REPUBLIC OF IRAQ - World Bank€¦ · 14/03/2016 · According to the hydro-geological...
Transcript of REPUBLIC OF IRAQ - World Bank€¦ · 14/03/2016 · According to the hydro-geological...
-
1
REPUBLIC OF IRAQ
Ministry of Construction, Housing, Municipalities & Public Works
Emergency Operation Development Projects (EODP)
(P155732)
Environmental and Social Management Plan (ESMP)
For the
AL-AWJA - OWAINAT WATER TREATMENT PLANT IN SALAH AL-
DIN GOVERNORATE
February, 12, 2017
SFG2336 V6P
ublic
Dis
clos
ure
Aut
horiz
edP
ublic
Dis
clos
ure
Aut
horiz
edP
ublic
Dis
clos
ure
Aut
horiz
edP
ublic
Dis
clos
ure
Aut
horiz
ed
-
2
Revision History
Version Revision
Date
Description or
Reason for Change
Discipline
Review
Director
Review Approval
Prepared by: Tatyana Gorskaya
Contributors:
-
3
EXECUTIVE SUMMARY
Introduction
This Environmental and Social Management Plan (ESMP) is prepared in accordance to the
Terms of Reference for Al-Awja - Owainat Water Treatment Plant, Salah Al-Din
Governorate within the framework of Emergency Operation for Development Project
(EODP) (P155732) (IBRD Loan No.: 8520). According to the World Bank environmental
safeguards the project is categorized as Category B.
Project Description
The project is located in the city of Tikrit, Salah Al-Din Governorate, approximately 140
km north of Baghdad.
Figure 1: Administrative Project Location
Output of the water treatment plant in 2200 m3/day for 22 hour operation per day; 1000
m3/hr.
-
4
The project consists of the following components:
Intake stricture.
Low lift pumps.
Sedimentation tank (2).
Filter tanks (6)
Alum system
Chemical building
Chlorine system
High lift pump station
Motor Control Center (MCC) building
Ground reservoir
Supervisory control and data acquisition (SCADA) system.
At present, the facilities are destroyed conditions and in completely non-operational
condition.
Figure 2: Present Condition of the Facilities
The area have received clearance from the Iraqi Armed Forces for the absence of
UXO/REW, however, accidental discovery is still possible. In case of the discovery, the
personnel should be immediately evacuated and armed forces contacted. The works could
be resumed only after removal of the munitions.
-
5
The project will require a Main Camp, the operational center, with prefabricated offices
and parking areas for administration and technical staff. This will also include areas for
materials testing and storage, and equipment cleaning and maintenance. The need for
residential accommodation is likely to be relatively minor. The accommodation at the camp
will be required for the security guards, 2 persons. The construction camp should have
independent sources of water and electricity, and the septic tank for the residential effluent
disposal. The construction camp will be located on the state-owned land within the
perimeter of the existing water pumping station.
The personnel requirements for the project are 47 persons including administrative staff,
technical staff, qualified construction crew and unskilled labor. All workers will be locally
hired.
The project comprises the rehabilitation of the existing facilities with no additional
structures or pipelines to be constructed. Therefore, the project will not require any
permanent or temporary land acquisition. As a result OP 4.12 will not be applied.
The total project duration is 6 months. The main goal of the project is the rehabilitation of
facilities for the provision of the potable water. The project is expected to provide drinking
water to approximately 35000 local residents and IDPs. At present, the residents rely
almost exclusively on the water delivered by water tankers for drinking purposes which
poses additional financial burden on household.
Work consists of a simple civil works such as cleaning work and raise dirt debris resulting
from combat operations and rehabilitation of all the damaged civil buildings such as Intake,
Sedimentation Tank, Filtration Building, Storage Tank, MCC Building and services
buildings and repainting buildings and replace and renovating pipes, bathrooms, doors,
windows and re-paving of internal roads and treatment of cracks in the sedimentation tank
and Storage Tank.
-
6
Most of the works in this project are the electrical and mechanical works include supply,
installation, and operation of the pumps, electric transformers, electric generator and the
replacement of cables and outdoor lightings.
The intake structure shall be constructed from reinforced concrete. The pump sump
(Basement) shall be designed as a water tight structure in two compartments for
independent operation during maintenance with bypass arrangement controlled by a 2 Nos.
sluice valves. The floor of the (Basement) shall be sloped to one corner with a sump to
pump accumulated settled sludge to the river using duplicated submersible pumps. The
Basement shall have access ladder and lighting. The channel from river to the intake
Basement shall be constructed according to the drawing from reinforced concrete the
contractor is responsible to make a full hydraulic study to design the final shape of the
channel. Rip-raping along the shoulder of the river for a distance of 50m from each side of
the channel to protect the structure and to direct the water to the channels. The necessary
arrangements are to be made to minimize the problem of settling of the suspended matter
at the channel bar during high turbidity seasons by using submerged scraping device.
The breakdown of duration of project activities is presented in the Table below:
Table 1: Duration of Construction Activities
# Activity Duration (man days)
1 Cleaning post-combat debris 75
2 Construction of the intake structure 75
3 Rehabilitation of Intake Structure 60
4 Rehabilitation of sedimentation tank 60
5 Rehabilitation of filtration facilities 60
6 Rehabilitation of storage tank 60
7 Rehabilitation of MCC building 60
8 Rehabilitation of service building 60
9 Replacing of pipes 35
10 Repair and paving of roads within the facility 14
11 Installation of doors and windows 28
11 Painting 38
-
7
# Activity Duration (man days)
12 Electrical and mechanical works 42
Baseline Conditions
The project is located in the city of Tikrit, Salah Al-Din Governorate, Iraq. The project
location is approximately 140km north of capital city of Baghdad. The project is located
directly on the bank of the Tigris River. The area is void of residential settlements,
industrial facilities and predominantly used for livestock grazing and limited rain-fed crop
cultivation during rainy periods.
Regional Geology, Topography and Seismic Activity
Stratigraphically, the project area is dominated by geological formations ranging from
Middle Miocene to Quaternary. In the project location the geological formation is
composed of thin-bedded, black bituminous limestone, dolomitic limestone and black
papery shale with streaks of thin black chert. The terrain is characterized as flat to gently
rolling plains, hills, and mountains. In the project area the elevations are ranging between
300-550 m asl. The maximum elevation is 543.5 m asl and the minimum elevation is 313.9
m asl.
The project area is located in the minor damage zone with the seismic activity of I-II on
MM scale.
Water Resources
According to the hydro-geological classification of Iraq, the project area is located in the
Low Fold hydro-geological zone. The Low Fold zone is filled by sedimentary formations
that range in age from Late Miocene to Recent: Fatha, Injana, Mukdadiyah and Bai Hassan,
and Quaternary cover. These formations represent the main aquifers in this zone. The
general trend of the groundwater movement is mainly from north and northwest towards
south and southeast.
The groundwater quality in the project area is slightly brackish with the salinity of 1000-
3000 ppm. The groundwater depth in the project area ranges from 10-20 m below surface.
-
8
The area consists of potentially fertile soils characterized as heavy alluvial soils, with some
organic content and a high proportion of clays. The soil classification is 68.4% silty loam,
20.9% silty clay loam and 10.7% is clay soil. The river bed is composed of fine sand, silt
and clays with rather high sedimentation load.
Climate
The climate in the project area is characterized as Mid-steppe and desert climate. The
average temperature is 22.2°C. The warmest month, on average, is July with an average
temperature of 35°C. The coolest month on average is January, with an average
temperature of 9.4°C. The average amount of precipitation per year is 348 mm per year.
The predominant wind direction is Northeast in the months November through to April,
and predominantly north-west in the months May-October. The mean average wind speed
is 10-12 km/h with the wind gusts reaching up to 26-28 km/h.
Ambient Air Quality and Noise
At present, there is no information on ambient air quality in the project area; no
measurements on air quality were performed previously. The roads in the area are mostly
rural unpaved roads and roads in rather bad conditions partially destroyed due to the war
conditions in recent years. The main source of pollution is dust generated through the
agricultural activities and use of the rural roads in addition to the dust generated by windy
conditions during dry periods. Potentially, there might be the additional air pollution from
the operating oil fields and/or refineries.
