marshlands, which

    are part of the Tigris‐Euphrates River Eco-region, are surrounded by desert xeric shrub

    lands and therefore are considered as important corridors for the wildlife.

    The project area is located in a close proximity to the Important Bird Area (IBA) –

    Samarrah Wetland, approximately 2.5-3 km north of the IBA. No conservation practices

    are exercised in the project area apart from the control of hunting to the extent they are

    controlled and monitored throughout the country.

    Socio-Economic Environment

    The total population of the Salah Al-Din Governorate is 1.5 million people, the population

    of Tikrit is approximately 160,000. The main demographic indicators are:

    Population growth rate is 2.6%, according to the available statistics until 2014;

    Age category of less than 15 years is 40% in 2012; the category of 15- 64 years of

    age is %56.9 in 2012.

    Population percentage in the urban areas is 69%, rural population was 31% for

    2014.

    Economic activity in Salah Al-Din is centered around agriculture. 44% of the

    governorate’s workforce is employed in the agricultural sector, the highest

    percentage among all 18 provinces.

    Salah Al-Din has 18% unemployment rate, and 39.9% live below the poverty line

    of $2.20 per day.

  • 10

    Illiteracy rate is 15.7% with the school enrollment: 78.3% primary education;

    14.7% secondary education.

    Education: One university (Tikrit University, 2900 students), 269 secondary

    schools, 16 vocational schools (commercial, industrial and technical), 11 teacher

    training institutes.

    Health: Salah Al-Din has 9 hospitals and 13 public medical clinics.

    Access to drinking water: 72.5%.

    Access to sanitary network: 82.4%.

    No sanitary landfills in the area, only authorized dumping sites; municipal waste

    collection rate is 43.1%

    Access to electricity grid: 89.6%

    Legal Aspects

    The applicable national legislation is as following:

    The Law for the Protection and Improvement of Environment No. 27, 2009;

    Forests and Woodlands Law No. 30 of 2009;

    Protection of Wild Animals and Birds No. 21 of 1979;

    Regulating Exploitation and Protection of Aquatic Life No. 46 of 1976;

    Ministry of Water Resources Law No. 50 of 2008;

    Public Health Law No. 89 of 1981, amended by Resolution No.54 of 2001;

    Iraqi Drinking Water Standard No. (417)-2001;

    Regulation for the Provision of Water Resources, No. 2, 2001;

    Regulation for the Protection of Rivers No. 25, 1967;

    Law No. 27 of 1999 concerning the establishment of the General Authority for

    Water and Sewage;

    Instructions No. 2 of 2014 on Environmental Protection from Municipal Waste;

    Directive No. (67) of 1986 Regulating the Debris Collection Areas;

    Clean Air Act No. 1 of 2004;

  • 11

    Noise Prevention Law No. 21 of 1966;

    Directive No. 4 of 1993 concerning occupational health, protection of workers

    against vibration;

    Instructions No. 3/1985 Concerning Occupational Safety;

    Law No. 6 of 1988 concerning the National Commission for Occupational Hygiene

    and Safety;

    Law No. 55 of 2002 for The Antiquities & Heritage of Iraq;

    Acquisition Law No.12. of 1981

    At present, there is no national Building Code in Iraq and the most commonly used are the

    ACI 318 codes.

    The main WB safeguard policies triggered by this project are:

    OP/BP 4.01 Environmental Assessment

    OP/BP 4.11 Physical Cultural Resources

    BP 17.50 Disclosure Policies

    OP 7.50 Projects on International Waterways

    According to OP 7.50 the riparian countries sharing the same water bodies should be

    informed about any developmental projects on international waterways. However, in case

    of this project the exceptions of notifying the riparian countries are applicable since the

    project is located in the lowest downstream riparian and will not adversely affect the quality

    and quantity of the water of other riparian states.

    In case of the difference between the National Legislation and WB Safeguard Guidelines,

    it has been agreed that the WB instructions will prevail over the national legislation

    provisions.

    The EHS Guidelines applicable to the project are:

    Environmental, Health, and Safety General Guidelines

    EHS Guidelines for Water and Sanitation

  • 12

    When host country regulations differ from the levels and measures presented in the EHS

    Guidelines, projects will be required to achieve whichever is more stringent.

    Impacts Assessment

    The assessment of the potential adverse impacts on different environmental parameters

    during the construction phase was done using the Leopold Matrix: on the horizontal axis,

    the actions which cause environmental impact, and on the vertical axis, the existing

    environmental receptors which may be affected by those actions.

    Rehabilitation/Construction Phase

    The adverse impacts of the rehabilitation/construction activities are expected to be minor

    to moderate and short-term. None of the identified impacts is evaluated as particularly

    severe. The anticipated impacts are:

    Increased potential of soil contamination during cleaning activities, inadequate

    waste disposal;

    Accidental spillage of fuel and lubricants during transportation of the construction

    materials;

    Contamination of groundwater through the leachate from improperly disposed

    construction debris and materials containing hazardous matter;

    Increased dust generation during clearance, and movement of heavy equipment and

    machinery;

    Increased noise and vibration levels during removal of post-combat debris, and

    heavy machinery movement;

    Potential of discovery of the artifacts during excavation and unintentional damage

    to those in case of accidental discovery;

    Some damage to landscape during clearance reducing the aesthetic appearance of

    the area;

    Habitat fragmentation of the freshwater habitat could occur during the construction

    of the intake structure due to the installation of the cofferdam thus causing the

    diversion of the water flow and additionally increased turbidity of the water.

  • 13

    Operation Phase

    During operational phase the impacts are anticipated to be minor. The scheduled

    maintenance works and repairs in case of emergency are very short-term and localized,

    therefore their impact is also considered as minor. The anticipated adverse impacts are:

    Potential soil contamination due to accidental overflow of the storm water drainage

    system;

    Surface water contamination through overflow of storm water, disposal of

    hazardous materials during regular and emergency maintenance;

    Air pollution due to the operations of the diesel generator and pumps, emissions of

    hazardous substances during the cosmetic maintenance of the buildings;

    Biodiversity: the impacts on biodiversity are considered very minor and localized

    and mostly related to the potential pollution of the habitat due to the inadequate

    waste management.

    Land use impacts are considered very minor and are related to inadequate waste

    management.

    Risk of ponding that may provide the breeding grounds to nuisance and disease

    carrying insects.

    Indirect, Cumulative and Residual Impacts

    Indirect impacts are considered to be minor: transportation of materials, excavation,

    clearance contribute to dust generation and vehicle and equipment emissions which settle

    on soils and in run off valleys during dry season consequently contributing to the transport

    of sediments and pollutants to the main water bodies and infiltration into the shallow

    aquifer.

    The main cumulative impact anticipated through implementation of this project is the

    incremental effect on of construction waste disposal on the waste management in the area

    already suffering from the lack of disposal facilities.

    Residual or irreversible impacts are considered to be very minor and mostly concern the

    use of the construction debris dumping sites as permanent municipal waste disposal areas.

  • 14

    Environmental and Social Management Plan

    The ESMP contains management measures avoidance, mitigation, as well as enhancements

    that would be implemented during the construction and operation/maintenance phase of

    the project.

