REPORT INDICATING STATUS OF CONSTRUCTION OF...
Transcript of REPORT INDICATING STATUS OF CONSTRUCTION OF...
REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES (220 kV & ABOVE) VIS-A-VISPROGRAMME DURING 2016-2017 As on 31-DEC-2016
Schedule
1. 2. 5. 6. 7. 8. 9. 10. 12.3.
Revised/Anticipate
d
11.
Construction progress StatusTarget Date
RemarkTowers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hcKM
Ckts(S/C)
&(D/C)
DAMODAR VALLEY CORPORATION (DVC)
Railway Crossing: SER, Ranchi approved in principle for 3 no.rail crossing on24.11.2014.Way leave charges has been deposited for 03 no. rail crossing &SER,Ranchi has given permission for execution of constrcution work of 03 no.rail crossing on 16.12.15 PTCC: Joint inspectionreport has been already submitted by AGM (NWO-CFA), O/o TheCGMT,Jharkhand circle,Ranchi on 15.09.15 to The DET(PTCC),E/Region,Inspection cell Kolkata.Forest Clearance: Working Clearance issued on 22.5.2015.Progress affected due to non-availability of tower materials. In order to solvefund crisis faced by Contractor (M/s ECI-SEW), approval has been arranged forpayment to the sub-vendor directly & subsequently 234 MT of tower materialshas been delivered at site.
NOV-14112Gola - Ranchi (PG) 226 168 118 01 D/C MAR-17220
Severe ROW problem in 17 no locations. SE Railway has given in principleclearance of crossing.Around 24 no. locations outside the ISP premises are being diverted again dueto severe ROW problem. Contractual issues cropped up due to repeated routediversion. Presently work is held up.Likely to be dropped.
37LILO of Mejia-Kalyaneswari at Burnpur S/S 79 55 0 02 D/C DEC-16220
Forest: Working clearance obtained on 6.3.13. Contractual issues cropped updue to delay in obtaining forest clearance as well as theft of materials (100 Ckm)from erected line. Rectification work of the theft portion of the line has beencompleted. 54 KM (i.e 108 CKM) of line has been charged at 220 KV from MTPSend on 09.9.15.Line checking & assessment for rectification work is underprogress.Restringing started at theft portion.
DEC-08342Mejia TPS - Gola 552 541 509 1483 D/C APR-17220
Forest:Working clearance obtained in Jan'13.PTCC Clearance:PTCC issued on 18.2.2014. Aviation clearance :ObtainedSlow progress due to non-availability of working gang due to fund crunch ofContractor (M/s Jyoti Structures). Approval has been arranged for payment tothe sub-vendor directly to solve above fund crisis of M/s
AUG-10311Raghunathpur TPS -Ranchi (PG) 439 439 439 3064 D/C MAR-17400
Trasmission Lines: Page 1 of 91
Legends
TL: Total Location STC: Stubs Cast TE: Towers Erected STG: Stringing Completed
Schedule
1. 2. 5. 6. 7. 8. 9. 10. 12.3.
Revised/Anticipate
d
11.
Construction progress StatusTarget Date
RemarkTowers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hcKM
Ckts(S/C)
&(D/C)
JSL which has subsequently resumed work in Sep 2015 for balanceportion.Charged at 400 KV upto Loc No 210 on 27.12.16.
Trasmission Lines: Page 2 of 91
Legends
TL: Total Location STC: Stubs Cast TE: Towers Erected STG: Stringing Completed
Schedule
1. 2. 5. 6. 7. 8. 9. 10. 12.3.
Revised/Anticipate
d
11.
Construction progress StatusTarget Date
RemarkTowers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hcKM
Ckts(S/C)
&(D/C)
NHPC LIMITED (NHPC)
JAN-17LILO of Lakhwar HEP- Muzaffarnagar at Vyasi HEP1 D/C 220
Trasmission Lines: Page 3 of 91
Legends
TL: Total Location STC: Stubs Cast TE: Towers Erected STG: Stringing Completed
Schedule
1. 2. 5. 6. 7. 8. 9. 10. 12.3.
Revised/Anticipate
d
11.
Construction progress StatusTarget Date
RemarkTowers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hcKM
Ckts(S/C)
&(D/C)
POWER GRID CORPORATION OF INDIA LIMITED (PGCIL)
18 locs. under severe ROW problem. Matter taken up with Stateadministration.Not yet resolved.Critical
APR-17114Ajmer (New) - Ajmer (RVPN) (Quad) 199 154 140 201 D/C APR-17400
Award placed in Aug'16. Engg. in progress.544Ajmer (new) - Bikaner line 8082 D/C MAY-19765
ROW at both ends.JUN-16486Allahabad - Kanpur line 652 628 594 2843 D/C JUN-17400
ROW being faced near Angul end. Huge forest involvement (REC held. Stage-Iclearance awaited). Critical. REC held. Observation raisedcomplied. To be putup to REC again.
DEC-15580Angul - Jharsauguda line 790 694 591 1134 D/C JUN-17765
Forest clearance received.Commissioning matching with down stream Padghe-Kudus & Kudus (MSETCL) S/s. MSETCL S/stn. Critical. ROW being faced.
AUG-14570Aurangabad (PG) - Padghe (PG) 773 713 681 3795 D/C JUN-17765
Stage-I Forest clearance (138ha.) received in Aug'15.Permission to workreceived in Oct'15. Severe ROW problem (involvement grape garden).Critical
JUL-14654Aurangabad - Boisar line 860 803 757 4166 D/C JUN-17400
Aurangabad - III - Aurangabad (PG)7 2xS/C 765
Work under progress.APR-18572Banaskanta - Chittorgarh line 856 578 401 08 D/C APR-18765
Work under progress.APR-1852Banaskanta - Sankhari line 78 21 0 09 D/C APR-18400
Ready for Commissioning 08/16.MAY-16338Betul - Khandwa (Quad) line 435 435 435 33810 D/C AUG-16400
Award placed in Aug'16.Engg. in progress.50Bhadla (PG) - Bhadla (RVPN) line 8211 D/C JAN-19400
Award placed in Sep'16. Engg. in progress.400Bhadla - Bikaner line 48412 D/C JAN-19765
Work under progress.JUL-18618Bhuj Pool - Banaskanta line 792 107 22 013 D/C JUL-18765
Bays at NTPC awarded in May'16. Completion of bay by NTPC delayed.26Biharshariff (Ckt III & IV) - Kahalgaon (NTPC) 42 36 36 1814 D/C APR-17400
Award placed in Aug'16. Work under progress.700Bikaner - Moga (PG) line 1018 1115 D/C MAY-19765
Ready for Commissioning 9/16.JUN-152574Champa Pooling Station - Kurukshetra (HVDC)BIPOLE Line
3477 3477 3477 257416 BIPOLE
SEP-16800
Award placed in Mar'16. Engg. in progress.APR-1984Chilkaluraipeta - Narasaraopeta 11917 D/C APR-19400
Work under progress.APR-19550Chilkaluripeta - Cudappah 735 171 7518 D/C APR-19765
Work under progress.APR-1750Chittorgarh (New) - Chittorgarh (RVPN) (Quad) line 133 128 70 2519 D/C APR-17400
Work under progress.APR-18418Chittorgarh - Ajmer line 577 565 525 5120 D/C APR-18765
work under progress.APR-19Cudappah - Madhugiri 709 42 1821 D/C FEB-19400
Trasmission Lines: Page 4 of 91
Legends
TL: Total Location STC: Stubs Cast TE: Towers Erected STG: Stringing Completed
Schedule
1. 2. 5. 6. 7. 8. 9. 10. 12.3.
Revised/Anticipate
d
11.
Construction progress StatusTarget Date
RemarkTowers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hcKM
Ckts(S/C)
&(D/C)
Work under progress.360Cuddapah - Hindupur (Q) 534 187 120 022 D/C JUL-18400
Award placed in Jan'16.Efforts being made to complete in 2016-17 for start uppower to NTPC.
48Darlipalli TPS - Jharsuguda (Sundergarh) PS 60 35 19 023 D/C JUN-18765
5.0 Kms of stringing at Saharanpur Distt. under severe ROW.Delay in tree cutting by forest deptt. in Uttrakhand affected stringing.
NOV-14178Dehradun - Abdullapur 247 246 242 14124 D/C MAY-17400
Work progress affected due to ROW problem in western UP.NOV-11330Dehradun - Bagpat 443 443 443 32325 D/C JAN-17400
Severe ROW problem faced in Karnataka. Corridor compensation survey underprogress.
AUG-14244Dharmapuri (Salem New) - Somanahalli 336 323 276 17126 D/C JUN-17400
Severe ROW on Doda Distt. 02 loc. under court stay.NOV-14115Dulhasti - Kishenpur 340 335 328 10427 D/C MAR-17400
Aportion of line (279 Ckm) commissioned in April'12. balance portion under holddue to ECL.
314Durgapur-Jamshedpur (Balance Portion) 434 434 434 31428 D/C JUL-13400
Recently GO issued on 30.07.15 in which compensation is to be done on landvalue, to be finalised by concerned DCwith suport of State Govt. Balance surveyresumed on 27.07.16. Package being re-tendered for award of balance work.
NOV-08297Edamon (KSEB) - Muvattupuzha (PG) 438 159 105 2929 D/C JUN-18400
Ready for Commissioning 09/16. (Due to delay in Essar Generation Project &non finalization of gentry 6 ckm work is pending balance 446 ckm has been testcharged.
FEB-14446Essar Gujarat TPS - Bachau (Tripal) 606 606 606 44630 D/C SEP-16400
Work under progress.133Extn. Kudankulam APP - Tirunveli (Q) 185 112 72 531 D/C MAY-18400
Work under progress.160Farakka - Baharampur (Twin HTLS) 243 51 2 032 D/C APR-18400
Line charged in Mar'16.NOV-1686Farakka - Malda 0 8633 D/C MAR-16400
Work under progress.NOV-17203Gadarwara - Jabalpor Pool line 278 185 132 4534 D/C MAY-17765
Work under progress.NOV-17638Gadarwara - Warora Pooling Station 871 366 22035 D/C NOV-17765
Commissioned 04/16.AUG-14273Gaya - Varanasi 738 738 738 27336 S/C APR-16765
112Gola - Ranchi line37 D/C 220
Efforts are being made to complete earlier.APR-18720Jabalpur PS - Orai 969 868 783 21438 D/C APR-18765
Ready for commissioning 09/16.MAR-16277Jaipur (RVPNL) - Bhiwani (IInd Ckt) line 751 751 751 27739 S/C SEP-16765
Work under progress.Forest proposal submitted.397Jameling - Alipurdauar line (Q) (India Side) 496 72 140 D/C JAN-18400
Commissioning 06/16.NOV-13234Jharkhand Pool (Chandwa) - Gaya (Quad) line 332 332 332 23441 D/C JUN-16400
Huge forest involvement. Clearance awaited. Critical.DEC-15300Jharsuguda - Dharamjaygarh line 407 327 275 6842 D/C JUN-17765
Trasmission Lines: Page 5 of 91
Legends
TL: Total Location STC: Stubs Cast TE: Towers Erected STG: Stringing Completed
Schedule
1. 2. 5. 6. 7. 8. 9. 10. 12.3.
Revised/Anticipate
d
11.
Construction progress StatusTarget Date
RemarkTowers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hcKM
Ckts(S/C)
&(D/C)
Gen. Proj. delayed. However, contigency arrangement being worked outsubjectto availiblity of Gen Sw. Yd. which is expected by Feb'17.
OCT-1676Kakrapar APP - Navsari line 109 105 103 7043 D/C FEB-17400
Line completed. Gen. Proj. delayed. However, contigency arrangement beingworked out subject to availiblity of Gen Sw. Yd. which is expected by Feb'17.
OCT-16234Kakrapar APP - Vapi line 326 326 326 23444 D/C FEB-17400
ATS slowed-down to the extent possible to match Gen. (ant. by Oct'17).AUG-13110Kameng - Balipara 149 146 133 4445 D/C APR-17400
Ready for Commissioning 06/16.OCT-1441Kanpur (new) - Kanpur (exit) 62 62 62 4146 D/C JUN-16400
Ready for Commissioning 06/16.OCT-14466Kanpur - Jhatikara 1269 1269 1269 46647 S/C JUN-16765
Ready for Commissioning 08/16.MAY-16344Khandwa - Indore line 479 479 479 34448 D/C AUG-16400
Khargone TPP-Indore49 D/C 400
Work affected due to disturbance in Kashmir since Jul'16 & slow process toresolve compensation issue. State/MoP help required. All efforts shall be madeto complete line matching with Generation.
JUL-1778Kishanganga - Amargarh 150 90 3550 D/C JUL-17220
Work affected due to disturbance in Kashmir since Jul'16 & slow progress. Toresolve compensation issue. State/MOP help required.
MAR-18228Kishanganga - Wagoora 248 68 651 D/C MAR-18220
Due to distrubance in Kashmir since Jul'16. site work affected. 03 locs. inRamban under severe ROW problem. State/MoP help required.
JUL-13278Kishenpur - New Wanpoh line (132 KM D/C + 7 KMMulti Ckt)
399 396 395 27452 MC+D/C
MAR-17400
Kishenpur - Ratle, (Dulhasti- Kishenpur Second Cktstringing extending up to Ratle HP)
53 S/C 400
Work under progress.NOV-17356Kota - Jaipur (South) 529 326 29954 D/C NOV-17400
Efforts are being made to complete the line earlier. Work under progress.MAR-18190Kurukshetra - Jind line (Q) 270 253 234 3355 D/C MAR-18400
Work under progress.136LIIO of Both ckt of Rourkela - Raigarh (2nd line) atJharsaguda (Sundargarh)
200 33 16 056 D/C APR-19400
Commissioned 03/16..(Late Reported).NOV-1321LILO IN of Both Ckt Teesta-III - Kishanganj atRangpo
36 36 36 2157 MC+D/C
JUL-16400
Commissioned 05/16.61LILO of Meerut - Kaithal at Bagpat (Ckt-II) 177 177 177 6158 D/C MAY-16400
Testing under progress. Efforts are being made to complete by Jan'17.JUL-1717LILO of One Ckt Parbati Pooling Station - Amritsar atJalandhar
49 49 49 3459 D/C JUL-17400
Ready for Commissioning 06/16.112LILO of 400 kV D/C Baripada - Mendhasal at Pindiabil 107 107 107 11260 2xD/C JUN-16400
Award placed. Engg. in progress.JUL-172LILO of Abdullapur - Karchan wangtoo at Kala Amb 661 D/C JUL-17400
Work under progress. Severe ROW problem at Agra end.JUL-17108LILO of Agra - Bharatpur at Agra 173 151 134 4462 S/C JUL-17220
Trasmission Lines: Page 6 of 91
Legends
TL: Total Location STC: Stubs Cast TE: Towers Erected STG: Stringing Completed
Schedule
1. 2. 5. 6. 7. 8. 9. 10. 12.3.
Revised/Anticipate
d
11.
Construction progress StatusTarget Date
RemarkTowers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hcKM
Ckts(S/C)
&(D/C)
Efforts are being made to complete earlier.APR-1811LILO of Agra - Meerut at Aligarh 37 7 363 D/C APR-18765
Package re-awarded in Jun'16.Work commenced.DEC-1230LILO of Aizwol (PG) - Zemabawk at Melriat (PG) 16 0 0 064 D/C JUN-17132
Work under progress.107LILO of Bellary - Tumkur (Vasantnarsapur) line (Q) atTumkur Pool.
130 2265 D/C DEC-18400
Testing under progress. Completion matching with Alipurduar PS.3LILO of Birpara - Salakati line at Alipurduar (NewPooling Station)
7 7 7 566 D/C MAR-17220
Gen. Project delayed (ant. in 2017-18).Work under progress. Commissioning matching with associated HVDCTerminal.Severe ROW issues seriously affected progress.
JAN-1524LILO of Bishwanath Chariali - Agra at Alipurduar 64 64 54 867 HVDC MAR-17800
Testing under progress. Completion matching with Alipurduar PS.JAN-1513LILO of Bongaigaon - Siliguri at Alipurduar 23 23 23 1368 D/C MAR-17400
Award placed in Jan'16. Engg. & survey under progress.19LILO of Both Ckt Cuddapah - Hindupur line (Q) at NPKunta S/S
27 0 0 069 D/C MAY-17400
Award placed. Engg. in progress. Commissioning matching with S/stn. rajghatS/S land possesion in Dec'16.
MAY-17LILO of Both Ckt of Bawana - Mandola at Rajghat 8270 D/C MAY-17400
Award placed. Commissioning matching with Sub station. Delay in landacquisation (land acquired in Aug'16).
JUL-1770LILO of Both Ckt of Bmanauli - Samaypur atTughlakabad
15071 D/C JUL-17400
Work under progress.Severe ROW problem.71LILO of Both ckto of Mundra UMPP - Limbdi (Triple) atBachau.
103 33 7 072 D/C JUL-18400
ROW in balance work. Land owners demanding compensation as per guidelineby MOP. State Govt. yet to issue notification.Land owners has approched H'blecourt. Next date of hearing ia 16.01.17.
JUN-1650LILO of Dadri - Malerkotla at Kaithal 74 73 70 3773 D/C FEB-17400
Award placed in Apr'16. Engg. in progress.3LILO of Farakka - Jeerat line at Baharampur 5 0 0 074 S/C APR-18400
Award placed in Apr'16. Engg. in progress.30LILO of Farakka - Jeerat line at Sagahdighi 52 0 0 075 S/C APR-18400
19LILO of Gangtok - Melli at Rangpo76 S/C 132
Commissioned 11/14.NOV-147LILO of Gangtok - Rangit at Rangpo 21 21 21 777 S/C NOV-14132
Ready for Commissioning 12/2016.JUN-1438LILO of Gazuwaka - Vijayawada 400KV S/C line atVemagiri PS
56 56 56 3878 D/C DEC-16400
Commissioned 06/16.JUL-1728LILO of Gladni - Hiranagar at Samba (PG) 50 50 50 2879 D/C JUN-16220
Award placed in Jun'16. Engg. in progress.3LILO of Gooty - Tumkur (Vasantnarsapur) line (Q) atTumkur Pool.
1380 D/C DEC-18400
Works under progress.MAR-187LILO of Hyderabad - Kurnool at Maheshwaram 13 13 12 681 D/C MAR-18400
LILO of Jiribam - Aizawl at Turial82 D/C 132
Commissioned 04/16.MAY-1621LILO of Kadapa (Cuddapah) - Kolar at N.P. Kunta 32 32 32 2183 D/C APR-16400
Trasmission Lines: Page 7 of 91
Legends
TL: Total Location STC: Stubs Cast TE: Towers Erected STG: Stringing Completed
Schedule
1. 2. 5. 6. 7. 8. 9. 10. 12.3.
Revised/Anticipate
d
11.
Construction progress StatusTarget Date
RemarkTowers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hcKM
Ckts(S/C)
&(D/C)
Pooling Station
Efforts are being made to complete earlier.APR-1811LILO of Kanpur - Jhatikara at Aligarh 33 16 284 D/C APR-18765
Work under progress.194LILO of Kurnool - Thirvualam line at Cuddapah 282 33 16 085 D/C JUL-18765
Commissioned 03/13.DEC-121LILO of Loktak - Imphal at Imphal (New) line 5 5 5 186 D/C MAR-13132
Balance portion (02 Kms) of line being executed using under ground cable. Workaffected due to water logging. Severe ROW being encountered.
SEP-1016LILO of Lonikhand (MSETCL)- Kalwa at Navi Mumbai 25 25 25 1687 D/C MAR-17400
During the meeting with DC on 08,09,16. Raitha Sangha Requested to discusshigh compensation issue with energy minister. After support from State Govt.,compensation survey by Revenue deptt. is in progress.
JUL-1234LILO of Neelamangla - Hoddy line and LILO ofSomanhally - Hoddy at Yelahanka
25 25 25 1088 D/C JUN-17400
Award placed, Engg. in progress.Commissioning matching with Sub station.Delay in land acqurisation (land acquired in Aug'16).
MAY-1745LILO of One Ckt of Bamnauli - Jhattikara at Dwarka-I 5789 D/C MAY-17400
Ready for Commissioning 9/16.JUN-1628LILO of One ckt RAPP - Kankroli at Chittorgarh 54 54 54 2890 D/C SEP-16400
Award placed in Dec'16.120LILO of One ckt of 400 kV Bhadla (RVPN) - Bikaner(RVPN) line at Bikaner (New)
20291 D/C MAY-19400
Commissioned 04/16.OCT-1458LILO of Pune - Aurangabad at Pune (GIS) 67 67 67 5892 2xD/C APR-16400
1LILO of Ranganadi - Nirjuli at Pare HEP93 S/C FEB-17132
Award placed in Apr'16. Engg. in progress.2LILO of Sagardighi - Subhasgram line at Jeerat 5 0 0 094 S/C APR-18400
Award placed in Mar'16. Engg. & survey under progress.55LILO of Simhadri - Vijayawada line at Vimagiri-I (AP) 63 0 0 095 D/C JUL-18400
Work under progress.30LILO of Simhadri - Vijayawada line at Vimagiri-II 45 3 0 096 D/C JUL-18400
During the meeting with DC on 08,09,16. Raitha Sangha Requested to discusshigh compensation issue with energy minister. After support from State Govt.,compensation survey by Revenue deptt. is in progress.
DEC-1525LILO of Somanhally - Hoddy line at Yelahanka 25 25 25 1097 D/C JUN-17400
Work almost completed. Commissioning expected by Feb'17.APR-168LILO of Subhashgram - Jeerat at Rajarhat 16 16 16 898 S/C FEB-17400
LILO of Tilaiya - Balia line at Gaya99 D/C 765
Work under progress.118LILO of Vindhyachal - Jabalpur line (Q) (II Ckt.) atRewa PS
170 86 53100 D/C MAR-17400
LILO of Vishnu Prayag - Muzaffarnagar at TapovanVishnugarh HEP
101 D/C 400
Work under progress.NOV-17186LILO of Wardha - Parli at Warora PS (Q) 246 107 66102 2xD/C NOV-17400
LILO of one circuit of Dulhasti - Kishenpur at103 D/C 400
Trasmission Lines: Page 8 of 91
Legends
TL: Total Location STC: Stubs Cast TE: Towers Erected STG: Stringing Completed
Schedule
1. 2. 5. 6. 7. 8. 9. 10. 12.3.
Revised/Anticipate
d
11.
Construction progress StatusTarget Date
RemarkTowers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hcKM
Ckts(S/C)
&(D/C)
Ratle HEP.
Efforts are being made to complete earlier.APR-1872LILO of one ckt of Satna - Gwalior at Orai 102 100 78 0104 D/C APR-18765
Work under progress.APR-17224Lara STPS - Champa pooling Station line (Q) 306 231 205 38105 D/C APR-17400
Commissioned 04/16.APR-1736Lara STPS - Raigarh (Kotra) line 50 50 50 36106 D/C APR-16400
20Legship - New Malli107 D/C NOV-16220
17Leh-Kharu (And LILO of Leh-Nimmo)108 D/C 66
Commissioned 07/16.10Line for swapping of Purnea bay with Sasaram bay atBiharshariff s/s
17 17 17 10109 D/C JUL-16400
Completion matching with Gen. (Sch. uncertain). Works stand still on a/c oflocalm disturbance /agitation against big dam. Generation uncertain.
AUG-13335Lower Subhansiri - Biswanath Chariyali line -I 444 329 228 64110 D/C MAR-18400
Completion matching with Gen. (Sch. uncertaion).Works stand still on a/c of localdisturbancec /agitation against big dam. Gen. schedule uncertain.
AUG-13348Lower Subhansiri - Biswanath Chariyali line -II 465 327 196 35111 D/C MAR-18400
ROW in Lucknow end.JUN-16320Lucknow - Kanpur 449 408 392 113112 D/C MAY-17400
Severe ROW in Karnataka. Efforts being made to resolve with the help of StateGovt.
JUN-14132Madhugiri - Yelhanka 178 131 101113 D/C DEC-17400
Work under progress. Severe ROW problem being faced.MAY-16386Mauda-II - Betul (Quad) line 551 520 513 308114 D/C MAR-17400
Ready for Commissioning 08/16.JUL-1556Meja - Allahabad line 81 81 81 56115 D/C AUG-16400
Stage-I forest clearance awaited.Package re-awarded in Jun'16.DEC-1212Melriat (New) - Sihmui line 23 0 0 0116 D/C JUN-17132
Award placed in Aug'16. Engg. in progress.120Mohindergarh - Bhiwani line 150117 D/C AUG-18400
Line commissioned in Jul'15.DEC-122Mokokchung (PG) - Mokokchung (Nagaland) line 11 11 11 2118 D/C JUL-15132
Award placed in Aug'16. Engg. in progress.190Mundra UMPP - Bhuj Pool line 257119 D/C DEC-18400
Award placed in Aug'16. Work under progress.NLC - Karaikal line 312 4120 D/C NOV-17220
Work under progress.204Nabinagar-II - Gaya (Q) 289 51 9 0121 D/C JUN-19400
Work under progress.278Nabinagar-II - Patna (Q) 390 64 32 0122 D/C JUN-19400
Commissioned 10/2016.MAR-15406Nagapattinam Pooling Station - Salem (NMTCL) 543 543 543 406123 D/C OCT-16765
Commissioned 12/2016. (Remaining portion was taken as commissioned asVapi-Navsari line in Mar'13)
OCT-12161Navsari - Boisor line (Balance portion ) 567 567 567 161124 D/C DEC-16400
JUL-1514Neyveli TS-II - Neyveli TS-I125 D/C NOV-15400
Trasmission Lines: Page 9 of 91
Legends
TL: Total Location STC: Stubs Cast TE: Towers Erected STG: Stringing Completed
Schedule
1. 2. 5. 6. 7. 8. 9. 10. 12.3.
Revised/Anticipate
d
11.
Construction progress StatusTarget Date
RemarkTowers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hcKM
Ckts(S/C)
&(D/C)
Work under progress.MAY-1822Nizamabad - Dichpali 15 15 15126 D/C MAR-17400
Efforts are being made to complete earlier.APR-18664Orai - Aligarh 939 738 551 17127 D/C APR-18765
Efforts are being made to complete earlier.APR-1876Orai - Orai (Q) 111 100 93 18128 D/C APR-18400
Commissioning of Kudus S/S by MSETCL critical. Completion matching withAurangabad-Padghe line.
