1 G. Canzanelli Mission Report– May 2013 Mission Report of Giancarlo Canzanelli in Kosovo 9-10 May 2013 Background A proposal for a contract with the South RDA for the establishment of a RDA unit in Dragash and provide follow up to the Program findings en terms of LED was provided, according to the results of the previous mission on 8-10 April 2013. Objectives 1. To realize a meeting with the South RDA and verify the feasibility of the agreement related to the establishment of a RDA unit in Dragash 2. To discuss further issues related to the Program plans and the ILS LEDA actuation Agenda 02.05 Arrival to Prizren Meeting with Program Staff: Maria Helena, Besnik Cecelia, Kristina, Tom 03.05 Meeting with RDA Debriefing with Maria Elena and Besnik Cecelia Meeting with Besnik Cecelia for preparing follow up Departure Achieved Results 1. Feasibility of the agreement with South RDA for the establishment of the Dragash unit shared with the RDA director. Conditions agreed with him. 2. A draft plan for realizing complementary activities to the ILS LEDA agreement related to residual budget of the program for 2013 shared with Maria Elena and the program Staff 3. Simplification of the former proposed strategic development plan for Dragash LED shared and drafted 4. A specific plan of action of Besnik Cecelia prepared Activities 1. Agreement with South RDA. During the meeting with RDA the following main issues were discussed: a) Highlighting the regional framework where the Dragash unit will be working, as well as the regional role of RDA b) The importance of maintaining the unit in Dragash, because of proximity in services and the weak economy of the area c) Specifying better (and may be changing the name) of the “Steering Committee” mentioned in the UNDP proposal, according to the need of respecting the RDA statutory rules and regulations, and the need of a participation of Dragash associations (also the informal ones) to the work of the unit, on consultative bases.

Transcript of Report Mission Kosovo Canzanelli-May 2013 · Dragash municipality’s resources for the...

Page 1: Report Mission Kosovo Canzanelli-May 2013 · Dragash municipality’s resources for the sustainable, competitive long term development, due to the lack of qualitative and quantitative

1  G.  Canzanelli-­‐                                    Mission  Report–  May  2013  

Mission Report of Giancarlo Canzanelli in Kosovo 9-10 May 2013

Background

A proposal for a contract with the South RDA for the establishment of a RDA unit in Dragash and provide follow up to the Program findings en terms of LED was provided, according to the results of the previous mission on 8-10 April 2013.

Objectives

1. To realize a meeting with the South RDA and verify the feasibility of the agreement related to the establishment of a RDA unit in Dragash

2. To discuss further issues related to the Program plans and the ILS LEDA actuation

Agenda

02.05 Arrival to Prizren

Meeting with Program Staff: Maria Helena, Besnik Cecelia, Kristina, Tom

03.05 Meeting with RDA Debriefing with Maria Elena and Besnik Cecelia Meeting with Besnik Cecelia for preparing follow up Departure

Achieved Results 1. Feasibility of the agreement with South RDA for the establishment of the

Dragash unit shared with the RDA director. Conditions agreed with him. 2. A draft plan for realizing complementary activities to the ILS LEDA agreement

related to residual budget of the program for 2013 shared with Maria Elena and the program Staff

3. Simplification of the former proposed strategic development plan for Dragash LED shared and drafted

4. A specific plan of action of Besnik Cecelia prepared Activities 1. Agreement with South RDA.

During the meeting with RDA the following main issues were discussed: a) Highlighting the regional framework where the Dragash unit will be working,

as well as the regional role of RDA b) The importance of maintaining the unit in Dragash, because of proximity in

services and the weak economy of the area c) Specifying better (and may be changing the name) of the “Steering

Committee” mentioned in the UNDP proposal, according to the need of respecting the RDA statutory rules and regulations, and the need of a participation of Dragash associations (also the informal ones) to the work of the unit, on consultative bases.

Page 2: Report Mission Kosovo Canzanelli-May 2013 · Dragash municipality’s resources for the sustainable, competitive long term development, due to the lack of qualitative and quantitative

2  G.  Canzanelli-­‐                                    Mission  Report–  May  2013  

d) Specify better (through precise TOR’s the task, the activities, and contractual obligations of the person enrolled for the operations of the unit.

e) The importance for RDA of a partnership with UNDP f) The need of efforts for future self-sustainability of the RDA Dragash unit.

and the specific actions to be planned. g) The need for RDA of following the internal procedures for the approbation of

the agreement.

2. Draft plan for realizing complementary activities

A residual budget remains to be spent by the Program in 2013. Ideas for activities related to this budget were discussed, mainly for realizing synergies with the overall planning and in particular with the ILS LEDA commitments.

Some guidelines were shared:

I. To realize quick impact, visible initiatives at benefit of producers in the municipality, according to the ILS LEDA findings, and a preliminary review realized by Kristina (textile women) and Besnik (yellow plums, and dairy)

II. To avoid grant to businesses, for providing a rupture in the disseminated culture of “assisted, not profitable, condemned to failure” businesses if anytime granted.

III. To look for business initiatives, i.e. supported by a feasible business plan, that could and should financed through a mixt mechanism including • Microcredit • A small grant for start up (not more than 15% of the overall investment) • Technical assistance • Capacity building

3. Simplified Strategic Development Plan for Dragash LED

Tom solicited a simplified version of the former strategic development plan for Dragah LED; since the one proposed by ILS LEDA look too complex to the Municipal authorities.

A draft proposal of this new version was prepared (see annex 3), and it will be worked with Besnik Cecelia for the final draft.

4. Specific plan of action of Besnik Cecelia

A meeting was held with Bensik Cecelia, and discussion finalized to: a) Follow up with the assistance to the ILS LEDA missions b) Preparation of business plans for the initiatives related to the complementary

2013 budget, with particular reference to yellow plum, fruit and vegetable, dairy, beekeeping products, also in coordination with Di Stefano.

c) Verification of the conditions of the UNDP micro-grant initiative for looking to possible synergies for the Program

d) Verification of possible new donors for follow up in 2014

Recommendations 1. Follow up on the SOUTH RDA agreement

Follow up RDA and solicit them to send the official comments on the proposal, as agreed during the meeting.

An exchange of documents will follow until achieving the final agreed document, before the signature.

Page 3: Report Mission Kosovo Canzanelli-May 2013 · Dragash municipality’s resources for the sustainable, competitive long term development, due to the lack of qualitative and quantitative

3  G.  Canzanelli-­‐                                    Mission  Report–  May  2013  

ILS LEDA will be consulted and provide its inputs.

2. Complementary budget for 2013

Look at two options:

1 option (agreement with the micro-guarantee scheme): best option

• 20,000 USD for constituting a Dragash sub-account for special businesses (at least 5 business a year)

• 5,000 USD for micro-grant for start-up • 5,000 USD for technical assistance to business plan

The technical support and capacity building will be also provided by: • The RDA unit in Dragash • Bensik • ILS LEDA

2 Option (no agreement with the micro guarantee scheme)

• 10,000 USD Training for entrepreneurship • 5,000 support for business plans • 15,000 Grant of equipment for representative associations of famers (it

means association with a large number of members), on the base of a project in which the association increases the incomes of the sales of the members and they pay fees for the services provided due to the granted equipment.

