 International Conference Power Plants 2012  Society of Thermal Engineers of Serbia Oct. 30th - Nov. 2nd, 2012 - Zlatibor, Serbia http://e2012.drustvo-termicara.com/english/ Abstract In the Balkan and Central Europe, there is a large fleet of older oil & coal fired power plants with a potential for repowering into modern combined cycle power plants. This paper will review the specific HRSG design features required for such repowering projects. Compared to green field projects, repowering a steam turbine with a new train of gas turbine and HRSG includes some special challenges. The HRSGs have to be tailor made to suit the existing site constraints. We will explain how a Vertical type HRSG can be adapted and modelled to match a limited foot print. In addition we will present the specificities of the design of HRSGs when the Gas Turbine fires heavy fuel oil, as mandatory in some projects. CMI has recently completed such a large repowering projects, for instance Senoko Singapore; Dunamenti Hungary, Shoiaba/SEC/ Saoudi Arabia,  These experiences will be the support throughout this paper to explain these specific repowering challenges. Fig.1 CMI is a HRSG specialist and offers both Horizontal and Vertical designs

Transcript of Repowering Older Plants Вђ“ the View of the Hrsg

  • International Conference Power Plants 2012

    Society of Thermal Engineers of Serbia Oct. 30th - Nov. 2nd, 2012 - Zlatibor, Serbia

    http://e2012.drustvo-termicara.com/english/

    Abstract

    In the Balkan and Central Europe, there is a large fleet of older oil & coal fired power plants

    with a potential for repowering into modern combined cycle power plants. This paper will

    review the specific HRSG design features required for such repowering projects. Compared

    to green field projects, repowering a steam turbine with a new train of gas turbine and HRSG

    includes some special challenges. The HRSGs have to be tailor made to suit the existing site

    constraints. We will explain how a Vertical type HRSG can be adapted and modelled to

    match a limited foot print. In addition we will present the specificities of the design of HRSGs

    when the Gas Turbine fires heavy fuel oil, as mandatory in some projects. CMI has recently

    completed such a large repowering projects, for instance Senoko Singapore; Dunamenti

    Hungary, Shoiaba/SEC/ Saoudi Arabia, These experiences will be the support throughout

    this paper to explain these specific repowering challenges.

    Fig.1 CMI is a HRSG specialist and offers both Horizontal and Vertical designs

  • Background of Senoko Project

    In December 2004, Senoko Power of Singapore has completed an innovative plant

    repowering project. Three old large coal fired boilers had been demolished to be replaced by

    3 gas turbines of 250 MW each, coupled with a Heat Recovery Steam Generator (HRSG)

    based on state-of-the- art 3 pressures plus reheat. Produced steam is used in the former old

    steam turbine and condenser. This is the repowering concept of an old steam turbine, which

    has typically a longer life span than the boielrs. This paper reviews all of the specific

    characteristics of the HRSG for repowering as used for Senoko project but also at Dunamenti

    a 2010-2011 repowering project in Hungary.

    Compared to a greenfield plant, where standard reference plant concepts can apply,

    repowering projects must always be specific to suit existing plant layout and steam turbine

    operating conditions. This was especially true at the Senoko plant. Firstly, the new HRSGs

    had to match the very limited foot print of the old conventional boilers, where dimensions of

    the new HRSG had to be adapted. Then, the HRSG design was selected as Vertical type.

    Secondly, modular construction including highly prefabricated heat exchangers were

    required to match the 18 months stoppage. Finally, the Senoko facility is a very congested

    site with no room for large cranes. Consequently, hydraulic lifting jacks have been used

    instead for boiler erection of heavy items. A good deal of existing civil structures and cooling

    systems were re-used. After the first GT26 block, having the equivalent capacity of more

    than two of the smaller steam sets, has come into operation, it was possible to shut down

    the remaining two units for repowering. The second repowering step was then performed in

    a narrow 18 month window. Thanks to this two-stepsrepowering, the interruption time was

    minimal and the plant returned to service as scheduled at the end of 2004. Alstom was the

    project leader, and they in turn awarded the HRSG to CMI. The choice of CMI, as a specialist

    in the Vertical HRSG, was significant. The HRSGs are Vertical natural circulation with three

    pressure levels plus reheat : HP, 322 t/h at 128.9 barA, 568C; IP, 27.9 t/h at 41.5 barA,

    320C; LP 17.8 t/h saturated at 5.4 barA, 237C and RH, 332 t/h at 39.4 bar 568C.