AUG-1434Padghe (PG) - Kudus line 46 46 46 31129 D/C JUN-17400
Commissioned 04/16.JUN-16131Panchkula - Patiala 183 183 183 131130 D/C APR-16400
Work under progress.JAN-1836Parli - Parli (Q) 50 15 7131 D/C JAN-18400
Work underprogress.
JAN-18236Parli - Solapur 309 72 51132 D/C JAN-18765
Readiness of up stream & down stream network by Arunachal Pradesh Govt.Critical. Damage towers/fdns. due to floods taken up.
DEC-12102Pasighat - Roing line. 348 345 345 103133 S/C onD/C
MAR-17132
Pipalkoti HEP - Pipalkoti (THDC) (Kuwari Pass)134 D/C 400
Gen. expected beyond 2017-18. Work slowed-down to the extent possible tomatch Generation.(ant. by Mar'18)
JAN-15128Punatsangchu-I - Alipurduar 178 158 141 24135 D/C DEC-17400
Work under progress.Stringing commenced from Dec'16.MAR-1590RAPP - Kota line 133 89 75 8136 D/C JUN-17400
Award under progress.3676Raigarh (HVDC Stn.) - Pugalur (HVDC Stn.) HVDCBipole line
137 HVDC NOV-19800
ROW problem encountered due to addl. compensation demand by forestdwellers. Critical.
JAN-15714Raipur Pooling station - Wardha line -II 963 946 939 640138 D/C MAR-17765
Severe ROW problem at Rajarhat & farraka end as well as in Jharkhand area.LILO line expected in Jan'17 & Main line in Jun'17.
APR-16953Rajarhat - Purnea (with one LILO at Gokarana andanother at Farakka)
1219 1177 1081 582139 D/C JUN-17400
Ready for Commissioning 06/16.NOV-13138Ranchi - Jharkhand Pool line (Chandwa) 195 195 195 138140 D/C JUN-16400
Progress affecetd due to ROW problem & geogrephical condition. Due to non-availibility of downstream line, line shall not be utilized.
APR-1273Roing - Tezu line 244 244 235 61141 S/C onD/C
MAR-17132
Commissioned 06/16.37Roorkee - Saharanpur line (Ckt-II) 104 104 104 73142 D/C JUN-16400
Commissioned 05/16.APR-1337Roorkee - Saharanpur line (Quad) (Ckt-I) 104 104 104 37143 D/C MAY-16400
Severe ROW problem being faced.DEC-15219Salem - Madhugiri 574 500 441 56144 S/C MAR-17765
Severe ROW in Karnataka. Progress is slow due to severe ROW problem andpolice protection is being sought for work on site.
SEP-14245Salem Pooling Station - Madhugiri Pooling Station line 644 639 633 150145 S/C MAR-17765
Commissioned 08/16.MAY-156Sasaram - Allahabad line (1 ckt shifted from NR 12 12 12 6146 D/C AUG-16400
Trasmission Lines: Page 10 of 91
Legends
TL: Total Location STC: Stubs Cast TE: Towers Erected STG: Stringing Completed
Schedule
1. 2. 5. 6. 7. 8. 9. 10. 12.3.
Revised/Anticipate
d
11.
Construction progress StatusTarget Date
RemarkTowers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hcKM
Ckts(S/C)
&(D/C)
bus to ER bus) Addition
Completion matching with Daltonganj S/S delayed due to non-availability of S/Sland (land acquired in May'15).
NOV-12392Sasaram - Deltonganj line 523 521 521 382147 D/C OCT-17400
Severe ROW faced in the line.MAR-1725Sholapur STPP - Sholapur line - II 40 29 29 9148 D/C MAR-17400
ROW problem faced. Contract revived through assignment to JV partner. Workunder progress.
AUG-12336Sikar - Jaipur line 484 484 483 326149 D/C JAN-17400
Part line commissioned through contigency in Jun'12.( forming LILO of 132KVD/C Panchgaram - Dullovcherol at Silcher). Balance work re-award in Nov'16.
60Silchar - Hailakandi (Contingency arrangement) 109 92 79 35150 D/C JUN-17132
Major portion of line is in forest. severe ROW in vicinity of Aizwal town due to stiffresistance from influential local owner. package re-awarded in Jun'16. Workunder progress.
DEC-12286Silchar - Melriat (New) line (charged at 132KV) 456 373 243 112151 D/C SEP-17400
SEP-13Siliguri - Purnea152 D/C SEP-16400
Work under progress. ROW at Singrauli end.JUN-16150Singrauli - Allahabad line 436 274 227 42153 D/C JUN-17400
Work under progress.Severe ROW problem.25Solapur STPP - Solapur line - II (Q) 40 29 28 9154 D/C MAR-17400
Work under progress.APR-19286Srikakulam - Garividi 391 31155 D/C FEB-19400
Ready for Commissioning 09/16.AUG-16668Srikakulam PP - Vemagiri - II Pooling Station (VizagTL)
877 877 877 668156 D/C SEP-16765
Ready for Commissioning 12/1016.JUN-15552Srikakulam Pooling Station - Angul line 730 730 730 552157 D/C DEC-16765
Tapovan Vishnugadh - Kunwari Pass158 D/C 400
Generation project delayed expected by Sep'19. Efforts are being made to slowdown the work matching with Genration.
NOV-1714Tehri Gen. - Tehri Pooling Station (Q) 50 25 11159 D/C OCT-17400
Gen. project delayed (ant. by Sep'19). Work on the ATS are being slowed-downto match Generation.
NOV-174Tehri Pooling Station - Meerut 15160 D/C OCT-17765
Progress affecetd due to ROW problem & geogrephical condition. Due to non-availibility of downstream line, line shall not be utilized.
DEC-1296Tezu - Namsai line. 332 320 286 61161 S/C onD/C
JUN-17132
Due to delay in Generation. Work has been slowed-down to match withGeneration.
APR-17114Tirunelveli PS - Tuitcorin PS (Quad) line-1 33 0 0 0162 D/C APR-17400
Due to delay in Gen. Work has been slowed-down to match with Generation.APR-17116Tirunelveli PS - Tuitcorin PS (Quad) line-2 34 0 0 0163 D/C APR-17400
Work under progress.218Tumkur (Pavagada) Pool - Hiriyur 322 94 25164 D/C DEC-18400
Commissioned 11/2016.SEP-14731Tuticorin Pooling Station - Salem Pooling Station 1000 1000 1000 731165 D/C NOV-16765
Trasmission Lines: Page 11 of 91
Legends
TL: Total Location STC: Stubs Cast TE: Towers Erected STG: Stringing Completed
Schedule
1. 2. 5. 6. 7. 8. 9. 10. 12.3.
Revised/Anticipate
d
11.
Construction progress StatusTarget Date
RemarkTowers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hcKM
Ckts(S/C)
&(D/C)
Ready for Commissioning 09/2016.SEP-16107Unchahar - Fatehpur line (Powergrid Unchahar TL) 145 145 145 107166 D/C SEP-16400
Severe ROW problem. Permission to work obtained in Dec'15. Kudue S/stn.being implementated by MSETCL. Critical.
234Vapi (PG) - Kala - Kudus 239 179 156 150167 D/C MAY-17400
Ready for Commissioning 06/16.OCT-14652Varanasi - Kanpur 885 885 885 652168 D/C JUN-16765
Commissioned 10/2016.213Varanasi - Sarnath (Q) 306 306 306 213169 D/C OCT-16400
Work under progress.APR-19580Vemagiri - Chilkaluripeta 746 137170 D/C APR-19765
Work under progress.JUN-18760Vindhyachal - Jabalpur 1036 335 63171 D/C JUN-18765
Contract terminated 01 out of 02 nos due to unsatisfactory performance andfresh tender being taken up.The pkg. has been bifurcated into two pkgs. 01 pkg.awarded in Dec'14 & 2nd pkg. awarded in Feb'15. Remaining 01 pkg. alsoterminated in Aug'15 due to poor performance. However contract was revived inFeb'16. Severe ROW problem being encountered.
OCT-12696Wardha - Aurangabad (on 1200 kV) 961 927 844 450172 D/C JUN-171200
Work under progress. Wardha - Nizamabad link being expedited and effortsbeing made for early completion by Mar'17.
MAY-181072Wardha - Hyderabad line 1449 1259 1180 655173 D/C MAY-18765
Work under progress.NOV-17698Warora Pooling Station - Parli 919 303 170174 D/C JAN-18765
Trasmission Lines: Page 12 of 91
Legends
TL: Total Location STC: Stubs Cast TE: Towers Erected STG: Stringing Completed
Schedule
1. 2. 5. 6. 7. 8. 9. 10. 12.3.
Revised/Anticipate
d
11.
Construction progress StatusTarget Date
RemarkTowers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hcKM
Ckts(S/C)
&(D/C)
POWERGRID (Consultancy Work) (PGCONSULTANCY)
Yet to be awarded.(Arunachal Prades) Seppa - Bameng line1 S/C onD/C
132
Yet to be awarded.(Arunachal Pradesh) Along - Kambang line2 S/C onD/C
132
Yet to be awarded.(Arunachal Pradesh) Along - Yingkiong line3 S/C onD/C
132
Yet to be awarded.(Arunachal Pradesh) Changlang - Jairampur line4 S/C 132
Yet to be awarded.(Arunachal Pradesh) Chimpu (Itanagar) - Holongi line5 S/C onD/C
132
Yet to be awarded.(Arunachal Pradesh) Daporijo - Nacho line6 S/C onD/C
132
Yet to be awarded.(Arunachal Pradesh) Deomali - Khonsa line7 S/C 132
Yet to be awarded.(Arunachal Pradesh) Gerukamukh - Kikabali line8 S/C onD/C
132
(Arunachal Pradesh) Jairampur - Miao line9 S/C 132
Yet to be awarded.(Arunachal Pradesh) Kambang - Mechuka line10 S/C onD/C
132
Yet to be awarded.(Arunachal Pradesh) Khonsa - Changlang line11 S/C 132
Yet to be awarded.(Arunachal Pradesh) Khonsa - Longding line12 S/C 132
Yet to be awarded.(Arunachal Pradesh) Khupi - Seppa line13 S/C onD/C
132
Yet to be awarded.(Arunachal Pradesh) LILO of Daporijo - Along 132 KVS/C at Basar
14 S/C onD/C
132
Yet to be awarded.(Arunachal Pradesh) Likabali - Niglok line15 S/C on 132
Trasmission Lines: Page 13 of 91
Legends
TL: Total Location STC: Stubs Cast TE: Towers Erected STG: Stringing Completed
Schedule
1. 2. 5. 6. 7. 8. 9. 10. 12.3.
Revised/Anticipate
d
11.
Construction progress StatusTarget Date
RemarkTowers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hcKM
Ckts(S/C)
&(D/C)
D/C
Yet to be awarded.(Arunachal Pradesh) Miao - Namsai (PG) line16 S/C onD/C
132
Yet to be awarded.(Arunachal Pradesh) Naharlagun - Banderdewa line17 S/C onD/C
132
Yet to be awarded.(Arunachal Pradesh) Naharlagun - Gerukamukh line18 S/C onD/C
132
Yet to be awarded.(Arunachal Pradesh) Niglok - Pasighat New (Napit)19 S/C onD/C
132
Yet to be awarded.(Arunachal Pradesh) Palin - Koloriang line20 S/C onD/C
132
(Arunachal Pradesh) Pasighat New (Napit) - PasighatOld
21 S/C onD/C
132
Yet to be awarded.(Arunachal Pradesh) Pasighat Old - Mariyang line22 S/C onD/C
132
Yet to be awarded.(Arunachal Pradesh) Rilo - Sagali line23 S/C onD/C
132
Yet to be awarded.(Arunachal Pradesh) Rilo - Seijosa line24 S/C onD/C
132
Yet to be awarded.(Arunachal Pradesh) Roing (PG) - Anini line25 S/C onD/C
132
Yet to be awarded.(Arunachal Pradesh) Roing (PG) - Dambuk line26 S/C onD/C
132
Yet to be awarded.(Arunachal Pradesh) Sagali - Naharlagun line27 S/C onD/C
132
Trasmission Lines: Page 14 of 91
Legends
TL: Total Location STC: Stubs Cast TE: Towers Erected STG: Stringing Completed
Schedule
1. 2. 5. 6. 7. 8. 9. 10. 12.3.
Revised/Anticipate
d
11.
Construction progress StatusTarget Date
RemarkTowers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hcKM
Ckts(S/C)
&(D/C)
Yet to be awarded.(Arunachal Pradesh) Seppa - Rilo line28 S/C onD/C
132
Yet to be awarded.(Arunachal Pradesh) Tawang - Lumla line29 S/C onD/C
132
Yet to be awarded.(Arunachal Pradesh) Tezu (PG) - Halaipani line30 S/C onD/C
132
Yet to be awarded.(Arunachal Pradesh) Yingkiong - Tuting line31 S/C onD/C
132
Yet to be awarded.(Arunachal Pradesh) Ziro (PG) - Palin line32 S/C onD/C
132
Yet to be awarded.(Arunachal Pradesh) Ziro (PG) - Ziro New line33 S/C onD/C
132
Yet to be awarded.(Assam) Amingaon - Hazo line34 D/C 132
Yet to be awarded.(Assam) Dhemaji - Silapathar line35 S/C onD/C
132
Yet to be awarded.(Assam) Kahilipara - Guwahati Medical college (Including 2 km cable)
36 D/C 132
Awarded.(Assam) Kamakhya - Paltan Bazar37 S/C 132
Yet to be awarded.(Assam) LILO of Golaghat - Bokajan line at Sarupathar38 S/C 132
Yet to be awarded.(Assam) LILO of Jorhat (Gormur) - Nazira at Teok.39 S/C onD/C
132
Yet to be awarded.(Assam) LILO of Kamalpur - Kamakhya line atAmingaon S/S
40 S/C 120
Yet to be awarded.(Assam) LILO of Kamalpur - Sishugram line atAmingaon S/S
41 S/C 132
Yet to be awarded.(Assam) LILO of one circuit of Rangia - Rowta line atTangla
42 D/C 132
Trasmission Lines: Page 15 of 91
Legends
TL: Total Location STC: Stubs Cast TE: Towers Erected STG: Stringing Completed
Schedule
1. 2. 5. 6. 7. 8. 9. 10. 12.3.
Revised/Anticipate
d
11.
Construction progress StatusTarget Date
RemarkTowers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hcKM
Ckts(S/C)
&(D/C)
Yet to be awarded.(Assam) Rangia - Amingaon line43 D/C 220
Yet to be awarded.(Assam) Rupai - Chapakhowa line (including 2 kmcable)
44 D/C 132
Yet to be awarded.(Assam) Sonabil - Tezpur (New) line45 D/C 132
Yet to be awarded.(Assam) Tinsukia - Behiating (new Dibrugarh)46 D/C 220
Work under progress.JAN-17332(J&K) Alusteng - Drass - Kargil - Khalsti-Leh 1134 745 548 23247 S/C MAY-17220
MAY-1716(J&K) LILO of Leh - Kharu line 97 55 16 048 S/C MAY-1766
MAY-172(J&K) LILO of Leh - Nimmo line 13 13 9 149 S/C MAY-1766
SEP-19244(Maghalaya) Byrnihat (Killing) - Mawngap - NewShillong line
50 D/C SEP-19220
SEP-1934(Maghalaya) LILO of both circuits of MLHEP -Khliehriat line at Mynkre
51 D/C SEP-19132
SEP-19138(Maghalaya) Phulbari - Ampati line52 D/C SEP-19132
Yet to be awarded.(Manipur) Imphal (PG) - Ningthoukhong line53 D/C 132
Yet to be awarded.(Manipur) Kakching - Churachandpur (2nd ckt) line54 D/C 132
Yet to be awarded.(Manipur) Kakching - Kongba (2nd Ckt) line55 D/C 132
Yet to be awarded.(Manipur) LILO of Yurembam (Imphal-State) - Karongline at Gamphajol
56 S/C 132
Yet to be awarded.(Manipur) LILO of one circuit of Kongba - Kakchingline at Thoubal S/S
57 D/C 132
Yet to be awarded.(Manipur) Rengpang - Tamenlong line58 S/C onD/C
132
Yet to be awarded.(Manipur) Yaingangpokpi - Kongba (2nd Ckt) line59 D/C 132
Yet to be awarded.(Manipur) Yuremum - Karong - Mao (Manipur -Nagaland border) section of Yuremum-Karong-Kohimaline
60 S/C 132
Yet to be awarded.(Mizoram) Chawngte - S. Bungtlang line61 S/C 132
Yet to be awarded.(Mizoram) Lungsen - Chawngte line62 S/C 132
Yet to be awarded.(Mizoram) W. Phaileng - Marpara line63 S/C onD/C
132
Trasmission Lines: Page 16 of 91
Legends
TL: Total Location STC: Stubs Cast TE: Towers Erected STG: Stringing Completed
Schedule
1. 2. 5. 6. 7. 8. 9. 10. 12.3.
Revised/Anticipate
d
11.
Construction progress StatusTarget Date
RemarkTowers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hcKM
Ckts(S/C)
&(D/C)
Yet to be awarded.(Nagaland) LILO of Kohima - Meluri (Kiphire) at NewKohima
64 S/C 132
Yet to be awarded.(Nagaland) LILO of Kohima - Wokha line at NewKohima
65 S/C 132
Yet to be awarded.(Nagaland) LILO of Mokokchung (Nagaland) - Mariani(Assam) line at Longnak
66 D/C 132
Yet to be awarded.(Nagaland) New Kohima (Zadima) - New SecretariatComplex Kohima line
67 D/C 132
Yet to be awarded.(Nagaland) New Kohima - Mokokchung (PG)68 S/C onD/C
220
Yet to be awarded.(Nagaland) Tuensang - Longleng line69 S/C onD/C
132
Yet to be awarded.(Nagaland) Wokha (Doyang River) - Zunheboto -Mokokchung (Nagaland)
70 S/C onD/C
132
Yet to be awarded.(Sikkim) Chungthang - LILON point on Rabon - Maltingline
71 D/C 66
Yet to be awarded.(Sikkim) Chungthang - Lachen line72 D/C 66
MAR-1944(Sikkim) Dikchu - Parbing line73 D/C MAR-19132
JUN-1940(Sikkim) Dikchu - Singhik74 D/C JUN-19220
Yet to be awarded.(Sikkim) Dikchu Pool - Makha line75 D/C 66
Yet to be awarded.(Sikkim) Khamdong - Makha line76 S/C 66
Yet to be awarded.(Sikkim) Khamdong - Temi line77 S/C 66
Yet to be awarded.(Sikkim) Kumrek - Rorathang line78 D/C 66
Yet to be awarded.(Sikkim) LILO of Rangit - Melli (Power Deptt. Sikkim)132 kV S/C at Manpur line
79 D/C 132
Yet to be awarded.(Sikkim) LILO of Rangit - Melli (Power Deptt. Sikkim)132 kV S/C at Namchi line
80 D/C 132
Yet to be awarded.(Sikkim) Parbing - Pangthang line81 D/C 66
Yet to be awarded.(Sikkim) Parbing - Sichey line82 S/C 66
Yet to be awarded.(Sikkim) Parbing - Tadong line83 S/C 66
Trasmission Lines: Page 17 of 91
Legends
TL: Total Location STC: Stubs Cast TE: Towers Erected STG: Stringing Completed
Schedule
1. 2. 5. 6. 7. 8. 9. 10. 12.3.
Revised/Anticipate
d
11.
Construction progress StatusTarget Date
RemarkTowers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hcKM
Ckts(S/C)
&(D/C)
SEP-1812(Sikkim) Rangpo (PG) - Samardong84 D/C SEP-18220
SEP-1870(Sikkim) Rangpo (Samardong) - Dikchu Pool twin85 D/C SEP-18220
Yet to be awarded.(Sikkim) Rorathang - LiLo point on Pakyong - Rongliline
86 D/C 66
Yet to be awarded.(Sikkim) Samardong - Kumrek line87 D/C 66
Yet to be awarded.(Sikkim) Samardong - Mamring line88 S/C 66
Yet to be awarded.(Sikkim) Samardong - Namthong line89 S/C 66
JUN-1940(Sikkim) Singhik - Chungthang90 D/C JUN-19220
Yet to be awarded.(Sikkim) Singhik - Mangan line91 S/C 66
Yet to be awarded.(Sikkim) Singhik - Passidong line92 S/C 66
Yet to be awarded.(Tripura) Bagafa - Belonia line93 D/C 132
Yet to be awarded.(Tripura) Bagafa - Satchand (utilizing the corridor ofexisting Bagafa - Satchanda 66 kV line)
94 S/C onD/C
132
Yet to be awarded.(Tripura) Belonia - Sabroom line95 S/C 132
Yet to be awarded.(Tripura) Kailasahar - Dharmanagar line96 D/C 132
Yet to be awarded.(Tripura) LILO of Agartala (79 Tilla) - Dhalabil (Khowai)line
97 S/C 132
Yet to be awarded.(Tripura) LILO of Ambassa - P.K. Bari at Manu98 S/C 132
Yet to be awarded.(Tripura) LILO of one circuit of Surajmaninagar -Rokhia line at Gokulnagar
99 D/C 132
Yet to be awarded.(Tripura) Rabindra Nagar - Belonia line100 D/C 132
Yet to be awarded.(Tripura) Rabindra Nagar - Rokhia line101 D/C 132
Yet to be awarded.(Tripura) Udaipur - Amarpur line102 D/C 132
Yet to be awarded.(Tripura) Udaipur - Bagafa line103 D/C 132
Trasmission Lines: Page 18 of 91
Legends
TL: Total Location STC: Stubs Cast TE: Towers Erected STG: Stringing Completed
Schedule
1. 2. 5. 6. 7. 8. 9. 10. 12.3.
Revised/Anticipate
d
11.
Construction progress StatusTarget Date
RemarkTowers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hcKM
Ckts(S/C)
&(D/C)
ASSAM ELECTRICITY GRID CORP. LIMITED (AEGCL)
completed/ Ready to be charged.NOV-1323Agia - Matia (Dudhnoi) line 87 87 87 231 S/C onD/C
MAY-15132
Frequent Bandhs in BTAD area, forest clearance received, RoW at Loc 21,22 inforest area etc. are making the project slipped.
DEC-1310BTPS - Kokrajhar line 39 37 28 52 S/C onD/C
JAN-16132
1. Delay due to re alignment of line such as proposed airport at BTAD area, 800kV line of PGCIL, ROW, Local Problem etc. are attributing to the delay. Nowthere is almost settlement of RoW and compensation related issues, the Erectionwork is going on smoothly. How ever in Mushalpur areas (Baksa) District therehas been serious law and order issues and construction work is carried out bydeploying Security personnel.
JAN-13327Bongaigaon TPS - Rangia (Salakati) 517 494 452 773 D/C MAR-17220
Work in progress. Clearance and RoWSEP-1363Kokrajhar - Bilashipara - Gauripur 203 199 121 224 S/C onD/C
FEB-16132
Check survey done. Profile drawing approved.DEC-115Kukurmara - Azara line 24 0 05 S/C onD/C
MAR-16132
Completed on 06.07.2015.NOV-1310LILO of Jorhat - Bokakhat at Jorhat (West) S/S 9 9 9 36 D/C AUG-15132
completed 13.07.2015.NOV-134LILO of Namrup - Tinsukia at Bordubi S/S 9 9 8 57 D/C MAY-15132
in progress.NOV-135LILO of both ckt of Depota - Gohapur at Sonabil S/S 6 6 6 18 2xD/C JUN-16132
RoW & Water logging problems adversely affected erection work.DEC-1355LILO of one ckt Samaguri - Sarusajai line at SonapurS/S
41 31 0 09 D/C JAN-17220
commissioned on July 2015.JAN-1359LILO of one ckt of Tinsukia - Margherita at Rupai(Doomdooma) S/S
109 109 109 5910 D/C JUL-15132
completed.34Nazira - Mariani (Garmur) line 237 237 137 6911 S/C APR-13132
Completed/ Charged on 04.12.2015.NOV-1361Samaguri - Lanka line (2nd Ckt) 205 205 205 6112 S/C JUN-16132
completed in Dec' 2013.JAN-1342Samaguri - Nagaon line 142 142 142 4213 S/C onD/C
DEC-13132
In progress Railway crossing/ ROW/ compensation issue..NOV-1328Sonapur - Chandrapur line 51 39 11 014 D/C JUN-16132
In progress (compensation issue)..NOV-1352Sonapur - Jagirod line 86 40 25 015 D/C JUN-16132
Trasmission Lines: Page 19 of 91
Legends
TL: Total Location STC: Stubs Cast TE: Towers Erected STG: Stringing Completed
Schedule
1. 2. 5. 6. 7. 8. 9. 10. 12.3.
Revised/Anticipate
d
11.
Construction progress StatusTarget Date
RemarkTowers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hcKM
Ckts(S/C)
&(D/C)
BIHAR STATE ELECTRICITY BOARD (BSEB)
Work yet to start.JUN-16200Barauni TPS Exte. - Hazipur 403 335 288 521 D/C DEC-16220
SEP-03366Begusarai-Purnea 498 91 275 162 D/C DEC-16220
Betia-Raxaul (2nd circuiting)3 D/C 132
JUL-1536Bihta (New) - Bihta 64 2 0 04 D/C DEC-16220
108Bihta - Sipara5 D/C SEP-16220
MAR-1612Darbhanga - Darbhanga 15 12 10 06 D/C JAN-17220
Only railway crossing is to be carried out.DEC-15218Darbhanga - Motipur 401 401 400 2177 D/C DEC-16220
MAR-1647Darbhanga - Samastipur (New) 173 166 147 308 S/C onD/C
FEB-17220
JUN-16178Darbhanga - Supaul/Lokhi 327 322 320 1569 D/C JAN-17220
86Gaurichak - Bihta (New) 143 117 107 2210 D/C DEC-16220
Commissioned 06/16. (Late Reported).JAN-16183Gaya (PG) - Sonenagar (New) 299 299 299 18311 D/C JUL-16220
JUN-16141Kishanganj (New) - Madhepura 510 430 237 1612 D/C DEC-16220
Commissioned 10/2016.FEB-1516Kishanganj (PG) - Kishanganj (New) 42 42 42 1613 2xD/C OCT-16220
Completed.MAY-155LILO of 2nd ckt Pusouli (PG) - Ara (PG) at Pusouli(New).