In any case wait at least for the end of the Panettieri Mission and have inputs from him about equipment and possible businesses for beekeepers .

Page 4: Report Mission Kosovo Canzanelli-May 2013 · Dragash municipality’s resources for the sustainable, competitive long term development, due to the lack of qualitative and quantitative

4  G.  Canzanelli-­‐                                    Mission  Report–  May  2013  

ANNEX 1:

TERMS OF REFERENCE for establishing a Dragash Unit of the South RDA

1. Background

Taking into consideration the Project “Conservation of Biodiversity and Sustainable Land Use management in Dragash / Dragaš – Kosovo (thereby named as the Project)” defined:

I. A strategy for territorial economic development defined in consultation with the local actors, through the utilization of action-research for the bees, forest products, herbs, milk-meat value chains has been established.

II. The preliminary design of a comprehensive service system to entrepreneurs, producers, population, civil society organizations, and public institutions, in been designed, through three different options, including financial and not financial assets (see annex 2)

III. Both elements include the need for a multi-level governance, related to networks at government level (among the municipal departments of economy, agriculture, education etc.), at local civil society level (through associations), at local level (among civil society and public institutions), at inter-municipal level (among neighbor municipalities), at vertical level (coordination with the national government), also in consideration of the high risk of using only Dragash municipality’s resources for the sustainable, competitive long term development, due to the lack of qualitative and quantitative performance;

It is proposed that the RDA shall carry out following activities from June to December 2013:

a) Establish a Decentralized RDA Unit in Dragash for carrying out activities related to the economic development of this municipalities.

b) This Unit shall work under the fully responsibility of RDA.

c) This Unit will be steered by a Local Steering Committee, formed at least by:

• The RDA director or his/her representative • The Municipal Administration of Dragash • A representative of the milk and meat value chain as appointed by the

correspondent farmers and entrepreneurs • A representative of the fruit and vegetable and forest value chain as

appointed by the correspondent farmers and entrepreneurs • A representative of beekeeping value chain as appointed by the

correspondent farmers and entrepreneurs.

d) The role of the Steering Committee is to give guidance to the Unit and RDA as far as the plan of activity to be carried out, in accordance to the municipal development plan.

Page 5: Report Mission Kosovo Canzanelli-May 2013 · Dragash municipality’s resources for the sustainable, competitive long term development, due to the lack of qualitative and quantitative

5  G.  Canzanelli-­‐                                    Mission  Report–  May  2013  

e) The activities to be carried out shall be correspondent to the output of the Economic Surveys as produced by the Program (see http://www.ilsleda.org/activities/national-level-details.php?id=361)

f) The Unit will be coordinated by a responsible, selected through a public concourse and a committee constituted by the Program, the Municipality, ILS LEDA, and RDA, and appointed through TORs agreed by the Program and RDA.

g) The Unit will carry out during the period of the contract the following priority activities:

I. Promote and support the establishment and/or the initial operation of at least 4 farmers associations for the milk and meat, fruit and vegetables, forest, and beekeeping value chains

II. Provide a strategy for marketing the local products, also in connection with the surrounding municipalities (with priority to Prizren)

III. Promote mechanisms for facilitating access to finance

IV. Provide chances for access to project financing, looking for project opportunities, national and international partnership, calls for proposals, etc.

h) RDA will implement its current and foreseen activities and projects including the Dragash component (through the above mentioned UNIT)

The project will:

a) Provide technical support and accompaniment to the Unit responsible and Steering Committee for the implementation of their correspondent tasks, through a dedicated full time expert in Dragash

b) Provide technical support to RDA , through the ILS LEDA program of EURADA

c) Facilitate the relationship between RDA and Eurada.

d) Facilitate any other possible RDA international relationships

RDA, the Program, and ILS LEDA will work together for finding out mechanisms for assuring the technical, institutional, and financial sustainability of the UNIT after this contract will be expired.

2. Final Products

The final products of the activities will be:

1. The RDA UNIT in Dragash established, including the Steering Committee, and the responsible.

2. At least 4 value chain association supported in their establishment and/or initial operations.

3. The territorial marketing strategy for the Dragash products, possibly linked with regional products, and including territorial brand, preliminary designed.

Page 6: Report Mission Kosovo Canzanelli-May 2013 · Dragash municipality’s resources for the sustainable, competitive long term development, due to the lack of qualitative and quantitative

6  G.  Canzanelli-­‐                                    Mission  Report–  May  2013  

4. An assessment about available chances for accessing to finance by the small producers, and a document indicating complementary proposals, appropriate to the demand and the contextual framework of Dragash.

5. A plan for future technical, institutional, and financial sustainability put at work.

3. Budget

Item Cost (USD)

Actions carried out in accordance with the above mentioned ToR, by the UNIT responsible

12000

Transportation costs 2000

Administrative costs 1000

Total 15000

Page 7: Report Mission Kosovo Canzanelli-May 2013 · Dragash municipality’s resources for the sustainable, competitive long term development, due to the lack of qualitative and quantitative

7  G.  Canzanelli-­‐                                    Mission  Report–  May  2013  

Annex 2

DESIGN PROPOSAL FOR A TERRITORIAL COMPREHENSIVE SERVICE SYSTEM (CSS) IN THE

DRAGASH AREA Justification

According to the ILS LEDA TESSYA (Territorial Service System Analysis) based on a participatory exercise with the value chain focus groups, the needs and the demand of the services for economic development were assessed, with particular reference to the objective the local producer identified for their future.

This can be resumed as to consolidate and eventually to expand current market positioning trough increasing production and quality, and diversifying production and sales in foreign markets.

In the Municipality of Dragash development potential exist and it is given by the production of honey, forest fruits, herbs, milk and meat, textile, tourism, and culture system. In the municipality of Dragash no strong service institutions are present, with the exception of the LAG, which however is still a weak structure, with many problems of survival. On the other side people, especially the most disadvantaged ones, have great difficulties to access to the economic circuit and regular market, business services and credit. All this justifies the establishment of a system, if not one institution, able to guarantee delivery of a multitude of needed services in a comprehensive way. The ILS LEDA TESSYA has shown the most needed services are the following ones: A) Territorial animation

B) Business support

C) Project development and financing

D) Services for employment

1. Objective The objective of the initiative is to organize and efficient, effective, and self-sustainable mechanism or system for providing services to producers, population, local government, and other local institutions, than can support a long term economic development.

