Report Standart Traverse
Click here to load reader
-
Upload
amirul-yaakub -
Category
Documents
-
view
2.255 -
download
150
description
Transcript of Report Standart Traverse
1.0 INTRODUCTION
Cadastral surveying in Malaysia is a procedure that produces a map or plan for
a land parcel or a group of land parcel. The boundary mark and boundary line are
need to be show without any hesitating. Every line should have the value of bearing
and distance consequent to the accuracy of surveying follow to the circular and land
law.
Now a day, all survey work in Malaysia use e - Kadaster system to make sure
that the title survey more systematic and more efficient. According to the Circular
PUK 2009, the implementations of this e - Kadaster directly and indirectly influence
the conduct and procedures in carrying out the field work measures and processing in
the office. In this context, the cadastral survey that has been based on computing will
become more efficient.
GPS technology efficiently provides users precise positions. Nowadays, by
using modern GPS techniques such as Rapid-Static, Stop & Go and Real Time
Kinematics (RTK), many points can be observed in a relatively short period of time
with good accuracy as those obtainable by conventional EDM/Total Station
surveying. These can increase productivity, reduce cost and manpower, and at the
same time is capable to challenge the cadastre task. Furthermore, for multipurpose
cadastre surveys, GPS positioning is a desirable and adequate method for establishing
and strengthening the national and regional geodetic networks.
For this task, we were required to do a standard traverse to compare the
reading between solar observations and global positioning system (GPS). The
standard traverse is a series of high accuracy traverse. The linear accuracy in 1:25000
and the angular is 1.5” per station. The purpose of standard traverse is to density
secondary control point and as a control network for cadastral survey. It is for any
precise job such as control network for cadastral survey, mapping and geodetic
control network.
The standard traverse is done by observing horizontal distance, horizontal
angle, solar observation and GPS observation. The standard traverse observes by
angle method which is define the interior and exterior angle and the total should be
360. The solar observation is needed for the azimuth control at the starting bearing
and the correction for the traverse.
1
We had been given a task for standard traverse at around UiTM Perlis. We starting
and closing the standard traverse with CRM point.
1.1 Executive Summary
1.1.1 Name of Project
Standard Traverse
1.1.2 Objective
To compare the reading between solar observation and GPS
(Global Positioning System) by using CRM as control point.
To carry out Standard Traverse Survey in accordance with Survey
Department practice.
To expose student using instrument in horizontal angle
measurement concept and understanding the method whereby
never used before this.
1.1.3 Scope of work
In this practical, we plant the CRM point by using a steel pipe with
cement. So, the pipe will not easily disturbance. Solar and GPS
observation were used as a method to achieve the objective.
AutoCAD 2007 was used as software to draw a certified plan and
show standard traverse network.
1.2 Site Location
The location for this practical was around UiTM Perlis. Refer Figure 1.2.
Figure 1.2: Location of plan
2
2.0 THEORY OF WORK
There are the characteristics of the theory of cadastral surveying need to follow to get
the best result and work.
2.1 Reconnaissance
Reconnaissance is very important to get the general view and to know the
real topographical surface of the survey site.
To get the overall picture of the area to be survey can be done smoothly.
To identify any obstacles.
To locate traversing stations.
2.2 Station Marking
The traversing stations must be marked several days prior before
observation.
The traversing stations place in firm, stable and on level ground.
The traversing stations using pipe driven in concrete because stations
must be permanent and harder to disturbed.
2.3 Horizontal Angle Measurement
Standard traverse
Standard traverse consist a series of traverses high accuracy. The linear
accuracy in 1:25000 and the angular is 1.5” per station. The purpose of
standard traverse is to density secondary control point and as a control
network for cadastral survey. Beside that it used for mapping and
geodetic control network.
Control traverse
Control traverse is a series of control station to forming a network. The
linear accuracy in 1:15000 and the angular is 3.0” per station. It uses for
engineering work, monitoring, setting out, constructions and etc.
Since this traverses is needed and important to get the high accuracy, so
all the work must be properly done to avoid the errors. (human error,
gross error and an instrument error).