  • 15

    Mitigation Measures during Rehabilitation Phase

    Receptor Mitigation Measures Responsibility Supervision Total estimated

    Cost in US$

    1 Air quality

    Vehicle emissions

    Contractor to keep vehicles and machinery properly operated and maintained. Contractor to minimize unnecessary vehicle idling. Switch off any engine as soon as it is not used. Dust

    Minimize dust from materials (such as sand, cement) and construction activities by using covers, storage, control equipment, and increasing

    moisture content.

    Prepare concrete before going to the site to avoid movement of materials (gravel, sand, cement) if possible

    Minimize dust from vehicle movements, using water sprays or appropriate. Avoid the burning of materials on site. Switch off any engine as soon as it is not used. Hazardous Emissions

    Avoid storage of hazardous materials in open areas without proper covering; Provide adequate ventilation for work areas

    Contractor Contractor/Resident

    Engineer

    PMT

    The bidders will

    be able to

    include these

    costs in their

    bidding.

    Additional cost:

    1500 US $

    2 Noise

    Noise and vibration management

    Avoid or minimize transport through community areas. Switch off any engine as soon as it is not used. Contractor to minimize unnecessary vehicle idling Muffling of the equipment; Additional health check-ups for personnel handling the vibrating and noisy

    equipment

    Contractor Contractor/Resident

    Engineer

    PMT

    Additional cost

    for medical

    check ups

    2000 US $

  • 16

    Receptor Mitigation Measures Responsibility Supervision Total estimated

    Cost in US$

    3 Water resources

    Water run-off management (drainage plan)

    Raw materials used in construction, which can be carried by water runoff, must be located and stored away from paths for water runoff.

    Where possible or appropriate, schedule works to avoid heavy rainfall periods (i.e. during the dry season) and modify activities during extreme

    rainfall and high winds.

    Contractor Contractor/Resident

    Engineer

    PMT

    Hydrogeological

    Investigation:

    500 US $

    4 Soil

    Disposal of contaminated soil by truck to nearest authorized dumping areas. If surface drainage is disturbing the construction process, utilizing ditches,

    dikes and/or sandbags to divert this drainage from entering excavations.

    Adverse weather

    Site engineer is to monitor weather on a daily basis. No construction activities to

    be undertaken in strong winds or rains.

    Contractor Contractor/Resident

    Engineer

    PMT

    Delineation of

    excavated areas:

    300 US $;

    Emergency soil

    testing in case of

    accidental spills:

    1000 US $

    5

    Solid and

    hazardous

    wastes

    General:

    Keeping the site clean and tidy: a. Ensure there is no loose materials or debris lying around the site including the

    perimeter; and

    b. Vehicles are regularly checked for cleanliness (general aspect and making sure

    no leaks are occurring)

    Burning of waste is prohibited Reducing construction waste related to on-site construction and off-site

    manufacture or fabrication.

    Reusing the material on site (in situ or for new applications) whenever it is possible

    Contractor Contractor/Resident

    Engineer

    PMT

    Additional costs

    for disposal of

    hazardous

    materials:

    3000 US $

  • 17

    Receptor Mitigation Measures Responsibility Supervision Total estimated

    Cost in US$

    Monitoring the amount of site construction waste created to make sure it does not affect the surrounding and the adjacent areas.

    - Waste is not blocking pathways

    - Construction waste will be gathered in a specific zone of the construction

    site

    Contractor to evacuate any construction waste to nearest authorized dumping site and on a regular basis to avoid accumulation

    All staff will avoid littering. Provide the septic tank for the residential effluent from the construction camp

    to be disposed regularly at the designated areas.

    Hazardous materials:

    Provide adequate secondary containment for fuel storage tanks and for the temporary storage of other fluids such as lubricating oils and hydraulic fluids.

    Use impervious surfaces for refuelling areas and other fluid transfer areas. Provide portable spill containment and clean-up equipment on site, and train

    staff in the safe use of it.

    Provide adequate sanitation facilities serving all workers (mentioned in HSE).

    Paints with toxic ingredients or solvents or lead-based paints will not be used

    6 Flora & Fauna

    Provide training to the construction crew on the impact of disturbance and damage to habitats;

    Monitor the construction crew and provide punitive measures for illegal hunting and/or fishing;

    Provide the crew with fuel for cooking to avoid burning of natural materials; Apply waste management plan Provide regular dredging around the cofferdams for the intake structure to

    ensure sufficient depth and avoid creation of whirlpools around the

    cofferdam which will cause increased turbidity of the water; Strictly prohibited disposal of any of the construction materials into the river; In order to avoid damage to the vulnerable habitats and species, the

    construction works on the water intake is to take place during the dry season

    Contractor Contractor/Resident

    Engineer

    PMT

    Training if

    conducted by the

    third party:

    400 US $

  • 18

    Receptor Mitigation Measures Responsibility Supervision Total estimated

    Cost in US$

    when the level of the water in the river is the lowest and the breeding season

    is over; The under water intake structure should be located at least 1m below the

    surface and inflow velocity should not exceed 1.5 m/s to avoid suction in of

    young fish

    7 Topography and

    surface drainage

    Storage areas for construction materials should be located at sites that do not permit direct runoff into watercourses and are on land sloping at less than 1.5 %.

    Time limitation on works during rainy events; Regular maintenance of the equipment and machinery to avoid spillage of

    hazardous materials;

    Re-vegetation of cleared areas Timely and adequate disposal of liquid and solid waste in authorized areas.

    Contractor Contractor/Resident

    Engineer

    PMT

    Re-vegetation

    cost:

    1000 US $

    8 Access and

    traffic

    Set up warning signs in the workplace: o All safe footpaths are marked; construction materials are not

    blocking pathways

    o Site entrances and exits are clearly marked for visitors and delivery drivers to see; and

    o If present, site reception is clearly signposted OR all visitors are escorted to the reception.

    Designating specific parking areas for workers’ and visitors’ vehicles outside the construction area.

    Avoid or minimize transport through community areas. Traffic management system and staff training, especially for site access and

    near-site heavy traffic.

    Adjustment of working hours to local traffic patterns, e.g. avoiding major transport activities during rush hours or times of livestock movement

    Contractor Contractor/Resident

    Engineer

    PMT

    Additional costs

    for marking and

    signage:

    300 US $

    9 Health and

    Safety Provide adequate signage to prevent accidental falling into open areas Fencing of the work areas

    Contractor Contractor/Resident

    Engineer

    No additional

    costs; the cost is

    imbedded in

  • 19

    Health and safety environment (HSE)

    There is posted material indicating the nearest police station and hospital (with accident and emergency facilities).

    The contractor must take reasonable steps to prevent unauthorized people accessing the site.

    Training on handling of UXO/ERW Avoid the burning of materials on site. Provide a first aid kits in different places of the work site with the appropriate

    number of materials given the number of workers on site. The locations of

    the first aid kits will be provided to all workers.

    Providing extinguishers on work site. If work involving the use of flammable materials is being carried out, stop

    people smoking and do not allow other work activities involving potential

    ignition sources to take place nearby. Providing site boundaries by installing suitable physical boundaries (barriers,

    tape or fence).

    Marking excavation holes with physical boundaries (barriers, tape or fence) The contractor should put up barriers or covers in the area of openings and

    excavations.

    Store building materials (such as pipes, manhole rings, and cement bags) so that they cannot topple or roll over.

    Keep walkways and stairways free of tripping hazards such as trailing cables, building materials, and debris.