Similarly, no information on noise levels is available for the project area. However, the
noise level in the rural area with limited vehicle movement and limited agricultural
activities is not a significant issue.
Biological Environment
The project area is located in the Mesopotamian shrub desert terrestrial eco-region
considered as a transitional zone between the Syrian Desert and steppe region further north.
This terrestrial eco-zone is categorized as vulnerable and due to the security concerns have
received little focused study.
-
9
Vegetation reflects the Mesopotamian province of the Irano-Turanian eco-region and is
characterized by the dominance of the drought-tolerant low shrubs with a variety of grasses
and legumes.
The area of the project is located in a general area identified as a fly-way route for
migratory birds from Eastern Europe and West Siberia to Mesopotamia and Africa.
The riparian vegetation predominantly comprises reeds and rushes that grow in the wetland
areas and poplars, willows and tamarisk trees along river channels, banks, and beside
irrigation ditches throughout the country. The freshwater habitats of the marshlands, which
are part of the Tigris‐Euphrates River Eco-region, are surrounded by desert xeric shrub
lands and therefore are considered as important corridors for the wildlife.
The project area is located in a close proximity to the Important Bird Area (IBA) –
Samarrah Wetland, approximately 2.5-3 km north of the IBA. No conservation practices
are exercised in the project area apart from the control of hunting to the extent they are
controlled and monitored throughout the country.
Socio-Economic Environment
The total population of the Salah Al-Din Governorate is 1.5 million people, the population
of Tikrit is approximately 160,000. The main demographic indicators are:
Population growth rate is 2.6%, according to the available statistics until 2014;
Age category of less than 15 years is 40% in 2012; the category of 15- 64 years of
age is %56.9 in 2012.
Population percentage in the urban areas is 69%, rural population was 31% for
2014.
Economic activity in Salah Al-Din is centered around agriculture. 44% of the
governorate’s workforce is employed in the agricultural sector, the highest
percentage among all 18 provinces.
Salah Al-Din has 18% unemployment rate, and 39.9% live below the poverty line
of $2.20 per day.
-
10
Illiteracy rate is 15.7% with the school enrollment: 78.3% primary education;
14.7% secondary education.
Education: One university (Tikrit University, 2900 students), 269 secondary
schools, 16 vocational schools (commercial, industrial and technical), 11 teacher
training institutes.
Health: Salah Al-Din has 9 hospitals and 13 public medical clinics.
Access to drinking water: 72.5%.
Access to sanitary network: 82.4%.
No sanitary landfills in the area, only authorized dumping sites; municipal waste
collection rate is 43.1%
Access to electricity grid: 89.6%
Legal Aspects
The applicable national legislation is as following:
The Law for the Protection and Improvement of Environment No. 27, 2009;
Forests and Woodlands Law No. 30 of 2009;
Protection of Wild Animals and Birds No. 21 of 1979;
Regulating Exploitation and Protection of Aquatic Life No. 46 of 1976;
Ministry of Water Resources Law No. 50 of 2008;
Public Health Law No. 89 of 1981, amended by Resolution No.54 of 2001;
Iraqi Drinking Water Standard No. (417)-2001;
Regulation for the Provision of Water Resources, No. 2, 2001;
Regulation for the Protection of Rivers No. 25, 1967;
Law No. 27 of 1999 concerning the establishment of the General Authority for
Water and Sewage;
Instructions No. 2 of 2014 on Environmental Protection from Municipal Waste;
Directive No. (67) of 1986 Regulating the Debris Collection Areas;
Clean Air Act No. 1 of 2004;
-
11
Noise Prevention Law No. 21 of 1966;
Directive No. 4 of 1993 concerning occupational health, protection of workers
against vibration;
Instructions No. 3/1985 Concerning Occupational Safety;
Law No. 6 of 1988 concerning the National Commission for Occupational Hygiene
and Safety;
Law No. 55 of 2002 for The Antiquities & Heritage of Iraq;
Acquisition Law No.12. of 1981
At present, there is no national Building Code in Iraq and the most commonly used are the
ACI 318 codes.
The main WB safeguard policies triggered by this project are:
OP/BP 4.01 Environmental Assessment
OP/BP 4.11 Physical Cultural Resources
BP 17.50 Disclosure Policies
OP 7.50 Projects on International Waterways
According to OP 7.50 the riparian countries sharing the same water bodies should be
informed about any developmental projects on international waterways. However, in case
of this project the exceptions of notifying the riparian countries are applicable since the
project is located in the lowest downstream riparian and will not adversely affect the quality
and quantity of the water of other riparian states.
In case of the difference between the National Legislation and WB Safeguard Guidelines,
it has been agreed that the WB instructions will prevail over the national legislation
provisions.
The EHS Guidelines applicable to the project are:
Environmental, Health, and Safety General Guidelines
EHS Guidelines for Water and Sanitation
-
12
When host country regulations differ from the levels and measures presented in the EHS
Guidelines, projects will be required to achieve whichever is more stringent.
Impacts Assessment
The assessment of the potential adverse impacts on different environmental parameters
during the construction phase was done using the Leopold Matrix: on the horizontal axis,
the actions which cause environmental impact, and on the vertical axis, the existing
environmental receptors which may be affected by those actions.
Rehabilitation/Construction Phase
The adverse impacts of the rehabilitation/construction activities are expected to be minor
to moderate and short-term. None of the identified impacts is evaluated as particularly
severe. The anticipated impacts are:
Increased potential of soil contamination during cleaning activities, inadequate
waste disposal;
Accidental spillage of fuel and lubricants during transportation of the construction
materials;
Contamination of groundwater through the leachate from improperly disposed
construction debris and materials containing hazardous matter;
Increased dust generation during clearance, and movement of heavy equipment and
machinery;
Increased noise and vibration levels during removal of post-combat debris, and
heavy machinery movement;
Potential of discovery of the artifacts during excavation and unintentional damage
to those in case of accidental discovery;
Some damage to landscape during clearance reducing the aesthetic appearance of
the area;
Habitat fragmentation of the freshwater habitat could occur during the construction
of the intake structure due to the installation of the cofferdam thus causing the
diversion of the water flow and additionally increased turbidity of the water.
-
13
Operation Phase
During operational phase the impacts are anticipated to be minor. The scheduled
maintenance works and repairs in case of emergency are very short-term and localized,
therefore their impact is also considered as minor. The anticipated adverse impacts are:
Potential soil contamination due to accidental overflow of the storm water drainage
system;
Surface water contamination through overflow of storm water, disposal of
hazardous materials during regular and emergency maintenance;
Air pollution due to the operations of the diesel generator and pumps, emissions of
hazardous substances during the cosmetic maintenance of the buildings;
Biodiversity: the impacts on biodiversity are considered very minor and localized
and mostly related to the potential pollution of the habitat due to the inadequate
waste management.
Land use impacts are considered very minor and are related to inadequate waste
management.
Risk of ponding that may provide the breeding grounds to nuisance and disease
carrying insects.
Indirect, Cumulative and Residual Impacts
Indirect impacts are considered to be minor: transportation of materials, excavation,
clearance contribute to dust generation and vehicle and equipment emissions which settle
on soils and in run off valleys during dry season consequently contributing to the transport
of sediments and pollutants to the main water bodies and infiltration into the shallow
aquifer.
The main cumulative impact anticipated through implementation of this project is the
incremental effect on of construction waste disposal on the waste management in the area
already suffering from the lack of disposal facilities.
Residual or irreversible impacts are considered to be very minor and mostly concern the
use of the construction debris dumping sites as permanent municipal waste disposal areas.
-
14
Environmental and Social Management Plan
The ESMP contains management measures avoidance, mitigation, as well as enhancements
that would be implemented during the construction and operation/maintenance phase of
the project.