19 19 19 514 D/C 220
Commissioned 10/2016.JAN-1624LILO of Begusarai - Kanti at Samastipur 53 53 53 2415 2xD/C OCT-16220
work yet to be awardedLILO of Both Ckt of Purnea - Begusarai at BTPS Extn16 D/C 220
4LILO of Both ckt of Biharsharif - Begusarai at BTPSExtn.
9 5 2 017 D/C DEC-16220
DEC-15130LILO of Darbhanga - Kanti at Motipur 251 251 251 12418 D/C NOV-16220
Ready for commissioning 12/2016MAR-1690LILO of Darbhanga - Kanti at Musahari 175 175 175 9019 D/C DEC-16220
Detailed survey of APO to AP 14 done, rest under progress.126Madhepura - Lokhi 216 196 172 5020 D/C NOV-16220
79Motihari-Bettia 143 143 134 4021 D/C JAN-17132
78Motihari-Motihari 142 141 137 7222 D/C JAN-17132
119Motihari-Raxaul 213 194 14623 D/C JAN-17132
Trasmission Lines: Page 20 of 91
Legends
TL: Total Location STC: Stubs Cast TE: Towers Erected STG: Stringing Completed
Schedule
1. 2. 5. 6. 7. 8. 9. 10. 12.3.
Revised/Anticipate
d
11.
Construction progress StatusTarget Date
RemarkTowers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hcKM
Ckts(S/C)
&(D/C)
MAR-151Patna (PG) - Gourichak 3 3 1 024 S/C onD/C
NOV-16220
MAY-1562Pusouli (New) - Dehri 199 125 89 225 D/C DEC-16220
Commissioned 10/2016 (Late reported)25Samatipur (New) s/s - Samastipur s/s (initially chargedat 132 KV)
26 D/C NOV-16220
Trasmission Lines: Page 21 of 91
Legends
TL: Total Location STC: Stubs Cast TE: Towers Erected STG: Stringing Completed
Schedule
1. 2. 5. 6. 7. 8. 9. 10. 12.3.
Revised/Anticipate
d
11.
Construction progress StatusTarget Date
RemarkTowers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hcKM
Ckts(S/C)
&(D/C)
CHHATTISGARH STATE POWER TRANSMISSION CO. LTD. (CSPTCL)
Work is under progress.JUN-15155Korba (E) - Vishrampur (2nd Ckt.) 801 D/C DEC-16220
Tender under process.1LILO of Urla - PGCIL at Borjhara2 D/C MAR-17220
Ready for commissioning 12/2016MAY-14657Raita - Jagadalpur line 903 903 903 6573 D/C DEC-16400
Trasmission Lines: Page 22 of 91
Legends
TL: Total Location STC: Stubs Cast TE: Towers Erected STG: Stringing Completed
Schedule
1. 2. 5. 6. 7. 8. 9. 10. 12.3.
Revised/Anticipate
d
11.
Construction progress StatusTarget Date
RemarkTowers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hcKM
Ckts(S/C)
&(D/C)
DELHI TRANSCO LIMITED (DTL)
4Bamnauli - Dhansa1 M/C MAR-22220
1Bawana - Kanjhawala at Barwala2 D/C MAR-23220
10Bawana - Shalimarbagh3 D/C MAR-20400
Commissioned 06/2016. (Late Reported).JUN-1412Bawana-Rohini -II (Sec -29) line 38 38 38 124 D/C JUL-16220
7Budella - Punjabi Bagh5 M/C MAR-18220
12Dwarka - Budella6 D/C MAR-19220
5Dwarka - Janakpuri (U/G Cable)7 D/C MAR-20220
14Harsh Vihar - Patparganj & LILO at Preet Vihar8 2xD/C MAR-17220
MAR-15180Harsh Vihar - Patparganj line (U/G cable link)9 D/C SEP-16220
FEB-16Harsh Vihar - Preet Vihar10 D/C 220
9IP - Karolbagh11 D/C MAR-19220
16IP-Park Street-Electric Lane (Cable)12 S/C MAR-17220
5Karolbagh - Subzi Mandi (U/G Cable)13 D/C MAR-21220
9Kashmiri gate - IP Tower14 M/C MAR-18220
4Kashmirigate - Chandrawal (U/G Cable)15 D/C MAR-19220
7LILO of 2nd Ckt Kanjhawala - Njafgarh at Mundka16 D/C MAR-21220
5LILO of AIIMS - Ridge Valley at R.K.Puram17 D/C MAR-21220
1LILO of Bamanuli - Naraina at PPK-III18 2xD/C MAR-17220
12LILO of Bamnauli - Najafgarh at Budella19 D/C MAR-18220
4LILO of Bamnauli - Najafgarh at PPK-II20 D/C MAR-17220
1LILO of Bamnauli - Naraina at PPK-I21 D/C MAR-17220
32LILO of Bamnauli - Tughlakabad at Rangpuri22 M/C MAR-22400
1LILO of Bawana - Rajghat at Gopalpur23 D/C MAR-20400
1LILO of Gopalpur - Subzi Mandi at Chandrawal24 D/C MAR-19220
0LILO of Maharanibagh - Gazipur at Mayur Vihar25 D/C MAR-22220
0LILO of Maharanibagh - Masjid Moth at Nehru26 D/C MAR-21220
Trasmission Lines: Page 23 of 91
Legends
TL: Total Location STC: Stubs Cast TE: Towers Erected STG: Stringing Completed
Schedule
1. 2. 5. 6. 7. 8. 9. 10. 12.3.
Revised/Anticipate
d
11.
Construction progress StatusTarget Date
RemarkTowers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hcKM
Ckts(S/C)
&(D/C)
Place
6LILO of Maharanibagh - Sarita Vihar at Jasola27 2xD/C MAR-20220
2LILO of Mandola - Gopalpur at Budhpur/Nathupura28 D/C MAR-22220
1LILO of Mehrauli - BTPS at Tughlakabad29 D/C MAR-18220
3LILO of Narela - Mandola at Tikri Khurd30 D/C MAR-18220
1LILO of Pragati - Sarita Vihar at Maharanibagh31 D/C 220
1LILO of Tughlakabad - Mehrauli at Maidan Garhi32 M/C MAR-21220
MAR-15LILO of first ckt of double ckt of Pragati - Sarita Viharat maharani Bagh
33 D/C 220
MAR-15LILO of one ckt of Bamnauli - Najafgarh atPappankalan-II
34 S/C 220
MAR-15LILO of one ckt of Bamnauli - Naraina Ckt-I atPappankalan-I
35 S/C 220
8Lodhi Road - IP Tower36 D/C MAR-17220
2Okhla - Tughlakabad37 D/C MAR-18220
8Punjabi Bagh - Janakpuri (U/G Cable)38 D/C MAR-20220
4Ridge Valley - Naraina (2nd Ckt)39 D/C MAR-21220
12Shalimarbagh - Mangolpuri - Bundella40 D/C MAR-20220
5Shalimarbagh - Sanjay Gandhi Transport Nagar41 M/C MAR-19220
7Tughlakabad - Masjid Moth42 M/C MAR-18220
12Tughlakabad - R.K.Puram (U/G Cable)43 D/C MAR-20220
3Vasant kunj - DIAL (Cable)44 D/C MAR-21220
Trasmission Lines: Page 24 of 91
Legends
TL: Total Location STC: Stubs Cast TE: Towers Erected STG: Stringing Completed
Schedule
1. 2. 5. 6. 7. 8. 9. 10. 12.3.
Revised/Anticipate
d
11.
Construction progress StatusTarget Date
RemarkTowers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hcKM
Ckts(S/C)
&(D/C)
DEPARTMENT OF POWER ARUNACHAL PRADESH ()
Erection works completed. Only testing & commissioning left.LILO of Ranganadi - Itanagar at Pare HEP1 D/C DEC-16132
Trasmission Lines: Page 25 of 91
Legends
TL: Total Location STC: Stubs Cast TE: Towers Erected STG: Stringing Completed
Schedule
1. 2. 5. 6. 7. 8. 9. 10. 12.3.
Revised/Anticipate
d
11.
Construction progress StatusTarget Date
RemarkTowers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hcKM
Ckts(S/C)
&(D/C)
GOA ELECTRICITY DEPARTMENT (ED- GOA)
Proposals have been forwarded to Government. The approcal is awaited fromFinance Department.
120Colvale - Kadamba - Verna - Cuncolim line1 D/C MAR-19220
Letter of Intent will be issued to RECTPCL shortly, who has been appointed asProject Management consultant(PMC). Necessary approvals have beenobtatined from the Government.
20Colvale - Tuem2 D/C MAR-19220
Proposals have been forwarded to Government. The approcal is awaited fromFinance Department.
84Ponda - Verna 0 0 03 M/C MAR-19220
Trasmission Lines: Page 26 of 91
Legends
TL: Total Location STC: Stubs Cast TE: Towers Erected STG: Stringing Completed
Schedule
1. 2. 5. 6. 7. 8. 9. 10. 12.3.
Revised/Anticipate
d
11.
Construction progress StatusTarget Date
RemarkTowers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hcKM
Ckts(S/C)
&(D/C)
GUJARAT ENERGY TRANSMISSION CORP. LIMITED (GETCO)
Amreli - Babara line (AL-59)1 D/C 220
W I P / Severe RoW problems470Amreli - Kasor line 679 615 542 642 D/C MAR-17400
W I P / Severe RoW problems188BECL (Padva) - Botad line 292 169 115 03 D/C MAR-17220
A/T given on 03.08.2016SEP-166Bechraji - Maruti Suzuki line 12 9 3 04 D/C SEP-16220
Yet to award.340Bhachau - Radhanpur 0 0 05 D/C MAR-17220
Bhachunda - Varsana line (Twin AL-59)6 D/C 400
Bhatia - Bhogat line (AL-59)7 D/C 220
W I P / Severe RoW problems238Bhatiya-Kalwad line 373 101 59 08 D/C DEC-16220
Bhogat - Moti Gop line (AL-59)9 D/C 220
Bhogat - Ranavav line (AL-59)10 D/C 220
Yet to award240Bhogat-Kalavad 0 0 011 D/C MAR-17400
Heavy ROW (Deposit work)Botad - Parabadi (Ajmer) line 211 211 211 12412 D/C OCT-16220
199Chanranka - Veloda 265 264 261 15813 D/C JAN-17400
Yet to award200Chhara -Keshod 0 0 0 014 D/C MAR-17400
Yet to award40Chhatral - Dhanaj 0 0 015 D/C MAR-17220
Yet to award170Chikhli - Bhilad 0 0 016 D/C MAR-17220
WIP160Chorania - Botad 196 57 0 017 D/C MAR-17220
Chorania - Salejada line (AL-59)18 D/C 220
Yet to award71Choraniya - Viramgam 0 0 019 D/C MAR-17220
Yet to award120Fedra - Botad 0 0 020 D/C DEC-16220
Ready for Commissioning 07/16.MAR-1294GPPC (Pipavav)- Dhokadva 152 152 152 9421 D/C JUL-16220
Work in progress.JAN-1646Gavasad - Bhayali (DFCC) line 91 83 83 4122 D/C AUG-16220
wip194Gavasad - Salejada line 313 268 128 1323 D/C MAR-17220
Yet to award50Hadala - Rajkot-II 0 0 024 D/C MAR-17220
Trasmission Lines: Page 27 of 91
Legends
TL: Total Location STC: Stubs Cast TE: Towers Erected STG: Stringing Completed
Schedule
1. 2. 5. 6. 7. 8. 9. 10. 12.3.
Revised/Anticipate
d
11.
Construction progress StatusTarget Date
RemarkTowers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hcKM
Ckts(S/C)
&(D/C)
Hadala - Shapar line (Twin AL-59)25 D/C 400
Yet to award60Halvad - Charadva 0 0 026 D/C MAR-17220
W I P / Severe RoW problems76Halvad-Sadla 124 101 99 4927 D/C DEC-16220
Tender to be invited at risk purchase111Hazaira (GSEC) - Mota 182 107 94 2028 D/C AUG-17220
Commissioned 04/16.1Interconnection of one ckt of Jhanor - Navsari line withone ckt of Ukai - Kosamba line
129 D/C APR-16400
WIP139Jamnagar - Hadala 257 226 221 10730 D/C MAR-17220
Yet to award100Jasdan - Gondal 0 0 031 D/C MAR-17220
W I P / Severe RoW problems112Kalawad-Kangasiyali 191 158 138 5932 D/C MAR-17220
Commissioned 08/16.JAN-1539Kasor - Herang (DFCC) line 73 73 73 3933 D/C AUG-16220
Yet to award10Keshod - Keshod 0 0 034 D/C MAR-17220
Yet to award140Keshod - Timbdi 0 0 035 D/C MAR-16220
Yet toaward120Keshod - Visavadar 0 0 036 D/C MAR-17220
Work in progress.NOV-1553Kheralu - Dharewada (DFCC) line 97 64 36 037 D/C DEC-16220
Yet to award140Kosamba- Achhalia 0 0 0 038 D/C MAR-17400
Work in progress.NOV-1514LILO of Haldarwa - Zaghadia line 26 18 16 039 D/C MAR-17220
Yet to award80LILO of SSP- Asoj & SSP -Kasor lines at AchhaliaS/S
0 0 040 D/C MAR-17400
Work in progress.MAY-15100LILO of Amreli - dhasa line at Botad S/s 186 112 33 041 D/C DEC-16220
Yet to award40LILO of Bhatia - Kalav ad - Kangasiyali at Khambhalia 0 0 042 D/C SEP-16220
Commissioned 06/16.83LILO of Both ckt of Jamanvada - Varsana atBhachunda (AL-59) M/C
8343 2xD/C JUN-16220
LILO of Both ckt of Tebhda - Nyara line at Moti GopS/S (M/C line AL-59)
44 D/C 220
Yet to award50LILO of Chorania - Gondal at Rajkot-II 0 0 045 D/C MAR-17220
Yet to award40LILO of Chorania - Gondal at Shapar 0 0 046 D/C MAR-17220
WIP100LILO of Essar-Hadala line at Kalavad S/S 26 22 16 347 D/C DEC-16400
Trasmission Lines: Page 28 of 91
Legends
TL: Total Location STC: Stubs Cast TE: Towers Erected STG: Stringing Completed
Schedule
1. 2. 5. 6. 7. 8. 9. 10. 12.3.
Revised/Anticipate
d
11.
Construction progress StatusTarget Date
RemarkTowers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hcKM
Ckts(S/C)
&(D/C)
5LILO of Godhra -Kadana line at Lunawada48 D/C MAR-17220
Yet to award50LILO of Hadala - Sartanpar - Halvad at Tankara 0 0 049 D/C MAR-17220
Yet to award2LILO of Jambuva - Karamsad at Asodar 0 0 050 D/C MAR-17220
Yet to be awarded.116LILO of Jamnagar - Jetpur line-I at Sikka 178 0 0 051 D/C APR-17220
WIP. Case of 6 locations is pending in district court120LILO of Jamnagar - Jetpur line-II at Sikka 189 171 166 5652 D/C MAR-17220
yet to award10LILO of Jetpur - Rajkot at Metoda 0 0 053 D/C MAR-17220
AT given on 10.07.1520LILO of Karamsad - Vartej at Fedra 33 0 0 054 D/C SEP-16220
Work in Progress.60LILO of Karmsad -Vartej at Dhuvaran 152 143 94 1855 D/C DEC-16220
AT given on 10.07.201520LILO of Kasor - Vertej at Fedra 33 0 0 056 D/C MAR-16220
80LILO of Kasor-Amerli line at Fedra57 D/C OCT-16400
Commissioned 04/16.81LILO of Kasor-Botad at Dhuvaran CCPP-III 148 148 148 8158 D/C APR-16220
Yet to award24LILO of Morbi - Hadala at Tankara 0 0 059 D/C MAR-17220
WIP200LILO of Mundra (Adani)- Zerda line at Sankhari 45 0 0 060 D/C JAN-17400
Re tenderized; LOI issued on 13.06.2016.89LILO of Mundra - Hadala at Halvad. 136 124 67 061 D/C DEC-16400
17LILO of Navsari - Vav at Popada62 D/C 220
Yet to awardLILO of Navsari-Talangpore line at Utran 0 0 063 D/C APR-17220
Ready for Commissioning 08/16..62LILO of Radhanpur - Mehsana at Sankhari 98 98 98 6264 D/C AUG-16220
Commissioned 05/16.15LILO of Ranasan - Karamsad at Barejadi S/S 28 28 28 1565 D/C MAY-16220
Yet to award10LILO of Salejada - Bhat at Kerala 0 0 066 D/C MAR-17220
WIP50LILO of Sankhari - Jangral at Sankhar 53 53 48 467 D/C DEC-16220
Yet to award50LILO of Savarkundla - Visavadar at Bagasara 0 0 068 D/C MAR-17220
Tender reinvited for remaining portion. LOA given on 21.06.2016.APR-0934LILO of Shivalkha - Nanikhakhar at Kukma 54 40 40 1869 D/C APR-17220
Yet to award10LILO of Tappar - Hadala at Navlakhi 0 0 070 D/C MAR-17220
Yet to award20LILO of Ukat (Th) - Achhalia at Achhalia 0 0 0 071 D/C DEC-16220
Work in progress.AUG-137LILO of Vadavi - Chhatral line at Santej S/s 14 14 14 072 D/C MAR-17220
WIP100LILO of Vadavi-Zerda at Sankhari 45 473 D/C DEC-16400
Trasmission Lines: Page 29 of 91
Legends
TL: Total Location STC: Stubs Cast TE: Towers Erected STG: Stringing Completed
Schedule
1. 2. 5. 6. 7. 8. 9. 10. 12.3.
Revised/Anticipate
d
11.
Construction progress StatusTarget Date
RemarkTowers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hcKM
Ckts(S/C)
&(D/C)
Yet to award28LILO of Wanakbori -Soja line at Dehgam (PG) S/S 0 0 074 D/C MAR-17400
Work in progress.NOV-1620LILO of both circuit of 220 kV D/C Nyara - Thebda lineat Kalawad S/S
20 11 075 D/C 220
LOA given on 27.06.2016.JUN-16124LILO of one circuit of 220 kV D/C Kadana - Godharaline at 220 kV Zalod S/S
248 0 0 076 D/C 220
LILO of one ckt Gandhinagar TPS - Chhatral line atVadavi (AL-59)
77 D/C 220
LILO of one ckt of Hadala - Sartanpar line atWankaner (M/C tower by replacement of existing 132kV towers) (AL-59)
78 D/C 220
Yet to award80LILO of one ckt Kosamba-Chorania line at Fedra 0 0 079 D/C MAR-17400
Yet to award80LILO of one ckt Wanakbori -Soja line at Prantji S/S 0 0 080 D/C MAR-17400
MAY-1690LILO of one ckt of 400 kV D/C Kosamba - Chorainaline at 400 kv Sanand-II GIDC S/s
81 D/C 400
FEB-1746LILO of one ckt of 400 kV D/C Kosamba - Choranialine at 400 kV Pachchham S/s
82 D/C 400
LILO of one ckt of Akrimota - Nakhatrana line atBhachunda
83 D/C 220
28LILO of one ckt of Wanakbori - Asoj at Vyankatpura(Jarod)
84 D/C 220
LOI given on 12.04.2016 and work under progress.OCT-18168LILO on one circuit of 220 kV D/C Achhaliya -Vyankatpur line at 220 kV Kawant S/S
304 63 20 085 D/C 220
MAR-1443LLO of 220 kv Vadavi - Chhatral line at Santej S/s 74 47 29 086 D/C MAR-17220
Work in progress.MAR-1658Mitha - Becharji 103 83 63 087 D/C DEC-16220
Severe RoW issue666Mundra (Adani) - Zerda line 1 997 453 275 088 D/C MAR-17400
Yet to award290Nanikhakhar - Varsana - Chitrod 0 0 089 D/C MAR-17220
Work in progress.MAY-1680Palanpur - Amarigadh (DFCC) line 144 41 0 090 D/C MAR-17220
yet to award90Palitana - Talaja 0 0 091 D/C MAR-17220
Yet to award150Pipavav-Amreli 0 0 092 D/C MAR-17400
Yet to award50Pirana (PG) - Gatrad 0 0 093 D/C MAR-17220
WIP218Pooling station -Sankhari 275 217 192 5394 D/C MAR-17400
Yet to award60Prantij - Agiyol 0 0 095 D/C MAR-17220
Trasmission Lines: Page 30 of 91
Legends
TL: Total Location STC: Stubs Cast TE: Towers Erected STG: Stringing Completed
Schedule
1. 2. 5. 6. 7. 8. 9. 10. 12.3.
Revised/Anticipate
d
11.
Construction progress StatusTarget Date
RemarkTowers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hcKM
Ckts(S/C)
&(D/C)
Yet to award70Prantij - Dhansura 0 0 096 D/C MAR-17220
Radhanpur -Sankhari line (AL-59)97 D/C 220
Will be in line with generation project which is delayed350Salaya (EPGCL generating station )-Halvad 0 0 098 D/C MAR-17400
Yet to award200Sankhari-Prantij 0 0 099 D/C MAR-17400
Shapar - Babara line (AL-59)100 D/C 220
Shapar - Pachham (Fedra) line (Twin AL-59)101 D/C 400
Generation project is delayed so this evacuation line will be in line with thegeneration project
220Shapoorji Pallonji generating station 0 0 0102 D/C DEC-16400
Work in progress.AUG-15Soja - Joumang (DFCC) 75 51 9 0103 D/C DEC-16220
WIP280Soja-Zerda 447 64 32 0104 D/C NOV-18400
Yet to award140Suva - Achhalia 0 0 0105 D/C MAR-17220
Yet to award90Termination of GPEC - Haldarva at Achhalia 0 0 0106 D/C MAR-17220
WIP60Termination of one Achhalia- Jambuva line at Jarod 125 110 96 9107 D/C MAR-17220
DEC-0986Utran - Kosamba Line-II108 D/C 220
WIP13Vadavi - Chhatral 88 39 32 0109 D/C DEC-16220
plan changed to 220 kV Vadavi -Chatral LILO to 220 kV Santej (Dhanaj) - 50.66Ckm
38Vadavi - Dhanaj 88 54 43 0110 D/C DEC-16220
Work in progress.APR-1561Vadavi - Sanand (DFCC) line 108 35 2 0111 D/C MAR-17220
Yet to award53Vadavi - Viramgam 0 0 0112 D/C MAR-17220
WIP240Vadavi-Halvad 394 206 167 89113 D/C MAR-17400
W I PNOV-09239Vadinar(Essar)- Amreli (Balance) 365 309 256 113114 D/C DEC-16400
Yet to award60Varsana-Bhachau 0 0 0115 D/C DEC-16220
WIP220Varsana-halvad 378 168 109 0116 D/C MAR-17400
W I P / Severe RoW problems132Visavadar - Amreli line 221 219 216 84117 D/C FEB-17220
Ready for Commissioning 08/16.180Visavadar - Timbdi 301 301 301 180118 D/C AUG-16220
Yet to award2Wanakbori S/y -Wanakbori S/y (existing) 0 0 0119 D/C MAR-17400
WIP200Wanakbori TPS-Soja 157 29 20 0120 D/C MAY-18400
Trasmission Lines: Page 31 of 91
Legends
TL: Total Location STC: Stubs Cast TE: Towers Erected STG: Stringing Completed
Schedule
1. 2. 5. 6. 7. 8. 9. 10. 12.3.
Revised/Anticipate
d
11.
Construction progress StatusTarget Date
RemarkTowers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hcKM
Ckts(S/C)
&(D/C)
HARYANA VIDYUT PRASARAN NIGAM LIMITED (HVPNL)
Commissioned 06/16.8A5(Faridabad) - A4(Faridabad) (Ckt-I) 33 33 33 81 D/C JUN-16220
Work awarded to Inabensa Bharat Ltd. Contractual problem.Arbitrationcase.Work awarded to M/s Isolux. route survey under progress.
15Bhiwani - Bhiwani 0 0 0 02 D/C JAN-18220
Work awarded to Inabensa Bharat Ltd. Contractual problem. Arbitrationcase.Work re-awarded to M/s Isolux.
65Bhiwani - Isharwal 218 61 0 03 D/C JAN-18220
commissioned 12/201611Deepalpur - Sonipat (Sector- 6) 27 27 27 114 D/C DEC-16220
Ready for commissioning 02/2016 (Late Reported)MAY-1341Deepalpur-Sonepat HSIIDC Rai ( terminated at RajivGandhi s/s)
101 101 101 415 M/C DEC-16220
Work in progress.51Jajji - Rai line 113 104 101 416 D/C FEB-17220
Work of erection & stringing is in progress.99Kirori - Jind 149 149 148 927 D/C JAN-17400
Commissioned 05/2016.6LILO of 2nd Ckt Shahbad - Pehowa at Durala 11 11 11 68 D/C MAY-16220
Route survey under progress60LILO of Bastara - Kaul at Bhadson 119 0 0 09 D/C 220
Loop-Out portion commissioned on 24.06.2016 Loop-In portion's work in progress.
JUL-1384LILO of Chormar - Fathebad line at Hukmawali 169 164 146 4210 D/C MAR-17220
Work has been re-awarded with schedule completion period of one year. Partialroute of line has been approved. Final route approval under process.
5LILO of Madnpur - Kunihar line at Panchkula sector-3211 D/C FEB-17220
Work of line has been completed on 20.10.2014 only termination pending at 220kV sub station Pinjore, which is yet to be constructed.
6LILO of Naggal (PGCIL) - Baddi Line at Pinjore 46 46 46 612 D/C SEP-17120
Work awarded to Inabensa Bharat Ltd. Contractual problem.Arbitration case.Work re-awarded to M/s Isolux.
44LILO of Narwana - Mund at Khatkar (Jind) 0 0 0 013 2xD/C JAN-18220
Route survey under progress74LILO of Pehowa - Kaul at Bhadson 151 0 0 014 D/C 220
Commissioned 12/2016JUL-1378LILO of both Ckt of Cheeka - Durala at Sonta s/s 128 128 128 7815 D/C DEC-16220
Work yet to be award.1LILO of gurgaon Sec -72 - Sector 52 (A) at Sector 5716 D/C MAR-17220
Ready for Commissioning 08/16.53Palwal (Meghpur) - Meerpur Kurali 106 106 106 5317 D/C AUG-16220
Work has been re-awarded to M/s Isolux . Work yet to be start.1Panchgaon 400 kV - Panchgaon 220 kV 0 0 0 018 D/C OCT-17220
Work has been re-awarded with schedule completion period of one year.Partialroute approved. Work in progress.