    Everyone who works on any site must have access to adequate toilet and washing facilities, a place for preparing and consuming refreshments, and an

    area for storing and drying clothing and personal protective equipment (PPE). Contractor to ensure PPE (personal protective equipment) is used by all

    workers on site.

    Materials and equipment are tidily stacked, protected and covered where necessary. Additionally, there is adequate space for new materials to be

    stored in secured covered areas to avoid damage, theft, and to protect these

    items from weather conditions.

    Scaffolding for work in elevated areas such as ceiling painting should comply with the OSHA “General Requirements for Scaffolds §1926.451”

    PMT mandatory HSE

    measures

  • 20

    Receptor Mitigation Measures Responsibility Supervision Total estimated

    Cost in US$

    10 Handling

    Complaints

    Reducing impacts on the community through community and neighbour engagement.

    In cases of where there are minority communities speaking a different language in the area or working on site, notices are printed in the common

    local language.

    Provide the proper GRM for handling complaints

    Contractor Contractor/Resident

    Engineer

    PMT

    No additional

    costs

    11 Physical cultural

    resources

    In case of accidental discovery stop all works and contact the responsible authority within 24 hours;

    Provide training to the construction crew on the mode of conduct in case of accidental findings

    Contractor Contractor/Resident Engineer

    PMT

    No additional

    costs

    Total cost US$ (rehabilitation phase) 10,000 US $

    Mitigation Measures during Operation Phase

    Receptor Mitigation Measures Responsibility Supervision Total estimated

    Cost in US$

    1 Air quality

    including odors

    Water spraying for dust control in maintenance areas;

    Timely disposal of effluent from sanitary facilities in office buildings;

    Timely disposal of domestic waste

    Operator PMT No additional

    costs

    2 Noise Provision of PPE to maintenance personnel while handling the equipment Operator PMT No additional

    costs

  • 21

    Receptor Mitigation Measures Responsibility Supervision Total estimated

    Cost in US$

    3 Water resources Timely and adequate disposal of debris generated by maintenance activities and

    solid and liquid waste from office building;

    Maintaining the drainage ditches and manholes unblocked

    Operator PMT No additional

    costs

    4 Soil Maintaining the drainage channels unblocked;

    Adequate disposal of waste

    Operator PMT No additional

    costs

    5

    Solid and

    hazardous

    wastes

    Use of non-toxic paints for repairs of the buildings;

    Storage of hazardous materials used for repairs in sealed containers;

    Disposal of waste to authorized disposal sites;

    Avoid disposal of effluent into the river

    Undertake measures necessary to prevent leakage of chlorine gas from pipe

    work connection between the liquid chlorine gas.

    o A pictorial representation of the procedure for changing liquid chlorine

    containers with written instructions where necessary in Arabic and on

    plastic covered card mounted on a board fixed to the inside wall of the

    chlorine store. All tools necessary for changing the containers shall also

    be clipped to this board.

    o All necessary washers and couplings required when changing

    containers sufficient for five years operation.

    o A water spray bar to provide a water curtain fixed externally over the

    chlorine store and connected via solenoid operated valve direct to the

    delivery main from pumping station. The solenoid valve. This system

    must be provided with manual starting from outside the room for

    emergency.

    Filter backwash should be discharged into the sludge pit to be disposed

    according to the specification

    Operator PMT No additional

    costs

  • 22

    Receptor Mitigation Measures Responsibility Supervision Total estimated

    Cost in US$

    6 Flora & Fauna Keeping the manholes and ditches clean;

    Adequate waste disposal;

    Re-vegetation with the plants native to the area

    Operator PMT No additional

    costs

    7 Handling Complains

    Compliance with GRM Operator PMT No additional

    costs

    8 Public hygiene

    and quality of

    water

    Adequate waste disposal; Prevent leakages of water and accumulating of water in ponds prone to

    stagnation;

    Regular water testing for the compliance with the drinking water standard

    Operator PMT No additional

    costs

    Total cost US$ (Operation phase) No additional

    costs

  • 23

    Environmental and Social Monitoring Plan

    The ESMP will be shared with the contractor who will be contractually obligated to abide

    by it, with financial clauses associated to this obligation. Impacts are mitigated by detailed

    mitigation measures. Those measures are presented as a set of checklists that the contractor

    will follow.

    The following tables present monitoring measures in order to perform a non-harmful

    implementation of the project works to the environment and to reduce the risk of negative

    environmental impacts as far as possible.

    The frequency of the reporting:

    During rehabilitation/construction phase: bi-weekly

    During operation phase: quarterly

  • 24

    Monitoring Activities during Rehabilitation Phase

    Receptor Monitoring

    Activities Monitoring Indicators Frequency Responsibility Supervision

    Total

    estimated

    Cost in US$

    1 Air quality including odors

    Site inspection with

    the photo

    documentation;

    Air quality testing

    Air quality

    parameters: PM10,

    PM2.5, SO2, NOx,

    CO, Ozone and HC

    Compliance with

    dust abatement

    measures

    Inspection: weekly

    Testing: Once prior to

    the start of construction

    works to establish a

    baseline and once

    during the construction

    phase during the dry

    season.

    Contractor Resident

    engineer

    Testing done

    by accredited

    laboratories.

    Additional

    cost 2000 US

    $

    Camera: 250

    US $

    2 Noise

    Site inspection measuring the level

    of noise

    Compliance with the time limitations;

    Switching off the equipment not in

    use;

    Use of protective gear

    Weekly Contractor Resident engineer

    Hand held device for

    nose level

    measuring:

    200 US $

    3 Water resources

    Site inspection with photo

    documentation;

    Water testing

    Inspection:

    debris accumulation in water drainage

    areas;

    Alteration of water courses;

    Signs of spillage of hazardous materials

    Inspection:

    Bi-weekly during the rainy season,

    and after sporadic

    rains

    Once a month during the dry

    periods

    Contractor Resident

    engineer

    Testing done

    by accredited

    laboratories.

    Additional

    cost 3000 US

    $

    No additional

    costs for

    testing during

  • 25

    Receptor Monitoring

    Activities Monitoring Indicators Frequency Responsibility Supervision

    Total

    estimated

    Cost in US$

    Water testing (general):

    pH, Turbidity,

    Electrical Conductivity

    (EC), Color, Total

    Suspended Solids (TSS), Total Dissolved

    Solids (TDS), Chemical

    Oxygen Demand

    (COD), Biological

    Oxygen Demand

    (BOD), Polychlorinated

    Biphenyls (PCBs)

    Water testing during

    intake construction:

    Turbidity, Color, Total

    Suspended Solids

    (TSS), Total Dissolved Solids (TDS)

    Water testing: in the

    location of accidental

    spills of hazardous

    materials

    intake

    construction

    4 Soil

    Site inspection with photo

    documentation;

    Soil testing

    Inspection: signs of soil

    erosion, evidence of

    spills of fuel and

    lubricants

    Soil testing:

    Inspection: bi-weekly;

    Testing of the contaminated soil in

    the location of

    accidental spills of

    Contractor Resident

    engineer

    Testing done

    by accredited

    laboratories.