-
15
Mitigation Measures during Rehabilitation Phase
Receptor Mitigation Measures Responsibility Supervision Total estimated
Cost in US$
1 Air quality
Vehicle emissions
Contractor to keep vehicles and machinery properly operated and maintained. Contractor to minimize unnecessary vehicle idling. Switch off any engine as soon as it is not used. Dust
Minimize dust from materials (such as sand, cement) and construction activities by using covers, storage, control equipment, and increasing
moisture content.
Prepare concrete before going to the site to avoid movement of materials (gravel, sand, cement) if possible
Minimize dust from vehicle movements, using water sprays or appropriate. Avoid the burning of materials on site. Switch off any engine as soon as it is not used. Hazardous Emissions
Avoid storage of hazardous materials in open areas without proper covering; Provide adequate ventilation for work areas
Contractor Contractor/Resident
Engineer
PMT
The bidders will
be able to
include these
costs in their
bidding.
Additional cost:
1500 US $
2 Noise
Noise and vibration management
Avoid or minimize transport through community areas. Switch off any engine as soon as it is not used. Contractor to minimize unnecessary vehicle idling Muffling of the equipment; Additional health check-ups for personnel handling the vibrating and noisy
equipment
Contractor Contractor/Resident
Engineer
PMT
Additional cost
for medical
check ups
2000 US $
-
16
Receptor Mitigation Measures Responsibility Supervision Total estimated
Cost in US$
3 Water resources
Water run-off management (drainage plan)
Raw materials used in construction, which can be carried by water runoff, must be located and stored away from paths for water runoff.
Where possible or appropriate, schedule works to avoid heavy rainfall periods (i.e. during the dry season) and modify activities during extreme
rainfall and high winds.
Contractor Contractor/Resident
Engineer
PMT
Hydrogeological
Investigation:
500 US $
4 Soil
Disposal of contaminated soil by truck to nearest authorized dumping areas. If surface drainage is disturbing the construction process, utilizing ditches,
dikes and/or sandbags to divert this drainage from entering excavations.
Adverse weather
Site engineer is to monitor weather on a daily basis. No construction activities to
be undertaken in strong winds or rains.
Contractor Contractor/Resident
Engineer
PMT
Delineation of
excavated areas:
300 US $;
Emergency soil
testing in case of
accidental spills:
1000 US $
5
Solid and
hazardous
wastes
General:
Keeping the site clean and tidy: a. Ensure there is no loose materials or debris lying around the site including the
perimeter; and
b. Vehicles are regularly checked for cleanliness (general aspect and making sure
no leaks are occurring)
Burning of waste is prohibited Reducing construction waste related to on-site construction and off-site
manufacture or fabrication.
Reusing the material on site (in situ or for new applications) whenever it is possible
Contractor Contractor/Resident
Engineer
PMT
Additional costs
for disposal of
hazardous
materials:
3000 US $
-
17
Receptor Mitigation Measures Responsibility Supervision Total estimated
Cost in US$
Monitoring the amount of site construction waste created to make sure it does not affect the surrounding and the adjacent areas.
- Waste is not blocking pathways
- Construction waste will be gathered in a specific zone of the construction
site
Contractor to evacuate any construction waste to nearest authorized dumping site and on a regular basis to avoid accumulation
All staff will avoid littering. Provide the septic tank for the residential effluent from the construction camp
to be disposed regularly at the designated areas.
Hazardous materials:
Provide adequate secondary containment for fuel storage tanks and for the temporary storage of other fluids such as lubricating oils and hydraulic fluids.
Use impervious surfaces for refuelling areas and other fluid transfer areas. Provide portable spill containment and clean-up equipment on site, and train
staff in the safe use of it.
Provide adequate sanitation facilities serving all workers (mentioned in HSE).
Paints with toxic ingredients or solvents or lead-based paints will not be used
6 Flora & Fauna
Provide training to the construction crew on the impact of disturbance and damage to habitats;
Monitor the construction crew and provide punitive measures for illegal hunting and/or fishing;
Provide the crew with fuel for cooking to avoid burning of natural materials; Apply waste management plan Provide regular dredging around the cofferdams for the intake structure to
ensure sufficient depth and avoid creation of whirlpools around the
cofferdam which will cause increased turbidity of the water; Strictly prohibited disposal of any of the construction materials into the river; In order to avoid damage to the vulnerable habitats and species, the
construction works on the water intake is to take place during the dry season
Contractor Contractor/Resident
Engineer
PMT
Training if
conducted by the
third party:
400 US $
-
18
Receptor Mitigation Measures Responsibility Supervision Total estimated
Cost in US$
when the level of the water in the river is the lowest and the breeding season
is over; The under water intake structure should be located at least 1m below the
surface and inflow velocity should not exceed 1.5 m/s to avoid suction in of
young fish
7 Topography and
surface drainage
Storage areas for construction materials should be located at sites that do not permit direct runoff into watercourses and are on land sloping at less than 1.5 %.
Time limitation on works during rainy events; Regular maintenance of the equipment and machinery to avoid spillage of
hazardous materials;
Re-vegetation of cleared areas Timely and adequate disposal of liquid and solid waste in authorized areas.
Contractor Contractor/Resident
Engineer
PMT
Re-vegetation
cost:
1000 US $
8 Access and
traffic
Set up warning signs in the workplace: o All safe footpaths are marked; construction materials are not
blocking pathways
o Site entrances and exits are clearly marked for visitors and delivery drivers to see; and
o If present, site reception is clearly signposted OR all visitors are escorted to the reception.
Designating specific parking areas for workers’ and visitors’ vehicles outside the construction area.
Avoid or minimize transport through community areas. Traffic management system and staff training, especially for site access and
near-site heavy traffic.
Adjustment of working hours to local traffic patterns, e.g. avoiding major transport activities during rush hours or times of livestock movement
Contractor Contractor/Resident
Engineer
PMT
Additional costs
for marking and
signage:
300 US $
9 Health and
Safety Provide adequate signage to prevent accidental falling into open areas Fencing of the work areas
Contractor Contractor/Resident
Engineer
No additional
costs; the cost is
imbedded in
-
19
Health and safety environment (HSE)
There is posted material indicating the nearest police station and hospital (with accident and emergency facilities).
The contractor must take reasonable steps to prevent unauthorized people accessing the site.
Training on handling of UXO/ERW Avoid the burning of materials on site. Provide a first aid kits in different places of the work site with the appropriate
number of materials given the number of workers on site. The locations of
the first aid kits will be provided to all workers.
Providing extinguishers on work site. If work involving the use of flammable materials is being carried out, stop
people smoking and do not allow other work activities involving potential
ignition sources to take place nearby. Providing site boundaries by installing suitable physical boundaries (barriers,
tape or fence).
Marking excavation holes with physical boundaries (barriers, tape or fence) The contractor should put up barriers or covers in the area of openings and
excavations.
Store building materials (such as pipes, manhole rings, and cement bags) so that they cannot topple or roll over.
Keep walkways and stairways free of tripping hazards such as trailing cables, building materials, and debris.
Everyone who works on any site must have access to adequate toilet and washing facilities, a place for preparing and consuming refreshments, and an
area for storing and drying clothing and personal protective equipment (PPE). Contractor to ensure PPE (personal protective equipment) is used by all
workers on site.
Materials and equipment are tidily stacked, protected and covered where necessary. Additionally, there is adequate space for new materials to be
stored in secured covered areas to avoid damage, theft, and to protect these
items from weather conditions.
Scaffolding for work in elevated areas such as ceiling painting should comply with the OSHA “General Requirements for Scaffolds §1926.451”
PMT mandatory HSE
measures
-
20
Receptor Mitigation Measures Responsibility Supervision Total estimated
Cost in US$
10 Handling
Complaints
Reducing impacts on the community through community and neighbour engagement.
In cases of where there are minority communities speaking a different language in the area or working on site, notices are printed in the common
local language.