Page 8: Report Mission Kosovo Canzanelli-May 2013 · Dragash municipality’s resources for the sustainable, competitive long term development, due to the lack of qualitative and quantitative

8  G.  Canzanelli-­‐                                    Mission  Report–  May  2013  

2. The organization According to the outcomes of the ILS LEDA TESSY Analysis regarding the needed services, an optional organization, which with start the design could be as the following one in the picture 1. In order to implement this system the following considerations shall be done:

I. The system shall be self-sustainable in the long term. All the experiences that led to establish subsided organisms, terminated with the failure of the system after a number of years.

II. The previous consideration carries on another two ones: The first is the question “What the income of the system, if not public or international cooperation subsidies?”. It depends very much on the local context and in particular on the amount of money available from the local institutions (members or promoters of the system), and the availability of the “customers” to pay for the services.

These last two conditions seem to not exist in Dragash. Other way shall be then explored, as further pointed out.

III. The question is :”is the Dragash municipal dimension sufficient for

assuring a minimum volume of demand?” The Dragash population, NGO, other public institutions, and producers do not seem to achieve the minimum. level of demand, as shown in the Canzanelli paper “How to define the optimum administrative and geographic boundaries for a Local Economic Development Agency” (in http://www.ilsleda.org/usr_files/papers/7_how_to_define_040926.pdf) .

TERRITORIAL  SERVICE  SYSTEM  FOR  ECONOMIC  DEVELOPMENT  (TESSED)  

TERRITORIAL  ECONOMIC  PROMOTION  ECONOMIC  

DEVELOPMENT  (TESSED)  

BUSINESS    SUPPORT  

PROJECT    DEVELOPMENT    

SERVICE  FOR    EMPLOYEMNT    

Economic  Animation  

Information  System   Support  to  access  

to  finance  

Project  Elaboration  

Support  to  access  to  project  finance  

Labour  Demand  Supply  Matching  

Technical  Business  Assistance  

Page 9: Report Mission Kosovo Canzanelli-May 2013 · Dragash municipality’s resources for the sustainable, competitive long term development, due to the lack of qualitative and quantitative

9  G.  Canzanelli-­‐                                    Mission  Report–  May  2013  

IV. n order to assure the self-sustainability a public-private partnership shall be established At this purpose various alternatives can be studied: A] A mechanisms which coordinates different existing entities of neighbor municipalities (Dragash, Prizren, etc.) B] A new organization with an inter-municipal focus, an unique direction and municipal branches, which involves already existing service delivery organizations, but also the creation of new services. C] An initial effort made by Dragash with the intent of involve other neighbor municipalities in its start up. This option has two different outlook: using an existing institution (as the LAG), creating a new organization. The mechanism or organization shall be customer oriented as far as services, and externally oriented as far as finance.

The orientation to the customer is achieved building a strategy, that combines typology of the services with the typology of customers, and associate specific tolls for each combination.

In the case of Dragash the matrix is the following Table 1: Table1: matrix Service-Customers-Tools

PRIVATE SECTOR PUBLIC SECTOR

Territorial Animation Population Producers & Entrepreneurs

TOOLS • Sensitization-Awareness on local identity, contest, products

• Basic training • Family-School program • Promotion associations

Information Population Producers & Entrepreneurs

Municipalities

TOOLS • Community Mobile Info-program

Building Info-Centers

Business Support Population Producers & Entrepreneurs

TOOLS • Business plan model • Field visit program • Credit schemes

Project Development Local NGOs and Associations Municipalities and other public institutions

TOOLS Spread capacities in developing variated tyoes of projects

Spread capacities in developing variated tyoes of projects

Service for employment Population (unemployed) Enterprises

Public sector

TOOLS Labor Observatory Labor Observatory

Page 10: Report Mission Kosovo Canzanelli-May 2013 · Dragash municipality’s resources for the sustainable, competitive long term development, due to the lack of qualitative and quantitative

10  G.  Canzanelli-­‐                                    Mission  Report–  May  2013  

3. The different options

3.1 ption 1: An inter-municipal coordinated mechanism

This should be the result of an agreement, first of all, between the municipalities willing to work together for assuring the necessary support to themselves, to the population, and to the producers and making them in the position of being competitive and sustainable in the long term, as well as the municipalities capable of better performing in planning actions. The agreement shall be established among neighbor municipalities, which have commonalities, same willingness and interests, and can gather at least 200,000 residents. According to this agreement the municipal government’s shall involve the service delivery entities (public and private), and make them coordinated for articulating basic services, and produce synergic learning process. The coordination could be focused along two main issues: • Coordination by specialization: it means that there are entities which provides

services other ones do not provide-they are specialized-. If the entity 1 is specialised in the service A, and the entity 2 is specialized in the service B, they will provide their specific services in all the municipalities. The coordination consists in the relationships with the clients, that often require both services.

• Coordination by territory: If the entities A and B provide the same service, but in different territories, then they will keep doing so. The coordination consists in put in common knowledge and methodologies, and improve effectiveness by doing so

• Coordination by outsourcing: if an already organized effective entity exist and is able to provide multiple services in one municipality and not on the other ones, this one should generate a new branch in the other municipalities.

3.2 Option 2: A new organization with an inter-municipal focus

If the existing service providers are weak or none of them wants to assume the responsibility of coordinating the overall system, a new structure shall be taken into consideration. The inter-municipal focus shall remain for the previous assessment, and the inter-municipal task force or group should carry on the initiative. This group could be initially composed by the public authorities and then extended to the private and civil society sectors. The new structure could assume the legal form of a no profit mixed public-private association, whose members are: The municipalities, with the right of participating always to the management board, through one or more of their representatives; The representatives of the producers, through their associations The representative of the local NGOs

Page 11: Report Mission Kosovo Canzanelli-May 2013 · Dragash municipality’s resources for the sustainable, competitive long term development, due to the lack of qualitative and quantitative

11  G.  Canzanelli-­‐                                    Mission  Report–  May  2013  

The representative of civil society, through their associations (communitarian, sectoral, women, young people, etc.) Representative of university(ies) and the education sector A Promoting Group of this Comprehensive Service System (CSS) shall be constituted, and it (possibly with the support of the UNDP) shall: a) Promote membership

b) Prepare the statute

c) Define the organization

d) Elaborate the business plan or at least the financial plan for the first 5 years

e) Approve the financial plan and commit to it

f) Legalise the structure and constitute it formally with the full organisms and technical direction, according to the following picture 2

PICTURE 2 ORGANIGRAM OF A NEW LEGAL STRUCTURE FOR CSS

3.3 Option 3: Initial effort made by Dragash In the case of difficulties of encountering an agreement among various neighbor municipalities for achieving scale economies, and only after having tried it, a transitory solution could be pursued. Create the mechanism in Dragash, possibly with limited number of services (because of the sustainability), and then extend it with the involvement of

General  Assemby  

Management  Board  

Technical  Direction  

Advisory  Board  

Page 12: Report Mission Kosovo Canzanelli-May 2013 · Dragash municipality’s resources for the sustainable, competitive long term development, due to the lack of qualitative and quantitative

12  G.  Canzanelli-­‐                                    Mission  Report–  May  2013  

other municipalities and to other services, through an effective plan of action. At the beginning the prioritized services could be o Economic Animation o Project Development

Again the mechanism could be established through two alternatives A] using an existing structure, that in this case is the Local Action Group B] creating a new structure In the first case it is a complete renovation of the LAG, as fas as: ↗ The legal form, that shall be a mixed association between the Municipality

and the other groups of the private sector and civil society

↗ the organization, that shall include a management board a technical direction

↗ the technical direction that shall include a full time employed director, with th task of carrying on also the project development task, and other full time expert in economic animation

↗ the sustainability, that shall not depend only on the municipality.