    Additional

    cost 3000 US

    $

  • 26

    Receptor Monitoring

    Activities Monitoring Indicators Frequency Responsibility Supervision

    Total

    estimated

    Cost in US$

    pH, temperature,

    organic content, poly-

    aromatic hydrocarbons

    (PAHs); Faecal

    coliforms and Total coliforms

    hazardous materials

    if any

    5 Solid and hazardous wastes

    Site inspections

    Maintaining a record of type,

    quantity, and

    disposal location

    of solid and

    liquid waste

    generation;

    Storage conditions of hazardous

    materials;

    Disposal at designated sites

    Inspection: bi-weekly Contractor Resident

    engineer

    No additional

    costs

    6 Traffic

    Site inspections Site surveillance for the

    presence of

    fencing/barriers and

    warning signs, and traffic speed limitations

    Monthly Contractor Resident

    engineer

    No additional

    costs

    7 Flora & Fauna

    Site inspections Degree of habitat disruption due to

    construction activities:

    clearance of

    vegetation, signs of

    fire, presence of

    fishing and hunting

    equipment

    Degree of workers perception of

    Inspection: bi-weekly Contractor Resident

    engineer

    No additional

    costs

  • 27

    Receptor Monitoring

    Activities Monitoring Indicators Frequency Responsibility Supervision

    Total

    estimated

    Cost in US$

    necessity of habitat

    conservation

    Site restoration after work completion

    8 Topography and surface

    drainage

    Inspection and photo evidence

    Location of storage areas;

    Ceasing construction

    activities during

    rainy events;

    Re-vegetation of cleared areas

    Records of waste disposal.

    Inspection: bi-weekly Contractor Resident

    engineer

    No additional

    costs

    9

    Handling Complains

    Maintaining records of filed

    complaints and

    responses

    Time of response to the complaint;

    Number of complaints

    Monthly Contractor Resident

    engineer

    No additional

    costs

    10 Public health and safety

    Inspection and photo evidence

    Maintaining records of injuries

    and accidents with

    cause and location

    Provision and use of personal protective

    equipment to workers

    Installing construction and warning signs

    Inspection: bi-weekly Contractor Resident

    engineer

    No additional

    costs

    Total cost US$ (Operation/Maintenance phase) 8,450 US $

  • 28

  • 29

    Monitoring during Operation Phase

    Receptor Monitoring Activities Monitoring Indicators Frequency Responsibility Supervision Total

    estimated

    Cost in US$

    1 Air quality

    Surveillance Presence of unpleasant

    odors;

    Dust abatement

    measures

    Bi-weekly Operator WSD No additional

    costs

    2 Noise

    Noise level

    monitoring

    Ensure the noise levels

    are within the acceptable

    limits

    During maintenance and

    repairs

    Operator WSD No additional

    costs

    3 Water resources

    Surveillance;

    Water testing

    Ensure the drainage channels and culverts

    are clear of debris

    Water quality testing: pH, Turbidity, Electrical

    Conductivity (EC),

    Color, Total Suspended

    Solids (TSS), Total

    Dissolved Solids (TDS),

    Chemical Oxygen

    Demand (COD),

    Biological Oxygen

    Demand (BOD), Polychlorinated

    Biphenyls (PCBs)

    Surveillance:

    Bi-weekly during the rainy season

    Monthly during the dry season

    Water testing: Once per

    year during rainy season

    Operator WSD 500 for water

    testing

  • 30

    Receptor Monitoring Activities Monitoring Indicators Frequency Responsibility Supervision Total

    estimated

    Cost in US$

    4 Soil

    Surveillance;

    Soil testing Ensure the drainage

    channels and culverts

    are clear of debris

    Soil testing: pH, temperature, organic

    content, poly-aromatic

    hydrocarbons (PAHs )

    Surveillance:

    Bi-weekly during the rainy season

    Monthly during the dry season

    Soil testing: Once per

    year during rainy season

    at the location of

    disposal of filter

    backwash

    Operator WSD 300 for soil

    testing

    5 Solid and hazardous wastes

    Surveillance;

    Maintaining records of

    quantities of waste

    and location of its

    disposal

    Waste disposed at

    designated areas

    Monthly Operator WSD No additional

    costs

    6 Flora & Fauna

    Surveillance Condition of the

    manholes and ditches;

    Level of re-vegetation;

    Absence of ponds

    Surveillance:

    Bi-weekly during the rainy season

    Monthly during the dry season

    Operator WSD No additional

    costs

    7 Topography and surface

    drainage

    Surveillance Disposal of debris during

    maintenance and repairs

    Monthly Operator WSD No additional

    costs

  • 31

    Receptor Monitoring Activities Monitoring Indicators Frequency Responsibility Supervision Total

    estimated

    Cost in US$

    8 Access and traffic Surveillance Presence of warning

    signs at maintenance site

    During maintenance and

    repair works

    Operator WSD No additional

    costs

    9 Health and Safety

    Surveillance;

    Maintaining records of quantities of waste

    and location of its

    disposal

    Adequate warning about scheduled

    maintenance works;

    Timely and adequate disposal of waste

    Monthly Operator WSD No additional

    costs

    10 Handling Complaints Record keeping on

    received complaints

    Number of complaints

    and responses Quarterly

    Operator WSD No additional

    costs

    11 Physical cultural resources N/A N/A N/A N/A N/A

    Total cost US$ (Operation/Maintenance phase) 800 US $

    per year

  • 32

  • 33

    Public Consultations

    Due to the security concerns the general public consultation meeting was not possible to

    be conducted. However, a mini public consultation was conducted in addition to interviews

    with the residents of the area with the help of the questionnaire by the PMT on Nov.28,

    2016. The interviewed persons included 5 men and 3 women. During the meeting the local

    community was presented with the project details and the team addressed their concerns

    and recommendations. All present agreed that the reconstruction activities will have a

    strong positive impact from the social perspectives on the local community and will

    encourage the development of the area. Please refer to annexes 2 and 3 for more details.

    1. No claims were recorded or alleged regarding the ownership of the land where the

    rehabilitation activities to take place; all agreed that is governmental land property.

    2. No vegetation covers, crops, plants, trees…etc. will be removed in order to execute

    the rehabilitation activities.

    3. No infrastructure will be affected negatively due the reconstruction activities.

    4. No dislocation or resettlement will be needed for the implementation of the project.

    5. Information about a grievance mechanism was introduced and a translated GRM

    form was also provided. The participants were informed that they can submit their

    complaint to either site engineer, or to community leader or to PMT during

    construction.

    Grievance Redress Mechanism

    Bank procedures require that Grievance Redress Mechanisms (GRMs) be established and

    operational prior to commencement of the project, and that they continue to operate for one

    year following completion of the works for third party settlement of disputes. This GRM

    should take into account the availability of judicial recourse as well as traditional and

    community dispute resolution mechanisms.

    The project grievance redressed system should be developed in consultation with

    communities, which might include the following for written complaints:

  • 34

    1. First, the affected person sends his/her grievance in writing to the

    communities’/community leaders. The grievance note should be signed and dated

    by the aggrieved person. Where the affected person is unable to write, s/he should

    obtain assistance from the community to write the note and mark the letter with

    his/her thumbprint. The community should respond within 14 days.

    2. Second, if the aggrieved person does not receive a response or is not satisfied with

    the solution provided by the community, s/he lodges her or his grievance to PMT

    which should respond within 14 days.