Provide the proper GRM for handling complaints
Contractor Contractor/Resident
Engineer
PMT
No additional
costs
11 Physical cultural
resources
In case of accidental discovery stop all works and contact the responsible authority within 24 hours;
Provide training to the construction crew on the mode of conduct in case of accidental findings
Contractor Contractor/Resident Engineer
PMT
No additional
costs
Total cost US$ (rehabilitation phase) 10,000 US $
Mitigation Measures during Operation Phase
Receptor Mitigation Measures Responsibility Supervision Total estimated
Cost in US$
1 Air quality
including odors
Water spraying for dust control in maintenance areas;
Timely disposal of effluent from sanitary facilities in office buildings;
Timely disposal of domestic waste
Operator PMT No additional
costs
2 Noise Provision of PPE to maintenance personnel while handling the equipment Operator PMT No additional
costs
-
21
Receptor Mitigation Measures Responsibility Supervision Total estimated
Cost in US$
3 Water resources Timely and adequate disposal of debris generated by maintenance activities and
solid and liquid waste from office building;
Maintaining the drainage ditches and manholes unblocked
Operator PMT No additional
costs
4 Soil Maintaining the drainage channels unblocked;
Adequate disposal of waste
Operator PMT No additional
costs
5
Solid and
hazardous
wastes
Use of non-toxic paints for repairs of the buildings;
Storage of hazardous materials used for repairs in sealed containers;
Disposal of waste to authorized disposal sites;
Avoid disposal of effluent into the river
Undertake measures necessary to prevent leakage of chlorine gas from pipe
work connection between the liquid chlorine gas.
o A pictorial representation of the procedure for changing liquid chlorine
containers with written instructions where necessary in Arabic and on
plastic covered card mounted on a board fixed to the inside wall of the
chlorine store. All tools necessary for changing the containers shall also
be clipped to this board.
o All necessary washers and couplings required when changing
containers sufficient for five years operation.
o A water spray bar to provide a water curtain fixed externally over the
chlorine store and connected via solenoid operated valve direct to the
delivery main from pumping station. The solenoid valve. This system
must be provided with manual starting from outside the room for
emergency.
Filter backwash should be discharged into the sludge pit to be disposed
according to the specification
Operator PMT No additional
costs
-
22
Receptor Mitigation Measures Responsibility Supervision Total estimated
Cost in US$
6 Flora & Fauna Keeping the manholes and ditches clean;
Adequate waste disposal;
Re-vegetation with the plants native to the area
Operator PMT No additional
costs
7 Handling Complains
Compliance with GRM Operator PMT No additional
costs
8 Public hygiene
and quality of
water
Adequate waste disposal; Prevent leakages of water and accumulating of water in ponds prone to
stagnation;
Regular water testing for the compliance with the drinking water standard
Operator PMT No additional
costs
Total cost US$ (Operation phase) No additional
costs
-
23
Environmental and Social Monitoring Plan
The ESMP will be shared with the contractor who will be contractually obligated to abide
by it, with financial clauses associated to this obligation. Impacts are mitigated by detailed
mitigation measures. Those measures are presented as a set of checklists that the contractor
will follow.
The following tables present monitoring measures in order to perform a non-harmful
implementation of the project works to the environment and to reduce the risk of negative
environmental impacts as far as possible.
The frequency of the reporting:
During rehabilitation/construction phase: bi-weekly
During operation phase: quarterly
-
24
Monitoring Activities during Rehabilitation Phase
Receptor Monitoring
Activities Monitoring Indicators Frequency Responsibility Supervision
Total
estimated
Cost in US$
1 Air quality including odors
Site inspection with
the photo
documentation;
Air quality testing
Air quality
parameters: PM10,
PM2.5, SO2, NOx,
CO, Ozone and HC
Compliance with
dust abatement
measures
Inspection: weekly
Testing: Once prior to
the start of construction
works to establish a
baseline and once
during the construction
phase during the dry
season.
Contractor Resident
engineer
Testing done
by accredited
laboratories.
Additional
cost 2000 US
$
Camera: 250
US $
2 Noise
Site inspection measuring the level
of noise
Compliance with the time limitations;
Switching off the equipment not in
use;
Use of protective gear
Weekly Contractor Resident engineer
Hand held device for
nose level
measuring:
200 US $
3 Water resources
Site inspection with photo
documentation;
Water testing
Inspection:
debris accumulation in water drainage
areas;
Alteration of water courses;
Signs of spillage of hazardous materials
Inspection:
Bi-weekly during the rainy season,
and after sporadic
rains
Once a month during the dry
periods
Contractor Resident
engineer
Testing done
by accredited
laboratories.
Additional
cost 3000 US
$
No additional
costs for
testing during
-
25
Receptor Monitoring
Activities Monitoring Indicators Frequency Responsibility Supervision
Total
estimated
Cost in US$
Water testing (general):
pH, Turbidity,
Electrical Conductivity
(EC), Color, Total
Suspended Solids (TSS), Total Dissolved
Solids (TDS), Chemical
Oxygen Demand
(COD), Biological
Oxygen Demand
(BOD), Polychlorinated
Biphenyls (PCBs)
Water testing during
intake construction:
Turbidity, Color, Total
Suspended Solids
(TSS), Total Dissolved Solids (TDS)
Water testing: in the
location of accidental
spills of hazardous
materials
intake
construction
4 Soil
Site inspection with photo
documentation;
Soil testing
Inspection: signs of soil
erosion, evidence of
spills of fuel and
lubricants
Soil testing:
Inspection: bi-weekly;
Testing of the contaminated soil in
the location of
accidental spills of
Contractor Resident
engineer
Testing done
by accredited
laboratories.
Additional
cost 3000 US
$
-
26
Receptor Monitoring
Activities Monitoring Indicators Frequency Responsibility Supervision
Total
estimated
Cost in US$
pH, temperature,
organic content, poly-
aromatic hydrocarbons
(PAHs); Faecal
coliforms and Total coliforms
hazardous materials
if any
5 Solid and hazardous wastes
Site inspections
Maintaining a record of type,
quantity, and
disposal location
of solid and
liquid waste
generation;
Storage conditions of hazardous
materials;
Disposal at designated sites
Inspection: bi-weekly Contractor Resident
engineer
No additional
costs
6 Traffic
Site inspections Site surveillance for the
presence of
fencing/barriers and
warning signs, and traffic speed limitations
Monthly Contractor Resident
engineer
No additional
costs
7 Flora & Fauna
Site inspections Degree of habitat disruption due to
construction activities:
clearance of
vegetation, signs of
fire, presence of
fishing and hunting
equipment
Degree of workers perception of
Inspection: bi-weekly Contractor Resident
engineer
No additional
costs
-
27
Receptor Monitoring
Activities Monitoring Indicators Frequency Responsibility Supervision
Total
estimated
Cost in US$
necessity of habitat
conservation
Site restoration after work completion
8 Topography and surface
drainage
Inspection and photo evidence
Location of storage areas;
Ceasing construction
activities during
rainy events;
Re-vegetation of cleared areas
Records of waste disposal.