2.4 Azimuth control
3
The azimuth controls get by doing solar observation.
The angular check by solar observation at intervals not exceeding 25
stations.
The true bearing from solar observation was compared between Global
Positioning System (GPS).
2.5 Global Positioning System (GPS)
GPS satellite navigation system which is provides the location and time
information.
Geodetic GPS network for Peninsular Malaysia was first observed in
early 1992 and completed 1993 providing a consistence set of coordinates
in WGS84.
The GPS surveying has been practiced for various applications which
particularly in providing control for large engineering projects.
2.6 Cadastral Reference Mark (CRM)
According to survey circular 2009, part of survey datum is two new CRM
with distance not less than 30 meter.
The observation can be in static method with condition that both points
must observe on same time.
The observation takes about 40 minutes except the master set observation
where the observation was about an hour.
2.7 Adjustment
Tolerance between internal and external angle angle is 5”
Applied M correction
Final bearing for each line to be computed.
2.8 Angular and Linear Misclosure
Angular 1.5” per station
Linear misclosure 1:25000
3.0 EQUIPMENT
3.1 Standard Traverse equipment
4
Equipment Usage
Total station
Total station is the most important
equipment in survey.
It is used in traversing and detail survey.
Can be obtain bearings and distances
almost accurate using this equipment.
To get the straight line of sight.
Prism
As reflector unit where it will give the
information about bearing and distance
during the observation
Tripod
To hold the total station prism.
To make sure the total station or prism
is correctly positioned on the point and
level.
Hammer
Used to knock the nail at the hard
surface
Nail
Used to mark the station at the hard
surface
Figure 3.1: List of Traverse equipment
3.2 Solar Observation equipment
5
Equipment Usage
Total station
Total station is the most important
equipment in survey.
It is used in traversing and detail
survey.
Can be obtain bearings and distances
almost accurate using this equipment.
To get the straight line of sight.
Prism
As reflector unit where it will give the
information about bearing and distance
during the observation
Tripod
To hold the total station prism.
To make sure the total station or
prism is correctly positioned on the
point and level.
Sunglasses
Used with total station when during
solar observation and to prevent eyes
from directly contact with ultraviolet
radiation.
Figure 3.2: List of Solar observation equipment
3.3 Global Positioning System (GPS) equipment
6
Equipment Usage
Receiver
Receive data from satellite.
X,Yand Z data.
Tribach Used to attach base and rover.
Figure 3.2: List of GPS equipment
4.0 PROCEDURES OF WORK
7
4.1 Flow chart of work
4.2 Preparation
8
Preparation
1. Reconnaissance
2. Station marking
Field Work
1. Differential Field Test (DFT)
2. Traversing
3. Solar Observation
4. GPS Observation
Data Processing
1. GPS processing
2. AutoCAD
4.2.1 Reconnaissance
Before starting the survey, reconnaissance is important to
know and identified the topographical detail the place of the
area. Besides that, it needs to be done first to avoid any
obstacle during field work and to make sure field work done
smoothly.
4.2.2 Station marking
Station marking using pipe driven in concrete because
stations must be permanent and harder to disturbed. Station
making placed on level ground and must be mark several
days before observation
4.3 Field Work
4.3.1 Differential Field Test
The differential field test should be carried out at the start of
every new survey job to make sure that the instrument to be
used in a good condition. It is important to ascertain if the
EDM or total station is inacceptable working order.
Procedure of differential field test:
9
i. Set up instrument total station at point A and prism
at point B.
ii. Then measured the distance A to B.
iii. Mark point C between line A and B.
Figure 4.3: Differential field test
iv. Then move the instrument at point C and put the
prism at point A and B.
v. Then measure the distance CA and CB.
vi. Distance AB must be compared with total distance
CA + CB.