    3. Third, if the aggrieved person is not satisfied with the solution of PMT, s/he can go

    to the court.

    In any case, the PMT must maintain records of grievances and complaints, including

    minutes of discussions, recommendations and resolutions made. Participants were

    informed that they can submit their complaint to either site engineer, or to community

    leader or to PMT during construction. The community leaders’ information (mobile phone

    number) and PMT contact information (office and mobile phone numbers) will be available

    before implementation starts and will be posted at the entrance of the project site.

  • 35

    Table of Contents

    EXECUTIVE SUMMARY ................................................................................................. 3

    Introduction .......................................................................................................................... 3

    Project Description ................................................................................................................ 3

    Baseline Conditions .............................................................................................................. 7

    Regional Geology, Topography and Seismic Activity .................................................... 7

    Water Resources ............................................................................................................ 7

    Climate ........................................................................................................................ 8

    Ambient Air Quality and Noise ...................................................................................... 8

    Biological Environment ................................................................................................. 8

    Socio-Economic Environment ........................................................................................ 9

    Legal Aspects...................................................................................................................... 10

    Impacts Assessment ............................................................................................................ 12

    Rehabilitation/Construction Phase ................................................................................ 12

    Operation Phase ........................................................................................................... 13

    Indirect, Cumulative and Residual Impacts .................................................................. 13

    Environmental and Social Management Plan ....................................................................... 14

    Noise and vibration management ............................................................................. 15

    Water run-off management (drainage plan) .............................................................. 16

    Adverse weather ...................................................................................................... 16

    Health and safety environment (HSE) ...................................................................... 19

    Environmental and Social Monitoring Plan ......................................................................... 23

    Public Consultations............................................................................................................ 33

    Grievance Redress Mechanism ............................................................................................ 33

    Table of Contents .............................................................................................................. 35

    List of Tables ..................................................................................................................... 39

  • 36

    List of Figures.................................................................................................................... 40

    List of Abbreviations ......................................................................................................... 41

    1 INTRODUCTION ...................................................................................................... 42

    2 PROJECT DESCRIPTION ....................................................................................... 43

    2.1 Project Objectives and Outcomes ............................................................................. 43

    2.2 Main Project Components ........................................................................................ 44

    2.3 Condition of Existing Facilities ................................................................................ 44

    2.4 Clearance of UXO/ERW .......................................................................................... 45

    2.5 Construction Camp ................................................................................................... 45

    2.6 Personnel Requirements ........................................................................................... 46

    2.7 Land Acquisition ...................................................................................................... 47

    2.8 Project Duration ....................................................................................................... 47

    3 BASELINE CONDITIONS ....................................................................................... 49

    3.1 Project Location ....................................................................................................... 49

    3.2 Regional Geology, Topography and Seismic Activity ............................................... 50

    3.2.1 Geological Formations in the Project Area ..................................................... 50

    3.2.2 Seismology .................................................................................................... 50

    3.3 Water Resources ....................................................................................................... 51

    3.4 Climate ..................................................................................................................... 53

    3.5 Air Quality and Noise ............................................................................................... 54

    3.6 Biological Environment ............................................................................................ 55

    3.6.1 Terrestrial Environment ................................................................................. 55

    3.6.2 Aquatic Environment ..................................................................................... 57

    3.6.3 Status of Habitats ........................................................................................... 58

    3.6.4 Status of Species ............................................................................................ 59

    3.7 Socio-Economic Baseline Conditions ....................................................................... 59

    3.7.1 Demographic Indicators ................................................................................. 59

  • 37

    3.7.2 Land Use ....................................................................................................... 60

    3.7.3 Services ......................................................................................................... 60

    3.7.4 Sites of Archeological, Historical, Cultural and Religious Importance ............ 60

    3.7.5 Roads Infrastructure ....................................................................................... 61

    4 LEGAL ASPECTS ..................................................................................................... 62

    4.1 National Legislation ................................................................................................. 62

    4.1.1 General Environmental Legislation ................................................................ 62

    4.1.2 Water Resources ............................................................................................ 62

    4.1.3 Waste Management ........................................................................................ 65

    4.1.4 Air Quality ..................................................................................................... 66

    4.1.5 Ambient Noise and Vibration ......................................................................... 66

    4.1.6 Occupational Health and Safety ..................................................................... 67

    4.1.7 Cultural resources .......................................................................................... 67

    4.1.8 Land acquisition............................................................................................. 68

    4.2 International Conventions and Treaties ..................................................................... 68

    4.3 Applicable Engineering Standards ............................................................................ 68

    4.4 WB Safeguard Policies ............................................................................................. 71

    4.4.1 Environmental, Health, and Safety Guidelines ............................................... 73

    5 ENVIRONMENT AND SOCIAL IMPACT ASSESSMENT ................................... 77

    5.1 Impacts Significance Evaluation during Rehabilitation Phase ................................... 77

    5.2 Potential Adverse Impacts during Rehabilitation Phase............................................. 80

    5.2.1 Impacts on Soil .............................................................................................. 80

    5.2.2 Impacts on Water Resources .......................................................................... 80

    5.2.3 Impacts on Biodiversity ................................................................................. 80

    5.2.4 Impacts on Air Quality ................................................................................... 81

    5.2.5 Noise and Vibration Impacts .......................................................................... 82

    5.2.6 Land Use Impacts .......................................................................................... 83

  • 38

    5.2.7 Impacts on Utilities and Infrastructure............................................................ 83

    5.2.8 Impacts on Cultural, Religious and Historic Heritage Sites ............................. 84

    5.2.9 Damage to the Landscape .............................................................................. 84

    5.2.10 Public Safety .................................................................................................. 84

    5.2.11 Worker’s Safety ............................................................................................. 84

    5.2.12 Waste Management ........................................................................................ 85

    5.2.13 Construction Camp Impacts ........................................................................... 85

    5.3 Potential Adverse Impacts during Operational Phase ................................................ 86

    5.4 Indirect, Cumulative, and Residual Impacts .............................................................. 87

    6 ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN ............................... 89

    Noise and vibration management ............................................................................. 90

    Water run-off management (drainage plan) .............................................................. 90

    Adverse weather ...................................................................................................... 91

    Health and safety environment (HSE) ...................................................................... 93

    7 ENVIRONMENTAL AND SOCIAL MONITORING PLAN ................................. 97

    8 PUBLIC CONSULTATION RESULTS ................................................................. 105

    9 GRIEVANCE REDRESS MECHANISM .............................................................. 106

    10 ANNEXES ................................................................................................................ 107

    10.1 Annex 1: Chance Find Procedure ............................................................................ 107

    10.2 Annex 2: Public Consultations ................................................................................ 108

    10.3 Annex 3. Grievance Redress Form.......................................................................... 118

    10.4 Annex 4: Mitigation Measures during Construction Phase ...................................... 119

  • 39

    List of Tables

    Table 1: Estimate of Staffing Requirements......................................................................... 46

    Table 2: Duration of Construction Activities ....................................................................... 48

    Table 3: Typical Irano-Turanian Steppe Vegetation............................................................. 55

    Table 4: List of the Recorded Bird Species Recorded in the Project Area ............................ 56

    Table 5: Mammals in the Vicinity of the Project.................................................................. 56

    Table 6: Amphibians and Reptiles Recorded in the Project Area ......................................... 57