Inspection: bi-weekly Contractor Resident
engineer
No additional
costs
9
Handling Complains
Maintaining records of filed
complaints and
responses
Time of response to the complaint;
Number of complaints
Monthly Contractor Resident
engineer
No additional
costs
10 Public health and safety
Inspection and photo evidence
Maintaining records of injuries
and accidents with
cause and location
Provision and use of personal protective
equipment to workers
Installing construction and warning signs
Inspection: bi-weekly Contractor Resident
engineer
No additional
costs
Total cost US$ (Operation/Maintenance phase) 8,450 US $
-
28
-
29
Monitoring during Operation Phase
Receptor Monitoring Activities Monitoring Indicators Frequency Responsibility Supervision Total
estimated
Cost in US$
1 Air quality
Surveillance Presence of unpleasant
odors;
Dust abatement
measures
Bi-weekly Operator WSD No additional
costs
2 Noise
Noise level
monitoring
Ensure the noise levels
are within the acceptable
limits
During maintenance and
repairs
Operator WSD No additional
costs
3 Water resources
Surveillance;
Water testing
Ensure the drainage channels and culverts
are clear of debris
Water quality testing: pH, Turbidity, Electrical
Conductivity (EC),
Color, Total Suspended
Solids (TSS), Total
Dissolved Solids (TDS),
Chemical Oxygen
Demand (COD),
Biological Oxygen
Demand (BOD), Polychlorinated
Biphenyls (PCBs)
Surveillance:
Bi-weekly during the rainy season
Monthly during the dry season
Water testing: Once per
year during rainy season
Operator WSD 500 for water
testing
-
30
Receptor Monitoring Activities Monitoring Indicators Frequency Responsibility Supervision Total
estimated
Cost in US$
4 Soil
Surveillance;
Soil testing Ensure the drainage
channels and culverts
are clear of debris
Soil testing: pH, temperature, organic
content, poly-aromatic
hydrocarbons (PAHs )
Surveillance:
Bi-weekly during the rainy season
Monthly during the dry season
Soil testing: Once per
year during rainy season
at the location of
disposal of filter
backwash
Operator WSD 300 for soil
testing
5 Solid and hazardous wastes
Surveillance;
Maintaining records of
quantities of waste
and location of its
disposal
Waste disposed at
designated areas
Monthly Operator WSD No additional
costs
6 Flora & Fauna
Surveillance Condition of the
manholes and ditches;
Level of re-vegetation;
Absence of ponds
Surveillance:
Bi-weekly during the rainy season
Monthly during the dry season
Operator WSD No additional
costs
7 Topography and surface
drainage
Surveillance Disposal of debris during
maintenance and repairs
Monthly Operator WSD No additional
costs
-
31
Receptor Monitoring Activities Monitoring Indicators Frequency Responsibility Supervision Total
estimated
Cost in US$
8 Access and traffic Surveillance Presence of warning
signs at maintenance site
During maintenance and
repair works
Operator WSD No additional
costs
9 Health and Safety
Surveillance;
Maintaining records of quantities of waste
and location of its
disposal
Adequate warning about scheduled
maintenance works;
Timely and adequate disposal of waste
Monthly Operator WSD No additional
costs
10 Handling Complaints Record keeping on
received complaints
Number of complaints
and responses Quarterly
Operator WSD No additional
costs
11 Physical cultural resources N/A N/A N/A N/A N/A
Total cost US$ (Operation/Maintenance phase) 800 US $
per year
-
32
-
33
Public Consultations
Due to the security concerns the general public consultation meeting was not possible to
be conducted. However, a mini public consultation was conducted in addition to interviews
with the residents of the area with the help of the questionnaire by the PMT on Nov.28,
2016. The interviewed persons included 5 men and 3 women. During the meeting the local
community was presented with the project details and the team addressed their concerns
and recommendations. All present agreed that the reconstruction activities will have a
strong positive impact from the social perspectives on the local community and will
encourage the development of the area. Please refer to annexes 2 and 3 for more details.
1. No claims were recorded or alleged regarding the ownership of the land where the
rehabilitation activities to take place; all agreed that is governmental land property.
2. No vegetation covers, crops, plants, trees…etc. will be removed in order to execute
the rehabilitation activities.
3. No infrastructure will be affected negatively due the reconstruction activities.
4. No dislocation or resettlement will be needed for the implementation of the project.
5. Information about a grievance mechanism was introduced and a translated GRM
form was also provided. The participants were informed that they can submit their
complaint to either site engineer, or to community leader or to PMT during
construction.
Grievance Redress Mechanism
Bank procedures require that Grievance Redress Mechanisms (GRMs) be established and
operational prior to commencement of the project, and that they continue to operate for one
year following completion of the works for third party settlement of disputes. This GRM
should take into account the availability of judicial recourse as well as traditional and
community dispute resolution mechanisms.
The project grievance redressed system should be developed in consultation with
communities, which might include the following for written complaints:
-
34
1. First, the affected person sends his/her grievance in writing to the
communities’/community leaders. The grievance note should be signed and dated
by the aggrieved person. Where the affected person is unable to write, s/he should
obtain assistance from the community to write the note and mark the letter with
his/her thumbprint. The community should respond within 14 days.
2. Second, if the aggrieved person does not receive a response or is not satisfied with
the solution provided by the community, s/he lodges her or his grievance to PMT
which should respond within 14 days.
3. Third, if the aggrieved person is not satisfied with the solution of PMT, s/he can go
to the court.
In any case, the PMT must maintain records of grievances and complaints, including
minutes of discussions, recommendations and resolutions made. Participants were
informed that they can submit their complaint to either site engineer, or to community
leader or to PMT during construction. The community leaders’ information (mobile phone
number) and PMT contact information (office and mobile phone numbers) will be available
before implementation starts and will be posted at the entrance of the project site.
-
35
Table of Contents
EXECUTIVE SUMMARY ................................................................................................. 3
Introduction .......................................................................................................................... 3
Project Description ................................................................................................................ 3
Baseline Conditions .............................................................................................................. 7
Regional Geology, Topography and Seismic Activity .................................................... 7
Water Resources ............................................................................................................ 7
Climate ........................................................................................................................ 8
Ambient Air Quality and Noise ...................................................................................... 8
Biological Environment ................................................................................................. 8
Socio-Economic Environment ........................................................................................ 9
Legal Aspects...................................................................................................................... 10
Impacts Assessment ............................................................................................................ 12
Rehabilitation/Construction Phase ................................................................................ 12
Operation Phase ........................................................................................................... 13
Indirect, Cumulative and Residual Impacts .................................................................. 13
Environmental and Social Management Plan ....................................................................... 14
Noise and vibration management ............................................................................. 15
Water run-off management (drainage plan) .............................................................. 16
Adverse weather ...................................................................................................... 16
Health and safety environment (HSE) ...................................................................... 19
Environmental and Social Monitoring Plan ......................................................................... 23
Public Consultations............................................................................................................ 33
Grievance Redress Mechanism ............................................................................................ 33
Table of Contents .............................................................................................................. 35
List of Tables ..................................................................................................................... 39
-
36
List of Figures.................................................................................................................... 40
List of Abbreviations ......................................................................................................... 41
1 INTRODUCTION ...................................................................................................... 42
2 PROJECT DESCRIPTION ....................................................................................... 43
2.1 Project Objectives and Outcomes ............................................................................. 43
2.2 Main Project Components ........................................................................................ 44
2.3 Condition of Existing Facilities ................................................................................ 44
2.4 Clearance of UXO/ERW .......................................................................................... 45
2.5 Construction Camp ................................................................................................... 45
2.6 Personnel Requirements ........................................................................................... 46
2.7 Land Acquisition ...................................................................................................... 47
2.8 Project Duration ....................................................................................................... 47
3 BASELINE CONDITIONS ....................................................................................... 49
3.1 Project Location ....................................................................................................... 49
3.2 Regional Geology, Topography and Seismic Activity ............................................... 50
3.2.1 Geological Formations in the Project Area ..................................................... 50
3.2.2 Seismology .................................................................................................... 50
3.3 Water Resources ....................................................................................................... 51
3.4 Climate ..................................................................................................................... 53
3.5 Air Quality and Noise ............................................................................................... 54
3.6 Biological Environment ............................................................................................ 55
3.6.1 Terrestrial Environment ................................................................................. 55
3.6.2 Aquatic Environment ..................................................................................... 57
3.6.3 Status of Habitats ........................................................................................... 58
3.6.4 Status of Species ............................................................................................ 59