  • Site limited available area

    At Senoko, there were constraints imposed by the space occupied by the original fired boiler

    which had to contain the gas turbine, the HRSG and the connections to the steam turbine. So,

    available area per HRSG was limited to only 30.6 meters in length by 28.1 meters in width.

    HRSG with all auxiliaries (feedwater tank, feedwater pumps, sampling, dosing skid,) had to

    be included in such a reduced area. Inside the building, a cargo lift was also to be installed.

    All piping had to remain within this perimeter boundary because of the surrounding

    enclosure, and some limits of supply and even Alstoms equipment was located inside the

    HRSG enclosure creating major risks of interfaces. Last but not least, the GT outlet extended

    about 1 meter into the boiler enclosure, reducing even further the available area for HRSG.

    Therefore, it was challenging to install such a large HRSG in such a reduced area. At the early

    engineering stage, CMI exchanged with Alstom 3D model of HRSG including auxiliaries.

    Alstom then consolidated its 3D plant model with PDMS software. Detailed three dimension

    plant modelling prevented clashes at the engineering stage without adverse construction

    problem (Fig.2).

    Fig.2 HRSG modeling in 3 dimensions

  • Vertical HRSG flexibility

    Standard Vertical HRSG for such GT class F combined cycle typically measures an overall

    length of about 35 meters. This length is based on 20.4 meters tubes long which are the

    longest tubes for Vertical HRSG used by CMI without any other limitations. Such standard

    design applies for greenfield site or when there is no space limitation. Even though this

    standard boiler is already quite short, this was not short enough to match the Senoko

    repowering site. Unlike horizontal HRSG, boiler tube length impacts directly the boiler

    length; this is a specific feature of Vertical HRSG. CMI took advantage of this lateral and

    vertical space flexibility arrangement offered by the Vertical design (Fig.3).

    GT

    Overall boiler length 35 meters

    Typical tubes length 20.4 m

    Typical

    heigth

    9 m

    Fig. 3 Vertical HRSG overall length based on longest used boiler tubes

    This feature is very useful in case of repowering. As often, the boiler width was not such an

    issue in comparison with boiler length. For Senoko, the longest possible tube was 18.4

    meters and the boiler casing was enlarged in proportion. While making such casing

    adjustment to available space, the driving criterion is to keep the gas pressure drop

    unchanged. In other words, gas velocity and gas path cross section shall also remain

    unchanged (Fig.4). It is important to remember here that HRSG gas pressure drop is

  • proportional to the square of gas velocity, meaning that gas pressure drop (guaranteed value

    by HRSG supplier) is very sensitive to available gas flow cross section.

    Gas cross sectionGas cross

    section

    unchanged

    Longest

    tube

    20.4 m

    Reduced

    tube/boiler

    length

    FlexibleSlightly

    enlarged

    boiler

    width

    Fig. 4 Arrangement flexibility offered with shorter tubes.

    As a consequence of this wider casing, path had been divided in 3 wide sections instead of 2

    as usual for the standard solution. There were 3 heat exchanger modules side by side over 4

    levels for a total of 12 modules (Fig.5). The modules were completely shop prefabricated and

    hydrostatically tested in workshop. The largest module weighted 145 tonnes with overall

    dimensions 23.6 m * 3.9 m * 2.9m high. They were transported from harbour to site on

    hydraulic trailers.

    Heating

    surface

    modules

    flexible

    arrangement

    Standard

    'greenfield'

    arrangement

    Senoko

    enlarged

    casing width

    Fig. 5 Heat exchanger modules arranged in 2 or 3 modules in width

    This way, it became possible to fit the HRSG on this site. In case of available length is even

    shorter, a last option would be by means of entering flue gas on the large casing face instead

    of the standard small face (Fig. 4). This is a specific feature of the Vertical HRSG as the first

    Gas flow

  • heating surface is about 9 meters high (Fig.3), and this allows sufficient space for the inlet

    duct arrangement underneath. This option is applicable up to middle size HRSG and is useful

    in case of repowering plant where, for instance, the existing steel structure shall be

    recovered. But, this option was not requested at Senoko.