4. Advantage and disadvantage of the 3 alternative options

The advantage and disadvantages of the 3 solutions are compared according to 3 criteria 1. Feasibility 2. Sustainability 3. Effectiveness

The results of the comparative assessment are illustrated in the following table 2: Feasibility Advantage Disadvantage

Option 1 To realize a inter-municipal system for services, that is more efficient and effective.

Easier method for realizing inter institutional agreements

To be a non formal organization, and then dependent on the willingness of other management structures. When management change there is a risk of stop to the activities

Option 2 To realize a inter-municipal system for services, that is more efficient and effective

To be a formal organization and not dependent on other ones

It is more complex and time spending realizing inter institutional agreements.

Option3 It is a quick way to provide responses to the need of the Dragash population

Difficulty to establish a local system for the weakness of the existing one (LAG), and the lack of capacities (long time for forming them)

Page 13: Report Mission Kosovo Canzanelli-May 2013 · Dragash municipality’s resources for the sustainable, competitive long term development, due to the lack of qualitative and quantitative

13  G.  Canzanelli-­‐                                    Mission  Report–  May  2013  

Effectiveness Advantage Disadvantage

Option 1 Covering an inter municipal area two elements of effectiveness are provided: a) number of customers that justify any service; b) possibility of membership fees contributing to the income, and c) more negotiation power with national and international institutions

Difficulties of coordination and collaboration between different structures

Complex articulation of the delivery between the central office and the peripheral customers (possible the presence of municipal branches is required, and this influences the budget)

Option 2 To realize a inter-municipal system for services, that is more efficient and effective

To be a formal organization and not dependent on other ones

It is more complex and time spending realizing inter institutional agreements.

Complex articulation of the delivery between the central office and the peripheral customers (possible the presence of municipal branches is required, and this influences the budget)

Option3 It is a quick way to provide responses to the need of the Dragash population

Difficulty to establish a local system for the weakness of the existing one (LAG), and the lack of capacities (long time for forming them)

Sustainability Advantage Disadvantage

Option 1 It is the simplest system and then the more sustainable because It needs less budget

Since the weakness in the institutional framework and governance, the financial sustainability could be not sufficient for assuring long life to the system

Option 2 It is the most sustainable structure by the point of view of institutional and social sustainability.

Once resolved the income problems it assures long life

It is the more complex solution and the more expensive.

Option3 It does not need much investment and budget

It is institutionally sustainable, but because of the limited territorial dimension and of the customers, the structure has the risk of not growing, and responding to all the demand of services.

5. Financial Plans

The financial plan is a tool for defining: a) The investment needed for the establishment of the system

b) The possibility of financial self-sustainability, through the balance between income and costs for at least the first 3 years of life.

Page 14: Report Mission Kosovo Canzanelli-May 2013 · Dragash municipality’s resources for the sustainable, competitive long term development, due to the lack of qualitative and quantitative

14  G.  Canzanelli-­‐                                    Mission  Report–  May  2013  

6.1 : the investment plan The following table 3 shows the comparison for the three options:

Table 3: Investment for establishing CSS in the Dragash area (USD)

Item Option 1 Option 2 Option 3 Design 6000 6000 6000 Training and tools 10000 10000 10000 Legalization 3000 3000 3000 2 years running costs 33600 105000 64000 Car 20000 20000 20000 Tutoring the start up 20000 30000 10000 Total 92600 174000 113000

Notice that: 1) The running costs are referred to:

Table CSS Running Costs (USD)

2) A financial mechanism shall put in place, because it generally is a tremendous toll for generating income. At this purpose different alternatives, as illustrated in the annex 1, could be implemented. In any case this mechanism should generate from 8,000 USD a year for the service system 1 option), to 12,000 for the other ones.

6.2 The financial plan The 5 years financial plan for the first 5 years of the life are illustrated in the following table 5, 6 , and 7 for each one of the options, and they include annual running costs and typology of incomes, as it results from the ILS LEDA experience, an could come from: a) Investment fund, that is the initial external capital put at disposal,

possibly (strongly recommended) through a contract, better than a simple grant

b) Income from financial mechanism, that is what gained through agreement with financial institutions and/or beneficiaries, as illustrated in the annex 1 for various alternative schemes

Item 1

Option 2

Option 3

Option General Director 12000 12000 12000 Experts 19200 9600 Secretary 4800 4800 Running costs 9000 5400 Total 16800 45000 27000

Page 15: Report Mission Kosovo Canzanelli-May 2013 · Dragash municipality’s resources for the sustainable, competitive long term development, due to the lack of qualitative and quantitative

15  G.  Canzanelli-­‐                                    Mission  Report–  May  2013  

c) Membership, that is the voluntary or statutory annual contribution of the members of the service organisation

d) Project Financing, that is the income generated by the management of projects the service organization implements

e) Service sale, that is the income generated by selling services to institutions, international cooperation, national government, local authorities (i.e. professional management of public services, fairs, international events, etc.)

Table 5: 5 years Financial Plan for the 1st options

Table 6: 5 years Financial Plan for the 2nd option (USD)

Financial Plan for the Option 1: Informal Inter-municipal System Item 1 year 2 year 3 year 4 year 5 year

Income Investment fund 16800 16800 Income from financial mechanism 9000 9000 9000 9000 Membership 0 0 0 Project Financing 0 8000 8000 Service sale 0 0 0 Utility from previous year 0 0 9000 1200 1400 Total 16800 25800 18000 18200 18400

Cost 16800 16800 16800 16800 16800 Balance 0 9000 1200 1400 1600

Financial Plan for the Option 2: Formal organized inter-municipal structure

Item 1 year 2 year 3 year 4 year 5 year Income 1 2 3 4 5 Investment fund 45000 45000 15000 Income from financial mechanism 12000 12000 12000 12000 Membership 0 10000 10000 10000 10000 Project Financing 0 10000 10000 10000 Service sale 0 0 0 4000 2400 Utility from previous year 0 22000 24000 15000 Total 45000 67000 69000 60000 49400 Cost 45000 45000 45000 45000 45000 Balance 0 22000 24000 15000 4400