3.7 Socio-Economic Baseline Conditions ....................................................................... 59
3.7.1 Demographic Indicators ................................................................................. 59
-
37
3.7.2 Land Use ....................................................................................................... 60
3.7.3 Services ......................................................................................................... 60
3.7.4 Sites of Archeological, Historical, Cultural and Religious Importance ............ 60
3.7.5 Roads Infrastructure ....................................................................................... 61
4 LEGAL ASPECTS ..................................................................................................... 62
4.1 National Legislation ................................................................................................. 62
4.1.1 General Environmental Legislation ................................................................ 62
4.1.2 Water Resources ............................................................................................ 62
4.1.3 Waste Management ........................................................................................ 65
4.1.4 Air Quality ..................................................................................................... 66
4.1.5 Ambient Noise and Vibration ......................................................................... 66
4.1.6 Occupational Health and Safety ..................................................................... 67
4.1.7 Cultural resources .......................................................................................... 67
4.1.8 Land acquisition............................................................................................. 68
4.2 International Conventions and Treaties ..................................................................... 68
4.3 Applicable Engineering Standards ............................................................................ 68
4.4 WB Safeguard Policies ............................................................................................. 71
4.4.1 Environmental, Health, and Safety Guidelines ............................................... 73
5 ENVIRONMENT AND SOCIAL IMPACT ASSESSMENT ................................... 77
5.1 Impacts Significance Evaluation during Rehabilitation Phase ................................... 77
5.2 Potential Adverse Impacts during Rehabilitation Phase............................................. 80
5.2.1 Impacts on Soil .............................................................................................. 80
5.2.2 Impacts on Water Resources .......................................................................... 80
5.2.3 Impacts on Biodiversity ................................................................................. 80
5.2.4 Impacts on Air Quality ................................................................................... 81
5.2.5 Noise and Vibration Impacts .......................................................................... 82
5.2.6 Land Use Impacts .......................................................................................... 83
-
38
5.2.7 Impacts on Utilities and Infrastructure............................................................ 83
5.2.8 Impacts on Cultural, Religious and Historic Heritage Sites ............................. 84
5.2.9 Damage to the Landscape .............................................................................. 84
5.2.10 Public Safety .................................................................................................. 84
5.2.11 Worker’s Safety ............................................................................................. 84
5.2.12 Waste Management ........................................................................................ 85
5.2.13 Construction Camp Impacts ........................................................................... 85
5.3 Potential Adverse Impacts during Operational Phase ................................................ 86
5.4 Indirect, Cumulative, and Residual Impacts .............................................................. 87
6 ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN ............................... 89
Noise and vibration management ............................................................................. 90
Water run-off management (drainage plan) .............................................................. 90
Adverse weather ...................................................................................................... 91
Health and safety environment (HSE) ...................................................................... 93
7 ENVIRONMENTAL AND SOCIAL MONITORING PLAN ................................. 97
8 PUBLIC CONSULTATION RESULTS ................................................................. 105
9 GRIEVANCE REDRESS MECHANISM .............................................................. 106
10 ANNEXES ................................................................................................................ 107
10.1 Annex 1: Chance Find Procedure ............................................................................ 107
10.2 Annex 2: Public Consultations ................................................................................ 108
10.3 Annex 3. Grievance Redress Form.......................................................................... 118
10.4 Annex 4: Mitigation Measures during Construction Phase ...................................... 119
-
39
List of Tables
Table 1: Estimate of Staffing Requirements......................................................................... 46
Table 2: Duration of Construction Activities ....................................................................... 48
Table 3: Typical Irano-Turanian Steppe Vegetation............................................................. 55
Table 4: List of the Recorded Bird Species Recorded in the Project Area ............................ 56
Table 5: Mammals in the Vicinity of the Project.................................................................. 56
Table 6: Amphibians and Reptiles Recorded in the Project Area ......................................... 57
Table 7: Typical Aquatic and Riparian Vegetation in the Project Area ................................ 57
Table 8: List of Freshwater Fish Species ............................................................................. 58
Table 9: Population of Salah Al-Din Governorate for 2015 ................................................. 59
Table 10: Drinking Water Standard No. (417)-2001 ............................................................ 63
Table 11: Effluent Discharge Parameters ............................................................................. 65
Table 12: Ambient Air Quality Standard ............................................................................. 66
Table 13: Indicative Values for Sanitary Sewage Discharge ................................................ 74
Table 14: Rehabilitation Phase: Impacts Significance .......................................................... 78
Table 15: Noise Emission Levels dB (A) of Construction Equipment .................................. 82
Table 16: Noise Emission Levels dB (A) and Distance to the Equipment ............................ 82
Table 17: EPA Maximum Acceptable Leq (2005) ................................................................ 83
Table 18: Operation and Maintenance Phase: Impacts Significance ..................................... 86
Table 19: Mitigation Measures during Rehabilitation Phase ................................................ 90
Table 20: Mitigation Measures during Operation Phase ....................................................... 95
Table 21: Monitoring Activities during Rehabilitation Phase ............................................... 98
Table 22: Monitoring during Operation Phase ................................................................... 102
-
40
List of Figures
Figure 1: Project Location ................................................................................................... 43
Figure 2: Present Condition of the Facilities ........................................................................ 45
Figure 3: Administrative Location of the Project ................................................................. 49
Figure 4: Geological Formations in the Project Area ........................................................... 50
Figure 5: Seismic Map of the Project Area .......................................................................... 51
Figure 6: Depth to Groundwater in the Project Area ............................................................ 52
Figure 7: Temperatures and Precipitation in the Project Area (2002-2012) .......................... 54
Figure 8: Mesopotamian Shrub Desert Borders ................................................................... 55
Figure 9: Location of Samarrah Wetland IBA ..................................................................... 59
Figure 10: Historical and Cultural Heritage Sites in the Project Area ................................... 61
-
41
List of Abbreviations
AXO Abandoned explosive ordnance
EHS Environment, Health and Safety
ERW Explosive remnants of war
ESMP Environmental and Social Management Plan
GRM Grievance Redress Mechanism
Ha Hectare
ID Iraqi Dinar
Km Kilometer
MCC Motor Control Center
MM Modified Mercalli Scale
NGO Non-Governmental Organization
OP Operational Procedure
PMT Project Management Team
SCADA Supervisory Control and Data Acquisition
TDS Total Dissolved Solids
TSS Total Suspended Solids
TOR Terms of Reference
WB World Bank
UXO Unexploded ordnance
-
42
1 INTRODUCTION
This Environmental and Social Management Plan (ESMP) is prepared in accordance to the
Terms of Reference for Rehabilitation of Al-Awja - Owainat Water Treatment Plant, Salah Al-
Din Governorate within the framework of Emergency Operation for Development Project
(EODP) (P155732) (IBRD Loan No.: 8520).
According to the World Bank environmental safeguards the project is categorized as Category
B.
Ministry of Constriction, Housing, Municipalities and Public Works operates, as the core
mandate for Iraqi government, in the management, development, rehabilitation and
maintenance of water and sanitation facilities within Republic of Iraq.
The objectives of the ESMP are:
Identification of the baseline environmental and social conditions;
Identification of the potential adverse impacts during the rehabilitation/construction
and operational phases of the project related to the specific project activities;
Propose mitigation measures in order to minimize the adverse impacts identified;
Prepare the ESMP that will allow the adequate implementation of the proposed
mitigation measures.
-
43
2 PROJECT DESCRIPTION
The project is located in the city of Tikrit, Salah Al-Din Governorate, approximately 140 km
north of Baghdad.
Figure 1: Project Location
2.1 Project Objectives and Outcomes
The area of the project witnessed severe destruction during the last several years since the
armed conflict and occupation of the area by the Islamic State (“da’esh”). The region’s
infrastructure has been specifically targeted and currently in non-operational condition and
requires extensive rehabilitation. Within the framework of Emergency Operation for
Development Project (EODP) (P155732) (IBRD Loan No.: 8520) 4.9 million US $ are
allocated for the rehabilitation of Al-Awja - Owainat Water Treatment Plant.
The main project goal is rehabilitation of the water treatment plant for the provision of the
potable water. The expected project outcome is functioning water treatment facility with the
operational capacity of 1000m3/h.
-
44
The project is expected to provide drinking water to approximately 35000 local residents and
IDPs. At present, the residents rely almost exclusively on the water delivered by water tankers
for drinking purposes which poses additional financial burden on household. In some instances
the water is extracted from wells with the inadequate quality of water without any treatment
which poses significant health risks to the population.
2.2 Main Project Components
The project comprises the rehabilitation of a water treatment facility with the output of 2200
m3/day for 22 hour operation per day; 1000 m3/hr. The source of the raw water for treatment is
the Tigris River. The main project components are:
The project consists of the following components:
Intake stricture.