40Panchkula (PGCIL)- Panchkula Sector 32 44 29 4 019 D/C FEB-17220
Trasmission Lines: Page 32 of 91
Legends
TL: Total Location STC: Stubs Cast TE: Towers Erected STG: Stringing Completed
Schedule
1. 2. 5. 6. 7. 8. 9. 10. 12.3.
Revised/Anticipate
d
11.
Construction progress StatusTarget Date
RemarkTowers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hcKM
Ckts(S/C)
&(D/C)
HIMACHAL PRADESH POWER TRANSMISSION CORP. LTD. (HPPTCL)
12Chanju - Nakrot line 30 29 27 101 D/C MAY-16132
MAR-1745Charor -Banala 80 4 0 02 D/C MAR-17220
MAR-18110Dehan-Hamirpur3 D/C MAR-17220
Hatkoti - Gumma4 D/C 120
Delay FAC approval.MAR-1754Hatkoti-Pragati Nagar5 D/C MAR-17220
OCT-154Kairan-Chamera II (PG) 20 11 7 06 D/C MAY-16220
Commissioned 04/16.OCT-1539Kashang - Bhaba (2nd Ckt) 100 100 100 397 D/C APR-16220
Jhangi Pooling Station yet to be awarded.Kashang - Jangi Pooling Station8 D/C 220
Delay FCA approval.35Koti-Karian9 S/C MAR-17220
6LILO Jhakri A/Pur10 D/C MAR-17400
8LILO of Nalagarh-Baddi at Mandhala S/S11 D/C MAR-17220
Under planning stage.LILO of Both Ckt 132 kV D/C Kurthala - Bathri at220/132 Mazra GIS
12 2xD/C 132
Forest are involved and proposal for forest clearance submitted and it underprogress for Stage-I clearance . Likely to be issue shortly.
32LILO of Kasang - Bhbaba at Tidong-I 5713 D/C NOV-16220
Yet to award.1LILO of Parbati II HEP - Parbati-III Pooling station atSainj
14 D/C MAY-16400
Completed.1LILO of one ckt Kurthala - Bathri at Nakrot PoolingStation
1 1 1 115 D/C 132
Delay FAC approval pending for the lest three year. Stage -I clearance in July2015.
MAR-1720LILO of one ckt of Nathpa Jhakri - Abdullapur at SwaraKuddu
16 D/C MAR-17400
Delay FCA approval. (Work awarded ).OCT-1638Lahal -Bajoli HEP17 D/C MAR-17220
Delay FCA approval.OCT-1880Lahal-Chamera18 D/C MAR-17400
Under planning stage.Mazra GIS - 220 kV Karian S/S - 400/220 kV ChameraPS (PG)
19 D/C 220
33Nalagarh -Kunihar20 S/C MAR-17400
28Rauri-Kunihar21 D/C MAR-17220
18Shongtong Karcham HEP - Wangtoo (Quad)22 D/C 400
MAR-1724Snail -Hatkoti (Swara Kudu)23 D/C MAR-17220
Trasmission Lines: Page 33 of 91
Legends
TL: Total Location STC: Stubs Cast TE: Towers Erected STG: Stringing Completed
Schedule
1. 2. 5. 6. 7. 8. 9. 10. 12.3.
Revised/Anticipate
d
11.
Construction progress StatusTarget Date
RemarkTowers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hcKM
Ckts(S/C)
&(D/C)
Delay FCA approval.MAR-1754Sunda-Hatkoti24 D/C MAR-17220
Line is being constructed by HPPTCL under Green Energy Corridor Scheme.Tangnu Romai-I HEP - 220/132 kV Sunda S/S25 D/C 132
Uhl-III - Hamir Pur (By BVPCL)26 S/C onD/C
132
Trasmission Lines: Page 34 of 91
Legends
TL: Total Location STC: Stubs Cast TE: Towers Erected STG: Stringing Completed
Schedule
1. 2. 5. 6. 7. 8. 9. 10. 12.3.
Revised/Anticipate
d
11.
Construction progress StatusTarget Date
RemarkTowers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hcKM
Ckts(S/C)
&(D/C)
J&K POWER DEVELOPMENT DEPARTMENT (JKPDD)
Commissioned.31Alachi - Khalsi S/S 140 140 140 311 S/C JUN-1466
Commissioned.5Chutak HEP-Gramthong -II 29 29 29 52 S/C SEP-1266
Commissioned.10Chutak HEP-Kargil-I 55 55 55 103 S/C OCT-1266
Fund yet to be tied up.80Delina - Wahipora-Kishanganga4 D/C 220
Rerouting of line and ganglas s/s droped. Leh Army S/S shall be connected withLeh S/S.
9Ganglas - Leh Army base 46 22 0 05 S/C DEC-1666
Commissioned.27Gramthong -II - Sankoo 154 154 154 276 S/C SEP-1466
Commissioned23Khangral - Mulbek -II 117 117 117 237 S/C SEP-1466
Slow progress.51Kharu S/S - Himya S/S 242 239 204 368 S/C DEC-1666
Fund yet to be tied up.12LILO of Wagoora - Mirbazar at Lassipora9 D/C 220
Progress at 2 locations have been affected due to severe RoW issue and matterin court for one location.
12LILO of one ckt of Kishanpur - New wanpoh atBaglihar HEP
17 4 1 010 D/C DEC-16400
Commissioned.25Leh (C.P.) - Kharu S/S 107 107 107 2511 S/C SEP-1466
Rerouting of line and ganglas s/s droped. Leh Army S/S shall be connected withLeh S/S.
10Leh III - Ganglas 53 29 8 212 S/C DEC-1666
Commissioned.28Mulbek-II - Kargil -I 124 124 124 2813 S/C SEP-1466
Stringing completed.The line could not be charged due to dipute betweenPSTCL and JKPDD on sharing of cost of bay at Shahpur Khadi.
MAR-0840Thein (RSD)-Hiranagar (2nd ckt) 117 117 117 4014 S/C JUN-16220
Severe RoW and Court case.APR-0848Udhampur- Gladni 165 165 165 4815 S/C SEP-14220
ROW issue at Dangarpora.Original Project provision exhausted.MAR-0960Wagoora-Budgam- Zainkote 118 103 82 1716 D/C DEC-16220
ROW issues and slow pace of execution of work by contractor due to paddycultivation.
104Wagoora-Mirbazar 177 175 170 4917 D/C SEP-14220
Slow pace of execution of work in Zainkote-Alusteng section. Original Projectcost provision exhausted, For Alusteng - Miarbazar section contract case sent toGovt for approval.
MAR-10254Zainkote-Alusteng-Mirbazar 441 410 68 018 D/C MAR-17220
Trasmission Lines: Page 35 of 91
Legends
TL: Total Location STC: Stubs Cast TE: Towers Erected STG: Stringing Completed
Schedule
1. 2. 5. 6. 7. 8. 9. 10. 12.3.
Revised/Anticipate
d
11.
Construction progress StatusTarget Date
RemarkTowers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hcKM
Ckts(S/C)
&(D/C)
JHARKHAND STATE ELECTRICITY BOARD (JSEB)
Detail Survey going on.JAN-18220Chaibasa - Gua1 D/C JAN-18220
Line is passing through forest area of 4.70 Ha in Saraikela and Chaibasadivision, which involves three location(2km stringing). In principle approval hasbeen received in Sep 16. The amount for compliance of CA has deposit in Nov16, work permission is awaited from forest department.
APR-0979Chaibasa -Ramchandrapur 129 125 121 792 D/C MAR-17220
Forest clearance pending.FEB-17208Chatra - Latehar 327 323 305 743 D/C FEB-17220
Forest clearance pending.FEB-17114Chatra - PBCMP (Barkagaon) 171 54 21 04 D/C FEB-17220
FEB-1766Daltonganj - Garhwa 113 57 34 05 D/C FEB-17220
Detail survey going on.JAN-18148Dumka - Jasidih6 D/C JAN-18220
Line is passing through 81.843 Ha of forest area in Latehar division, whichinvolves ten location (7.67 Km Stringing). Forest proposal submitted in May 2013and fresh application submitted for issue of NOC of FRA based on CS map inSep 2016. Total 22 villages are affected. Gram Sabha meeting for 20 villagescompleted, balance two are remained for Dhurva and Bhajkum village. Districtadministration has to organized Gram Sabha meeting of issue of NOC.
81Essar (Latehar) - Latehar 118 102 88 227 D/C MAR-17400
LOI issued on 08.11.2016.MAY-18160Giridih - Jamua8 D/C MAY-18220
LOI issued on 08.11.2016.MAY-18160Giridih - Jasidih9 D/C MAY-18220
LOI issued on 08.11.2016.MAY-18100Godda - Lalmatia10 D/C MAY-18220
Line is passing through 12.24 Ha in Dumka division, 12.1 Ha in Devghar division,0.388 Ha in Dhanbad division and 6.2169 Ha in Jamtara division, which involvesone location (16.14km stringing). Project proposal has been submitted to DFO,Dhanbad and Jamtara in Dec 16 and for Dumka, Deoghar division it will besubmitted in Jan 17.
203Govindpur - Dumka 332 331 330 20311 D/C MAR-17220
Line is passing through 13.221 Ha of forest area in Ranchi division whichinvolves sixteen location (2.06km stringing). The proposal uploaded in Jun 15.RMOEF raised queries in Nov 16 regarding details of forest line, treeenumeration and possibility of alternate route. DFO, Ranchi submitted reply inDec 16.
65Hatia - Namkum (PGCIL) 127 67 53 012 D/C MAR-17220
Survey held up due to non-finalisation of PTPS substation layout.LILO of Patratu - Hatia at PTPS by MC Tower13 D/C 220
70LILO of one ckt TTPS - Govindpur at Phase-III14 D/C SEP-16220
Trasmission Lines: Page 36 of 91
Legends
TL: Total Location STC: Stubs Cast TE: Towers Erected STG: Stringing Completed
Schedule
1. 2. 5. 6. 7. 8. 9. 10. 12.3.
Revised/Anticipate
d
11.
Construction progress StatusTarget Date
RemarkTowers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hcKM
Ckts(S/C)
&(D/C)
Line is passing through forest area of 179.977 Ha in Ranchi, Ramghar andLatehar district which involves 39 locations (24.92km Stringing). Proposalsubmitted in Jul 13 and fresh application submitted for issue of NOC on FRAbased on CS map in Sep 2016. Total 13 villages are involved and Gram sabhameeting for 20 villages completed except tow villages i.e Dhurva and Bhajkum.District administration has to organized Gram sabha meeting for issue of NOC.DC, Ranchi has to issue rectified GS report.
220Latehar (JSEB) - PTPS 308 256 237 5415 D/C MAR-17400
LOI issued on 08.11.2016.MAY-1870P.T.P.S. - Ratu16 D/C MAY-18220
Line is passing through 10.94 Ha of forest area in Ranchi/Ramghar division,which involves six location (3.84KM stringing). The forest proposal originallysubmitted in April,2013 and combined proposal uploaded in Aug,2015. RMoEFforwarded queries in Nov,2016. DFO, Ranchi has submitted reply in DEC-16 andDFO, Ramghar yet to submit reply.
102PTPS - Bero (New Ranchi) 140 131 128 8517 D/C MAR-17400
Line is passing through forest area 103.621 Ha in Bokaro division and 1.275 inHazaribagh division, which involves 67 location (47km stringing). Proposalsubmitted to MOEF. Gram Sabha proceeding of total eleven villages of Bokarodistrict have been received. NOC and FRA are yet to be issued by districtadministration.
181TTPS - Govindpur 295 229 202 3618 D/C MAR-17220
Trasmission Lines: Page 37 of 91
Legends
TL: Total Location STC: Stubs Cast TE: Towers Erected STG: Stringing Completed
Schedule
1. 2. 5. 6. 7. 8. 9. 10. 12.3.
Revised/Anticipate
d
11.
Construction progress StatusTarget Date
RemarkTowers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hcKM
Ckts(S/C)
&(D/C)
KARNATAKA POWER TRANSMISSION CORP. LIMITED (KPTCL)
Work under progress.AUG-0741Beerenahalli - Thallak (Chitradurga) (Balance portion) 73 51 36 01 D/C MAR-17220
This work is included in (BPS-New Madhugiri Near Tumakuru)workBellary (PS) - C.N. Hally 1242 D/C APR-17400
Work under progress.DEC-16437Bellary (PS) - New Madhugiri (near Tumakur) 647 645 636 3983 D/C APR-17400
This work is not in planned works.5Bellary (TPS) - Bellary (PS)4 D/C AUG-16400
Work under progress.JUL-1464Bidadi (PGCIL) - Magadi S/S 63 13 0 05 D/C NOV-16220
220-66 kV MC line from 220 kV Kothipura to Bidadi S/s:(1) ROW problems pending in DC Court Ramanagar for Loc 15 since 2012.(2) ROW problems to be solved locally at 8 locations 2,3,4,4A,5, 6,33,77.
Final Notice issued to M/s ABB & M/s Deepak cables for termination of thecontract on 14.12.2015 by CEE, Tz. The contract is terminated on 25.01.2016.The Joint inventory along with M/s ABB & M/s Deepak Cable completed.Tendered on 10.05.2016 for balance work.
FEB-08174Bidadi - Kothipura (Channapatna) 82 63 26 D/C MAR-17220
Chitradurga - Hiriyur S/S7 D/C 220
Applied for BBMP permission on 16.6.2016. Approval awaited.Excavation work for Jointing in Nimhans premises is under progress.
11HSR Layout - Nimhans S/S 0 0 0 98 UGCable
NOV-16220
Hiriyur (PG) - Hiriyur S/S9 S/C 220
Hosadurga - CN Halli line10 D/C 220
Work under progress.MAY-1465Ittagi - Kudligi line 119 78 67 011 D/C DEC-16220
This work is being carried out on self execution basis.20JSW TPS - Bellary (PS) 39 39 15 012 D/C MAR-17400
Work under progress.JUL-1431LILO on one ckt of Nelamangala - Anchepalya line atMagadi
63 13 0 013 D/C NOV-16220
LILO of Both ckt of Nelamangala - Talaguppa at CNHalli
14 D/C DEC-16400
LILO of Chikkodi - Ghataprabha at Mughalkod15 D/C 220
Work short closed vide O.M No. CEE/TZ/GLB/SEE(O)/AEE-3/2014-15/3830.37dtd 12.09.2014 of Chief Engineer, Elec, Transmission zone, Gulbarga . To beretendered.
1LILO of Gadag - Lingapur at Koppal 2 116 D/C MAR-17220
Work under progress.(1) ROW problems at corridor between 4 & 5 pending inJMFC, Hoskote, Additional Civil Judge(Junior division) since
SEP-0726LILO of Hoody-Kolar at Hoskote 55 35 31 017 D/C MAR-17220
Trasmission Lines: Page 38 of 91
Legends
TL: Total Location STC: Stubs Cast TE: Towers Erected STG: Stringing Completed
Schedule
1. 2. 5. 6. 7. 8. 9. 10. 12.3.
Revised/Anticipate
d
11.
Construction progress StatusTarget Date
RemarkTowers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hcKM
Ckts(S/C)
&(D/C)
9.12.10.(2)Loc 4 & 5: Case filed by party at High court vide Writ Petition: 46532-533/2012 dtd: 19.11.2012 seeking injunction.(3) Loc 4 : The petitioner has obtained stay order vide WP 32606-32607/2013from the Hon'ble High Court against the proceedings in the OS No: 253/2010 on02.09.13.(4) Loc 36 : Case No: MAG(CR)/1/13-14 at DC Court, B'lore Rural.Posted forOrders.Being pursued.
LILO of Narendra - Haveri at Haveri (Dharwad District)18 D/C 220
Work under progress.AUG-146LILO of RTPS - Lingasugur S/C line at Mallat (Manvi) 13 12 12 619 D/C DEC-16220
Work under progress.FEB-0835LILO of Shimoga - Mysore at Dandiganahally 68 65 61 2220 D/C FEB-17220
Work under progress. (1) Local ROW problems at locations: (i)9,10,14A,16,-being pursued.(2) DC COURT:For corridor 8-9 & 10-11: Case filed in DC court on 27.05.2013. Being pursued.(ii) Loc 16: Case filed at DC Court on 26.11.2014. Being pursued.
JUN-119LILO of Somanahalli - Malur at Vikas Tech Park 32 27 26 321 D/C MAR-17220
Work under progress.JUL-14120Madhugiri - Pavagada 212 210 199 3422 D/C NOV-16220
Work terminated on 12.05.2016. Balance works to be retendered.SEP-0915Shanthigrama - B4 line ( near Hedanahalli limits) 34 34 32 923 D/C DEC-16220
Malur-Kolar line charged (42 Ckm). The line from Malur end upto Loc 137charged (68.98 Ckm).The line from Somanahalli end upto Loc 55 charged (23.64Ckm). Total line charged 134.62 Ckm.Balance works to be retendered.Case pending in High Court:(i)Loc 84,85,86,88 & 89: Case filed by KPTCL in DC Court on 27.01.2014. Beingpursued.(ii) Loc 84,85,86,88 & 89 : Case filed by party in Court of Junior Civil Judge ,Bangalore Rural district on 11.02.2014. Being pursued.(iii) Loc 135,135A,135B, 135C & 136 : case filed in High Court by party (IndiaInternational School) on 19.06.2013. Being pursued.(iv)At Loc 59 (for stub concreting): Case pending in High court since
MAR-08180Somanahalli - Malur - Kolar 272 267 267 14024 D/C MAR-17220
Trasmission Lines: Page 39 of 91
Legends
TL: Total Location STC: Stubs Cast TE: Towers Erected STG: Stringing Completed
Schedule
1. 2. 5. 6. 7. 8. 9. 10. 12.3.
Revised/Anticipate
d
11.
Construction progress StatusTarget Date
RemarkTowers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hcKM
Ckts(S/C)
&(D/C)
31.08.2013 being pursued.
Line work short closed vide OM No CEE/TZB/SEE(O)/AE-3/15-16/925-31 dated:12.08.2015.
OCT-0823Somananahalli Malur I & II lines - Jigani 34 6 4 025 D/C MAR-17220
Termination of Nelamangala - Talaguppa at CN Halli26 D/C DEC-16400
Commissioned 11/2016.22Thallak - M/s BARC27 D/C NOV-16220
220 kV DC line from 220 kV Tubinakere S/s to Kothipura S/s :(1) (i) ROWproblems pending in JMFC Ramanagara for- (a) Loc 81 since 2009(ii) ROW problems pending in JMFC Channapatna for - (a)Loc 129-130 since20092)ROW problems pending in DC Court Ramanagar for (a) Loc 133: Case filed on24-08-2011.Reserved for orders on 09.02.2016.(3)ROW problems at locations 208: being pursued locally.
final Notice issued to M/s ABB & M/s Deepak cables for termination of thecontract on 14.12.2015 by CEE, Tz. The contract is terminated on 25.01.2016.The Joint inventory along with M/s ABB & M/s Deepak Cable completed.Tendered on 10.05.2016 for balance work.
JUN-09137Tubinakere- Kothipura 278 278 257 8728 D/C MAR-17220
Work terminated on 19-Sep-15. Balance works to be retendered.MAR-1139Vajamangala - Kadakola 55 49 45 029 D/C MAR-17220
Work under progress.
Terminal Bay: Concreting of foundations: CT 6/6, CVT: 5/6, LA's: 5/6, Isolator:7/8, breaker: 2/2 completed. Cable duct completed. Breaker erected. Mountingstructure erected and 2 Circuit Breakers erected.
JAN-1638Vasanthanarasapura - Antharasanahally 97 96 95 3430 D/C NOV-16220
Work under progress.JUL-1689Vasanthanarasapura - Madhugiri 209 190 164 5631 D/C NOV-16220
Work under progress.AUG-17284Yermarus TPS - Bellary Pooling Station 398 290 232 032 D/C AUG-17400
Detailed survey completed.Estimate is being prepared.
Yermarus TPS - Gulbarga33 D/C DEC-16400
Trasmission Lines: Page 40 of 91
Legends
TL: Total Location STC: Stubs Cast TE: Towers Erected STG: Stringing Completed
Schedule
1. 2. 5. 6. 7. 8. 9. 10. 12.3.
Revised/Anticipate
d
11.
Construction progress StatusTarget Date
RemarkTowers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hcKM
Ckts(S/C)
&(D/C)
KERALA STATE ELECTRICITY BOARD (KSEB)
ATS of Pallivasal Extension HEP. Work is yet to start.LILO of Idukki-Udumalpet at Pallivasal HEP 5 0 0 01 D/C MAR-17220
ATS of Thottiar HEP.May be deleted, as the work is not targeted in the Annual Plan of 2015-16.
LILO of Ldukki - Kozikode at Kodakpara2 D/C 220
Re-tendering in Dec,1557Pothencode - Kattakkada 108 103 72 03 D/C FEB-17220
ATS of Thottiar HEP. May be deleted, as the work is not targeted in the AnnualPlan of 2015-16.
Thottiyar - Kodakpara4 D/C MAR-17220
Trasmission Lines: Page 41 of 91
Legends
TL: Total Location STC: Stubs Cast TE: Towers Erected STG: Stringing Completed
Schedule
1. 2. 5. 6. 7. 8. 9. 10. 12.3.
Revised/Anticipate
d
11.
Construction progress StatusTarget Date
RemarkTowers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hcKM
Ckts(S/C)
&(D/C)
M.P. POWER TRANSMISSION CORPORATION LIMITED (MPPTCL)
95Ashta - Shajapur1 D/C 220
Ashta - Ujjian S/S2 D/C 400
Badnawar - Kanwan line3 D/C 220
Betul - Gudgaon4 D/C 220
Commissioned 08/2016 (Reported Late)36Bina s/s - M/s Bharat Oman Refinaries Ltd. Agasod,Bina
5 D/C DEC-16220
36Bina-Bina (M/s BORLA) 366 D/C 220
80Dada Dhuniwale TPP - Moondi Pooling Point7 D/C 400
Gudgaon(220) - Gudgaon(132)8 D/C 132
Work in progress59Gwalior (Malanpur) - Morena line 101 72 34 09 D/C MAR-17220
180Handia - Ashta(2nd stage)10 D/C 400
Indore (PGCIL) - Ujjian11 D/C 400
160Julwaniya - Kukshi12 D/C 220
Julwaniya - Sendhwa13 D/C 220
Kanwan (220) - Kanwan (132)14 D/C 132
Kanwan (220) - Teesgaon15 D/C 132
Kanwan - Dhar line16 D/C 220
220Katni - Damoh17 D/C 220
Commissioned 04/16.1LILO of 220 kV Katni - Satna at PGCIL Satna 118 D/C APR-16220
30LILO of Bhilai - Seoni at Balaghat / Kirnapur19 D/C 400
LILO of Both Ckt Nagda - Neemuch at Mandsaur S/s20 D/C 220
LILO of Both ckt Badod - Suwasara at Suwasara S/s21 D/C 132
LILO of Both ckt Badod -Kota - Modak at SuwasaraS/s
22 D/C 220
LILO of Both ckt Neemuch - Mandsaur at MandsaurS/s
23 D/C 132
Trasmission Lines: Page 42 of 91
Legends
TL: Total Location STC: Stubs Cast TE: Towers Erected STG: Stringing Completed
Schedule
1. 2. 5. 6. 7. 8. 9. 10. 12.3.
Revised/Anticipate
d
11.
Construction progress StatusTarget Date
RemarkTowers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hcKM
Ckts(S/C)
&(D/C)
40LILO of Both ckt of Badod - Ujjain at Ujjain24 D/C 220
40LILO of Damoh - Bhopal at Sagar25 D/C 400
40LILO of Handia - Barwaha at Handia26 D/C 220
40LILO of Indira Sagar - Satpura at Handia27 D/C 400
40LILO of Indore - Itarsi at Handia28 D/C 400
20LILO of Indore-II - Ashta at Shankargarh29 D/C 220
4LILO of Jabalpur - Amarkantak at Gorabazar30 D/C 220
20LILO of Khandwa (PGCIL) - Rajgarh at Chhegaon31 D/C 400
40LILO of Nagda - Rajgarh at Badnawar32 D/C 400
Commissioned 06/16.15LILO of Pithampur - Indore line at 220kV Pithampur-IIs/s
26 26 26 1533 D/C JUN-16220
40LILO of Ratlam - Badnagar at Badnawar34 D/C 220
LILO of Ratlam-Daloda 220 kV line at Jaora35 D/C 220
Work stopped.MAR-1724LILO of both Ckt. of Badnagar- Ratlam At Badnawar400 kV S/S
20 436 D/C MAR-17220
8LILO of both ckt Indore - Pithampur at Indore37 D/C 220
40LILO of both ckt Nagda - Ujjain at Ujjain38 D/C 220
40LILO of both ckt of Ratlam - Badnagar at Badnawar39 D/C 220
Work Stopped.APR-1766LILO of one Ckt of Ashta- Dewas line at 220 kV S/SChapda S/S
104 1840 D/C APR-17220
10LILO of one ckt of Bina - Gwalior at Datia41 D/C 220
FEB-1735LILO of one ckt Indore-II- Indore(400kV) at Indore(N/Z)
21 20 442 D/C 220
Commissioned 06/16.52LILO of one ckt of 220kV Bhopal - Ashta line atMungaliyachhap s/s
89 89 89 5243 D/C JUN-16220
2LILO of one ckt of Bansagar (Tons) - Satna at Sirmour44 D/C 220
10LILO of one ckt of Bina - Sagar at Bina45 D/C 220
13LILO of one ckt of Indore - Barwaha at Simrol46 D/C 220
20LILO of one ckt of Khandwa (PGCIL) - Rajgarh47 D/C 400
Trasmission Lines: Page 43 of 91
Legends
TL: Total Location STC: Stubs Cast TE: Towers Erected STG: Stringing Completed
Schedule
1. 2. 5. 6. 7. 8. 9. 10. 12.3.
Revised/Anticipate
d
11.
Construction progress StatusTarget Date
RemarkTowers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hcKM
Ckts(S/C)
&(D/C)
(PGCIL) at Chhegaon
4LILO of one ckt of Pithampur - Rajgarh (PGCIL) atDhar
48 D/C 220
LILO of one ckt of Satna (PGCIL) - Bina(PGCIL) atSagar
49 S/C 400
LILO of one ckt of Vindhychal - Satna at Nigrie50 D/C 400
6LILO of second ckt of Auraiya - Malanpur at Mehgaon51 D/C 220
10LILO of second ckt of Damoh - Tikamgarh at Damoh52 D/C 220
Work in progress.MAR-1711LILO pf 2nd Ckt. of Bansagar - Satna line at Kotar220kV S/s.