Page 16: Report Mission Kosovo Canzanelli-May 2013 · Dragash municipality’s resources for the sustainable, competitive long term development, due to the lack of qualitative and quantitative

16  G.  Canzanelli-­‐                                    Mission  Report–  May  2013  

Table 7: 5 years Financial Plan for the 3rd option (USD)

Financial Plan for the Option 3: Formal organized municipal structure Item 1 year 2 year 3 year 4 year 5 year Investment fund 27000 27000 10000 Income from financial mechanism 12000 12000 12000 12000 Membership

Project Financing 0 6000 6000 10000 Service sale 0 0 0 Utility from previous year 0 12000 13000 4000 Total 27000 39000 40000 31000 26000 Cost 27000 27000 27000 27000 27000 Balance 0 12000 13000 4000 -1000

6. Conclusions

A comprehensive service system or Service HUB for supporting local Economic Development (SHED) in the Dragash area is needed: 1st) because the producers, the population, and the local institutions need to be supported in carrying on their activities, being effective, efficient, and competitive 2nd) because in absence of this system the support is requested and dependent on external resources, either at national or international level, and it is the contrary of a sustainable long term. The efficiency (customers/resource ratio), effectiveness (impact on socio economic development), and sustainability (income-cost ratio) are higher if the territorial dimension is higher. The municipal area of Dragash alone is far from assuring these conditions. In the current situation three options are alternative response for the implementation of the system: A] An informal inter-municipal organization, coordinating different service providers (public and private) and amalgamating them. B] A formal organized structure for providing services at multi-municipal level C] A formal Municipal structure, as first step of a larger inter-municipal organization In order to implement these options an investment is needed between 92,600 USD to 174,000 USD, that include items as

• Design • Training and tools • Legalization • 2 years running costs • Car • Tutoring the start up

Page 17: Report Mission Kosovo Canzanelli-May 2013 · Dragash municipality’s resources for the sustainable, competitive long term development, due to the lack of qualitative and quantitative

17  G.  Canzanelli-­‐                                    Mission  Report–  May  2013  

This investment can come from the international cooperation, European Union, or even National Government, or a combination of all: For being really self-sustainable, that is one of the condition for the possibility of being permanent (as similar experiences show in Pnud –through the ART program-, and outside, as shown in www.ilsleda.org), it is important the balance of income-costs in the first 5 years. Two assets are crucial: 1) A 2 year contract which assure the start-up sustainability, while the structure

become capable to run alone

2) A financial mechanism for facilitating access to credit or capitalization of enterprises supported by the service system, such as Guarantee Fund or other ones (see annex 1), which assure income to the SHED not dependent on public or international resources..

The countable exercise shows the sustainability is possible, provided the previous two conditions are respected, and in addition the system can count on: a) Capacity of project development and financing (in all the cases)

b) Capacity collecting membership fees, and selling services to customers in the case of the formal inter-municipal structure.

Page 18: Report Mission Kosovo Canzanelli-May 2013 · Dragash municipality’s resources for the sustainable, competitive long term development, due to the lack of qualitative and quantitative

18  G.  Canzanelli-­‐                                    Mission  Report–  May  2013  

ANNEX A TOOLS FOR GENERATING INCOME FOR THE SERVICE SYSTEM AS LINKED

TO THE ACCESS OF POPULATION TO BUSINESSS CREDIT Four possible credit schemes can be identified in the case of Dragash:

1. USING CURRENT GOVERNMENT GRANT SCHEME 2. USING CURRENT REGULAR CREDIT SCHEME, THROUGH SHARING INTEREST 3. USNG CURRENT CREDIT SCHEME, TROUGH ADDITIONAL CREDIT FOR

SERVICES 4. GRANT FOR REVOLVING/COMMUNITARIAN FUND

1. USING CURRENT GOVERNMENT GRANT SCHEME

The ministry of agriculture has launched a guarantee fund scheme for facilitating access to credit for the agriculture sector, and removing the obstacles for farmers and small entrepreneurs (interest rate, collaterals).

It is an interesting initiative, although so far we don’t know the specific rules.

Anyway, the ILSLEDA experience in this topic teaches

a) The agreement with the bank shall be very clear, for avoiding risks of mismanagement

b) The small farmers and entrepreneurs shall be assisted into the access process, mainly for the definition of the business plan, the assurance of the business feasibility, and the follow up to the entrepreneurs after the loan has been disbursed.

The problem is the need of assuring technical support, while assuring also the sustainability of this support, provided the “customers” are not able to pay for the service.

Furthermore the technical service shall include promotion and information, identification of the most competitive opportunities, building networks and associations, support marketing. Without these cross-cutting activities the attention to the small farmers and entrepreneurs risk to remain without great impact at territorial level, and in the long range.

In order to address the problem, various alternatives could be implemented, as the following ones:

I. The Ministry of Agriculture provides the technical assistance, through qualified personnel settled at least at regional level (two/three technicians per region), in charge on the public budget

II. The Ministry of Agriculture establishes a Fund for contracts with intermediaries for providing the above mentioned services, and assigns them through a bid or through a qualification process.

III. In this last case a Service Hub for Economic development in the Dragash area could be established and provide the needed services.

IV. An agreement with the Ministry of Agriculture could be established for sharing the interests accumulated by the Guarantee Fund capital deposited in the Bank, for compensating the services provided for its implementation.

The problem is that such an HUB does not exist in Dragash and in the neighbor municipalities, and its establishment could follow the recommendations provided in this same document.

Page 19: Report Mission Kosovo Canzanelli-May 2013 · Dragash municipality’s resources for the sustainable, competitive long term development, due to the lack of qualitative and quantitative

19  G.  Canzanelli-­‐                                    Mission  Report–  May  2013  

2. USING CURRENT REGULAR CREDIT SCHEME, THROUGH SHARING INTEREST

An agreement could be established between the Municipality of Dragash (and possibly other municipalities) with an existing financial institution (including banks) with the double aim of enlarging the client market (farmers and small producers) for the bank, and assuring feasibility to the business plan and capacities of the business management of the correspondent investment.

This agreement shall include the possibility of sharing the interest rate paid by the customer with the service provider, which assures the good result of the scheme.

Larger the number of potential clients, larger it is the interest of the bank. It means the joint effort of neighbor municipalities for realizing scale economies.

3. USING CURRENT CREDIT SCHEME, TROUGH ADDITIONAL CREDIT FOR SERVICES

In this case two different agreements shall be established

i) Service provider (the Dragash Hub)-Bank ii) Service provider- customer

In the first case the bank shall accept a business plan, which includes a component of technical assistance pre and post the loan disbursement, as structural element of the business feasibility.

In the second case the customer shall accept to pay the services provided, this cost be part of the business plan and of the investment, and the correspondent amount go directly to the Service Provider, and repaid through the credit.

This feature could also be applied to the Guarantee Fund scheme, providing added value to the sustainability of the services.