    Table 7: Typical Aquatic and Riparian Vegetation in the Project Area ................................ 57

    Table 8: List of Freshwater Fish Species ............................................................................. 58

    Table 9: Population of Salah Al-Din Governorate for 2015 ................................................. 59

    Table 10: Drinking Water Standard No. (417)-2001 ............................................................ 63

    Table 11: Effluent Discharge Parameters ............................................................................. 65

    Table 12: Ambient Air Quality Standard ............................................................................. 66

    Table 13: Indicative Values for Sanitary Sewage Discharge ................................................ 74

    Table 14: Rehabilitation Phase: Impacts Significance .......................................................... 78

    Table 15: Noise Emission Levels dB (A) of Construction Equipment .................................. 82

    Table 16: Noise Emission Levels dB (A) and Distance to the Equipment ............................ 82

    Table 17: EPA Maximum Acceptable Leq (2005) ................................................................ 83

    Table 18: Operation and Maintenance Phase: Impacts Significance ..................................... 86

    Table 19: Mitigation Measures during Rehabilitation Phase ................................................ 90

    Table 20: Mitigation Measures during Operation Phase ....................................................... 95

    Table 21: Monitoring Activities during Rehabilitation Phase ............................................... 98

    Table 22: Monitoring during Operation Phase ................................................................... 102

  • 40

    List of Figures

    Figure 1: Project Location ................................................................................................... 43

    Figure 2: Present Condition of the Facilities ........................................................................ 45

    Figure 3: Administrative Location of the Project ................................................................. 49

    Figure 4: Geological Formations in the Project Area ........................................................... 50

    Figure 5: Seismic Map of the Project Area .......................................................................... 51

    Figure 6: Depth to Groundwater in the Project Area ............................................................ 52

    Figure 7: Temperatures and Precipitation in the Project Area (2002-2012) .......................... 54

    Figure 8: Mesopotamian Shrub Desert Borders ................................................................... 55

    Figure 9: Location of Samarrah Wetland IBA ..................................................................... 59

    Figure 10: Historical and Cultural Heritage Sites in the Project Area ................................... 61

  • 41

    List of Abbreviations

    AXO Abandoned explosive ordnance

    EHS Environment, Health and Safety

    ERW Explosive remnants of war

    ESMP Environmental and Social Management Plan

    GRM Grievance Redress Mechanism

    Ha Hectare

    ID Iraqi Dinar

    Km Kilometer

    MCC Motor Control Center

    MM Modified Mercalli Scale

    NGO Non-Governmental Organization

    OP Operational Procedure

    PMT Project Management Team

    SCADA Supervisory Control and Data Acquisition

    TDS Total Dissolved Solids

    TSS Total Suspended Solids

    TOR Terms of Reference

    WB World Bank

    UXO Unexploded ordnance

  • 42

    1 INTRODUCTION

    This Environmental and Social Management Plan (ESMP) is prepared in accordance to the

    Terms of Reference for Rehabilitation of Al-Awja - Owainat Water Treatment Plant, Salah Al-

    Din Governorate within the framework of Emergency Operation for Development Project

    (EODP) (P155732) (IBRD Loan No.: 8520).

    According to the World Bank environmental safeguards the project is categorized as Category

    B.

    Ministry of Constriction, Housing, Municipalities and Public Works operates, as the core

    mandate for Iraqi government, in the management, development, rehabilitation and

    maintenance of water and sanitation facilities within Republic of Iraq.

    The objectives of the ESMP are:

    Identification of the baseline environmental and social conditions;

    Identification of the potential adverse impacts during the rehabilitation/construction

    and operational phases of the project related to the specific project activities;

    Propose mitigation measures in order to minimize the adverse impacts identified;

    Prepare the ESMP that will allow the adequate implementation of the proposed

    mitigation measures.

  • 43

    2 PROJECT DESCRIPTION

    The project is located in the city of Tikrit, Salah Al-Din Governorate, approximately 140 km

    north of Baghdad.

    Figure 1: Project Location

    2.1 Project Objectives and Outcomes

    The area of the project witnessed severe destruction during the last several years since the

    armed conflict and occupation of the area by the Islamic State (“da’esh”). The region’s

    infrastructure has been specifically targeted and currently in non-operational condition and

    requires extensive rehabilitation. Within the framework of Emergency Operation for

    Development Project (EODP) (P155732) (IBRD Loan No.: 8520) 4.9 million US $ are

    allocated for the rehabilitation of Al-Awja - Owainat Water Treatment Plant.

    The main project goal is rehabilitation of the water treatment plant for the provision of the

    potable water. The expected project outcome is functioning water treatment facility with the

    operational capacity of 1000m3/h.

  • 44

    The project is expected to provide drinking water to approximately 35000 local residents and

    IDPs. At present, the residents rely almost exclusively on the water delivered by water tankers

    for drinking purposes which poses additional financial burden on household. In some instances

    the water is extracted from wells with the inadequate quality of water without any treatment

    which poses significant health risks to the population.

    2.2 Main Project Components

    The project comprises the rehabilitation of a water treatment facility with the output of 2200

    m3/day for 22 hour operation per day; 1000 m3/hr. The source of the raw water for treatment is

    the Tigris River. The main project components are:

    The project consists of the following components:

    Intake stricture.

    Low lift pumps.

    Sedimentation tank (2).

    Filter tanks (6)

    Alum system

    Chemical building

    Chlorine system

    High lift pump station

    Motor Control Center (MCC) building

    Ground reservoir

    Supervisory control and data acquisition (SCADA) system.

    2.3 Condition of Existing Facilities

    At present, the facilities are in destroyed conditions and in completely non-operational

    condition:

  • 45

    Figure 2: Present Condition of the Facilities

    2.4 Clearance of UXO/ERW

    Unexploded ordnance (UXO) are weapons that for some reason fail to detonate as intended,

    thereby becoming unexploded ordnance. These unstable explosive devices are left behind

    during and after conflicts and pose dangers similar to landmines.

    Abandoned explosive ordnance (AXO) is explosive ordnance that has not been used during

    armed conflict and has been left behind and is no longer under control of the party that left it

    behind. It may or may not have been primed, fuzed, armed, or otherwise prepared for use.

    Explosive remnants of war (ERW) are explosive munitions left behind after a conflict has

    ended. They include unexploded artillery shells, grenades, mortars, rockets, air-dropped

    bombs, and cluster munitions. Under the international legal definition, ERW consist of UXO

    and AXO, but not mines.

    The risk of the presence of UXO/ERW in the area is that it might not be immediately discovered

    after the conflict especially if buried deep underground or under the rubble of destroyed

    buildings.

    The area have received clearance from the Iraqi Armed Forces for the absence of UXO/REW,

    however, accidental discovery is still possible. In case of the discovery, the personnel should

    be immediately evacuated and armed forces contacted. The works could be resumed only after

    removal of the munitions.

    2.5 Construction Camp

    A Main Camp, the operational center, with prefabricated offices and parking areas for

    administration and technical staff. This will also include areas for materials testing and storage,

  • 46

    and equipment cleaning and maintenance. The need for residential accommodation is likely to

    be relatively minor. The accommodation at the camp will be required for the security guards,

    2 persons.