19 853 D/C MAR-17220
230Maheshwar (HEP) - Rajgarh (Dhar)54 D/C 220
Mandsaur - Marut Shakti Pool55 D/C 220
240Moondi Pooling Point - Handia56 D/C 400
Work in progress.JUN-17115Morena (400kV S/s CWRTL Adani Group) - SabalgarhDCDS line
173 4257 D/C JUN-17220
80Morena - Malapur58 D/C 220
Nagda - Mandsaur59 D/C 400
150Nagda - Ujjain line60 D/C 400
Neemuch - Ratangarh line61 D/C 220
Nigri TPP - Satna62 D/C 400
150Pithampur - Badnawar DCDS63 D/C 400
60Pithampur - Gandhinagar64 D/C 220
280Pithampur - Moondi Pooling Point65 D/C 400
Work stopped.JUN-1771Pithampur -Depalpur 129 120 6366 D/C JUN-17220
70REVA TPP - Moondi Pooling Point67 D/C 400
Ratangarh(400 )- Ratangarh(132)68 D/C 132
Sailana - Ratlam69 D/C 220
Sailana(400) - Sailana(132)70 D/C 132
Trasmission Lines: Page 44 of 91
Legends
TL: Total Location STC: Stubs Cast TE: Towers Erected STG: Stringing Completed
Schedule
1. 2. 5. 6. 7. 8. 9. 10. 12.3.
Revised/Anticipate
d
11.
Construction progress StatusTarget Date
RemarkTowers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hcKM
Ckts(S/C)
&(D/C)
Original Contract terminated and Retendered.160Satna - Chhatarpur (2nd ckt) 0 0 0 1571 S/C MAR-17220
Second circuiting of Alot - Sitamau 132 kV line72 S/C 132
Second circuiting of Jhabua - Meghnagar 132 kV line73 S/C 132
Second circuiting of Rajgarh - Petlawad 132 kV line74 S/C 132
Second circuiting of Rajgarh-Jhabua 132 kV line75 S/C 132
Second circuiting of Ratlam - Daloda 220 kV line76 S/C 220
Sendhwa (220_ - Sendhwa (132)77 D/C 132
Sendhwa(220) - Pansemal (132)78 D/C 132
40Shri Singaji TPP - Moondi Pooling Point79 D/C 400
Work stopped.JUN-1744Shujalpur - Narsinghgarh Line 144 69 2480 D/C JUN-17220
90Ujjain - Dewas81 D/C 220
Trasmission Lines: Page 45 of 91
Legends
TL: Total Location STC: Stubs Cast TE: Towers Erected STG: Stringing Completed
Schedule
1. 2. 5. 6. 7. 8. 9. 10. 12.3.
Revised/Anticipate
d
11.
Construction progress StatusTarget Date
RemarkTowers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hcKM
Ckts(S/C)
&(D/C)
MAHARASHTRA STATE ELEC. TRANSMISSION COMPANY LTD. (MSETCL)
Commissioned 05/16.10400 kV Aurangabad II (Thaptitanda) - 765 kVAurangabad III (Ektuni) (Ckt 3 & 4)
18 18 18 101 D/C MAY-16400
Commissioned 12/2016.2ACC Limited - LMEL Ghugus 22 S/C DEC-16220
Work in progress.Order of this line given in three sections for early completion of work. twosections alotted to M/s. G K Power and one section alotted to M/s. Amit-AshaEnterprises.
104Akola - Anjangaon 114 64 58 03 D/C MAR-17220
Forest Involved: Nashik Zone - 32 Hec (27 locations)Vashi Zone - 116 hec (60 locations) Proposal pending at Addl. PCCF, NodalNagpur from 15.02.16.ROW: (Nasik Zone) For 39 locations: Cases filed. Hon. Collector Pune delegatedthe powers to SDO Revenue Manchar.Loc. No. 33 - Due to GMRT issue and intervene of MLA Junnar, SDO RevenueManchar has instructed that unless this issue is resolved, orders will not beissued.(Vashi Zone) ROW cases for 27 locations pending at Collector, Thane office.Rly Crossing: 100KV Railway crossing involved for total 4 Nos. Loc(Mumbai-Nashik central railway near Vashind, Tadavali):-On 12.08.2015 reminder letter given to Sr. DEN, CST w/r to track crossingapproval on dtd. 12.08.2015.
447Babhaleshwar - Kudus 708 547 480 1524 D/C DEC-17400
Work in progress.ROW Case Filed Order Awaited [9].
140Balapur - Malegaon line 228 96 40 05 D/C MAR-17220
Commissioned 10/2016.9Bhandup - Borivali line on M/C tower (from loc. no. 20to 48)
96 S/C onM/C
OCT-16220
The work stopped due to1) Severe RoW2) Forest ssue.The existing contract closure proposal is approved by C.O.The balance work shall be executed by placed new contract.
MAR-0753Boisar (PG)-Wada 211 173 165 287 S/C onD/C
DEC-17220
Ready for Commissioning 08/16.DEC-11331Boisar II-Borivali 261 261 261 3318 M/C AUG-16220
Work in progress.81Chandrapur II - Tadali (MIDC) 89 74 70 349 D/C DEC-16220
Commissioned 09/16.21Chandrapur MIDC - Ballarshah (Ckt- I ) 66 66 66 2110 D/C SEP-16220
Trasmission Lines: Page 46 of 91
Legends
TL: Total Location STC: Stubs Cast TE: Towers Erected STG: Stringing Completed
Schedule
1. 2. 5. 6. 7. 8. 9. 10. 12.3.
Revised/Anticipate
d
11.
Construction progress StatusTarget Date
RemarkTowers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hcKM
Ckts(S/C)
&(D/C)
21Chandrapur MIDC - Ballarshah (Ckt- II)11 D/C 220
ROW issue at 7 locations.Highway crossing at Loc. No. 117, 118 & 134/05, 134/06 - Proposal issubmitted.
87Eklahare - Pimpalgaon 158 138 127 1312 D/C DEC-16220
Jejuri-Hinjewadi-I & Jejuri-Hinjewadi-II are the same. Packages were given forconvenience of completion of work.
Forest: 17.25 Hectar forest involved.Reports from Range Forest Office Nasrapur & Paud are in process as per strictinstruction by DFO Pune on dt.15-06-2016.ROW issue at 46 locations.
207Jejuri - Hinjewadi - I & II 276 201 179 6713 D/C JUN-17400
ROW Cases filed order awaited [23]Order received. [10]Forest Locs.JSl has submitted GPS Polygaon of survey no. 489 Mauza-raukgaon in r/oKalmeshwar-katol section on 29.07.16
170Kalmeshwar - Warud 277 175 73 014 D/C JUN-17220
Commissioned 12/2016.3Kalwa - Borivali (under Mumbai Strengthening) 315 S/C onM/C
DEC-16220
Commissioned 10/2016.9Kalwa - Borivali line M/C tower (from loc no. 20 to 48) 916 S/C onM/C
OCT-16220
Forest permission received on 14.01.2013 for SGNP(81.42 Hec) and on17.09.2012 for teritorial forest(117.28 Hec). ROW Problem:Balance foundation Loc. No. 22, 17 (Police protection required for Loc. No. 22)Balance ercetion - Loc. No. 11,12,17,18,19,22.Outage will be availed in Sept-16 to carry out the balance work.
63Kalwa-Borivali 52 50 46 4717 M/C DEC-16220
Severe ROW problem. Slow progress by agency.75Kandalgaon - Dasturi SCDC line 236 92 0 018 S/C onD/C
JUN-17220
Work in progress.ROW cases filed, order awaited [7].
144Kopargaon tap - Babhaleshwar 117 90 2 019 M/C APR-17220
Forest Involved: 10.36 Ha Received FRA certificate.GOI Nagpur informed queries to GOM, MSETCL & Nodal Nagpur on 07.06.16National Highway (NH-69) crossing: Reminder letter given to NHAI
MAR-11106Koradi II - Butibori 189 133 117 2220 D/C onM/C
APR-17220
Trasmission Lines: Page 47 of 91
Legends
TL: Total Location STC: Stubs Cast TE: Towers Erected STG: Stringing Completed
Schedule
1. 2. 5. 6. 7. 8. 9. 10. 12.3.
Revised/Anticipate
d
11.
Construction progress StatusTarget Date
RemarkTowers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hcKM
Ckts(S/C)
&(D/C)
regarding approval of long pending cases vide no:3162 Dt:26.08.15.
ROW Case Filled Order Awaited [3] : 4, 53, 138P.O. Order Received [13] : 13, 13A, 29, 48, 51/52, 142A, 143, 144, 156, 31, 99,102, 120
38Koradi II to Koradi -III line (ckt.II) 111 111 111 821 D/C JAN-17400
Commissioned 12/201638Koradi-II - Koradi-III (Ckt-I) 111 111 111 3822 D/C DEC-16400
ROW:Cases filed but order awaited [6].Forest involved:Order awaited [1].
84Kumbhari S/S - Bale 134 122 78 2023 D/C MAR-17220
Commissioned 05/16.13LILO of Kolhapur - Sawantwadi at Mudhaltitta(Bidri)S/S (Tap line, Ckt-II)
45 45 45 1324 D/C MAY-16220
ROW issue at 15 locations.Railway crossing at Loc. No. Locs : 00 4/0, 00 5/0 - Feasibility report submittedon 25.06.15.Highway crossing involved st Loc. No. I /0, I / I, 00 6/0, 00 7/0 - Proposalsubmitted.
21LILO of 220KV Bhugaon - Warora-I at Warora 42 34 18 225 D/C DEC-16220
Work in progress.ROW Cases filed but order awaited [2]Railway crossing: Loc. No. 187, 188.Proposal submitted to Railway authorities.Forest Locs. [1]Forest Proposal Submitted Approval Awaited [1] : 187
170LILO of 400KV Bhusawal - Aurangabad ckt-II atAurangabad (Thaptitanda)
273 233 197 7026 D/C NOV-16400
Work in progress.37LILO of Bhigwan - Walchandnagar at Loni Deokar S/S 64 20 0 027 D/C MAR-17220
Commissioned 08/16.14LILO of Bhugaon - Pusad at Wardha (PG) 33 33 33 1428 D/C AUG-16220
Stringing work is balance due to non-availability of disc insulators.80LILO of Chandrapur - Parli ckt-I at Nanded(Khumbhargaon)
113 113 113 6329 D/C DEC-16400
Work is in progress.25LILO of Kolhapur - Solapur at Elkud 37 37 37 2330 D/C DEC-16400
Work in progress.39LILO of Pandharpur - Malinagar at Bhalwani S/S 64 43 0 031 D/C MAR-17220
The work is stopped due to1) Severe ROW2) Forest issue
MAR-0716LILO of Tarapur-Borivli at Boisar II 15 15 12 1132 D/C MAR-17220
Commissioned 09/2016 (Late reported)2LILO on 220 KV Pandharpur - Malinagar line for33 D/C NOV-16220
Trasmission Lines: Page 48 of 91
Legends
TL: Total Location STC: Stubs Cast TE: Towers Erected STG: Stringing Completed
Schedule
1. 2. 5. 6. 7. 8. 9. 10. 12.3.
Revised/Anticipate
d
11.
Construction progress StatusTarget Date
RemarkTowers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hcKM
Ckts(S/C)
&(D/C)
M/s Vittal SSK Co-generation Plant
Commissioned 06/16.1LILO on 220 kV Kandalgaon Topworth for M/s PioneerGas Power Ltd.
134 D/C JUN-16220
Commissioned 10/2016.96LILO on 220kV Shivajinagar-Satana line (Fromloc.No.211) at 220kV Gangapur S/s
9635 D/C OCT-16220
Forest involvment: Work Stopped, new survey to be carried outRoW : Cases filed for 8 locations at Addl. collector Jawhar office.
6LILO on 400KV Padghe - Tarapur line at 400KVPadghe-II (Kudus)
12 3 0 036 D/C MAR-17400
Work is in progress.32LILO on Both circuits of Waluj - Jalna at Taptitanda S/s 39 33 27 037 M/C APR-17220
Work in progress.64Lamboti - Vairag SCDC 107 81 0 038 S/C onD/C
MAR-17220
Work in progress.
P.O. Order received [5]
97Malegaon - Kalwan 179 167 149 3639 D/C MAR-17220
Work is in progress.ROW: Cases filed but order awaited [2].
78Nagewadi - Taptitanda 130 79 4 040 D/C APR-17220
Work is to be carried out under ORC.30Nagothane - Wadkhal 93 56 44 041 D/C MAR-17220
Arbitral award- Group C. Tenderisation is in process for balance work.32Nanded - Krishnoor 51 28 0 042 M/C JUN-17220
Work is in progress.128Partur - Nagewadi line 221 162 132 043 D/C MAR-17220
ROW Case filed but order awaited[2]104Phaltan - Walchandnagar 177 166 161 7344 D/C SEP-16220
Work is in progress.49SCDC Karad - Koyna 170 153 139 3645 S/C onD/C
DEC-16220
Commissioned 05/16.11Tap on Babhaleshwar - Chalisgaon for Kopergaon S/S(Ckt-II)
1146 D/C MAY-16220
ROW Locs. [16]1. Case Filled OrderAwaited [16] : 2, 6, 9, 10,11, 12, 13, 14, 15, 16, 17,18, 19A, 19B, 26, 272. Order Received [0] :Forest Locs. [3]1. Forest Proposal
32Uppalwadi - Mankapur 28 1 0 047 M/C DEC-17220
Trasmission Lines: Page 49 of 91
Legends
TL: Total Location STC: Stubs Cast TE: Towers Erected STG: Stringing Completed
Schedule
1. 2. 5. 6. 7. 8. 9. 10. 12.3.
Revised/Anticipate
d
11.
Construction progress StatusTarget Date
RemarkTowers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hcKM
Ckts(S/C)
&(D/C)
Submitted ApprovalAwaited [3] : 1 CTT, 7, 82. Forest ApprovalReceived [0] :Work not started by agency.RAILWAY-Loc. no. 3&4
& Loc. no. 21 & 22Proposal yet to be prepared by Agency. Regular follow up being done.
NHAI/Highway Proposal forlocs No 12-13 & 40-41sub. to NHAI vide ltrno. 306 Dtd. 05.03.15,Ref no. 306
54Uppalwadi - New Pardi 45 0 0 048 M/C DEC-17220
Work in progress.ROW involved [42 nos.]Cases filed [4 nos.]Order received [38 nos.]
322Wardha (PGCIL) - Ghatodi 547 405 219 049 D/C JUN-17220
Work in progress.165Warora - Wardha 289 284 283 13450 D/C DEC-16220
Trasmission Lines: Page 50 of 91
Legends
TL: Total Location STC: Stubs Cast TE: Towers Erected STG: Stringing Completed
Schedule
1. 2. 5. 6. 7. 8. 9. 10. 12.3.
Revised/Anticipate
d
11.
Construction progress StatusTarget Date
RemarkTowers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hcKM
Ckts(S/C)
&(D/C)
MEGHALAYA ENERGY CORP. LTD. (MeECL)
Work 98% completed on 11.02.2016 except at the tapping point. This will betaken up along with the line integration work at Killing S/s as soon as theupgradation SCADA work at Killing sub-station is completed. Tower location 19 /19 location completed, stringing MC- 5.82 km, D/C-0.34km, S/C-0.6km &stringing only for one circuit-3.006km (Total- 21.746ckm) completed.
17Killing (Byrnihat)-EPIP-I 19 19 19 221 M/C JAN-17132
Work completed and line charged on 28.01.2014.Line was commissioned withthe connected sub-station on 22.12.2015.
5LILO of Agia - Nangal at Mendipathar 9 9 9 52 D/C JAN-14132
No issue on forest clearance and no court cases.Work held up due to ROWproblem. The PHED,GOMe has complained and filed an FIR against Loc No. 3to 8. Overall status is 90% completed.
10LILO of Mawlai - Cherra at Mawngap. 16 15 15 53 D/C MAR-17132
Work completed & commissioned on 20.11.2015.1LILO of NEHU - Khliehriat line at Mustem 4 4 4 14 D/C NOV-15132
No issues on forest clearance. Detail survey & check survey (1.6 km) for the 132kV LILO is completed. Stub setting at 6/ 7 locations and erection of towers at 6 /7 locations have been completed.
6LILO of NEIGRIHMS - Khliehriat at Lad Nongkrem 7 6 6 05 D/C MAR-17132
Survey works for 132 kV LILO is completed.20LILO of Rongkhon - Ampati at Praharinagar 30 0 0 06 D/C SEP-18132
The line was completed and commissioned on 21.12.2011.66Mawngap - Sumer 102 102 102 667 D/C DEC-11132
Work Completed and line charged on 06.08.2013.92Nangalbibra - Agia 316 316 316 928 S/C AUG-13132
As in Serial 3 below for New Umtru - EPIP-II line.1New Umtru - Umtru HEP 3 1 0 09 S/C MAR-17132
No issues of forest clearance. The 132 kV line works have been completedexcept for the terminal equipments at Umtru HEP (to be done by MePGCL) andat EPIP-II sub-station.Tower erected is 8/8 locations. Stringing completed -1.71ckm. The project is expected to be completed by March 2017.
2New Umtru HEP - Norbong (EPIP-II) 8 8 8 210 D/C MAR-17132
No issues on forest clearance and no court cases. Work is presently underprogress.
33Rongkhon S/S - Ampati 102 101 98 1911 D/C MAR-17132
Trasmission Lines: Page 51 of 91
Legends
TL: Total Location STC: Stubs Cast TE: Towers Erected STG: Stringing Completed
Schedule
1. 2. 5. 6. 7. 8. 9. 10. 12.3.
Revised/Anticipate
d
11.
Construction progress StatusTarget Date
RemarkTowers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hcKM
Ckts(S/C)
&(D/C)
ORISSA POWER TRANSMISSION CORPORATION LTD. (OPTCL)
SEP-1622Balimela - Malkangiri 78 78 78 221 S/C JAN-17220
kindly make the ckm as 54 ckmJUN-2028Bhanjanagar - Aska 112 12 D/C 220
Commissioned 11/2016.DEC-0920Bidanasi -Cuttack 38 38 38 203 D/C NOV-16220
JAN-15160Bolangir - Kesinga 323 243 0 04 D/C AUG-17220
Work in progress.96Cuttack (OPTCL) - Pratapsasan 172 18 3 05 D/C MAR-17220
Since this is repeated may be deletedJUN-1340IB - Lapanga 606 D/C MAR-17400
May be deleted as repeated in Sl. 1417Jayanagar (OPTCL) - Jayanagar (PGCIL) 37 25 0 07 D/C MAR-17220
kindly make the Ckm as 200 instead of 96Ckm.JUN-1796Kesinga - Baliguda 376 548 D/C 220
The CKM may be indicated as 14.802 CKM.SEP-1715Keunjhar - Keunjhar PG 30 0 0 09 D/C 220
Commissioned in 2014 (Late Reported)7LILO of (Existing) Budhipadar-Burla at Lapanga 19 19 19 710 D/C DEC-16220
Work Order issued10LILO of (Existing) Bhanjanagar - Meramundali atNarasinghpur
21 0 0 011 D/C MAR-17220
The work is taken up throogh OPTCL empanelled Rate Contract HolderDEC-163LILO of Indravati - Theruvali at Kashipur 13 8 0 012 D/C DEC-16220
Work is taken up through OPTCL empanelled Rate Contract HolderDEC-160LILO of Katapalli - Bolangir at Bargarh (New) 2 2 0 013 D/C MAR-17220
tHE ckm MAY BE INDICATED AS 10.2 ckmMAR-1710LILO of Meramundali - Duburi Ckt-I at Goda Chhak 24 1214 D/C 220
Ready for Commissioning 12/2016.6LILO of Rengali - Tarkera at Bonai 17 17 17 615 D/C DEC-16220
Ongoing worksFEB-1832LILO of one ckt of Indravati - Thervali line at Jaypatna 66 0 0 016 D/C FEB-18220
My be deleted as the project is yet to be awardedJUN-1360LILO of one ckt of Rengali - Tarkera at Deogarh17 D/C 220
The CKM may be indicated as 67.254 CKMFEB-1867Malkangiri - Kalimela 120 0 0 018 S/C 220
The CKM may be indicated 58.30 CKMMAR-1758Pandiabili PGCIL - Pratapasan line 107 25 019 D/C 220
The line CKM may be corrected as 38 CKMs.SEP-1638Restoration of IB - Lapanga line 62 56 5420 D/C MAR-17400
Trasmission Lines: Page 52 of 91
Legends
TL: Total Location STC: Stubs Cast TE: Towers Erected STG: Stringing Completed
Schedule
1. 2. 5. 6. 7. 8. 9. 10. 12.3.
Revised/Anticipate
d
11.
Construction progress StatusTarget Date
RemarkTowers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hcKM
Ckts(S/C)
&(D/C)
POWER AND ELECTRICITY DEPARTMENT, MIZORAM (P&ED Mizo)
The 132KV Sihhmui substation was constructed by P&E, Govt. of Manipur andcompleted on 31.03.2016.
Bawktlang (Kolasib) S/S - Sihhmui S/S1 D/C DEC-16132
5LILO of Zemabawk - W.Phaileng at Sihhmui 0 0 02 S/C DEC-13132
Line has been constructed upto the peripheral boundary of Turial HEP.Works for extention of the line up to the 132kV Tuirial Swyd is under progress byP&E dept, Mizoram.
Tuirial HEP - Bawktlang (Kolasib) S/S3 S/C DEC-16132
Trasmission Lines: Page 53 of 91
Legends
TL: Total Location STC: Stubs Cast TE: Towers Erected STG: Stringing Completed
Schedule
1. 2. 5. 6. 7. 8. 9. 10. 12.3.
Revised/Anticipate
d
11.
Construction progress StatusTarget Date
RemarkTowers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hcKM
Ckts(S/C)
&(D/C)
POWER TRANSMISSION CORP. OF UTTARAKHAND LTD. (PTCUL)
DPR prepared. DPR submission to funding agency is in progress.146Almora-Pithoragarh 0 0 0 01 D/C DEC-16220
Construction of line as per Connectivity Schedule of Generators in YamunaValley.
94Arakot -Mori and LILO of Arakot -Mori at Hanol Tuni 0 0 0 02 D/C MAR-18220
Construction of line as per Connectivity Schedule of Generatiors in YamunaValley.
52Devsari-Karanprayag 0 0 0 03 D/C NOV-17220
Construction of line as per Connectivity Schedule of Generators in YamunaValley.
76Jakhol -Sankri -Mori and LILO of Jakhol -Sankri -Moriat Natwar Mori
0 0 0 04 D/C MAR-18220
Contract has been awarded on 06.05.11 to M/s TATA Project Ltd., contracteffective date is 14.10.11 and GMVN has not given the permission to cross theAuli Ropeway, hence crossing by underground cable is proposed at Joshimath.Land sliding zone being encountered at village Malli Tangri and Talli Tangri thesurvey and forest case yet to be completed. Forest Case of 51.3 Hect. is underpreparation. Total Progress 6%.
40Joshimath - Kunwari Pass (Pipalkoti)5 D/C DEC-17220
Retendering is under Process.184Kuwari Pass (Pipalkoti)-Karanprayag -Srinagar 0 0 0 06 D/C DEC-16400
Contract has been awarded on 06.05.11 to M/s TATA Project Ltd. contracteffective date is 03.09.11 and will be taken after award of 400 KV Pipalkoti S/s.Total Progress 11%.
2LILO of Muzaffarnagar - Vishnu Prayag at KuwariPass (Pipalkoti)
6 0 0 07 D/C AUG-16400
Construction of line as per Schedule of construction of Singoli HEP and to beconstructed by L&T.
5LILO of Baramwari - Srinagar at Singoli Bhatwari 0 0 0 08 D/C OCT-16220
Tendering is under process.12LILO of Kashipur - Pantnagar line at Jaffarpur9 D/C MAR-17220
The work at Pala Maneri HEP stopped as per GOI order.10LILO of Loharinagpala - Koteshwar at Pala - Maneri 0 0 0 010 D/C 400
Construction of line as per connectivity schedule of generatiors in Yamuna Valley10LILO of Mori - Dehradun line at Nogaon11 D/C MAR-18220
Construction of line as per Schedule of construction of Langrasu.16LILO of Nandprayag -Karanprayag at Langrasu 0 0 0 012 D/C NOV-17220
Tendering is under process.1LILO of Rishikesh-Dehradun at Harrawala 0 0 0 013 D/C AUG-16220
10LILO of Roshanabad - Puhana line at Imlekhera(Pirankaliyar)
14 D/C MAR-17220
LoA is to be issued.10LILO of Roshnabad -Puhana at Pirankaliyar S/S 0 0 0 015 D/C MAR-17220
Tender has been floated.70LILO of Vyasi HEP - Dehradun at Dehradun (PG) 0 0 0 016 D/C MAR-17220
Trasmission Lines: Page 54 of 91
Legends
TL: Total Location STC: Stubs Cast TE: Towers Erected STG: Stringing Completed
Schedule
1. 2. 5. 6. 7. 8. 9. 10. 12.3.
Revised/Anticipate
d
11.
Construction progress StatusTarget Date
RemarkTowers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hcKM
Ckts(S/C)
&(D/C)
S/S
Regarding Forest land Transfer proposal nodal officer Dehradun raised queriesvide letter no 3042 dated 01-06-2013. Reply of the same is being done. Totalprogress 13%
24Lata Tapovan- Joshimath 36 0 0 017 D/C DEC-17220
The work at Loharinagpala HEP stopped as per GOI order.180Loharinagpala-Koteshwar line 0 0 0 018 D/C 400
Construction of line as per Connectivity Schedule of Generators in YamunaValley.
200Mori -Dehradun 0 0 0 019 D/C MAR-18220
Forest approval granted on 02.04.2013.agreement with M/s Lanco has beendone
182Rudrapur(Brahmwani) - Ghansali-Srinagar line 248 0 0 020 D/C DEC-16220
Commissioned 07/16.28Srinagar HEP - Sringar 400 kV S/S. 39 39 39 2821 D/C JUL-16400
Survey work is in progress in the alternative route proposed by M//s cobra.Thego ahead was issued through this alternate route on dated 24/12/2014.detailedsurey of 189 Km completed.Forest case preparation in progress and profilepotting in progress
304Sringar - Kashipur 0 0 0 022 D/C DEC-18400
Tower foundation-20/21 and Tower erection-19/21.Total progress-90%12Twin Zebra - Dehradun (PGCIL) 21 20 19 923 D/C JUL-16220
Contract has been awarded on 06.05.11 to M/s TATA Project Ltd. contracteffective date is 03.09.11 Forest case prepared for 43.694 Hect. and submittedto DFO Joshimath/ DM Chamoli. NOC from 04 Nos. village panchyat NaurakhAgthalla, Tangri Talli and Tangri Malli is pending. Matter is being pursuedGOU/District Administration.