4. GRANT FOR REVOLVING COMMUNITARIAN FUND

A grant could be given to a community association/s (or alternative similar organization/s) representing common interests at territorial or sectoral level, with the aim of facilitating loans to the people involved in it, and repaying the services needed for supporting the borrowers (business plans, feasibility, etc.)

The community organisation decides how to provide the loans and whom to on a revolving criteria base. It could be done through an agreement with a financial institutions (strongly recommended) or via internal signed regulations.

One of the most important rules is the customer shall return an amount which includes:

a) The received loan plus b) The depreciation estimation plus c) The payment of the services provided to the borrower plus d) A risk assurance

These rules assure the long life sustainability of the businesses and of the scheme.

The problem is the absence of such type of reliable organisations in Dragash.

In this case a strong effort should be provided for implementing it or them.

Page 20: Report Mission Kosovo Canzanelli-May 2013 · Dragash municipality’s resources for the sustainable, competitive long term development, due to the lack of qualitative and quantitative

20  G.  Canzanelli-­‐                                    Mission  Report–  May  2013  

ANEX  3    United  Nations  Development  Programme    Conservation   of   Biodiversity   and   Sustainable   Land   Use  Management  in  Dragash/Dragaš  

Municipal   Development   Plan   for   the   Municipality   of  Dragash/Dragaš  2012  -­‐  2022    

FINAL  VERSION  

Working  document,  for  internal  use  only    

Local  Economic  Development  strategy    

EURADA-­‐ILS  LEDA  Maria  Elena  Zuniga  Barrientos  -­‐  Project  Manager  

           

Dragash  /  Dragaš,  Kosovo        December    2012  

Page 21: Report Mission Kosovo Canzanelli-May 2013 · Dragash municipality’s resources for the sustainable, competitive long term development, due to the lack of qualitative and quantitative

21  G.  Canzanelli-­‐                                    Mission  Report–  May  2013  

 General  goals    Improve   the   economic   performance   of   the   municipal   system,   mainly   in   terms   of  employment   and   income   for   the   population,   through   the   valorization   of   the   local  resources,   their   organization   on   value   chains,   and   upgrade   of   capacities   of   being  competitive   while   maintaining   a   long   term   sustainable   environment,   social   d   gender  equity.  Objectives    

1. Establish   solid   links   between   producers   and   municipality,   among   the   municipal  departments   (economy,   agriculture,   education   etc.),   and   between   Dragash   and  neighbor  municipalities,  and  possible  cooperation  with  the  national  government.  

2. Improve   the   economic   performance   and   competitiveness   of   endogenous   products,  with   specific   reference   to   the   ones   with   high   impact   potential   on   long   term  development,   such   as   bees,   milk,   meat,   herbs,   forest   products,   forest   fruits   and  mushrooms,  and  the  cultural  and  tourist  system.  

3. Establish   a   mechanism   for   providing   services   to   entrepreneurs,   producers,  population,   civil   society   organizations,   and   public   institutions,   for   assuring   a  sustainable  long  term  socio-­‐economic  development.  

4. Realise   design,   implementation,   and   financial   raising   for   priority   infrastructure  projects.  

5. Realise   and   implement   an   effective   territorial  marketing   either   for   promoting   the  territorial   image   at   national   and   international   level,   and   for   attracting   external  resources  to  be  used    coherently  with  shared  strategic  guidelines.  

6. Improve  capacities  on  economic  development  planning.  

 Actions  

A) Establish  links  for  the  economic  system    A1) Support   existing  associations  of  producers   and  promote  new  associations   in   the  

economic  sectors  (beekeepers,  breeders,  dairies,  etc.)  A2) Promote  Forums  of  value  chains  participated  by  the  Associations  of  producers  and  

traders  with  the  main  functions  of  • continuously  updating  the  strategic  guidelines,  • maintaining  cohesion  and  coherence  among  the  producers  in  the  implemention  of  the  strategic  plan    

A3) Establish   a   MUNICIPAL   FORUM   for   economic   development   and   planning,  including  municipality,   representatives  of   the  Value  Chain  Forums,   experts,  with  the  task  of  sharing  priorities  for  the  annual  and  multi-­‐annual  strategies  and  plans  regarding  economic  development,  and  monitoring  the  implementation.  

A4) Establish  inter-­‐municipal  cooperation  agreements  with  neighbor  municipalities.      

B) Improve  the  economic  performance  and  competitiveness  B1) Improving   the   performance   of   the   Bees,   Forest,   Herbs,   Meat,   Milk   value   chains  

through:  B11)   improving   their  productivity,   also   through   introduction  of   innovations  and  

new  production  techniques.  B12)   exploiting   all   the   local   economic   potential,   through   introducing   new  

businesses  for  diversifying  the  products  

Page 22: Report Mission Kosovo Canzanelli-May 2013 · Dragash municipality’s resources for the sustainable, competitive long term development, due to the lack of qualitative and quantitative

22  G.  Canzanelli-­‐                                    Mission  Report–  May  2013  

B13)    improving  marketing  strategies  for  increasing  sales    at  local,  national,  and  at  least  regional  (Balkans)  level.  

 B2) For  the  Textile  and  Clothes  value  chain:  

B21)  stimulate  creation  of  enterprises  for  valorizing  the  current  know  how  and  its  competitive  potential,  also  through  reinforcing  and  disseminating  capacities    B22)  elaborate  detailed  strategic  guidelines.    

B3) Improve   the   economic   and   social   impact   of   the   tourist   resources   of   Dragash  through   the   institution   of   a   Local   Tourist   System,   based   on   the   valorization   of  main   attractors,   such   as   environment,   bio-­‐diversity,   hospitality,   services,   local  productions,  and  culture.  .  

C) Establish  a  mechanism  for  providing  services  for  Local  Economic  Development  C1) Establish   a  mechanism   for   the   delivery   of   comprehensive   services   for   economic  

development,   with   priority   to   economic   animation   (stimulation   of   local   actors  towards   the   valorization  of   the   local   resources,   stimulation   and   support   of   local  networks   and   associations,   provision   of   information;   access   to   finance   (for  capitalizing  the   local  businesses,  without  penalty   for  the   local  people);     technical  assistance  (assistance   to   the  preparation  of  business  plans   for  accessing   to  bank  and   finance,   for   improving  productivity  and  competitiveness,   commercialization,  animal   sanitation,   quality   control),   vocational   training,   project   Development;  Support   to   innovation   (improving   capacities   for   identifying   and   supporting   the  transfer   of   technologies,   as   well   as   innovative   practices   available   in   Kosovo   or  internationally  and  favoring  transfer/adaptation).  

C2) This   system   shall   be   self-­‐sustainable,   and   include   existing   services   and   new  needed   ones.   It   shall   also   include   a   partnership   management   board   (with  representatives  of  the  local  partners),  and  a  skilled  technical  structure.  

C3) Assure  a  sustainable  start-­‐up  period  to  the  system,  through  financing  the  first  two  years  operations,  and  the  elaboration  of  the  five  years  financial  plan.  