10
A 68.825 B
A 38.846 C 29.978 B
4.3.2 Procedure of traversing
i. Start from know point line (CRM 1 to CRM 2).
ii. Set up the instrument at station CRM 2 and set 00 000
00 0 in circle left and target to station CRM 1
iii. Observe to station 1.
iv. Take the horizontal angle’s reading of station 1.
v. Take the vertical angle’s reading of station 1.
vi. Take the distance’s reading of station CRM 2 to
Station 1.
vii. at station CRM 2 and set 1800 000 00 0 in circle right
and target to station CRM 1 and observe to station 1
viii. at station CRM 2 and set 900 000 00 0 in circle left
and target to station 1
ix. Observe to station CRM 1.
x. Take the horizontal angle’s reading of station CRM
1.
xi. Take the vertical angle’s reading of station CRM 1.
xii. Take the distance’s reading of station CRM 1 and
CRM 2.
xiii. At station CRM 2 and Set 2700 000 00 0 in circle right
and target to station 1 and observe station CRM 1
xiv. Repeat the same step for station 3, 4, 5,6,7,8 and 9.
4.3.3 Procedure of solar observation
11
CRM 1
CRM 2
1
i. Put the total station on CRM 2 and prism on CRM 1.
ii. Then focus on prism and set RO value.
iii. Make sure that the total station is in face left
iv. Total station was set to RO then click ok. The
bearing was recorded automatically then target to
the sun.
v. Using face left, the sun position was observed on the
crosshair in the total station then click ok.
vi. Make sure that the sun is position as in diagram
below:
1st Sun position using face left 2nd Sun position using face left
vii. Change to face right then click ok.
viii. Make sure that the sun is position as in diagram
below:
1st Sun position using face right 2nd Sun position using
face right
ix. Close to RO back. Then click save.
x. Repeat the same step for another set.
12
4.3.4 Procedure of GPS observation
i. Set up a base receiver of Topcon GT at pillar 1.
ii. Set up a survey configuration and coordinate system
in base receiver. The projection that was used is
WGS 84.
iii. After finish set up the basic information, start
collects the data with press button FN to start the
recording and write down the time and date of
observation for reference when do the processing.
iv. Next, move to the rover receiver at the station 1.
v. At the rover, press the button FN to start the
recording and write down the time and date of
observation for reference when do the processing.
vi. After both of the instrument start collects the data,
wait until minimum 40 minutes to 1 hour for
recording the data.
vii. After 40 minutes, stop the recording at rover receiver
by press button FN again.
viii. After that, move the rover to the next station.
ix. Repeat step v until viii for station 2, 8 and 9.
13
4.4 Data Processing
4.4.1 GPS processing
The process of GPS data will be done by using Topcon
Tools 8 software. The steps are shown as below:
i. Create a new job in Topcon Tools 8.
ii. Do the setting at job configuration such as
projection, datum and others.
iii. Browse the raw data which had been download
from GPS instrument such as Topcon GT.
iv. After that, insert the coordinate easting and
northing of base station.
v. Do the processing at occupation view. Disable
the broken line which cannot be used in
processing.
vi. Next, choose GPS + Postprocessing and the
report will be shown. Refer figure 4.4.1(A) and
4.4.1(B).
vii. The report will show in detail about the
coordinate of each point, elevation, projection
and others.
14
Figure 4.4.1(A)
Figure 4.4.1(B)
4.4.2 AutoCAD
i. Key in data from booking traversing into
AutoCAD to produce a standard traverse plan.