40Vishnugad - Kuwari Pass (Pipalkoti) 62 0 0 024 D/C DEC-16400
Trasmission Lines: Page 55 of 91
Legends
TL: Total Location STC: Stubs Cast TE: Towers Erected STG: Stringing Completed
Schedule
1. 2. 5. 6. 7. 8. 9. 10. 12.3.
Revised/Anticipate
d
11.
Construction progress StatusTarget Date
RemarkTowers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hcKM
Ckts(S/C)
&(D/C)
PUNJAB STATE TRANSMISSION CORPORATION LIMITED (PSTCL)
Ready for Commissioning 08/16.71Bajakhana - Bagha Purana 103 103 103 711 D/C AUG-16220
Due to poor performance and slow progress by the contractor, work ordercancelled. Short term tenders are being recalled.
129Goindwal Sahib - Bottianwala 201 163 160 02 D/C MAY-17220
Commissioned 06/16.30Kanjali - Science city line (Jalandhar) 58 58 58 303 D/C JUN-16220
Forest case pending.OCT-1623LILO of 220KV Patran - Kakrala & Patran - Rajila lineat 400KV PGCIL Patran
41 37 35 214 D/C FEB-17220
Commissioned 05/16.48LILO of Ferozepur - Talwandi Bhai line at Sadiq 80 80 80 485 D/C MAY-16220
Commissioned 06/16.21LILO of GGSSTP - Jamsher at Jadla 41 41 41 216 D/C JUN-16220
Commissioned 06/16.21LILO of Ganguwal - Mohali at Majra 40 40 40 217 D/C JUN-16220
Commissioned 06/16.50LILO of Malout - GNDTP Bhatinda at Badal 84 84 84 508 D/C JUN-16220
Ready for Commissioning 08/16.68LILO of Patiala - Mandi Gobindgarh at Rajpura 109 109 109 689 D/C AUG-16220
Ready for Commissioning 08/16.6LILO of one ckt of Ganguwal - Gobindgarh-II at Bhari 13 13 13 610 D/C AUG-16220
Forest case pending.Railway case approved.DEC-1652LILO of one ckt. 220KV Nakodar - Rehanajattan line at220KV Hoshiarpur
94 90 4411 D/C MAY-17220
Work in progress. Forest case pendingDEC-1625LILO of one ckt. of 220KV Humbran - Ferozpur Road(Ludhiana) at 220KV Ladowal
41 34 24 1512 D/C MAY-17220
Work is in progress.Committee formulated for sale of trees28Ludhiana - Doraha 95 95 84 1813 D/C MAY-17220
Work is in progress. Forest & Railway cases pending. Initially line length in RFDtaken as 60 Ckm. Now the line length is 101 Ckm.
101Makhu - Algaon 159 142 113 3014 D/C MAY-17220
Work is in progress.92Makhu - Rashiana 146 131 113 5515 D/C MAY-17220
Work is in progress. Forest pending and Railway case cleared.30Malout - Abohar 95 67 2516 D/C JUN-17220
Work in progress. Forest case of Ludhiana and Sangrur In Principal approvalreceived. Ferozepur case pending with DFO.
105Moga - Mehal Kalan 170 163 161 7417 D/C MAR-17220
Forest cases pending with DFO Ferozepur. Railway case approved.76Mukatsar - Kotkapura 129 118 115 1218 D/C MAR-17220
Work is in progress.47Mukatsar - Malout 83 81 79 119 D/C MAR-17220
Work is in progress.Forest case - Patiala case approved. Sangrur case pendingwith PCCF Mohali.
21Nabha -Bhawanigarh 80 76 76 1520 S/C onD/C
DEC-16220
Work is in Progress.Forest case- Ludhiana case approved. Phillaur case pending.Railway case - one case approved and one case pending.
67Nakodar - Ladhowal 122 118 109 1821 D/C MAY-17220
Trasmission Lines: Page 56 of 91
Legends
TL: Total Location STC: Stubs Cast TE: Towers Erected STG: Stringing Completed
Schedule
1. 2. 5. 6. 7. 8. 9. 10. 12.3.
Revised/Anticipate
d
11.
Construction progress StatusTarget Date
RemarkTowers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hcKM
Ckts(S/C)
&(D/C)
Work is in progress.71Nakodar - Rehana 121 121 121 7022 D/C DEC-16220
Work in progress. Forest case pending.74Rajpura - Devigarh 114 114 95 723 D/C FEB-17220
Commissioned 06/16.59Rajpura - Lalru 98 98 98 5924 D/C JUN-16220
Work deferred for the time being62Sarana- Kotli Surat Malli line 185 70 0 025 S/C onD/C
AUG-16220
Trasmission Lines: Page 57 of 91
Legends
TL: Total Location STC: Stubs Cast TE: Towers Erected STG: Stringing Completed
Schedule
1. 2. 5. 6. 7. 8. 9. 10. 12.3.
Revised/Anticipate
d
11.
Construction progress StatusTarget Date
RemarkTowers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hcKM
Ckts(S/C)
&(D/C)
RAJASTHAN VIDYUT PRASARAN NIGAM LIMITED (RVPNL)
Commissioned 04/16.118Aau - Badisid 196 196 196 1181 D/C APR-16220
Bid Opened. W.O process initiated.80Ajmer (400 kV) - Bherunda (TK)2 D/C 220
KFW funded scheme. Tech feasibility of line is being reviewed.50Akal (1)- Jaisalmer -23 D/C MAR-17400
W.O awarded to M/S TATA Project Ltd.480Akal -Jodhpur (New) 618 592 549 2604 D/C JUL-17400
W.O. awarded to M/s Unique Structures & Towers Ltd., Bhilai (W.O from M/STrans Era withdrawn.) Forest involved. Permission awaited.
45Anta -Kota (PG) (Extension) 135 116 115 315 D/C MAR-17400
30Badisid-Bap6 D/C MAR-17220
KFW funded scheme .W.O. awarded to M/S Monte Carlo.280Barmer-Bhinmal (PG) 444 507 D/C MAR-17400
W.O. awarded to M/S Unitech. Forest involved . Permission to work received on10.11.16.
379Bhadla-Bikaner 511 509 500 2688 D/C MAR-17400
Commissioned 06/16.63Bhadla-Kanasar 105 105 105 639 D/C JUN-16220
W.O. awarded to M/S Best & Crompton Ltd.APR-14320Bhilwara TPS -Ajmer 432 432 431 30210 D/C MAR-17400
Commissioned 06/16. (Late Reported).JAN-1278Bhinmal - Sayla line 132 132 132 7811 D/C JUL-16220
PPP mode. W.O. awarded to M/S KEC BKNR SKR Tr.Ltd.420Bikaner -Sikar (PG) 448 284 18512 D/C MAR-17400
Ready for Commissioning 08/16.90Chatrail-Ramgarh 146 146 146 9013 D/C AUG-16220
Ready for Commissioning 08/16.51Chittorgarh - Sawa 91 91 91 5314 D/C AUG-16220
"W.O. awarded to M/s SPML Infra.ROW problem at loc no. 2&3."
99Chittorgarh-Bhilwara 134 134 131 81375215 D/C MAR-17400
.Dahanu - Degchu GSS16 D/C 132
W.O. awarded to M/s Ramjee Power Work stopped due to severe ROW problemat Loc. no. 9-10 & 12 to 63.
31Dhod-Danta Ramgarh 101 4417 S/C JAN-17220
Ready for commissioning 12/2016.APR-093Extension of Bikaner- Barsinghsar at Barsinghsar TPS 10 10 10 318 S/C DEC-16220
Trasmission Lines: Page 58 of 91
Legends
TL: Total Location STC: Stubs Cast TE: Towers Erected STG: Stringing Completed
Schedule
1. 2. 5. 6. 7. 8. 9. 10. 12.3.
Revised/Anticipate
d
11.
Construction progress StatusTarget Date
RemarkTowers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hcKM
Ckts(S/C)
&(D/C)
KFW funded scheme. Bidding process to be initiated.30Gajner -Kolayat19 D/C MAR-17220
Ckt-I from 220 kV GSS I.G. Nagar-132 kV GSS Sitapura-220 kV GSS Sitapuraalready charged on 132 KV level and will remain charged on 132 KV Voltagelevel as per the scheme.Ckt.-II 220 KV GSS I.G. Nagar-220 KV GSS Sitapura work almost completed.Permission of shutdown of PGCIL lines at I.G. Nagar end awaited which isrequired for line crossing. Ckt. II is expected to be completed and charged on220 KV voltage level upto Jan'17
17Indira Gandhi Nagar -Sitapur (Upgradation) 29 29 29 1720 D/C DEC-16220
Forest involved . Clearance awaited.JAN-1380Jaipur North (400 kV GSS) - Manoharpur (Turnkey) 141 137 134 7421 D/C MAR-17220
KFW funded scheme. W.O. awaded to M/s TATA Project Ltd.260Jaisalmer -2 -Barmer22 D/C MAR-17400
W.O. is to be awarded100Jaisalmer-2 - Akal line23 S/C 400
W.O. awaded to M/s Navdurga.Actual line length is 119.652 ckm . work completed on dt. 20.12.16
DEC-12120Jethana - Ajmer line 203 203 203 12024 D/C JAN-17220
W.O. awarded to M/s Hitech.OCT-1221Jodhpur (400 kV GSS) - Banar 35 35 27 1225 D/C JAN-17220
Work order awarded to M/s R.S. Infra Noida.APR-1090Jodhpur (New) - Barli (TK) 158 158 158 8926 D/C JAN-17220
Work order awarded to M/s R.S. Infra Noida.ROW problem at Loc no. 8/0APR-1040Jodhpur (New) - Jhalamand (TK) 64 64 63 3527 D/C 220
Severe ROW problem. Revised proposal for OH line and cable under approval.12Jodhpur - NPH Jodhpur28 D/C 220
W.O. awarded to M/s Classic Coal, work stopped due to ROW problem.16Jodhpur CHB - Soorsagar 31 19 0 029 D/C JAN-17220
W.O awarded to M/s Kay Cee Energy & Infra Private Limited.34Kalisindh TPS - Bhawanimandi 108 108 106 730 S/C JAN-17220
14Kunda ki dhani-Purana Ghat (upgradation)31 D/C 220
under KFW20LILO of Kolayat -Bajju at Kolayat32 D/C MAR-17220
Commissioned 08/16.10LILO of 220 kV Jodhpur (220 kV GSS) - Pali at 400 kVGSS Jodhpur (New)
18 18 18 1033 D/C AUG-16220
Commissioned 10/2016 (Reported Late)1LILO of 220KV Jodhpur -400KV Jodhpurinterconnector at 220KV Jhalamand
1 4 4 134 D/C DEC-16220
6LILO of 2nd Ckt Sikar (RVPN), Ratnagarh at Sikar35 D/C MAR-17220
Trasmission Lines: Page 59 of 91
Legends
TL: Total Location STC: Stubs Cast TE: Towers Erected STG: Stringing Completed
Schedule
1. 2. 5. 6. 7. 8. 9. 10. 12.3.
Revised/Anticipate
d
11.
Construction progress StatusTarget Date
RemarkTowers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hcKM
Ckts(S/C)
&(D/C)
Commissioned 04/16.3LILO of Chabra TPS - Anta line at SupercriticalChhabta TPS
336 D/C APR-16400
W.O. awarded to M/s Unique Structures & Towers Ltd., Bhilai (W.O from M/STrans Era withdrawn.) Forest involved. Permission awaited.
1LILO of Chabra TPS -Dahra at Anta (2nd ckt) 5 5 337 D/C MAR-17400
KFW funded scheme. W.O. Is to be awarded .20LILO of Chandan- Pokaran at Pokaran38 D/C MAR-17220
Commissioned 04/16.1LILO of Jodhpur (GSS) - Jodhpur at Barli 6 6 6 139 D/C APR-16220
Commissioned 06/16.AUG-0999LILO of Jodhpur - Merta line at Jodhpur (New) 140 140 140 9940 D/C JUN-16400
ADB funded scheme. W.O. awarded to M/s TATA Project.390LILO of Jodhpur -Merta at Pooling station Badla 547 522 452 11441 D/C MAR-17400
Ready for Commissioning 08/16.30LILO of Kankroli (PG) -Debari at Amberi 60 60 60 3042 D/C AUG-16220
Commissioned 04/16.40LILO of Kota (PG) -Bhilwara at Mandalgarh 76 76 76 4043 D/C APR-16220
under KFW20LILO of PS 1- Bajju at PS 1/Bajju44 D/C MAR-17220
LILO of VKIA - Kukas at Jaipur (North) (Turnkey)45 D/C 220
Ready for commissioning 12/2016.1LILO of both ckts Ramgarh GTPS -Dechu at Ramgarh 1 1 1 146 D/C DEC-16220
w.o. is to be awarded20LILO of both ckts Ramgarh GTPP -Dechu line atPokaran
47 D/C MAR-17220
Commissioned 10/201658LILO of one ckt Jaipur (South) to Chaksu at Goner 101 101 101 5848 D/C OCT-16220
Commissioned 04/16.102LILO of one ckt Raj west -Jodhpur at Jodhpur (New) 138 138 138 10249 D/C APR-16400
Work under progress expected to be commissioned upto Mar'1733LILO of one ckt of Ramgarh GTPS - Dechu atAmarasagar
60 60 60 3350 D/C MAR-17220
5Mansarovar - Chambal (Cable System)51 D/C 220
W.O awarded to M/s Kay Cee Energy & Infra Private Limited.35Modak - Bhawanimandi 123 123 123 4052 S/C JAN-17220
W.O. awarded to M/s RS Infra. Line charged on 33 KV on dt 30.06.1666PS 1 /Bajju -Bhadla 107 107 107 6653 D/C AUG-16220
Commissioned 11/2016 (Reported Late)SEP-12104Phagi GSS (Jaipur) - Heerpura line 126 126 126 10454 D/C DEC-16400
W.O awarded to M/s Varsana Ispat.(W.O. withdrawn from M/s. GET) .Two nos. of NHAI crossing awaited.
SEP-12210Phagi(Jaipur south-765 kV)-Ajmer line 283 276 252 3155 D/C MAR-17400
Trasmission Lines: Page 60 of 91
Legends
TL: Total Location STC: Stubs Cast TE: Towers Erected STG: Stringing Completed
Schedule
1. 2. 5. 6. 7. 8. 9. 10. 12.3.
Revised/Anticipate
d
11.
Construction progress StatusTarget Date
RemarkTowers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hcKM
Ckts(S/C)
&(D/C)
W.O awarded to M/s Moji Constructions. Forest involved. Clearance awaited.Court stay at 1 loc.Railway crossing approval awaited at 1 loc.
240Pratapgarh- Chittorgarh 407 378 322 13856 D/C JAN-17220
ADB funded scheme. W.O awarded to M/S TATA Project Ltd.200Ramgarh (Jaisalmer)-Akal (Jaisalmer ) 278 273 264 12057 D/C MAY-17400
W/O awarded to M/s SEW Hyderabad320Ramgarh -Bhadla 446 416 321 12058 D/C MAR-17400
W/O awarded to M/S Moji Construction , Jpr. Forest involved . Clearanceawaited.
25Sirohi-Pindwara 106 6459 S/C MAR-17220
commissioned 07/2015 (Late Reported)1Sitapura- Sitapura (Existing) (Upgradation) 3 3 3 160 D/C DEC-16220
AUG-1121Soorpora - Banar line 35 35 27 1261 D/C JAN-17220
Work order awarded to M/s Aster Chennai.Case for diverting route due to airforce approved, work under progress.
JAN-13480Suratgarh TPS - Babai ( Jhunjhunu) 676 611 572 28862 D/C JAN-17400
PPP mode. Work order awarded to M/s Adani Trans Raj Ltd.340Suratgarh TPS- Bikaner63 D/C MAR-17400
KFW funded scheme . W.O. is to be awarded.140Undoo - Pokaran64 D/C 220
Trasmission Lines: Page 61 of 91
Legends
TL: Total Location STC: Stubs Cast TE: Towers Erected STG: Stringing Completed
Schedule
1. 2. 5. 6. 7. 8. 9. 10. 12.3.
Revised/Anticipate
d
11.
Construction progress StatusTarget Date
RemarkTowers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hcKM
Ckts(S/C)
&(D/C)
SIKKIM POWER DEVELOPMENT CORPORATION LTD. (SIKKIM)
.Dikchu - Gangtok1 D/C 132
Dikchu HEP - Dikchu Pool2 D/C 132
Out of two towers, both have been completed. Stringing yet to be started.Progress hampered due to shortage of money(demonetisation) to disbursepayment to labour. It is interim arrangement being constructed by generationcompany for evacuation of power.
1LILO of Teesta III - Rangpo 400 kv line at Dikchu 2 2 1 03 D/C NOV-16400
Trasmission Lines: Page 62 of 91
Legends
TL: Total Location STC: Stubs Cast TE: Towers Erected STG: Stringing Completed
Schedule
1. 2. 5. 6. 7. 8. 9. 10. 12.3.
Revised/Anticipate
d
11.
Construction progress StatusTarget Date
RemarkTowers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hcKM
Ckts(S/C)
&(D/C)
TAMILNADU TRANSMISSION CORPORATION LTD. (TANTRANSCO)
Work under progress.ROW issues at 7 locationsDEC-1655Arasur (PGCIL) - Gobi S/S 188 182 177 411 S/C MAR-17220
Work awarded to M/s.Gammon India Ltd.,Design of towers and foundation worksare under progress
320Ariyalur - Thiruvalam PGCIL 485 52 D/C APR-18765
Work awarded to M/s.Rahul Cables and under progress.2Basin Bride - Pulianthope (UG Cable)3 S/C JUN-17220
Tender is to be floated23Basin Bridge - TNEB HQ (UG Cable) 0 0 0 04 S/C MAR-17220
SC line of 19.369 Ckt Kms energised on 19.12.16.AUG-1537Common Point (from Karamadai) - Thudialur 68 65 63 195 S/C MAR-17220
Work under progress.SEP-16348Cuddalore - Veerapuram (SP Koil) Via Neyveli. 702 572 505 656 D/C MAR-17220
Work under progress58Dharmapuri - Gurubarapally 232 223 223 547 S/C MAR-17220
Work awarded and is being commenced. Cable to be supplied8Guindy - R.A.Puram S/S8 S/C 220
Work under progress. objection encounted in several locationsSEP-1660Ingur - Arasur (PGCIL) 229 159 149 79 S/C MAR-17220
works are under progress. 5 Locations are under court case and is beingfollowed up.
FEB-1452Kalivanthapattu - Sholinganallur 91 87 82 4410 D/C MAR-17400
Work held up due to ROW issue in 15/3,15/4 and 15/6. Enquiry attended on29.06.16 at Dist Collector /Tuticorin . Report given by Tashildar to RDO/Tuticorin.RDO/Tuticorin conducted peace committee on 28.07.16 and requested to givecompensation to land owners based on the rates fixed by Agricultural Dept.
MAR-1524Kanarpatty - Kayathar 39 36 33 1811 D/C MAR-17400
Ready for commissioning 12/2016.220Karaikudi - Kamudhi 319 319 319 22012 D/C DEC-16400
One. no. ROW issue at Loc.249. Letter addressed to District Collector/Maduraifor Police Protection and for enter upon permission.
DEC-11137Karaikudi - Sembatty 559 558 548 13213 S/C MAR-17220
Commissioned 07/2016 (Late ReportedAUG-1521Karamadai - Common Point 80 80 80 2114 S/C DEC-16220
load flow analysis is under process.This may be deleted.4Karamadai - Pushep15 D/C 220
Work under progress. Railway crossing involved at 2 locations.MAR-15170Kavanoor - Karaikudi (Existing) 327 325 322 10016 D/C MAR-17220
Retender floated with due date for tender opening on 07.01.17112Kayathar - Thennampatty17 D/C MAR-18400
Work under progressDEC-16130Kayathar - Tuticorin S/S 228 201 174 5718 D/C MAR-17220
To be retenderd since M/s.EPIL was black listed. There is a case in the courtvide MP.No:1 of 2015 and WP No:21319 of 2015. Stay vacation Petition filedvide MP.No: 2 of 15.
10Kilpauk - CMRL Central Jail19 S/C 220
Works are under progress. Koladi - PH Road: OH Line work underAPR-1228Koladi - PH Road (Alamathy - Koyembedu) 69 69 69 2520 D/C MAR-17220
Trasmission Lines: Page 63 of 91
Legends
TL: Total Location STC: Stubs Cast TE: Towers Erected STG: Stringing Completed
Schedule
1. 2. 5. 6. 7. 8. 9. 10. 12.3.
Revised/Anticipate
d
11.
Construction progress StatusTarget Date
RemarkTowers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hcKM
Ckts(S/C)
&(D/C)
progress. Stub: 69/69, TE:69/69, stringing : 26/28 completed.Mean while linedeviation involved, for which tender is under process. For cable laying from PHroad to Koyambedu, circuit to be terminated at Koyembedu (CMRL) for whichwork cable laying completed in 2 sections.Joint work to be commenced.
Line work completed. Linking with the terminal tower will be taken up with thecommissioning of Dharmapuri 400 kV SS.
1LILO in 2nd Ckt of MTPS -III - Thiruvalam atDharmapuri
21 D/C OCT-16400
Line work completed. Linking with the terminal tower will be taken up with thecommissioning of Dharmapuri 400 kV SS.
1LILO in Ist Ckt of MTPS - III - Thiruvalam atDharmapuri
22 D/C OCT-16400
Commissioned 09/16.JUL-161LILO of 230 kV Chekkanurani - TTPS (feeder-I) at 230kV Kinnimangalam
5 5 5 123 D/C SEP-16220
tub setting and tower erection is under progress. ROW issues involved atLocations 33-35. Enter upon permission awaited from DistrictCollector/Coimbatore and from District Collector/Erode for Loc.106. Further insome locations land owners objection involved and is being solved.
AUG-1590LILO of Arasur - Karamadi at Shenbagapudur S/S 126 120 115 2824 D/C MAR-17220
Work under progress. 13 nos. Mono pole tower involved.AUG-1524LILO of Arasur - Palladam at Tiruppur 45 40 36 725 D/C MAR-17220
Work under progressJUL-1612LILO of Chekkanurani - Kayather at Kinnimangalam 5 5 526 D/C MAR-17220
Ready for Commissioning 06/16.52LILO of Deviakurichy - Pudhansanthai at Valayapatty 96 96 96 5227 D/C JUN-16220
Ready for commissioning 12/2016.62LILO of Existing Ingur - Palladam at Kurukathi S/S 128 128 128 6228 D/C DEC-16220
Work under progress60LILO of Existing Paramathi - Alundur at Valayapatty 116 112 99 529 D/C FEB-17220
Ready for Commissioning 06/16.1LILO of Existing SP Koil - Thiruvalam at KanchipuramS/S
3 3 3 130 D/C JUN-16220
Ready for Commissioning 06/16.16LILO of Existing Sunguvarchatram - Arni atKanchipuram S/S
40 40 40 1631 D/C JUN-16220
Ready for commissioning 12/2016.54LILO of Existing Trichy - Perambalur atJambunathapuram S/S
102 102 102 5432 D/C DEC-16220
Commissioned 04/16.2LILO of Gummidipoondi - M/s Michelin Tyres line atThervoykandigai 400 kV S/S
233 D/C 220
Ready for Commissioning 06/16.APR-1624LILO of Kalpakkam - Arani at Purisai 49 49 49 2434 D/C JUN-16220
Estimate is under scrutiny for floating tender190LILO of Karaikudi - Pugalur feeder-I at Vellalaviduthi35 D/C APR-17400
Commissioned 09/16.223LILO of Kayathar - Karaikudi line at 400 kV 22336 D/C SEP-16400
Trasmission Lines: Page 64 of 91
Legends
TL: Total Location STC: Stubs Cast TE: Towers Erected STG: Stringing Completed
Schedule
1. 2. 5. 6. 7. 8. 9. 10. 12.3.
Revised/Anticipate
d
11.
Construction progress StatusTarget Date
RemarkTowers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hcKM
Ckts(S/C)
&(D/C)
Kamudhi s/s
Ready for commissioning 12/2016.1LILO of Korattur - Koyembedu at Ambattur (3rd MainRoad)
5 5 5 137 D/C DEC-16220
work completed3LILO of Mettur - Karimangalam at Dharmapuri S/s 19 19 19 338 S/C DEC-16220
Cable Laying and Jointing work completed7LILO of Mylapore - Taramani at RA puram S/s39 D/C 220
Work under progress. Objection encounted at sevaral locations.Enter upon permission obtained from District Collector/Tiruppur and work underprogress. Action is being taken for getting entry permission from DistrictCollector/Karur.
62LILO of Myvady - Pugalur at Kurukathi 124 98 61 540 D/C MAR-17220
work under progress60LILO of Paramathi - Alandur at Valaypatty 116 112 99 541 D/C FEB-17220
Work awarded to M/s Gammond India on 24.09.2016. Tower design is underprocess.
APR-1780LILO of Pugalur - Kalivanthapattu line at Ariyalur 765KV s/s
2842 2xD/C APR-17400
Ready for Commissioning 06/16.5LILO of Siruseri - Taramani (Kids park) line at 400 kVOttiyambakkam S/S
543 D/C JUN-16220
Ready for commissioning 12/20165LILO of Siruseri - Tharamani at Sholinganallur 16 16 16 544 D/C DEC-16220
Due to long penging Court case, revised route is under study.DEC-1012LILO of Sriperumbadur- Arni at Sunguvarchatram 28 10 3 045 D/C MAR-17220
Work already awarded to M/s.CCI and yet to be commenced. Based on therevised approval, route approval and estimate is under preparation.
18LILO of Sriperumbudur - Koyambedu at Guindy (UGCable)
0 0 0 046 S/C MAR-17220
LOA is under perusal.16LILO of Sunguvarchatram - Alamathy at Vellavedu(Guindy)
47 D/C OCT-17400
Work awarded on 03.09.15.Stup setting work is under progress.Railway crossingapproval to be obtained for 2 location.