C4) Establish   a   financial   mechanism,   as   a   Guarantee   Fund,   for   facilitating   access   to  finance   for   entrepreneurs,   population,   and   producers   with   difficulty   of   being  covered  by  bank  credits  

C5) Improve  capacities  of  the  management  board  and  technical  structure      

D) Realise   design,   implementation,   and   financial   raising   for   priority  infrastructure  projects    The  following  projects  have  the  priority:  

D1) Fair  and  special  event  space  D2) Waste  management  D3) Laboratories  for  quality  control  D4) Tourism  info  center  D5) Capacity  building  or  forming  skills  needed  by  value  chain  development  

 E) Realise  and  implement  an  effective  territorial  marketing    E1) Define   the   municipal   socio-­‐economic   personality,   through   identifying   and  

synthetizing   the   main   characteristics   as   far   as   the   tangible   and     intangible  territorial  parts,   i.e.    geographic  position  and  morphological  character,  social  and  

Page 23: Report Mission Kosovo Canzanelli-May 2013 · Dragash municipality’s resources for the sustainable, competitive long term development, due to the lack of qualitative and quantitative

23  G.  Canzanelli-­‐                                    Mission  Report–  May  2013  

relational  capital  level,  productive  sector  and  market’s  characteristics,  intensity  of  economic   and   cultural   external   exchanges,   cultural   heritage,   spirit   of   the   place,  social   and   civic   values   system,   services   system,   infrastructure,   and   level   of  knowledge  for  social  economic  development    

E2) Define   the   image   the   local   actor   want   to   provide   within   and   outside   of   the  territory,   possibly   sharing   it  with   the   neighbor  municipalities,   and   establish   the  correspondent  icon-­‐logos  

E3) Define   the   communication   instruments   for   better   disseminating   the   profile   and  the   image   of   the   territory,   either   for   promoting   the   territory,   marketing   its  product-­‐resources,  attracting  external  resources,  starting  from  the  Balkan  region  and  Europe.  

E4) Improve   skills   in   communication   and   information   technology,   through   an  university  agreement  for  an  educational  program  on  the  issue    

F) Improve  capacities  on  economic  development  planning  F1) Realise  a  university  diplomat  or  specialized  180  hours  course  on  Local  Economic  

Development  Strategies  and  Planning,  with  the  aim  of  disseminating  capacities  of  civil  servants  and  civil  society.  The  first  course  is  for  training  trainers  at  university  and   governmental   level,   with   the   participation   of   representatives   of   the   civil  society,  with   the   aim  of   experimenting   a   course,   that   could  be   replicated.   It  will  have  modules,  articulated  as  it  follows:  

• Module   1:   Territorial   Economic   Development   (TED)   and   Globalization   (10  hours)  

• Module  2:  Territorial  development  strategies:  tools  for  analysis,  mapping,  and  strategic  framework  (45  hours)  

• Module  3:  Governance  for  Territorial  Economic  Development  (25  hours)  • Module  4:  Local  economic  development  planning  (30  hours  days)  • Module  5:  Services  for  economic  development  (40  hours)  • Module  6.  Territorial  Marketing  (30  hours)    

 Further  Planning    

• Governance:   Next   year   development   plan,   through   the   established   MUNICIPAL  FORUM,  and  establishment  of  the  evaluation  and  monitoring  system  

• Competitiveness:    -­‐ Plan  of  the  implementation  of  the  Strategic  Guidelines  (by  value  chain),  -­‐ Plan   of   the   action-­‐research,   in   order   to   continuously   update   the   Survey   of   the  Resources   and   consequently   update   the   Strategic   Guidelines   of   I   and   further  levels  (integrated  strategies)  

-­‐ Provide  Quality  (ISO),  Food  safety  (HACCP),    Organicity  and  Halal  certification  • Services:  Strengthen  the  support  to  territorial  international  trade  and  innovation    • Territorial   Marketing:   Establishment   of   a   territorial   brand,   and   international  

positioning  at  least  at  regional  and  European  level.  

Responsibility  /  Institutional  Framework    

• Municipality  of  Dragash  have   the   institutional   task  and  responsibility  of   endorsing  

Page 24: Report Mission Kosovo Canzanelli-May 2013 · Dragash municipality’s resources for the sustainable, competitive long term development, due to the lack of qualitative and quantitative

24  G.  Canzanelli-­‐                                    Mission  Report–  May  2013  

the  plan,  and  coordinating  it,   in  harmony  with  the  institutions  which  constitute  the  Forum,   and   the   national   government.   The   municipality   should   also   facilitate   the  establishment   of   a   comprehensive   system   of   support   services,   possibly   in  collaboration  with  neighbor  municipalities.    

• The   Dragash   Economic   Development   Forum   (DEDeF),   constituted   by   the  Municipality  and  the  representatives  of  the  productive  sector  and  civil  society,  with  the  task  of  identifying  the  objectives  and  priority  of  development,  and  monitoring  

• The   value   chains   forums,   with   the   task   of   facilitating   common   actions   among   the  actors,  who  participate,  and  represent  them  in  the  DEDeF  

• The   National   Government   (Ministries   of   Agriculture,   Forest,   Tourism,   Economy),  with  the  responsibility  of  coordinating  actions  with  the  municipalities  

• The   private   sector   as   major   driving   force   of   the   economy,   as   it   is   represented  through  the  sectoral  associations  

 Justification  The  municipality  of  Dragash  can  be   typified,     according   to   the  Euroepan  Union  Leader   approach,   as   an   area  with  biodiversity,  which  has   some  differentiation,  potential  of  cultural  natural  tourism  attraction,  as  well  as  a  border  area,  but  with  problems   in   maintaining   and   valorizing   its   human   and   natural   heritage,  problems   of   productivity   and   competitiveness,   unemployment,   poverty,   and  emigration. In   general   the   available   strategic   options   for   different   types   of   areas   are   as   it  follows:  •     complementary   strategies   in   territories   that   already   have   good   level   of  competitiveness;  • integration   and   critical  mass   strategies,   in   very   fragmented   territories,  with  no   tradition   or   culture   of   collaboration,   weakened   by   the   absence   of  coordination  instruments;  

• diversification   and   consolidation   strategies   in   areas   with   negative   trend   in  competitiveness   (mature   sectors   with   comparative   factors   rather   than  competitive  advantage);  

• recovery   and   re-­‐valorization   strategies   in   areas   where   resources   and  traditional  skills  are  going  to  disappear  but  with  competitive  potential;  

• rebalancing   strategies   in   areas   where   development   is   concentrated   in   one  part  of  the  area,  while  in  other  parts  there  is  a  situation  of  decline;  

• backup  and   spread  and  animation   strategies   in   areas   suffering   from   intense  rural   exodus   or   isolation,   where   there   is   a   strong   trend   in   abandoning   the  agriculture  and/or  closing  the  remaining  businesses,  and  a  need  for  utilizing  creativeness  strategies.  