15
5.0 RESULT AND ANALYSIS
5.1 Result
5.1.1 Booking form for standard traverse
Station Face Left ’ ”
Face Right ’ ”
Vertical Angle ’ ”
Distance(m)
Final Distance(m)
16
12
3
00 00 00
202 24 12
180 00 00
22 24 17
89 19 36
(270 39 58)
195.704
(195.704)
195.704
32
1
90 00 00
247 35 40
270 00 00
67 35 42
90 24 57
(269 34 47)
70.416
(70.416)
70.416
23
4
00 00 00
217 48 46
180 00 00
37 48 59
88 57 57
(271 01 53)
246.364
(246.364)
246.343
43
2
90 00 00
232 11 12
270 00 00
52 11 10
90 39 25
(269 20 31)
195.701
(195.702)
195.702
34
5
00 00 00
178 34 31
180 00 00
358 34 39
85 32 19
(274 27 33)
133.121
(133.121)
133.121
54
3
90 00 00
271 25 22
270 00 00
91 25 20
91 00 42
(268 59 13)
246.365
(246.365)
246.365
45
6
00 00 00
171 24 09
180 00 00
351 23 59
88 42 51
(271 16 58)
114.835
(114.836)
114.836
65
4
90 00 00
278 35 54
270 00 00
98 36 01
94 27 56
(265 31 38)
133.120
(133.120)
133.120
56
7
00 00 00
209 41 37
180 00 00
29 41 45
89 26 00
(270 33 45)
58.415
(58.415)
58.415
76
5
90 00 00
240 18 25
270 00 00
60 18 21
91 16 30
(268 44 53)
114.838
(114.838)
114.838
67
8
00 00 00
197 21 45
180 00 00
17 21 41
90 45 22
(269 14 26)
158.344
(158.344)
158.344
87
6
90 00 00
252 38 12
270 00 00
72 38 14
90 31 44
(269 28 12)
58.421
(58.421)
58.421
78
9
00 00 00
158 56 10
180 00 00
338 56 04
91 32 59
(268 26 58)
59.974
(59.974)
59.974
98
7
90 00 00
291 03 48
270 00 00
111 03 50
89 14 26
(270 45 12)
158.339
(158.339)
158.339
17
6.0 Final bearing for standard traverse by Global Positioning System
GPS
Station Face Left ’ ”
Face Right ’ ”
Mean Angle ’ ”
Bearing ’ ”
Final Bearing ’ ”
12
3
00 00 00
202 24 12
180 00 00
22 24 17
202 24 14.5+2.25
104 52 16M=35”
104 51 41
202 24 12 202 24 17 202 24 17 104 51 41
32
1
90 00 00
247 35 40
270 00 00
67 35 42
157 35 41+2.25
262 27 59Datum
262 27 59
157 35 40 157 35 42 157 35 43
23
4
00 00 00
217 48 46
180 00 00
37 48 59
217 48 52.5-1.75
142 41 07M=-01’10”
142 39 57
217 48 46 217 48 59 217 48 51 142 39 57
43
2
90 00 00
232 11 12
270 00 00
52 11 10
142 11 11-1.75
284 52 16M=-35”
284 51 41
142 11 12 142 11 10 142 11 09 284 51 41
34
5
00 00 00
178 34 31
180 00 00
358 34 39
178 34 35+2
141 15 44M=-01’45”
141 13 59
178 34 31 178 34 39 178 34 37 141 13 59
54
3
90 00 00
271 25 22
270 00 00
91 25 20
181 25 21+2
322 41 07M=-01’10”
322 39 57
181 25 22 181 25 20 181 25 23 322 39 57
45
6
00 00 00
171 24 09
180 00 00
351 23 59
171 24 04-0.7
132 39 47M=-2’19”
132 37 28
171 24 04 171 23 59 171 24 03 132 37 28
65
4
90 00 00
278 35 54
270 00 00
98 36 01
188 35 57.5-0.7
321 15 44M=-01’45”
321 15 59
188 35 54 188 36 01 188 35 57 321 15 59
56
7
00 00 00
209 41 37
180 00 00
29 41 45
209 41 41-2
162 21 26M=-2’54”
162 18 32
209 41 37 209 41 45 209 41 39 162 18 32
76
5
90 00 00
240 18 25
270 00 00
60 18 21
150 18 23-2
312 39 47M=-2’19”
312 37 28
150 18 25 60 18 21 150 18 21 312 37 28
18
67
8
00 00 00
197 21 45
180 00 00
17 21 41
197 21 43+2
179 43 11M=-3’29”
179 39 42
197 21 45 197 21 41 197 21 45 179 39 42
87
6
90 00 00
252 38 12
270 00 00
72 38 14
162 38 13+2