Low lift pumps.
Sedimentation tank (2).
Filter tanks (6)
Alum system
Chemical building
Chlorine system
High lift pump station
Motor Control Center (MCC) building
Ground reservoir
Supervisory control and data acquisition (SCADA) system.
2.3 Condition of Existing Facilities
At present, the facilities are in destroyed conditions and in completely non-operational
condition:
-
45
Figure 2: Present Condition of the Facilities
2.4 Clearance of UXO/ERW
Unexploded ordnance (UXO) are weapons that for some reason fail to detonate as intended,
thereby becoming unexploded ordnance. These unstable explosive devices are left behind
during and after conflicts and pose dangers similar to landmines.
Abandoned explosive ordnance (AXO) is explosive ordnance that has not been used during
armed conflict and has been left behind and is no longer under control of the party that left it
behind. It may or may not have been primed, fuzed, armed, or otherwise prepared for use.
Explosive remnants of war (ERW) are explosive munitions left behind after a conflict has
ended. They include unexploded artillery shells, grenades, mortars, rockets, air-dropped
bombs, and cluster munitions. Under the international legal definition, ERW consist of UXO
and AXO, but not mines.
The risk of the presence of UXO/ERW in the area is that it might not be immediately discovered
after the conflict especially if buried deep underground or under the rubble of destroyed
buildings.
The area have received clearance from the Iraqi Armed Forces for the absence of UXO/REW,
however, accidental discovery is still possible. In case of the discovery, the personnel should
be immediately evacuated and armed forces contacted. The works could be resumed only after
removal of the munitions.
2.5 Construction Camp
A Main Camp, the operational center, with prefabricated offices and parking areas for
administration and technical staff. This will also include areas for materials testing and storage,
-
46
and equipment cleaning and maintenance. The need for residential accommodation is likely to
be relatively minor. The accommodation at the camp will be required for the security guards,
2 persons.
The amount of effluent generated by the construction camp is considerable, as it was estimated
that the average water consumption might constitute up to 100 m3/day. Residential solid waste
containing organic waste from construction camps is approximately 1.5 kg/person/day. The
construction camp should have independent sources of water and electricity, and the septic tank
for the residential effluent disposal.
2.6 Personnel Requirements
The personnel requirements for the project are 47 persons including administrative staff,
technical staff, qualified construction crew and unskilled labor. All workers will be locally
hired. The estimate of the staffing requirements is presented in the Table below:
Table 1: Estimate of Staffing Requirements
Type Job Title Number
Administrative Staff
Secretary 1
IT support 1
Serving personnel 1
Security personnel 2
Parking attendants 2
Logistics Coordinator 1
Warehouse/storage coordinator 2
HR officer 1
Procurement officer 1
Technical Staff
General Manager/Team Leader 1
Senior Civil Engineer 1
Materials Engineer 1
Civil Engineer 2
Structural Engineer 1
Geo-technical Engineer 1
Drainage Engineer 1
Quantity Surveyor 1
HS&E specialist 2
Social expert 1
Quality Assurance Engineer 1
-
47
Type Job Title Number
Construction Crew Machinery and equipment operators 12
Unskilled labor 10
Total 47
2.7 Land Acquisition
The project comprises the rehabilitation of the existing facilities with no additional structures
or pipelines to be constructed. Therefore, the project will not require any permanent or
temporary land acquisition. The construction camp is to be located on governmental property
within the perimeter of the existing facilities. Accordingly OP 4.12 will not be applied.
2.8 Project Duration
The total project duration is 6 months. Work consists of a simple civil works such as cleaning
work and raise dirt debris resulting from combat operations and rehabilitation of all the
damaged civil buildings such as Intake, Sedimentation Tank, Filtration Building, Storage Tank,
MCC Building and services buildings and repainting buildings and replace and renovating
pipes, bathrooms, doors, windows and re-paving of internal roads and treatment of cracks in
the sedimentation tank and Storage Tank.
Most of the works in this project are the electrical and mechanical works include supply,
installation, and operation of the pumps, electric transformers, electric generator and the
replacement of cables and outdoor lightings.
The intake structure shall be constructed from reinforced concrete. The pump sump (Basement)
shall be designed as a water tight structure in two compartments for independent operation
during maintenance with bypass arrangement controlled by a 2 Nos. sluice valves. The floor of
the (Basement) shall be sloped to one corner with a sump to pump accumulated settled sludge
to the river using duplicated submersible pumps. The Basement shall have access ladder and
lighting. The channel from river to the intake Basement shall be constructed according to the
drawing from reinforced concrete the contractor is responsible to make a full hydraulic study
to design the final shape of the channel. Rip-raping along the shoulder of the river for a distance
of 50m from each side of the channel to protect the structure and to direct the water to the
channels. The necessary arrangements are to be made to minimize the problem of settling of
the suspended matter at the channel bar during high turbidity seasons by using submerged
scraping device.
-
48
The breakdown of project activities is presented in the Table below:
Table 2: Duration of Construction Activities
# Activity Duration (man days)
1 Cleaning post-combat debris 75
2 Rehabilitation of Intake Structure 60
3 Rehabilitation of sedimentation tank 60
4 Rehabilitation of filtration facilities 60
5 Rehabilitation of storage tank 60
6 Rehabilitation of MCC building 60
7 Rehabilitation of service building 60
8 Replacing of pipes 35
9 Repair and paving of roads within the facility 14
10 Installation of doors and windows 28
11 Painting 38
12 Electrical and mechanical works 42
-
49
3 BASELINE CONDITIONS
This chapter presents a comprehensive overview of the existing conditions in the vicinity of
the project area and adjacent facilities.
3.1 Project Location
The project is located in the city of Tikrit, Salah Al-Din Governorate, Iraq. The project location
is approximately 140km north of capital city of Baghdad. The project is located directly on the
bank of the Tigris River. Figure below shows the administrative location of the project.
Figure 3: Administrative Location of the Project
The land use of the area is void of residential settlements, industrial activities and cultivation.
The area is used by the local population mostly for grazing of the livestock.
-
50
3.2 Regional Geology, Topography and Seismic Activity
3.2.1 Geological Formations in the Project Area
The project is located in the north-eastern part of the Arabian Peninsula, which is a region of
tectonic compression of particularly unstable area marked by convergent movements of the
Arabian and Eurasian Plates that closed Tethys paleo-ocean and formed Zagros Belt in the
north-eastern part of the Arabian Plate. Stratigraphically, the project area is dominated by
geological formations ranging from Middle Miocene to Quaternary. In the project location the
geological formation is composed of thin-bedded, black bituminous limestone, dolomitic
limestone and black papery shale with streaks of thin black chert.
The terrain is characterized as flat to gently rolling plains, hills, and mountains. In the project
area the elevations are ranging between 300-550 m asl. The maximum elevation is 543.5 m asl
and the minimum elevation is 313.9 m asl.
Figure 4: Geological Formations in the Project Area1
3.2.2 Seismology
Tectonically Iraq is located in a relatively active seismic zone at the northeastern boundaries
of the Arabian Plate. Seismic zoning of Iraq is divided into four zones where the areas of no
damage zone of MM = III and less covering mainly the stable shelf region. Then the minor
damage zone follows which covers the intensities IV- V covering the Zagros Foothills and the
1 Red circle marks the location of the project area
W01
-
51
Mesopotamian Geosyncline. Then the moderate damage zone follows with intensity range of
VI-VII which actually covers the Zagros Tauros thrust zones. The major damage zone with
intensity of VIII is located on the Zagros thrust outside the Iraqi borders.
The project area is located in the minor damage zone with the seismic activity of I-II on MM
scale.
Figure 5: Seismic Map of the Project Area2
3.3 Water Resources
According to the hydro-geological classification of Iraq, the project area is located in the Low
Fold hydro-geological zone. The Low Fold zone is filled by sedimentary formations that range
in age from Late Miocene to Recent: Fatha, Injana, Mukdadiyah and Bai Hassan, and
Quaternary cover. These formations represent the main aquifers in this zone. The general trend
of the groundwater movement is mainly from north and northwest towards south and southeast.