APR-1420LILO of Thatchankurichi - Eachangadu at Poiyur 52 47 42 648 D/C MAR-17220
Work awarded and under progress40LILO of Thiruvarur - Kadalangudi at Kumbakkonam 92 67 4249 D/C MAR-17220
Cable already laid. Termination to be done1LILO of Tonidapet - Mylapore at TNEB HQ (UG Cable) 0 0 0 050 D/C DEC-17220
Ready for Commissioning 06/16.13LILO of Tuticorin Sipcot - Checkanurani line atSavasapuram S/s
1351 D/C JUN-16220
Commissioned 08/16.APR-16124LILO of both ckt of MTPS stage III - Arasur (PGCIL) atKaramadai
95 95 95 12452 M/C AUG-16400
Stringing will be taken up on commisisoning of Aaikadavu 400 kV SS.2LILO of existing Othakalmandapam feeder-I atsanctioned Anaikadavu 400 kV S/S
53 D/C MAR-17220
Tender opened on 08.12.16 and under process30LILO of one ckt Thppagundu - Anaikadavu atUdumalpet
54 D/C 400
Trasmission Lines: Page 65 of 91
Legends
TL: Total Location STC: Stubs Cast TE: Towers Erected STG: Stringing Completed
Schedule
1. 2. 5. 6. 7. 8. 9. 10. 12.3.
Revised/Anticipate
d
11.
Construction progress StatusTarget Date
RemarkTowers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hcKM
Ckts(S/C)
&(D/C)
Retender floated with due date of opening on 8.12.1630LILO of one ckt of Thappagundu - Anaikadavu 400 lineat Udumalpet (PGCIL) S/S
55 D/C APR-17400
Tender to be floated50LILO of the exisiting 230 kV Ingur - Kurukathi -Palladam feeder at sanctioned Rasipalayam 400 kVS/S
6156 D/C MAR-17220
Tender under process40LILO of the exisiting 230 kV Myvady - Kurukathi -Pugalur feeder at sanctioned Rasipalayam 400 kV SS
8957 D/C DEC-18220
Dharmapuri 400 KV SS has been sanctioned. Hence, work will be taken upaccording to that BP.
200MTPS St.III - Singarpet 0 0 0 058 D/C JUN-16400
Work under progressAPR-1411Manali - Korattur 20 14 13 259 D/C JAN-16400
Note being put up to BOARD for specification approval and to call for tender9Manali - Pulianthoppe60 D/C APR-17400
Note being put up to BOARD for specification approval and to call for tender40Manali - Pulianthoppe S/S61 S/C APR-17400
Draft specification under preparation for obtaining Concurrence from JICA.APR-1722Manjakuppam - Korattur62 D/C 400
Works are nearing completion.One ckt radially energised from Kavanoor end.130Muthuramlingapuram - Kavanoor (Kamudhi) 229 229 229 12363 D/C MAR-17220
Work under progress. Cable laying work completed in 26/26 sections and136/150 Joints. 18/24 nos. Termination at Mylapore end completed.Balance terminations work under progress.
APR-1425Mylapore - Tharamani (UG Cable) 0 0 0 064 D/C MAR-17220
Commissioned 12/2016 (Loc. 15 to Loc. 130)APR-1434Neyveli - Eachengadu S/S 149 149 149 3465 S/C DEC-16220
Estimate is under scrutiny.APR-19380North Chennai 765 KV PS - Ariyalur 765 KV s/s66 D/C APR-18765
Work under progress.Reserve Forest clearance involved in 4 locations andproposal forwarded.
24Ottiyambakkam - Kits S/s 50 47 44 2167 D/C MAR-17220
works are under progress. 6 Locations under ROW issue.APR-1470Ottiyambakkam - Omega 150 141 141 3268 D/C MAR-17220
Laying and Jointing work completedAPR-121PH Road - Koyambedu (UG Cable) 0 0 0 069 D/C DEC-16220
Tower loc bet 160-190 court case WP NO 21202/2015 at Highcourt,Chennai.Erode collector enquiry conducted on 27.06.16. Orders toexecuted the work in original route has been received. Work will be taken up.
APR-1362Palladam - Ingur 249 239 209 3470 S/C onD/C
MAR-17220
Note being put up to BOARD for specification approval and to call for tender11Pulianthope - Pulianthoppe71 D/C APR-17400
Trasmission Lines: Page 66 of 91
Legends
TL: Total Location STC: Stubs Cast TE: Towers Erected STG: Stringing Completed
Schedule
1. 2. 5. 6. 7. 8. 9. 10. 12.3.
Revised/Anticipate
d
11.
Construction progress StatusTarget Date
RemarkTowers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hcKM
Ckts(S/C)
&(D/C)
Ready for Commissioning 06/16.AUG-1477Rasipalayam - Anaikadavu 115 115 115 7772 D/C JUN-16400
Work under progressJUN-17390Rasipalayam - Dharmapuri (Palavadi) 554 450 377 5973 D/C JUN-17400
Work under progress. ROW issues involved at 4 Locations. DistrictCollector/Dharmapuri approached for solving the issues and enter uponpermission granted. In the mean while, case filed at High Court.Next hearing on10.01.17
390Rasipalayam - Salem 558 556 555 37374 D/C MAR-17400
Work awarded and under progress.AUG-1631Shenbagapudur - Karuvalur 122 96 6575 S/C MAR-17220
LOA is under perusal.12Sholinganallur - Guindy76 D/C 400
Work under progress. Reserved forest clearence involved in 4 locations(Loc No: 22,23,41 & 42). Proposal sent and is being followed up.
24Sholinganallur - KITS 50 47 40 1777 D/C MAR-17220
LOA is under perusal.40Sholinganallur 400 kV S/S (Perumbakkam) - Guindy400 kV S/S
78 D/C APR-17400
Tender under process46Shoolagiri - Hosur S/s79 D/C 220
Line work is under modification. Revised administrative approval is underprocess.
SEP-0620Sriperumbudur -Korattur (Changing of conductor) 70 0 0 1280 S/C MAY-13220
Ready for Commissioning 06/16.MAR-15358Thappakundu - Anaikadavu 500 500 500 35881 D/C JUN-16400
Work under progressAPR-155Thervaikandigai - Korattur 9 9 782 D/C MAR-17400
Work under progressAPR-1574Thervaikandikai - Korattur 103 58 2383 D/C JUN-17400
Work completed and may be deleted from the list.40Thingalur Common Point-Gobi84 S/C MAR-14220
Work under progress. Cable laying in 24/24 sections completed. Joints 54/69nos. erected.
10Thiruverkadu - Ambattur 3rd Main road S/S85 S/C JAN-17220
Commissioned 12/2016.19Thudiyalur s/s - Common point at loc. 81 to 148(Associated line of Karamadai 400 KV s/s -single cktonly)
1986 S/C DEC-16220
Ready for commissioning 12/2016.MAR-1515Tirunelveli (Abishekapatty) - Kanarpatty 49 49 49 1587 S/C DEC-16400
Work awarded to M/s.Rahul Cables and under progress.5Tondiarpet - Pulianthope (UG Cable)88 S/C MAR-17220
Work under progress. Total Length of the line is 61.650 CkmSEP-1650Veeranam - Abhishekapatty (PGCIL) 11 11 7 5889 S/C MAR-17220
Work under progressSEP-1625Veeranam - Kodikurichi 85 83 490 S/C MAR-17220
It is proposed to reduce the UG cable route length from 20 km to 16.5 km basedon revised survey. The OH-UG co-ordinates finalized. Estimatesubmitted on 01.07.2016 . Revised bid document is under preparation
40Vellavedu - Guindy 400 kV S/S (U/G Cable)91 D/C APR-17400
Trasmission Lines: Page 67 of 91
Legends
TL: Total Location STC: Stubs Cast TE: Towers Erected STG: Stringing Completed
Schedule
1. 2. 5. 6. 7. 8. 9. 10. 12.3.
Revised/Anticipate
d
11.
Construction progress StatusTarget Date
RemarkTowers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hcKM
Ckts(S/C)
&(D/C)
Due to poor progress by the contractor, termination notice issued for terminationof the contract.For the balance works tender to be floated
MAR-1255Villupuram - Ulundurpet 183 164 8 092 S/C MAR-17220
Work awarded to M/s.Rahul Cables and under progress.2Vyasarpadi - Pulianthoppe (UG Cable)93 D/C MAR-17220
Trasmission Lines: Page 68 of 91
Legends
TL: Total Location STC: Stubs Cast TE: Towers Erected STG: Stringing Completed
Schedule
1. 2. 5. 6. 7. 8. 9. 10. 12.3.
Revised/Anticipate
d
11.
Construction progress StatusTarget Date
RemarkTowers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hcKM
Ckts(S/C)
&(D/C)
TRANSMISSION CORPORATION OF ANDHRA PRADESH LIMITED. (APTRANSCO)
Commissioned 07/16.21400 KV Karamadai S/S - 230 KV Thudiyalur S/S (Partof line from Loc. 1 to 81)
211 S/C onD/C
JUL-16220
130Chittoor 400 kV SS-Mananapalli2 D/C MAR-17220
Ready for commissioning 12/2016DEC-1018Gaddamvaripalli- Goddumari 31 31 31 183 D/C DEC-16220
70Garividi - Garividi4 D/C 220
100Garividi - Pydibhimavaram5 D/C 220
Commissioned 08/16.92Garividi - Tekkali (2nd Ckt) line 926 S/C AUG-16220
Works are under progress75Garividi-Bobbili 130 126 115 517 D/C DEC-16220
The purchase Order was issued on 31.03.2016. Works under progress.Hindupur - Uravakonda 349 137 828 D/C 400
Hindupur - Penukonda9 D/C 220
136Jammalamadugu - Betamacherla10 D/C 220
Line works are under progressJAN-15172Jammalamadugu - Chakrayapet 296 283 281 16411 D/C NOV-16220
Works are under progress. 10 Nos tower foundations and 2.8 km stringing inForest reach are pending for want of forest clearance.
JAN-15198Jammalamadugu - Porumamilla 338 328 327 19312 D/C OCT-16220
works are under progress.JUL-1454Jammalamadugu - Tirumalayapalli 89 80 6013 D/C DEC-16220
Ready for Commissioning 06/16.JUL-15255Jammalamadugu - Uravakonda 347 347 347 25514 D/C JUN-16400
Works under progress.300Kalpaka - Proposed Garividi S/S 358 286 232 3315 D/C JUN-17400
61Kalyandurg-Anantapur16 S/C DEC-16220
Works are under progress30Kamavarapukota - Kamavarapukota 16 7 0 017 D/C SEP-16220
90Kamavarapukota - Nuziveedu18 D/C 220
Ready for Commissioning 10/2016.SEP-15179Kamavarapukota - Surypet (Kamavarrapukota -Chinnakorukondi)
242 242 242 17919 D/C OCT-16400
Works are under progress.DEC-14200LILO of Both ckt Pulivendula - Hindupur at Gollapuram 91 66 41 020 D/C SEP-16220
Works are under progress140LILO of Pendurthy - Garividi at Garividi 202 29 0 021 D/C 220
80LILO of Podili - Nellore at Atmakur22 D/C 220
Shadnagar - Yeddumailaram line commissioned on 07.03.201412LILO of Shadnagar - Yeddumailaram atYeddumailaram
19 19 19 1223 D/C MAR-14220
Trasmission Lines: Page 69 of 91
Legends
TL: Total Location STC: Stubs Cast TE: Towers Erected STG: Stringing Completed
Schedule
1. 2. 5. 6. 7. 8. 9. 10. 12.3.
Revised/Anticipate
d
11.
Construction progress StatusTarget Date
RemarkTowers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hcKM
Ckts(S/C)
&(D/C)
22LILO of Uravakonda - Kalyandurga at Borampalli24 D/C 220
Works under progress.104LILO of both ckt 400kV RTPP (IV) - Chittoor at 400kVKalikiri S/S
127 5125 D/C 400
200Muddanur (RTPP) - Dharmavaram26 D/C 220
100Muddanur-Anantapur (3rd line)27 S/C onD/C
DEC-16220
Commissioned 04/16.4N P Kunta PS - 400 kV N P Kunta (PGCIL) S/S 428 D/C APR-16220
60Narketpally_Suryapet29 S/C onD/C
DEC-16220
All the works are completed except 0.11 Ckm of stringing of the lineNOV-1632Narnoor s/s - Gani S/S 50 50 50 3230 D/C JAN-17400
15Narsapur-Doultabad31 S/C DEC-16220
15Narsapur-Manoharabad32 S/C DEC-16220
20Nirmal-Nandipeta33 S/C DEC-16220
10Nizamabad-Janakampeta34 S/C DEC-16220
112Numa - Juyarni 166 165 162 7035 D/C JUN-16400
20Oddugudem-Koyagudem36 D/C DEC-16220
36Oglapur(Warangal 400 kV SS)-Warangal 220 kV SS37 D/C DEC-16220
MAY-15213Peddajanagampalli - Chittoor line 321 320 313 14838 D/C FEB-17400
Commissioned 06/16.121RTPP (Muddanur) - Chinakampalli 12139 D/C JUN-16220
MAY-15216Rayalaseema TPP - Peddajamgampalli line 321 308 299 15040 D/C FEB-17400
Commissioned 27.03.201317Rentachintala - Macherla S/S 58 58 58 1541 S/C MAR-13132
Commissioned 08/14.16Rentachintala - Nagarjuna Sagar Plant 34 34 34 1642 S/C AUG-14132
110Sattenapalli - Guntur43 D/C 220
Works under progress.220Sattenapalli 400kV s/s - Podili s/s 299 183 12644 D/C JUN-17400
20Somayajulapalli - Gani/Panyam S/S45 D/C 220
commissioned 11/2016.JUL-1543Tungabhadra river - Yemmiganur 57 57 57 4346 D/C NOV-16400
Trasmission Lines: Page 70 of 91
Legends
TL: Total Location STC: Stubs Cast TE: Towers Erected STG: Stringing Completed
Schedule
1. 2. 5. 6. 7. 8. 9. 10. 12.3.
Revised/Anticipate
d
11.
Construction progress StatusTarget Date
RemarkTowers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hcKM
Ckts(S/C)
&(D/C)
Works are under progress.MAR-1572Uravakonda - Borampalli 112 108 93 047 D/C DEC-16220
Works are under progress.NOV-14100Uravakonda - Kalyanduring 160 147 137 4248 D/C OCT-16220
Commissioned 06/16.DEC-1432Uravakonda - Vajrakarur 57 57 57 3249 D/C JUN-16220
Works under progress.Vemagiri - Kamavarapukota 268 65 36 050 D/C 400
The works are getting delayed due to severe resistance from farmers and landOwners through their lands. These people are demanding huge compensationthat the compenasation fixed up by Revenue authories and not allowing theworks to be carried out. Water logged areas, collasable soil, existing crops andfrequent rains are also the reasons for delay to take up the line works. However,construction activity is being continued with the help of Revenue and otherconerned authorites. Initially line length in RFD taken as 712 Ckm. Now the linelength is 485 Ckm.
NOV-15712Vizag TPP - Kamavarapukota 697 686 670 35051 D/C MAR-17400
84ppannadorapalem - Bobbili (Ckt-II)52 D/C 220
Trasmission Lines: Page 71 of 91
Legends
TL: Total Location STC: Stubs Cast TE: Towers Erected STG: Stringing Completed
Schedule
1. 2. 5. 6. 7. 8. 9. 10. 12.3.
Revised/Anticipate
d
11.
Construction progress StatusTarget Date
RemarkTowers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hcKM
Ckts(S/C)
&(D/C)
TRANSMISSIPN CORPORATION OF TELANGANA (TSTRANSCO)
Ready for Commissioned 08/16.14Budidampadu - Bhongiri (2nd Ckt) 24 24 24 141 D/C AUG-16220
WORK UNDER PROGRESS108Burgampadu (Common Point) - Manuguru 156 154 142 812 D/C MAR-17400
25Chilakallu - Narketpally 42 42 41 203 D/C JUL-16220
Work not commenced due to ROW Problem.200Gajwel - Narsapur 0 0 0 04 D/C AUG-17400
Ready for commissioning 12/201636Ghanapur - Marripally - Nagole (Uppal) 72 72 72 365 D/C DEC-16220
work under progress145Jagityal - Nirmal 202 200 200 1446 D/C MAR-17400
Stringing work is commenced.144Jaipuram - Jagityal 202 169 135 587 D/C MAR-17400
WORK UNDER PROGRESSMAR-1778Julurupadu - KTPS (Stage-VII) 118 101 54 168 D/C 400
WORK UNDER PROGRESSMAR-17222Julurupadu - Suryapet S/S 306 275 174 239 D/C 400
WORK UNDER PROGRESS112Julurupadu S/S - Burgampadu 157 133 112 3410 D/C MAR-17400
24Kalwakurthy-Dindi 3rd line11 S/C DEC-16220
15Kamareddy-Bhumpally12 S/C DEC-16220
Ready for Commissioning 10/2016SEP-15170Kamavarapukota - Surypet ( Chinnakorukondi -Suryapet)
234 234 234 17013 D/C OCT-16400
48LILO of (Ckt-II) of Miryalaguda - Khammam atSuryapet S/S
81 81 81 4414 D/C JUL-16220
42LILO of (Ckt-I) of Miryalaguda - Khammam at SuryapetS/S
68 68 68 4115 D/C JUL-16220
2LILO of Bhoothpur - Kalwakurthy at Thimmajipet 4 4 2 116 D/C AUG-16220
2LILO of Bhoothpur - Kalwakurthy at Thimmajipet (Ckt-II)
4 4 2 117 D/C AUG-16220
DEC-1314LILO of Budidampadu - Bhongiri at Waddekothapally18 D/C 220
24LILO of Chillakallu S/S - Narketpally line atHuzurnagar S/S
42 42 42 2219 D/C JUL-16220
Cable laying and jointing completed. OFC cable works in progress.18LILO of Ghanapur - Malkaram at Moulali20 D/C 220
3LILO of Srisailam - Mamidipally at Dindi S/s 11 11 9 021 D/C DEC-16400
Ready for commissioning 12/2016.34LILO of Vizag - Khammam (Ckt-I) at Asupaka 49 49 49 3422 D/C DEC-16400
Works are under progress.11LILO of Wanaparthy - Ragimanagadda at 17 15 14 923 D/C JUL-16220
Trasmission Lines: Page 72 of 91
Legends
TL: Total Location STC: Stubs Cast TE: Towers Erected STG: Stringing Completed
Schedule
1. 2. 5. 6. 7. 8. 9. 10. 12.3.
Revised/Anticipate
d
11.
Construction progress StatusTarget Date
RemarkTowers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hcKM
Ckts(S/C)
&(D/C)
Singotam X Road SS
24LILO of one Ckt of Chilakallu - Narkatpally at SuryapetS/S
40 22 0 024 D/C JUL-16220
Commissioned 05/16. (Late Reported).21Lower Jurala HEP - Upper Jurala 36 36 36 2125 D/C MAY-16220
All works completed and line commissioned on 03.11.201411Mamidipally S/S M/s K.S.K. Photo Voltaic near FabcityRavirala (V)
37 37 37 1126 D/C JUL-14220
Works are under progress.13/14 Nos Cable joints completed and remainingworks are under progress
14Marripally common point- Hayatnagar S/S XLPE cable 827 DC UGcable
MAY-16220
commissioned 10/2015 (Late Reported).9Moulali - Osmania University 928 DC UGcable
DEC-16220
Severe R.O. W Problem.Work is under progress222Nandiwanaparthi - Shankarpalli 315 313 309 18029 D/C JAN-17400
Commissioned 07/16. (Late Reported).40Parigi - Kosigi line 128 128 128 4030 D/C JUL-16220
Commissioned 04/16.90Parigi 220 kV S/S - Shankarpally 400 kV S/S 9031 D/C APR-16220
Commissioned 10/2016 (Late Reported)74Pulichintala HEP - Huzurnagar line 132 132 132 7432 D/C NOV-16220
Commissioned 04/16.34Ramagundam - Mandamarri (Bellampally) (2nd Ckt) 3433 D/C APR-16220
Work awarded to L&T/KEC in 9/2015 with completion period of 15 months.298Singareni - Nirmal 17434 D/C JUN-17400
Ready for Commissioning 08/16.240Suryapet - Nandiwanaparthi line 343 343 343 24035 D/C AUG-16400
Severe ROW problems462Suryapet - Shankarpalli 658 654 647 38536 D/C SEP-16400
240Vadarevu - Amangal 0 0 0 037 S/C AUG-16765
Commissioned 11/2016.147Veltoor - Thungabhadra River (Q) line 200 200 200 14738 D/C NOV-16400
80Veltur-Thimmajipet 127 127 122 4239 D/C AUG-16220
Works are in progress135Yeddumailram - Pargi 137 137 137 9040 D/C 220
Trasmission Lines: Page 73 of 91
Legends
TL: Total Location STC: Stubs Cast TE: Towers Erected STG: Stringing Completed
Schedule
1. 2. 5. 6. 7. 8. 9. 10. 12.3.
Revised/Anticipate
d
11.
Construction progress StatusTarget Date
RemarkTowers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hcKM
Ckts(S/C)
&(D/C)
TRIPURA STATE ELECTRICITY CORPORATION LIMITED (TSECL)
AGTP - Agartala line1 D/C 132
AGTP - Kumarghat line2 S/C 132
ROW problems affected the work31Gamai Tilla - Dhalabil 107 101 78 173 S/C SEP-13132
20LILO of Rokia - Udaipur at Melaghat for connection toMonoarchak
40 0 0 04 D/C JUN-15132
Work in progress.42Monarchak - Surajmani Nagar 150 49 38 65 D/C SEP-16132
All works completed in non forest land. Stage- I clearance received andcompliance for conditions completed.
47P.K. Bari - Kanchanpur 113 109 99 176 S/C MAR-15132
Completed 9/1318Surajmani Nagar - Agartala 79 Tilla Grid S/S 71 71 71 187 D/C SEP-13132
Fund proposed in World Bank.6Surajmani Nagar - Badarghat 0 0 0 08 D/C AUG-16132
Completed 9/133Surajmani Nagar - Rabindra nagar 13 13 13 39 D/C SEP-13132
3.598 KM line in forest land for which TSECL will apply for forest clearance. LOAissued
20Surajmani Nagar - Rokhia 80 32 5 010 D/C DEC-14132
Proposed under NEC.50Surajmani Nagar - Udaipur 50 0 0 011 D/C JUN-15132
Fund not yet tied up. Proposed under World Bank Financing /SPA/NEC.260Surajmani nagar-P.K.Bari 0 0 0 012 D/C MAR-17400
Trasmission Lines: Page 74 of 91
Legends
TL: Total Location STC: Stubs Cast TE: Towers Erected STG: Stringing Completed
Schedule
1. 2. 5. 6. 7. 8. 9. 10. 12.3.
Revised/Anticipate
d
11.
Construction progress StatusTarget Date
RemarkTowers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hcKM
Ckts(S/C)
&(D/C)
U.P. POWER TRANSMISSION CORPORATION LTD. (UPPTCL)
Row at 2 locations resolved, Fdn & Erec WIP.24132 kV D/C Agra cantt. - 400 kV Agra(South) 44 42 41 201 D/C JAN-17132
WIP, ROW at loc no 141,143,144 & 30, Rly Xing approval pending.138220 KV D/C Sohawal PG - Barabanki line 225 221 220 572 D/C JAN-17220
Commissioned 06/16.14400 kV Gonda - 220 kV Gonda Interconnector (oneckt)
143 D/C JUN-16220
WIPAUG-16142Agra (UP) - Mathura line 382 382 382 1404 S/C JAN-17400
Foundation & Erection work complete, Stringing work in progress.AUG-16139Agra(UP) - Agra (South) 203 203 203 595 D/C JAN-17400
WIPMAR-1669Aligarh - Atrauli 125 102 78 226 D/C JAN-17220
Almost complete.190Aligarh - Sikandarabad 258 258 258 1887 D/C JAN-17400
Work yet to be awarded.Allahabad (PG) - Rewa Road (Allahabad)8 D/C 400
1) Rly X-ing- Demand note awaited from Rly.Stringing Work in progress.
350Allahabad - Banda Line 484 484 482 1739 D/C JAN-17400
Commissioned 09/16.5Anpara B - Anpara D (2nd ckt) 23 23 23 510 D/C SEP-16400
Tree cutting identification done. Action is pending with DFO,Kaimoor. power linecomplete, OPGW stringing in progress.
JAN-12416Anpara D - Unnao 1225 1107 1033 33411 S/C JAN-17765
Work to be taken up after completion of lines at S. No. 1,2&3.43Aurai - Mizapur 147 129 82 012 S/C JAN-17220
Work to be taken up after completion of lines at S.No. 1,2&3.71Aurai - Phoolpur 216 210 195 4813 S/C JAN-17220
Commissioned 05/16.15Baghpat - Baghpat (PG) 56 56 56 1514 S/C MAY-16220
Commissioned 06/16.74Bahraich - 400 kv Gonda line (one ckt.) 7415 D/C JUN-16220
Charged on 31.10.1119Balrampur - Utraula 56 56 56 1916 S/C OCT-11132
Foundation, Erection work along with Stock verification in progress.216Banda - Orai DCQ 295 276 121 017 D/C JAN-17400
26.05.14 Barkhera-pilibhit Section, Ickt. Energised on10.02.12. II ckt. On 14.2.12Barkhera (Bajaj) - Dohna 203 203 203 12918 D/C MAR-15132
Bayas - Dohna19 D/C 132
Bayas - Pilibhit20 D/C 132
.Bhognipur - Gatampur21 S/C 765
Bhognipur - Jawarharpur22 S/C 765
Bhognipur - Moradabad/Rampur23 S/C 765
.Bhognipur - Orai (PG)24 2xS/C 765
Trasmission Lines: Page 75 of 91
Legends
TL: Total Location STC: Stubs Cast TE: Towers Erected STG: Stringing Completed
Schedule
1. 2. 5. 6. 7. 8. 9. 10. 12.3.
Revised/Anticipate
d
11.