    Boiler modular construction

    Heat exchangers modules were factory assembled under strict CMI quality control. As per

    CMI standard design, each module was made of parallel serpentine tubes mounted on tube

    support plates and connected to headers at each ends. As a result of this module prefabrication

    design, only header to header welds had to be carried out at site. An important constraint at

    Senoko site was to ensure that there would be enough access around the operating unit for the

    repowering of the second and third units. The hydraulic trailers carrying the modules had to

    manoeuvre around the operating unit of phase 1 (Fig. 6). To perform so precision movement,

    trailers selected were self-propelled rather than tractor pulling. This allowed more flexibility

    in those manoeuvres because of the reduced convoy length, and its large angle orientation

    wheels. Also, those advantages offered by the self-propelled trailer were required for the final

    positioning of modules inside boiler frame due to limited space left as explained hereafter.

    Those hydraulic trailers proved to be very accurate in this exercise with a positioning

    tolerance of only 1 or 2 mm. Taking into account maximum trailer turning radius, a cinematic

    study of movement sequence had been performed by CMI during engineering.

  • Module lifting with jacks

    Senoko site precluded the use of a large crane. In case of prefabricated modules for

    Horizontal HRSG, large cranes are typically needed to tilt and lift them. Instead for Senoko,

    module lifting was performed with 28 hydraulic jacks installed on top of steel structure. This

    module erection procedure is standard for CMI Vertical HRSG. The first module was brought

    to position in the frame and its 7 tube support plates were attached to those jacks through

    suspension cables and plates. The hydraulic trailer was then lowered, transferring module

    weight carried to those cables. The process was repeated for the other two modules to

    complete this first level. This completed level was then jacked up sufficiently for the next

    level of modules to be placed underneath it similarly, and the process was repeated until all 4

    levels of modules had been suspended (Fig. 8). It is important to note that modules remained

    always in horizontal position; module tilting operation is not required for Vertical HRSG

    erection. The complete assembly was then jacked up to its final position in the steel structure.

    At that stage, the complete pressure parts weight amounting to 1450 tonnes was still hang on

    those 28 jacks. By introducing pins in suspensions plates and lowering jacks, weight was

    Fig. 6 Boiler modules on hydraulic trailor had to manoeuvre on congested site

  • transferred to the 28 final suspensions points. Hydraulic jacks were released, dismantled and

    reinstalled on the next unit. Then, adjacent header ends were welded together; no other

    internal pressure part welding was needed except for a few tube/tube welds between level 1

    and level 2. From modules arrival harbour up to final suspension of the 12 modules on to the

    boiler frame, it took only 6 days without using crane, nor even scaffolding. This is a

    remarkable short time also due to this work repeat.

    Fig. 7 Second level of module ready to be lifted Fig. 8 Completion of 12 modules suspended

    Typically, hydraulic jacks are better synchronized in jacking up than lowering loads.

    Lowering load is a feature that is not normally needed by CMI module erection procedure

    described hereabove. However, at Senoko, space was so limited (Fig. 10) that this special

    feature was required. Indeed, when the erection of each module is in a gradually reducing

    area, the problem is to get the third module exactly aligned relative to the 2 aside modules

    already suspended. Hydraulic jacking system had been selected to get the capability to lift

    and to lower the complete load in a synchronized way. Synchronization between jacks is very

    critical during the lowering down because of the risk of unbalanced pressure between jacks

    and consequently uneven load distribution on the steel structure. Considering the 1450 tonnes

    hanging on this jacking system, uncontrolled load distribution between the 28 jacks would

    have been unacceptable. To give clearance to the trailer to manoeuvre for the third module to

    be positioned exactly underneath, the whole assembly was jacked up of several meters and

    then relowered at the initial elevation to install suspensions plates. Hydraulic jacking system

  • proved to be very accurate in positioning with a maximum tolerance of only one of two

    millimetres (Fig.9).