2 Adapted from: Alsinawi, S.A. (2001) .Seismological Considerations of the Eastern Arab Region. Proceedings of the Euro-Mediterranean Seminar on Natural, Environmental and Technological Disasters, Algers, Algeria
-
52
Generally, the salinity of the groundwater increases from north to south. It increases from the
recharge sources at the high land areas (less than 1000 mg/l), towards the discharge areas along
the Mesopotamia Zone and Al-Jazira Zone (more than 10000 mg/l). Groundwater quality is
mainly bicarbonate at the recharge areas, and becomes sulphatic at the discharge areas. The
groundwater quality in the project area is slightly brackish with the salinity of 1000-3000 ppm.
The groundwater depth in the project area ranges from 10-20 m below surface.
Figure 6: Depth to Groundwater in the Project Area
The surface water is characterized as perennial run-off streams mostly filled with water in
winter rainy season and dry in summer. The majority of these streams discharge the water into
Tigris River with the contribution to the river flow negligible (0.2 MCM on average for the
year 2008). The area consists of potentially fertile soils characterized as heavy alluvial soils,
with some organic content and a high proportion of clays. The soil classification is 68.4% silty
loam, 20.9% silty clay loam and 10.7% is clay soil. The river bed is composed of fine sand, silt
and clays with rather high sedimentation load.
No analysis is available for the ambient water quality in the Tigris River at or near the intake
location of the project, however, no signs of certain contamination were observed. A study was
W01
-
53
made on ambient water quality of the River further downstream at Baghdad (based on sampling
campaign Jun-Dec 2008)3 and the results have shown that the pH for the water samples vary
from 7.91 to 8.1 with an average value 8.02, conductivity vary from 793.42 to 1189.76 µs/cm,
TDS values range from 519.17 to 787.67 mg/L with an average value of 700.77 mg/L, turbidity
values range from a minimum of 24.58 to a maximum of 33.22 with an average value of 28.06
(NTU), Ca is ranging from 136.67 mg/L to 69.38 mg/L, SO4 has an average concentration of
303.17 mg/L, chloride concentration ranges from 64.25 mg/L to 100.92 mg/L, and Al and Fe
range from 0.11 to 0.77 mg/L, respectively. The Iraqi Standard for drinking water is presented
in Table 11 in Chapter 4.1.2.
3.4 Climate
The climate in the project area is characterized as Mid-steppe and desert climate. The average
temperature for the year in Tikrit is 22.2°C. The warmest month, on average, is July with an
average temperature of 35°C. The coolest month on average is January, with an average
temperature of 9.4°C.
The highest recorded temperature is 48.9°C in July. The lowest recorded temperature is -4.4°C
in February.
The average amount of precipitation per year in is 348 mm. The month with the most
precipitation on average is December with 78.7 mm of precipitation. The month with the least
precipitation on average is June with an average 0 mm. In terms of liquid precipitation, there
are an average of 27.1 days of rain, with the most rain occurring in December with 5.8 days of
rain, and the least rain occurring in June with 0.0 days of rain.
3 Khadem, A.J. Assessment of Water Quality in Tigris River-Iraq by Using GIS Mapping, Natural Resources,
2013, 4, 441-448.
-
54
Figure 7: Temperatures and Precipitation in the Project Area (2002-2012)
The predominant wind direction is Northeast in the months November through to April, and
predominantly north-west in the months May-October. The mean average wind speed is 10-12
km/h with the wind gusts reaching up to 26-28 km/h.
3.5 Air Quality and Noise
At present, there is no information on ambient air quality in the project area; no measurements
on air quality were performed previously. The area is predominantly agricultural rural area.
Although there are oil fields in the Khanaqin District, their approximation to the project area
is unknown at present. The roads in the area are mostly rural unpaved roads and roads in rather
bad conditions partially destroyed due to the war conditions in recent years. The main source
of pollution is dust generated through the agricultural activities and use of the rural roads in
addition to the dust generated by windy conditions during dry periods. Potentially, there might
be the additional air pollution from the operating oil fields and/or refineries.
Similarly, no information on noise levels is available for the project area. However, the noise
level in the rural area with limited vehicle movement and limited agricultural activities is not a
significant issue.
-
55
3.6 Biological Environment
3.6.1 Terrestrial Environment
The project area is located in the Mesopotamian shrub desert terrestrial eco-region4 considered
as a transitional zone between the Syrian Desert and steppe region further north. This terrestrial
eco-zone is categorized as vulnerable and due to the security concerns have received little
focused study.
Figure 8: Mesopotamian Shrub Desert Borders
The vegetation of the region is similar to the Irano-Turanian eco-region and is characterized by
the dominance of the drought-tolerant low shrubs with a variety of grasses and legumes.
Herbaceous and dwarf shrub sage brush (Artemisia sp) communities tend to dominate in
deeper, non-saline soils and often occur in association with grasses. The recorded vegetation is
presented in the Table below:
Table 3: Typical Irano-Turanian Steppe Vegetation
Retama raetam Artemisia herba-alba Ferula communis
Noaea mucronata Asphadelus aestivus Lepidium aucheri
Salsola spp. Urginea maritima Cnicus spp.
Astragalus spinosis Circium alatum Paronychia argentea
Ballouta undulata Achillea fragrantissima Hordeum bulbosum
Thymus capitatus Aegilops ovata Crepis aspera
4 National Report on Biodiversity in Iraq, July 2010
-
56
The area of the project is located in a general area identified as a fly-way route for migratory
birds from Eastern Europe and West Siberia to Mesopotamia and Africa. The list of known
bird species recorded in the area is presented in the Table below:
Table 4: List of the Recorded Bird Species Recorded in the Project Area5
Scientific name Common name 2015 Red List
category
Haematopus ostralegus Eurasian Oystercatcher NT
Vanellus vanellus Northern Lapwing NT
Limosa lapponica Bar-tailed Godwit NT
Calidris canutus Red Knot NT
Calidris ferruginea Curlew Sandpiper NT
Larus armenicus Armenian Gull NT
Francolinus francolinus Black Francolin LC
Mareca strepera Gadwall LC
Mareca penelope Eurasian Wigeon LC
Marmaronetta angustirostris Marbled Teal NT
Aythya nyroca Ferruginous Duck LC
Ciconia ciconia White Stork LC
Plegadis falcinellus Glossy Ibis LC
Vanellus leucurus White-tailed Lapwing LC *LC-Least Concern; NT – Near Threatened; VU - Vulnerable
Large mammals that are associated with this ecoregion include: wolves (Canis lupus); Red fox
(Vulpes vulpes); Golden jackals (Canis aureus); caracals (Caracal caracal); jungle cats (Felis
chaus); Mongoose species (Herpestes sp); wildcats (Felis silvestris); Common otter (Lutra
lutra); and Greater Horseshoe Bat (Rhinolophus ferrumequinum). Goitered gazelle (Gazella
subgutturosa) and European badgers (Meles meles) can be found in more vegetated areas.
However, the status of these species is unknown and their presence was not recorded and is
highly unlikely in the project area. The mammalian species recorded in the region include:
Table 5: Mammals in the Vicinity of the Project
Scientific Name Common Name IUCN Status
Hemiechinus auritus Long-eared Hedgehog LC
Paraechinus aethiopicus Ethiopian Hedgehog LC
Crocidura suaveolens Lesser white-toothed shrew LC
Suncus murinus Asian House Shrew LC
Suncus etruscus Pygmy White-toothed Shrew LC
5 R.F. Porter et al, Birds of the Middle East, First Princeton Field Guide Edition, 2004
-
57
Scientific Name Common Name IUCN Status
Otonycteris hemprichii Desert Long-eared Bat LC
Allactaga euphratica Euphrates Jerboa NT
Jaculus jaculus Lesser Egyptian Jerboa LC
Gerbillus cheesmani Cheesman's Gerbil