In   the   case  of  Dragash   the  optimal   strategy   is   a   combination  of   the   integration  strategy  with   the   animation     strategy,   through   the   realization   of   economies   of  scale   and   purpose   (value   chains),   creation   of   links   between   the   actors   and  institutions  at  municipal  level  and  also  with  other  municipalities,  and  promoting  collective  action  and  an  intense  animation  and  technical  assistance.  The  aim  is  to  introduce   new   dynamism,   through   the   restoration   of   confidence   of   local  

Page 25: Report Mission Kosovo Canzanelli-May 2013 · Dragash municipality’s resources for the sustainable, competitive long term development, due to the lack of qualitative and quantitative

25  G.  Canzanelli-­‐                                    Mission  Report–  May  2013  

populations  in  the  value  of  resources  and  in  their  capacity  for  action,  innovation,  and   creativeness.   The   spread   animation   designates   large   territorial   actions  aimed  at   to   enhance   ideas  and   innovative  projects,   and  provide  a   recognizable  and  effective  image  of  Dragash  and  Kosovo  territories,  to  reduce  dependence  on  external  changes  and  introduce  strong  elements  of  competitiveness,  in  terms  of  expertise   in   niche   markets,   diversification   and   production   differentiation,  increased  productivity  and  quality.   This  strategy  has  to  be  backed  by  complementary  approaches  to  succeed  in  the  long  run,  and  they  combine:  • the  participatory  approach,   through   the   involvement   in   the  decision  making  process  of  the  public  and  social  actors  

• the   focus   on   human   development   and   the  MDGs:   it   assumes   that   "the   basic  objective  of  development  is  to  enhance  human  freedoms  in  a  process  that  can  expand  personal  skills,  all  while  expanding  the  options  available  for  people  to  live  a  full  and  creative  life.In  particular  the  Millennium  Development  Goals  is  referred  to  live  a  long  and  healthy  life,  education,  access  to  resources  needed  for   a   decent   standard   of   living   and   to   participate   in   social,   economic   and  political  life  of  the  community.  

• the   reduction   of   inequality   and   exclusion   that   aims   to   a   better   allocation   of  resources,  taking  into  account  in  particular  the  situation  of  social  exclusion  of  different  populations.    

• the  reduction  of  the  gender  inequality:  it  involves  breaking  the  gaps  between  women  and  men,  showing  the  different  effects  of  conflict  on  different  sectors  of   the   population,   and   the   denial   of   choices   and   freedoms   of   women   as  subjects  of  rights  and  citizenship,  and  ensuring  affirmative  action  by  women  (for  their  interests  and  needs)  as  well  as  other  vulnerable  populations.  

• the  protection  of  the  environment,  biodiversity,  and  cultural  heritage,  that  are  necessary   to   ensure   the   welfare   of   current   and   future   population   and  resources  development  assets.

 Available  resources  and  competitive  advantages  The  municipal  potential  for  competitive  and  sustainable  economic  development  consists  in  various  resources,  once  adequately  valorized  and  networked,  such  as  bees,   herbs,   forest   products,   livestock   (milk   and   meat),   textile,   culture,   and  tourism.  In   general   their   competitive   advantage   consist   in   intrinsic   environmental  sustainability,  the  good  chances  of  high  production  through  farming,  due  to  their  intrinsic   characteristics   of     the   local   germplasms;   in   the   good   chances   of  obtaining  varieties  of  product,  due   to   the  existence  of    many  extended  and  not  degraded  gathering/farming  areas  belonging  to  several  different  ecosystem;  the  recognizable   prestige   of   the   products,   because   the   Šar   region   is   generally  recognized  as  an  area  characterized  by  a  significant  level  of  biodiversity;  the  high  level  of  healthiness  and  quality  of  many  local  products;  the  geographical  position  in  the  boarder  of  two  countries.  Specific  added  value  for  each  value  chains  are  also  present.  

Page 26: Report Mission Kosovo Canzanelli-May 2013 · Dragash municipality’s resources for the sustainable, competitive long term development, due to the lack of qualitative and quantitative

26  G.  Canzanelli-­‐                                    Mission  Report–  May  2013  

Services   for   supporting   economic   development   are   very   scarce,   with   some  exception  in  the  municipal  agriculture  and  tourism  department.  A  LAG  (Local  Action  Group)  exists  ,  but  it  is  really  not  functioning.  It  consists  of  only   one   person   doing   some   projects   on   voluntary   base.   On   the   paper   it   is  constituted  by  25  members,  but  they  are  individuals  and  not  representatives  of  civil   society   organisations.   It   is   depending   on   the   municipality,   although   the  municipal  department  is  not  really  supporting  it.   It  has  elaborated  and  realized  some  small  projects,  but   its   task   is   far   from  supporting  the  economic  and  rural  development    Obstacles  The  main  obstacles  consist  in  Ø the   small   production   scale,   due   to   the   little   number   of   residents,  entrepreneurs,   and   producers,   and   to   the   productive   possible   production  volumes;  and  the  difficulty  of  organizing  appropriate  services  

Ø the  scarce  knowledge  of  the  ecosystems  Ø the  lack  of  adequate  technical  skills  Ø the  lack  of  adequate  equipment  Ø the  low  quality  of  territorial  relational  capital  Ø the  lack  of  enterprise  organization  Ø the  bad  quality  of  the  internal  relationships  Ø the  lack  of  external  relationships  (whit  other  value  chains)  Ø the  lack  of  market  knowledge  Ø the  low  level  of  certification  (ISO,  HACCP,  Organicity,  Halal)  of  the  products  Ø the  lack  of  an  integrated  Waste  Management  System  Ø the  lack  of  an  integrated  Water  Management  System  Ø the  lack  of  services  for  improving  the  local  economic  performance.  

 The   above   mentioned   economic   development   strategy   is   aimed   to   reduce   the  obstacles  to  the  full  valorization  of  the  local  endogenous  resources,  as  mean  for  achieving   the   economic  development   objectives   of   improving   employment   and  income   for   the   population,   and   upgrading   the   capacities   of   being   competitive  while   maintaining   a   long   term   sustainable   environment,   social   and   gender  equity.  The   strategic   4   steps   for   achieving   these   objectives   are   illustrated   In   the  following  picture  and  guide  the  presented  strategic  plan  of  actions.              

 

①  Improve  capacities  of  local  producers  and  their  organizations  

④    

Position  the  local  products  in  the  proper  niche  markets,  also  through  territorial  

brand  

②  Link  the  local  producers  with  correspondent  ones  in  neighbor  municipalities  

④    

Position  the  local  products  in  the  proper  niche  markets,  also  through  territorial  

brand                                                                                            ③  Establish  a  mechanism  for  providing  effective  and  efficient  services  for  economic  development  in  a  proper  scale  