    Fig. 9 Module erection Fig. 10 Self propelled trailer manoeuvres in limited space

    Indoor HRSG

    Indoor HRSG was specified indoor by Senoko Power. Not only is the Singapore climate

    characterized by temperatures in the low to mid 30s and high relative humidity for much of

    the year, but the power plant is located on the coast and buildings provide protection against

    airborne salt. The main purpose was weather protection, but enclosure was also used for noise

    abatement in terms of far field acoustical emissions. It is to be noted here that boiler stack

    was also equipped with a flap damper for inside weather protection, and boiler bottling up to

    keep it warm during outage. Compared to Horizontal HRSG, stack damper is a standard

    feature of CMI Vertical HRSG as the stack is centred on HRSG. For enclosure support, the

    main HRSG steel structure was easily extended to a secondary frame wrapped and attached

    all around. Senoko Power had specified to CMI architects some colours and aesthetic criteria

    (Fig. 11). For instance, all building side walls were extended 2 meters above roof platforms in

    order to hide top equipment such as silencers and louvers. Those louvers were installed for the

    natural ventilation of building.

  • Dunamenti, Hungary

    Fig. 11 Senoko repowering HRSG buildings phase 1 (CCP3) on left, and phase 2

    (CCP4&5) on rigth

    Fig. 12 Dunamentia G3 (GDF-SUEZ ELECTRABEL) BUDAPEST, Hungary

  • After the G2 repowering project in 1995, CMI supplied a HRSG for the G3 project that was

    commissioned in 2011.

    SHOIABA HRSG project summarized:

    10 vertical HRSGs, outdoor Flue gas by-pass stack (as option) Crude oil firing with sootblowers Hot casing (external rockwoll insulation) 2P (LP steam for the external deaerating FWT) Natural circulation Site conditions: 9 to 50C ASME design HRSG prefabricated in 4 pressure part modules Number of tubes: 3456 tubes of 17 meters Stack

    Fig. 13 Shoiaba/SEC/ Saoudi Arabia, General Arrangement Drawing

  • Specificities of a HRSG designed for continuous fuel oil firing in the Gas Turbine:

    Heavy duty gas turbines operate typically on natural gas, without risk of fouling and

    typical dew point at 60C

    Both Horizontal or Vertical HRSG are suitable such purpose

    Crude oil has high sulfur content with Acid Dew Point around 145C

    High sulfur content dictates the proper HRSG selection because all metallic surfaces

    must remain above ADP to prevent internal corrosion

    Temperature of condensate water entering finned tubes must be controlled to remain

    above ADP to avoid acid formation on tubes

    It limits the heat recovery in the back end of the HRSG

    Ducting metal must remain above ADP which is not feasible with internal insulation.

    HRSG must be externally insulated with hot ducting walls at gas temperature (no

    condensation occurrence)

    For HRSGs operated on continuous crude oil, heat exchangers are designed as follow:

    Finned tubes with maximum ~160 fins per meter

    Solid fins prefered

    Staggered or inline tubes arrangement

    On line cleaning Sootblowers inside tube banks

    Off line Water washing system capability and drains

    Limitation of tube rows per bank for efficient cleaning

    Good accessibility of pressure parts for inspection

    Fig. 14 CMI has designed many HRSGs behind gas turbines firing light and heavy fuel oil.

  • Conclusions

    There is real potential for repowering of old steam turbines in the Balkans. In a lot of old

    conventional plants, fired boilers have exhausted their useful life before its steam turbine.

    Over the years, much has been said about repowering, but very little has been done so far.

    Repowering of those old steam sets into efficient combined cycle with new GTs and HRSG is

    a cost effective solution. Today, available gas turbines can provide the exhaust energy for

    steam turbines of 120 -150 MW of which there are many examples in Europe dating back

    from the 1970s. These units could be repowered so as to increase power supply with a

    significant improvement in operating efficiency, flexibility and emissions. CMI has

    completed the Senoko and Dunamenti plants, which are a very successful example of such

    repowering. At Senoko, the Vertical HRSG has been proofed to be very accommodating for

    those the specific repowering constraints, which always require a tailor made design to suit

    limited space. In addition CMI Vertical HRSGs are uniquely fit behind Gas Turbine firing

    fuel oils.

    To be presented by:

    Pascal Fontaine, Product Manager, CMI Liege Belgium.