342 21 26M=-2’54”
342 18 32
162 38 12 162 38 14 162 38 15 342 18 32
78
9
00 00 00
158 56 10
180 00 00
338 56 04
158 56 07+2
158 39 20M=-4’04”
158 35 16
158 56 10 158 56 04 158 56 09 158 35 16
98
7
90 00 00
291 03 48
270 00 00
111 03 50
201 03 49+2
359 43 11M=-3’29
359 39 42
201 03 48 201 03 50 201 03 51 359 39 42
7.0 Final bearing for standard traverse by Solar Observation
Station Face Left ’ ”
Face Right ’ ”
Mean Angle ’ ”
Bearing ’ ”
Final Bearing ’ ”
12
3
00 00 00
202 24 12
180 00 00
22 24 17
202 24 14.5+2.5”
104 52 36M= -3”
104 52 33
19
202 24 12 202 24 17 202 24 17 104 52 333
21
90 00 00
247 35 40
270 00 00
67 35 42
157 35 41+2.5”
262 28 19Datum
262 28 19
157 35 40 157 35 42 157 35 412
34
00 00 00
217 48 46
180 00 00
37 48 59
217 48 52.5-1.5”
142 41 27M= -6”
142 41 21
217 48 46 217 48 59 217 48 51 142 41 214
32
90 00 00
232 11 12
270 00 00
52 11 10
142 11 11-1.5”
284 52 36M= -3”
284 52 33
142 11 12 142 11 10 142 11 09 284 52 333
45
00 00 00
178 34 31
180 00 00
358 34 39
178 34 35+2.0”
141 16 04M= -9”
141 15 55
178 34 31 178 34 39 178 34 37 141 15 555
43
90 00 00
271 25 22
270 00 00
91 25 20
181 25 21+2.0”
322 41 27M= -6
322 41 21
181 25 22 181 25 20 181 25 23 322 41 21
45
6
00 00 00
171 24 09
180 00 00
351 23 59
171 24 04-1.0”
132 40 07M= -12”
132 39 55
171 24 04 171 23 59 171 24 03 132 39 55
65
4
90 00 00
278 35 54
270 00 00
98 36 01
188 35 57.5-1.0”
321 16 04M= -9”
321 15 55
188 35 54 188 36 01 188 35 57 321 15 55
56
7
00 00 00
209 41 37
180 00 00
29 41 45
209 41 41-2.0”
162 21 46M= -15”
162 21 31
209 41 37 209 41 45 209 41 39 162 21 31
76
5
90 00 00
240 18 25
270 00 00
60 18 21
150 18 23-2.0”
312 40 07M= -12
312 39 55
150 18 25 60 18 21 150 18 21 312 39 556
78
00 00 00
197 21 45
180 00 00
17 21 41
197 21 43+2.0”
179 43 31M= -18
179 43 13
197 21 45 197 21 41 197 21 45 179 43 138
76
90 00 00
252 38 12
270 00 00
72 38 14
162 38 13+2.0”
342 21 46M= -15”
342 21 31
162 38 12 162 38 14 162 38 15 342 21 317
800 00 00 180 00 00 158 56 07
+2.0”158 39 40M= -21”
158 39 19
20
9 158 56 10 338 56 04158 56 10 158 56 04 158 56 09 158 39 19
98
7
90 00 00
291 03 48
270 00 00
111 03 50
201 03 49+2.0”
359 43 31M= - 18”
359 43 13
201 03 48 201 03 50 201 03 51 359 43 13
7.1 Analysis
8.0 CONCLUSION
From the analysis data above, we can conclude that, this practical task
teaches us how to do the standard traverse. The standard traverse is more
21
accurate than the control traverse. It is because the linear accuracy of
control traverse is about 1: 8000 and angular 3.0” per station while the
linear accuracy of standard is 1: 25000 and angular 1.5” per station. Other
than that, their applications are different.
We establish nine marks which are consist of four CRM point and five
stations for our traverse. All the four CRM point are marked by using
steel pipe and cement. Meanwhile the rest of stations are marked by using
pegs. The method to get the coordinate of the CRM point is obtained by
using static method. The solar observation is done for azimuth control.