    The amount of effluent generated by the construction camp is considerable, as it was estimated

    that the average water consumption might constitute up to 100 m3/day. Residential solid waste

    containing organic waste from construction camps is approximately 1.5 kg/person/day. The

    construction camp should have independent sources of water and electricity, and the septic tank

    for the residential effluent disposal.

    2.6 Personnel Requirements

    The personnel requirements for the project are 47 persons including administrative staff,

    technical staff, qualified construction crew and unskilled labor. All workers will be locally

    hired. The estimate of the staffing requirements is presented in the Table below:

    Table 1: Estimate of Staffing Requirements

    Type Job Title Number

    Administrative Staff

    Secretary 1

    IT support 1

    Serving personnel 1

    Security personnel 2

    Parking attendants 2

    Logistics Coordinator 1

    Warehouse/storage coordinator 2

    HR officer 1

    Procurement officer 1

    Technical Staff

    General Manager/Team Leader 1

    Senior Civil Engineer 1

    Materials Engineer 1

    Civil Engineer 2

    Structural Engineer 1

    Geo-technical Engineer 1

    Drainage Engineer 1

    Quantity Surveyor 1

    HS&E specialist 2

    Social expert 1

    Quality Assurance Engineer 1

  • 47

    Type Job Title Number

    Construction Crew Machinery and equipment operators 12

    Unskilled labor 10

    Total 47

    2.7 Land Acquisition

    The project comprises the rehabilitation of the existing facilities with no additional structures

    or pipelines to be constructed. Therefore, the project will not require any permanent or

    temporary land acquisition. The construction camp is to be located on governmental property

    within the perimeter of the existing facilities. Accordingly OP 4.12 will not be applied.

    2.8 Project Duration

    The total project duration is 6 months. Work consists of a simple civil works such as cleaning

    work and raise dirt debris resulting from combat operations and rehabilitation of all the

    damaged civil buildings such as Intake, Sedimentation Tank, Filtration Building, Storage Tank,

    MCC Building and services buildings and repainting buildings and replace and renovating

    pipes, bathrooms, doors, windows and re-paving of internal roads and treatment of cracks in

    the sedimentation tank and Storage Tank.

    Most of the works in this project are the electrical and mechanical works include supply,

    installation, and operation of the pumps, electric transformers, electric generator and the

    replacement of cables and outdoor lightings.

    The intake structure shall be constructed from reinforced concrete. The pump sump (Basement)

    shall be designed as a water tight structure in two compartments for independent operation

    during maintenance with bypass arrangement controlled by a 2 Nos. sluice valves. The floor of

    the (Basement) shall be sloped to one corner with a sump to pump accumulated settled sludge

    to the river using duplicated submersible pumps. The Basement shall have access ladder and

    lighting. The channel from river to the intake Basement shall be constructed according to the

    drawing from reinforced concrete the contractor is responsible to make a full hydraulic study

    to design the final shape of the channel. Rip-raping along the shoulder of the river for a distance

    of 50m from each side of the channel to protect the structure and to direct the water to the

    channels. The necessary arrangements are to be made to minimize the problem of settling of

    the suspended matter at the channel bar during high turbidity seasons by using submerged

    scraping device.

  • 48

    The breakdown of project activities is presented in the Table below:

    Table 2: Duration of Construction Activities

    # Activity Duration (man days)

    1 Cleaning post-combat debris 75

    2 Rehabilitation of Intake Structure 60

    3 Rehabilitation of sedimentation tank 60

    4 Rehabilitation of filtration facilities 60

    5 Rehabilitation of storage tank 60

    6 Rehabilitation of MCC building 60

    7 Rehabilitation of service building 60

    8 Replacing of pipes 35

    9 Repair and paving of roads within the facility 14

    10 Installation of doors and windows 28

    11 Painting 38

    12 Electrical and mechanical works 42

  • 49

    3 BASELINE CONDITIONS

    This chapter presents a comprehensive overview of the existing conditions in the vicinity of

    the project area and adjacent facilities.

    3.1 Project Location

    The project is located in the city of Tikrit, Salah Al-Din Governorate, Iraq. The project location

    is approximately 140km north of capital city of Baghdad. The project is located directly on the

    bank of the Tigris River. Figure below shows the administrative location of the project.

    Figure 3: Administrative Location of the Project

    The land use of the area is void of residential settlements, industrial activities and cultivation.

    The area is used by the local population mostly for grazing of the livestock.

  • 50

    3.2 Regional Geology, Topography and Seismic Activity

    3.2.1 Geological Formations in the Project Area

    The project is located in the north-eastern part of the Arabian Peninsula, which is a region of

    tectonic compression of particularly unstable area marked by convergent movements of the

    Arabian and Eurasian Plates that closed Tethys paleo-ocean and formed Zagros Belt in the

    north-eastern part of the Arabian Plate. Stratigraphically, the project area is dominated by

    geological formations ranging from Middle Miocene to Quaternary. In the project location the

    geological formation is composed of thin-bedded, black bituminous limestone, dolomitic

    limestone and black papery shale with streaks of thin black chert.

    The terrain is characterized as flat to gently rolling plains, hills, and mountains. In the project

    area the elevations are ranging between 300-550 m asl. The maximum elevation is 543.5 m asl

    and the minimum elevation is 313.9 m asl.

    Figure 4: Geological Formations in the Project Area1

    3.2.2 Seismology

    Tectonically Iraq is located in a relatively active seismic zone at the northeastern boundaries

    of the Arabian Plate. Seismic zoning of Iraq is divided into four zones where the areas of no

    damage zone of MM = III and less covering mainly the stable shelf region. Then the minor

    damage zone follows which covers the intensities IV- V covering the Zagros Foothills and the

    1 Red circle marks the location of the project area

    W01

  • 51

    Mesopotamian Geosyncline. Then the moderate damage zone follows with intensity range of

    VI-VII which actually covers the Zagros Tauros thrust zones. The major damage zone with

    intensity of VIII is located on the Zagros thrust outside the Iraqi borders.

    The project area is located in the minor damage zone with the seismic activity of I-II on MM

    scale.

    Figure 5: Seismic Map of the Project Area2

    3.3 Water Resources

    According to the hydro-geological classification of Iraq, the project area is located in the Low

    Fold hydro-geological zone. The Low Fold zone is filled by sedimentary formations that range

    in age from Late Miocene to Recent: Fatha, Injana, Mukdadiyah and Bai Hassan, and

    Quaternary cover. These formations represent the main aquifers in this zone. The general trend

    of the groundwater movement is mainly from north and northwest towards south and southeast.

    2 Adapted from: Alsinawi, S.A. (2001) .Seismological Considerations of the Eastern Arab Region. Proceedings of the Euro-Mediterranean Seminar on Natural, Environmental and Technological Disasters, Algers, Algeria

  • 52

    Generally, the salinity of the groundwater increases from north to south. It increases from the

    recharge sources at the high land areas (less than 1000 mg/l), towards the discharge areas along

    the Mesopotamia Zone and Al-Jazira Zone (more than 10000 mg/l). Groundwater quality is

    mainly bicarbonate at the recharge areas, and becomes sulphatic at the discharge areas. The

    groundwater quality in the project area is slightly brackish with the salinity of 1000-3000 ppm.

    The groundwater depth in the project area ranges from 10-20 m below surface.