The comparison of bearing between solar observation and GPS
observation for line CRM 1-2 is 20”. The comparison of bearing between
observed bearing (solar observation) and solar observation for line station
8-9 is 21”. The comparison of bearing between observed bearing (GPS
observation) and GPS observation for line station 8-9 is 4’4”. Meanwhile
the comparison of distance between observed distance and GPS
observation for line CRM 1-2 and station 8-9 are -0.008 respectively. The
angular misclosure is 3” per stations and this standard traverse achieved
limit accuracy 1: 131287.
9.0 COMMENTS
WAN NUR ADILIN BT WAN RAMLAN 2012481308
22
In this practical, l has learnt many things in doing standard traverse. There are:
1. I learn how to establish station using the metal pipe in concrete.
2. I have learned how to conduct the various cadastral control survey
methods.
3. I also learn how to know the difference of the control traverse and standard
traverse.
4. I can know how to do the standard traverse and booking.
5. I also know the difference between internal and external must not more
than ± 05”.
6. The correction for mean angle should not more than ±2.5”.
7. The bearing correction for each station is shall not more than ± 1.5” and
the linear misclose must get at least 1:25,000.
We start this practical by establishing the station by using steel pipe and
cement. The station must be established before any measurement was
made in order to get a higher accuracy. Next, we start our observation by
doing link traverse. After the finish a link traverse, we do a GPS
observation to get the coordinate for the traverse at station 1, 2,8 and 9.
GPS observation is done by using Topcon and static observation method
was made. After that, we do solar observation at station 2 and 8 to
determine the azimuth. The readings of solar observation were compared
with the GPS observation in order to get the best result.
WAN HAFISHAH BT WAN MOHAMED 2012437202
From this survey, there are many things I need to recall what have I learned before
this. Start from reconnaissance until produced standard traverse plan. We need to do
23
reconnaissance before start survey to avoid any obstacle during traversing such as
choose the best station to do solar observation. By doing this survey, we don’t have
many problems in field work but that problems come when we start to calculate the
data. According to the standard traverse, we have to take the angle exceed or less 360
degree. In order to have a precise measurement, we have to make sure that every
aspect in doing this practical in good condition such as the instrument.
Furthermore, in this practical I know to differentiate between control traverse and
standard traverse which is standard traverse is a series of high accuracy traverse
compared with control traverse. The misclosure for standard traverse is 1: 25000
compared with misclosure other traverse only 1:8000 for first class.
Last but not least, a special thanks to our lecturer SrKhairulAzhar and En. Nadzari b
Yahaya for their helps and guided us to conduct this work, also a special thanks to my
group members because give a full commitment in complete this practical work either
in field work and preparing a report. We hope that we can make a more good work for
other practical work.
MOHD SHAFIQ AZFAR BIN MOHD NAZERI 2012877076
First a foremost, I would like to thanks to our lecture Sr. KhairulAzhar that
have been thought us about on how to conduct a standard traverse survey. Actually
24
we have learnt this subject before, so we do it again for this semester. As usually, we
have briefing by Sr. KhairulAzhar on how to conduct this job and what are the
specification needs. As usually, we do a reconnaissance survey on place that we want
to setup our point of Cadastral Reference Mark (CRM). Besides that, I have learnt on
how to use a GNSS that is global positioning system. We use a static method that is
base and rover technique. Then we collect our data to be calculated and process by
using Topcon tools software. We produce four point of coordinate Cadastral
Reference Mark (CRM) that is two points at first station and two point a last station.
We use an open close traverse method that is start with known point and end with
known point. We also do a solar observation on a first station and last station. The
objective of this survey is to compare the coordinate by using solar observation and
global positioning method. We do our traverse along 500 metre and according the rule
and regulation of PKUP 2009. I learn on how to calculate a standard traverse and
process the data until get the final plan. Furthermore, not forget to our team that give
fully commitment to done this practical even has many problem but we can solve and
handle it professionally. Thank you.
25