    Figure 6: Depth to Groundwater in the Project Area

    The surface water is characterized as perennial run-off streams mostly filled with water in

    winter rainy season and dry in summer. The majority of these streams discharge the water into

    Tigris River with the contribution to the river flow negligible (0.2 MCM on average for the

    year 2008). The area consists of potentially fertile soils characterized as heavy alluvial soils,

    with some organic content and a high proportion of clays. The soil classification is 68.4% silty

    loam, 20.9% silty clay loam and 10.7% is clay soil. The river bed is composed of fine sand, silt

    and clays with rather high sedimentation load.

    No analysis is available for the ambient water quality in the Tigris River at or near the intake

    location of the project, however, no signs of certain contamination were observed. A study was

    W01

  • 53

    made on ambient water quality of the River further downstream at Baghdad (based on sampling

    campaign Jun-Dec 2008)3 and the results have shown that the pH for the water samples vary

    from 7.91 to 8.1 with an average value 8.02, conductivity vary from 793.42 to 1189.76 µs/cm,

    TDS values range from 519.17 to 787.67 mg/L with an average value of 700.77 mg/L, turbidity

    values range from a minimum of 24.58 to a maximum of 33.22 with an average value of 28.06

    (NTU), Ca is ranging from 136.67 mg/L to 69.38 mg/L, SO4 has an average concentration of

    303.17 mg/L, chloride concentration ranges from 64.25 mg/L to 100.92 mg/L, and Al and Fe

    range from 0.11 to 0.77 mg/L, respectively. The Iraqi Standard for drinking water is presented

    in Table 11 in Chapter 4.1.2.

    3.4 Climate

    The climate in the project area is characterized as Mid-steppe and desert climate. The average

    temperature for the year in Tikrit is 22.2°C. The warmest month, on average, is July with an

    average temperature of 35°C. The coolest month on average is January, with an average

    temperature of 9.4°C.

    The highest recorded temperature is 48.9°C in July. The lowest recorded temperature is -4.4°C

    in February.

    The average amount of precipitation per year in is 348 mm. The month with the most

    precipitation on average is December with 78.7 mm of precipitation. The month with the least

    precipitation on average is June with an average 0 mm. In terms of liquid precipitation, there

    are an average of 27.1 days of rain, with the most rain occurring in December with 5.8 days of

    rain, and the least rain occurring in June with 0.0 days of rain.

    3 Khadem, A.J. Assessment of Water Quality in Tigris River-Iraq by Using GIS Mapping, Natural Resources,

    2013, 4, 441-448.

  • 54

    Figure 7: Temperatures and Precipitation in the Project Area (2002-2012)

    The predominant wind direction is Northeast in the months November through to April, and

    predominantly north-west in the months May-October. The mean average wind speed is 10-12

    km/h with the wind gusts reaching up to 26-28 km/h.

    3.5 Air Quality and Noise

    At present, there is no information on ambient air quality in the project area; no measurements

    on air quality were performed previously. The area is predominantly agricultural rural area.

    Although there are oil fields in the Khanaqin District, their approximation to the project area

    is unknown at present. The roads in the area are mostly rural unpaved roads and roads in rather

    bad conditions partially destroyed due to the war conditions in recent years. The main source

    of pollution is dust generated through the agricultural activities and use of the rural roads in

    addition to the dust generated by windy conditions during dry periods. Potentially, there might

    be the additional air pollution from the operating oil fields and/or refineries.

    Similarly, no information on noise levels is available for the project area. However, the noise

    level in the rural area with limited vehicle movement and limited agricultural activities is not a

    significant issue.

  • 55

    3.6 Biological Environment

    3.6.1 Terrestrial Environment

    The project area is located in the Mesopotamian shrub desert terrestrial eco-region4 considered

    as a transitional zone between the Syrian Desert and steppe region further north. This terrestrial

    eco-zone is categorized as vulnerable and due to the security concerns have received little

    focused study.

    Figure 8: Mesopotamian Shrub Desert Borders

    The vegetation of the region is similar to the Irano-Turanian eco-region and is characterized by

    the dominance of the drought-tolerant low shrubs with a variety of grasses and legumes.

    Herbaceous and dwarf shrub sage brush (Artemisia sp) communities tend to dominate in

    deeper, non-saline soils and often occur in association with grasses. The recorded vegetation is

    presented in the Table below:

    Table 3: Typical Irano-Turanian Steppe Vegetation

    Retama raetam Artemisia herba-alba Ferula communis

    Noaea mucronata Asphadelus aestivus Lepidium aucheri

    Salsola spp. Urginea maritima Cnicus spp.

    Astragalus spinosis Circium alatum Paronychia argentea

    Ballouta undulata Achillea fragrantissima Hordeum bulbosum

    Thymus capitatus Aegilops ovata Crepis aspera

    4 National Report on Biodiversity in Iraq, July 2010

  • 56

    The area of the project is located in a general area identified as a fly-way route for migratory

    birds from Eastern Europe and West Siberia to Mesopotamia and Africa. The list of known

    bird species recorded in the area is presented in the Table below:

    Table 4: List of the Recorded Bird Species Recorded in the Project Area5

    Scientific name Common name 2015 Red List

    category

    Haematopus ostralegus Eurasian Oystercatcher NT

    Vanellus vanellus Northern Lapwing NT

    Limosa lapponica Bar-tailed Godwit NT

    Calidris canutus Red Knot NT

    Calidris ferruginea Curlew Sandpiper NT

    Larus armenicus Armenian Gull NT

    Francolinus francolinus Black Francolin LC

    Mareca strepera Gadwall LC

    Mareca penelope Eurasian Wigeon LC

    Marmaronetta angustirostris Marbled Teal NT

    Aythya nyroca Ferruginous Duck LC

    Ciconia ciconia White Stork LC

    Plegadis falcinellus Glossy Ibis LC

    Vanellus leucurus White-tailed Lapwing LC *LC-Least Concern; NT – Near Threatened; VU - Vulnerable

    Large mammals that are associated with this ecoregion include: wolves (Canis lupus); Red fox

    (Vulpes vulpes); Golden jackals (Canis aureus); caracals (Caracal caracal); jungle cats (Felis

    chaus); Mongoose species (Herpestes sp); wildcats (Felis silvestris); Common otter (Lutra

    lutra); and Greater Horseshoe Bat (Rhinolophus ferrumequinum). Goitered gazelle (Gazella

    subgutturosa) and European badgers (Meles meles) can be found in more vegetated areas.

    However, the status of these species is unknown and their presence was not recorded and is

    highly unlikely in the project area. The mammalian species recorded in the region include:

    Table 5: Mammals in the Vicinity of the Project

    Scientific Name Common Name IUCN Status

    Hemiechinus auritus Long-eared Hedgehog LC

    Paraechinus aethiopicus Ethiopian Hedgehog LC

    Crocidura suaveolens Lesser white-toothed shrew LC

    Suncus murinus Asian House Shrew LC

    Suncus etruscus Pygmy White-toothed Shrew LC

    5 R.F. Porter et al, Birds of the Middle East, First Princeton Field Guide Edition, 2004

  • 57

    Scientific Name Common Name IUCN Status

    Otonycteris hemprichii Desert Long-eared Bat LC

    Allactaga euphratica Euphrates Jerboa NT

    Jaculus jaculus Lesser Egyptian Jerboa LC

    Gerbillus cheesmani Cheesman's Gerbil