Construction progress StatusTarget Date
RemarkTowers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hcKM
Ckts(S/C)
&(D/C)
Bilhaur - Sandila25 S/C 765
Bilhaur - Kanpur (PG)26 D/C 400
Line Changed New Line is Hapur(765)-Faridnagar.40Dasna (400) - Faridnagar 0 0 0 027 S/C DEC-16220
11 KV lines to be shifted, SEW intimated their personnel shall be reaching siteshortly.
83Deoria - Rasra 253 253 253 8228 S/C JAN-17220
1. PTCC clearance is still pending at Delhi, M/s SEW haS not submitted revisedPTCC proposal & surveyer has not been deployed in spite of repeated requestsand their promises. 2. Erec & Strg gangs to be deployed by 15.10.2016 notdeployed yet, being persued . 3. Firm reported that revetment has to be doneon six locs to complete the work , SE Bareilly to finalise.
48Dohna - C.B. Ganj 92 92 88 3629 S/C JAN-17220
.Dopaha - Anpara30 D/C 765
Dopaha - Ghazipur31 D/C 765
Dopaha - Varanasi / Jaunpur32 D/C 765
Strg WIP.Dumariaganj- - Utraula 114 114 113 3833 S/C JAN-17132
.Ghatampur - Moradabad / Rampur34 2xS/C 765
Ghatampur - Kanpur (PG)35 D/C 400
Ghazipur - Varanasi / Jaunpur36 S/C 400
Line completed.41Gokul-Mitai(Hathras) 134 134 134 4137 S/C JAN-17220
WIP.460Gonda - Shahjehanpur (PG) 543 295 14038 D/C DEC-16400
23Gr. Noida - JPSK 0 0 0 039 S/C 220
1. Foundation & Erection work is in progress.2.Shutdown applied for HVDC electrode line of PGCIL.
88Gr. Noida - Noida (Quad) 148 146 146 8540 D/C JAN-17400
Commissioned 08/16.60Hardoi - Shahjahanpur (PG) line 6041 D/C AUG-16220
Line to be constructed on Monopole. Held up16Indirapuram - Pratap Vihar 0 0 0 042 D/C 220
Jawaharpur - G Noida43 D/C 765
Jawaharpur - Agra (UP)44 D/C 765
Jawarpur - Mainpuri45 D/C 765
Khurja - Hapur46 S/C 765
Trasmission Lines: Page 76 of 91
Legends
TL: Total Location STC: Stubs Cast TE: Towers Erected STG: Stringing Completed
Schedule
1. 2. 5. 6. 7. 8. 9. 10. 12.3.
Revised/Anticipate
d
11.
Construction progress StatusTarget Date
RemarkTowers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hcKM
Ckts(S/C)
&(D/C)
Commissioned 09/16.1LILO 220 kV of Muradnagar - Shamli at Baghpat 20 20 20 147 S/C SEP-16220
LILO Mainpuri (PG) - Harduaganj at Jwrpur48 D/C 220
ROW at 7 locations, Administrative help required Erec WIP, letter from MDUPPTCL written to DM.
12LILO of 132 kV Bodla - Kheragarh at 400 kV Agra(South)
18 11 10 049 D/C JAN-17132
Erec. WIP, ROW at balance 05 locations Administrative help required, letter fromMD UPPTCL written to DM. being pursued locally.
12LILO of 132 kV Kirawaki-Mathura at 400 kV Agra(South)
25 20 1650 D/C JAN-17132
Fdn & Erec WIP.20LILO of 132 kV Shamshabad- 400 kV Agra (South) at132 kV Gwalior Road
30 29 19 051 D/C JAN-17132
01 no Fdn gang is working, ROW at 01 locs, EE asked to persue ROW ofbalance location with with local Administration.
12LILO of 132 kV Shamshabad-Kheragarh at 400 kVAgra(South)
21 19 19 552 D/C JAN-17132
WIP120LILO of 220 kV Hathras-Gokul at 400 kV s/s Mathura 185 161 120 1653 D/C JAN-17220
Commissioned 09/16.68LILO of 220 kV Mainpuri (PG) - Mainpuri line atSirsaganj
6854 D/C SEP-16220
Commissioned 09/16.157LILO of 220 kV Orai - Mainpuri line at Bah S/S 258 258 258 15755 D/C SEP-16220
Commissioned 06/16.10LILO of 220 kV Parichha - Banda line at Mahoba 1056 D/C JUN-16220
Commissioned 09/16.AUG-16156LILO of 400 kV Agra (UP) - Muradnagar 400 kV S/Cline at Agra (UP) 765/400 kV S/S
219 219 219 15657 D/C SEP-16400
Foundation work complete, Erection & Stringing work in progress.AUG-1664LILO of Agra - Muradnagar at Mathura 88 88 86 2058 D/C JAN-17400
LILO of Agra - Muradnagar at Kurja59 D/C 4.4
Almost complete.LILO of Aligarh - Sikandarabad 258 258 258 18860 D/C JAN-17400
LILO of Anpara - Mau at Ghazipur61 D/C 400
Work not Started.120LILO of Azamgarh - Sultanpur at Tanda62 D/C 400
WIP.90LILO of Bhauti - Orai at Sikandara 104 95 31 063 D/C JAN-17220
LILO of Bhognipur - Mbd at Bilhaur64 D/C 765
LILO of Ghatampur - Mbd at Sandila65 D/C 765
04 no Erec gangs working in the meeting on 25.11.2016, Firm assured tocomplete line by 15.01.17
40LILO of Gorakhpur - Basti at Bansi 155 151 69 066 S/C JAN-17220
Commissioned 06/16.3LILO of Harduaganj - Mainpuri S/C line at SikandraRau
367 D/C JUN-16220
LILO of Mainpur (765) Aligarh (400) at Jwrpur68 D/C 400
LILO of Mainpur - Etah at Jwrpur69 D/C 220
Trasmission Lines: Page 77 of 91
Legends
TL: Total Location STC: Stubs Cast TE: Towers Erected STG: Stringing Completed
Schedule
1. 2. 5. 6. 7. 8. 9. 10. 12.3.
Revised/Anticipate
d
11.
Construction progress StatusTarget Date
RemarkTowers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hcKM
Ckts(S/C)
&(D/C)
LILO of Mainpuri - Gr Noida at Khurja70 D/C 765
ROW held in location no.- 5/0, 30/3, 45/0 and 46/0.60LILO of Meza - Rewa Road at Masuli (Allahabad) 104 101 90 2271 D/C JAN-17400
.104LILO of Mohanpur - Behat line72 S/C 220
01 no Fdn gang & 01 no Erec gang working.30LILO of Muradnagar - Loni at Ataur 26 16 8 073 S/C JAN-17220
Line has been completed but can't be charged due to non completion of 220 KVBay at 400 KV S/s Orai.
6LILO of Orai - Bhauti at Orai 15 15 15 474 S/C JAN-17220
.LILO of Panki - Muradnagar at Jwrpur75 D/C 400
Work not Started.LILO of Sarnath - Azamgarh at Varanasi / Jaunpur76 D/C 400
12LILO of Unnao - Bareilly at Shahjahanpur77 D/C 400
.LILO of Unnao - Mainpur at Bilhaur78 D/C 765
Ready for Commissioning 09/16.AUG-1673LILO of one ckt of 400 kV Agra (UP) - Agra (PG) 400kV D/C line at Agra (UP) 765/400 kV S/S
100 100 100 7379 D/C SEP-16400
Ready for commissioning 09/16.AUG-16337Lalitpur TPS - Agra (UP) Ckt-I 955 955 955 33780 S/C SEP-16765
WIPAUG-16334Lalitpur TPS - Agra (UP) Ckt-II 902 902 897 28981 S/C JAN-17765
Commissioned 08/16.30Lucknow PG (400) - Kursi Road 67 67 67 3082 D/C AUG-16220
220Mathura - Jawaharpuram83 D/C 400
Line charged on 22.12.16 from reverse side.66Mathura(4) -Chhata line 119 119 119 3484 D/C DEC-17220
Meja - Bargarh85 D/C 765
Land not finalised.36Morti - Pratap Vihar 0 0 0 086 D/C 220
Charged on 30/09/15.0Muradnagar-Agra line 087 D/C SEP-15400
Commissioned 04/16. (Late Reported.)216Roza - Dohna 340 340 340 21688 D/C APR-16220
Firm is not turning up.104Saharanpur (PG)-Behat89 D/C MAR-17220
Commissioned 05/16.29Sahupuri-Bhelupur 39 39 39 2990 D/C MAY-16220
Sandila - Farrukhabad91 S/C 400
Sandila - Lucknow Hardoi Road92 S/C 400
Line withdrawn from the scope of M/S SEW.110Sitapur - Nighasan 336 336 328 9493 S/C JAN-17220
Work held up due to Fdn ROW at loc. No.23,140,151,152,157,190,248,248A,248B,249 & 250 . Erection ROW at loc no.6,15,137,145, 176 & Stringing ROW at loc. No. 210, 211, 219,
185Sohawal - Tanda 348 337 309 10794 D/C JAN-17220
Trasmission Lines: Page 78 of 91
Legends
TL: Total Location STC: Stubs Cast TE: Towers Erected STG: Stringing Completed
Schedule
1. 2. 5. 6. 7. 8. 9. 10. 12.3.
Revised/Anticipate
d
11.
Construction progress StatusTarget Date
RemarkTowers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hcKM
Ckts(S/C)
&(D/C)
283, 284, 285, 286 & 287 to be resolved by field level.
WIP200Tanda - Gonda 241 97 54 095 D/C JAN-17400
Varanasi / Jaunpur - Gorakhpur96 D/C 400
Varanasi/Jaunpur - Aurai97 D/C 400
Varanasi/Jaunpur - Azamgarh98 D/C 400
Varanasi/Jaunpur - Meja99 D/C 765
Trasmission Lines: Page 79 of 91
Legends
TL: Total Location STC: Stubs Cast TE: Towers Erected STG: Stringing Completed
Schedule
1. 2. 5. 6. 7. 8. 9. 10. 12.3.
Revised/Anticipate
d
11.
Construction progress StatusTarget Date
RemarkTowers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hcKM
Ckts(S/C)
&(D/C)
WEST BENGAL STATE ELECTRICITY TRANSMISSION CO. LIMITED (WBSETCL)
MAY-1713Alipurduar - Alipurduar (PG) 25 14 4 01 D/C AUG-17220
JAN-17340Gokarna - N. Chanditala 514 386 85 02 D/C DEC-17400
Commissioned 05/16.APR-16107Kharagpur - Egra 205 205 205 1073 D/C MAY-16220
SEP-16277Kharagpur - N. Chanditala 407 405 398 2204 D/C MAR-17400
APR-19LILO of 132 kV One Ckt of Rammam-II - NBU atRammam -III HEP
5 D/C 132
FEB-1794LILO of Arambag - Durgapur 400 kV S/C at N.Chanditala
128 74 8 06 D/C MAR-18400
SEP-162LILO of Arambag - PPSP 400 kV D/C at N. PPSP 4 4 2 07 D/C DEC-16400
AUG-1731LILO of Arambag - Rishra at N. Chanditala 63 30 17 08 D/C AUG-17220
CompletedSEP-1613LILO of Bakreswar - Gokarna at Sadaipur 25 25 25 129 D/C MAR-17220
FEB-1711LILO of Gokarna Sagardighi TPS at Sagardighit (GIS) 21 19 18 910 D/C APR-17220
FEB-1736LILO of Howrah - Foundry Park at N. Chanditala. 36 33 20 211 D/C onM/C
FEB-17220
CompletedFEB-1712LILO of Jeerat - KTPS 400 kV S/C at N. Chanditala 22 22 22 1212 D/C+S/C
JAN-17400
FEB-178LILO of Jeerat - Kasba at Barasat 11 5 2 013 D/C onM/C
APR-17200
AUG-1714Rajarhat (PG) - N. Town II C 58 2 1 014 D/C DEC-17220
APR-19Rammam-III - NJP line15 D/C 132
JUL-1589Sagardighi - Gokarna 154 152 140 1416 D/C MAR-17400
PGCIL is executing the work as a deposit work of WBPDCL. The work is stalleddue to repeated theft. WBPDCL asked PGCIL to take up with the present vendorfor resumption of work or deploy a new vendor by cancelling the existingcontract.
OCT-08224Santaldhi TPS - Bishnupur 347 347 325 19317 D/C JUN-16220
AUG-1758Subashgram (PG) - Baruipur 117 8 0 018 D/C AUG-17220
SEP-0821Teesta LDP -III - Teesta LDP-IV 94 87 72 1319 S/C MAR-17220
Trasmission Lines: Page 80 of 91
Legends
TL: Total Location STC: Stubs Cast TE: Towers Erected STG: Stringing Completed
As on 31-DEC-2016
Schedule
1. 2. 5. 6. 7. 8. 9. 10. 12.3.
Revised/Anticipate
d
11.
Construction progress StatusTarget Date
RemarkTowers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hcKM
Ckts(S/C)
&(D/C)
ADANI POWER LTD. (APL)
MAR-19128Aurangabad - Padghe 169 7 0 01 D/C 765
MAR-19322Bilaspur - Rajnandgaon 419 174 85 02 D/C JUL-18765
NOV-1849Champa -Dharmajayagarh (Quad) 143 70 36 03 S/C JAN-18765
MAY-1898Gwalior - Morena (Quad) 152 59 5 04 D/C JAN-18400
CommissionedLILO of Korba-Mopka at Swastic TPP 1325 D/C 132
MAR-19169LILO of one ckt of Aurangabad - Padghe (hexa) atPune
169 14 3 06 D/C MAY-18765
NOV-1894Raigarh - Champa (Quad) 247 139 69 07 S/C JAN-18765
NOV-1880Raipur - Rajnandgaon 105 77 52 08 D/C JUL-18765
NOV-18532Rajnandgaon - Warora 689 153 83 09 D/C JUL-18765
NOV-186Sasan - Vindhyachal (Quad) 18 4 0 010 S/C JAN-18765
MAR-1942Sipat - Bilaspur (Quad) 62 18 13 011 S/C NOV-17765
JAN-1954Vindhyachal - Vindhyachal (Quad) 82 34 0 012 D/C JAN-18400
ATHENA CHHATTISGARH POWER LIMITED (ACPL)
Commissioned 4/16 (Late Reported)50Athena Singhitarai - Raigarh Pooling Station (nearKotra)
75 75 75 501 D/C MAY-16400
BAJAJ ENERGY PVT. LTD. (BEPL)
Existing line.Balrampur-Utraula line1 D/C 132
BHARAT ALUMINIUM CO. LTD. (BALCO)
Commissioned 06/2016 (Late Reported).46Balco - Dharamjaygar Pooling Station 72 72 70 461 D/C DEC-16400
CORPORATE POWER LTD. (CPL)
6Corporate TPP - Jharkhand Pooling Station 111 D/C AUG-16400
.216Latehar - Namkum 320 293 274 1322 D/C AUG-16400
Costal Energen Private Limted (CEPL)
Commissioned 10/201624Mutiara TPP(Coastal Energen Gen. Switchyard) -Tuticorin Pooling Station (Balance portion)
32 32 32 241 D/C OCT-16400
Trasmission Lines: Page 1 of 11
Legends
TL: Total Location STC: Stubs Cast TE: Towers Erected STG: Stringing Completed
Schedule
1. 2. 5. 6. 7. 8. 9. 10. 12.3.
Revised/Anticipate
d
11.
Construction progress StatusTarget Date
RemarkTowers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hcKM
Ckts(S/C)
&(D/C)
D.B.POWER CORP. LTD. (DBPCL)
Line completed. (Interim)30LILO of Raigarh - Raipur (3rd Ckt) at Baradhara TPP (Interim arrangement)
44 44 44 301 D/C MAY-13400
DANS ENERGY PVT. LTD. (DEPL)
Commissioned 11/2016.(Interim connection removed- LILO on one ckt of NewMelli - Rangpo D/C tr. Line at Jorethang ).
20Jorethang HEP - New Melli 35 35 35 201 D/C NOV-16220
DIRANG ENERGY PVT. LTD. (DEPL)
Gongri - Dinchang Pooling Station1 D/C 220
ESSAR POWER TRANSMISSION CO. LTD. (EPTCL)
Executing agency has mobilized the T&P and TSEs machine at site to start thework. Due to severe RoW issues, local disputes & resistance from farmers theprogress has badly hampered. Delay of fund disbursement is also played amajor role in delay of project progress. EPTCL is working on resolving the fundissue for completion of the balance work on priority.
670Mahan -Sipat 942 938 909 3941 D/C DEC-17400
.Navbharat TPP - Angul P.S. (PG)2 D/C 400
.Tori - Jhharkhand Pooling Station3 D/C 400
Essel Infra Projects Ltd. (ESSEL)
252Babai - Bhiwani1 D/C 400
370Hyderabad - Kurnool2 D/C 765
SEP-16278Kurukshetra - Malerkotla line 377 377 377 2783 D/C JAN-17400
a)b)Forest approval is pending. Due to non-receipt of forest approval, approx.12Km. of stringing stretches are affected.b)RoW severe at remaining 1 locations in Ckt-1 and 02 locations in Ckt-2affecting the construction work.
JUL-16152LILO of both ckt Barh - Gorakhpur at Motihar 210 207 202 1144 D/C FEB-17400
a)Affected Forest Approval (Punjab Portion) due to NGT Order: Stage I approvalgranted on 16th Sept 2016, which is subject to final Order of Honble NGT in thesubjudice matter of OA 161 & 162 of 2016, regarding tree cutting in the state.Even though the Stage I Forest Clearance is received, the tree cutting is notbeing allowed due to NGT Order.
SEP-16298Malerkotal - Amritsar line 414 409 405 2385 D/C JAN-17400
Trasmission Lines: Page 2 of 11
Legends
TL: Total Location STC: Stubs Cast TE: Towers Erected STG: Stringing Completed
Schedule
1. 2. 5. 6. 7. 8. 9. 10. 12.3.
Revised/Anticipate
d
11.
Construction progress StatusTarget Date
RemarkTowers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hcKM
Ckts(S/C)
&(D/C)
b)Severe RoW at remaining 5 locations foundation.
a)High density of trees affecting the construction work as lot of resistance isbeing faced at site.b)RoW at 1 No locations/stretches is affecting the construction work.
JUL-16129Muzaffarpur - Darbhanga line 178 178 176 1226 D/C JAN-17400
86Rishikesh - Koteshwar7 D/C 400
240Sohwal - Lucknow8 D/C 400
186Tanda - Sohwal9 D/C 400
478Warangal - C Peta10 D/C 765
270Warangal - Hyderabad11 D/C 765
108Warangal - Warangal12 D/C 400
666Warora - Warangal13 D/C 765
GATI INFRASTRUCTURE LTD. (GATI)
Line commissioned.Chujachen HEP - Rangpo PS1 D/C 132
Commissioned 04/13. (Interim arrangement)47LILO of Melli - Gantok at Chuzachen (LILO point atnamthang)
91 91 91 472 D/C APR-13132
Work yet to be awarded.10LILO of one circuit of Chujachen - Rangpo line atBhasmay
3 2xS/C MAY-18220
GMR ENERGY LIMITED (GMR ENERG)
.Alaknanda HEP - Joshimath1 D/C 220
For start up power,work completed 5/12.1LILO of Talchar -Meramundli at Kamalanga TPP 3 3 3 12 D/C MAY-12400
GUPTA ENERGY PVT. LTD. (GEPL)
.LILO of one ckt of Bhadrawati -Parli at GEPL TPS1 D/C 400
HIMGIRI HYDRO ENERGY PVT LTD (HHEPL)
Panan HEP - Mangan1 2xD/C 220
HINDUJA NATIONAL POWER CORP (HNPC)
Commissioned 05/14. for startup power.15Vizag ( Hinduja) TPP - Kalpaka 25 25 25 151 D/C MAY-14400
IDEAL ENERGY PROJECTS LTD. (IEPL)
Trasmission Lines: Page 3 of 11
Legends
TL: Total Location STC: Stubs Cast TE: Towers Erected STG: Stringing Completed
Schedule
1. 2. 5. 6. 7. 8. 9. 10. 12.3.
Revised/Anticipate
d
11.
Construction progress StatusTarget Date
RemarkTowers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hcKM
Ckts(S/C)
&(D/C)
Completed (Interim)0LILO of Mouda - Wardha at Bela 2 2 2 01 D/C NOV-12400
IL & FS TAMIL NADU POWER COMPANY LIMITED (ITPCL)
Commissioned 01/15. (Late reported.)95Cuddalore - Naggapattinam 138 138 138 951 D/C JAN-15400
IND BHARATH POWER INFRA LIMITED (IBPIL)
Line completed but could not be charged as trees cutting is under progress.84Ind Barath - Jharsuguda pooling Station 125 125 125 841 D/C DEC-16400
47LILO of Rouekila - Raigarh at Ind Barath 72 72 72 472 D/C JUN-15400
ISPAT ENERGY LTD (ISPAT)
Under planning stage by WBSETCL.180Haldia TPP - Egra1 D/C 220
5Haldia TPP - Haldia (New) 15 15 5 02 D/C JUL-16220
JAIN ENERGY TRADING LTD (JAIN ETL)
.Jain Energy TPS - Dharamjaygarh Korba Poolingstation
1 D/C MAR-17400
JAL POWER CORP. LTD. (JPCL)
Work of 220kV line has been awarded to M/s. Ashish Infratech and completionperiod is 8 months from start of work. Generation project will take about 2½years for completion as against 8 months for completion of associatedtransmission line, there will be no mismatch for evacuation of power. It may alsobe mentioned that route survey of transmission line has been completed anddesign work of transmission system including towers (15 nos.) has also beencompleted. 220kV GIS bays at PGCIL substation at New Melli have also beenawarded to M/s. PGCIL as deposit work. Line length is 3.3 KM. Associatedtransmission system comprises of 220kV GIS in PH building, 3.3 km long 220kVD/C line from PH to PGCIL pooling station at New Melli. Work for 220kV GISsubstation at PH has been awarded to M/s. Siemens and GIS equipment hasalready been delivered at site.
7Rangit IV - New Melli line 151 D/C MAR-19220
KALPATARU POWER TRANSMISSION LIMITED (KPTL)
234Alipurduar (PG) - Siliguri (PG)1 D/C 400
420Kishanganj(PG) - Darbhanga (DMTCL)2 D/C 400
Trasmission Lines: Page 4 of 11
Legends
TL: Total Location STC: Stubs Cast TE: Towers Erected STG: Stringing Completed
Schedule
1. 2. 5. 6. 7. 8. 9. 10. 12.3.
Revised/Anticipate
d
11.
Construction progress StatusTarget Date
RemarkTowers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hcKM
Ckts(S/C)
&(D/C)
KORBA WEST POWER COMPANY LIMITED (KWPCL)
Commissioned 05/2016 (Late Reported)37Avantha Bhandar TPS (Korba West) - Raigarh (Kotra) 64 64 64 371 D/C DEC-16400
Interim arrangement.10LILO of on Ckt of Raigarh - Raipur at AvanthaBhandar (Korba west ) TPS
22 22 22 102 D/C DEC-13400
KVK ENERGY PVT. LTD. (KVK)
Work yet to Start.16LILO of Mendasal - Baripada at Nilanchal TPP 0 0 0 01 D/C JUN-16400
Kudgi Transmission Company Limited (KTCL)
Commissioned 08/16.DEC-15185Madhugiri - Bidadi 256 256 256 1851 D/C AUG-16400
Ready for Commissioning 09/16.DEC-15758Narendra (New) - Madhugiri 867 867 867 7582 D/C SEP-16765
LANCO ENERGY (P) LTD,. (LEPP)
Work yet to start.48Babandh TPP - Angul Pooling Station 72 0 0 01 D/C DEC-16400
15LILO of Seoni - Wardha at Lanco Vidarbha TPS 162 D/C MAR-17765
.95Lanco Amarkantak - Champa Pooling Station 158 96 12 03 D/C JUN-16400
8Phata HEP-Baramwari (Rudrpur) 20 0 0 04 D/C DEC-16220
Work in generation project is stopped for since 2013.Routing of one circuit of Jorthong - New Melli viaRangit - IV
5 D/C MAR-19220
Detail survey completed section 164 approval received. Work yet to started.25Teesta VI HEP - Rangpo Pooling Station6 D/C 220
MADHYA BHARAT POWER CORPORATION LIMITED (MBPCL)
Rongnichu - Rangpo Pooling Station1 D/C 220
MALANA POWER COMPANY (MPCL)
Chango Yangthang - Ka Dogri Pooling Station1 D/C 220
.Ka Dogri - Jangi Pooling Station2 D/C 400
MONNET POWER COMPANY LIMITED (MPCL)
62Malibrahmani - Angul 108 100 80 201 D/C JUL-16400
NORTH EAST TRANSMISSION CO. LTD. (NETC)
Stringing Completed but cannot be commissioned since loop out42Byrnihat - Azara (1st ckt) 124 124 124 421 D/C JUL-14400
Trasmission Lines: Page 5 of 11
Legends
TL: Total Location STC: Stubs Cast TE: Towers Erected STG: Stringing Completed
Schedule
1. 2. 5. 6. 7. 8. 9. 10. 12.3.
Revised/Anticipate
d
11.
Construction progress StatusTarget Date
RemarkTowers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hcKM
Ckts(S/C)
&(D/C)
arrangement by Meghalaya State Electricity Board is not ready at Byrnihat 400kV S/S.
NORTH KARANPURA TRANSMISSION CO. LTD. (NKTCL)
NOV-13220Agra - Gurgaon1 D/C DEC-16400
NOV-13240Bareilly - Meerut2 S/C DEC-16765
NOV-1320Gurgaon - Gurgaon (PG)3 D/C DEC-16400
NOV-13220Lucknow - Bareilly4 S/C DEC-16765
NOV-13334Seoni - Sipat / Korba (Pooling).5 S/C DEC-16765
NSL NAGAPATNAM POWER PVT. LTD. (NSLNPPL)
Project Authority intimated that PGCIL yet to award construction of work.46NSL TPP - Angul 0 0 0 01 D/C 400
PATRAN TRANSMISSION COMPANY LIMITED (PATRANTCL)
Commissioned 06/16.MAY-161LILO of both ckt of Patiala - Kaithal at Patran 2 2 2 11 D/C JUN-16400
RELIANCE POWER TRANSMISSION LTD. (RPTL)
.Moti Khavdi TPP - Jam Nagar1 D/C 400
RKM POWERGEN PVT. LIMITED (RKMPPL)
Commissioned (Interim Arrangement). De-LILO activity completed.LILO of Raigarh (Kotra) - Raipur at Uchpinda (InterimArrangement)
73 73 73 391 D/C 400
Commissioned 10/2016 (41.42 CKm on D/C & 11 CKm on M/C)53Uchpinda (RKM Powergen Private Ltd.) - Kotra s/s(Raigarh) line
88 88 88 532 D/C OCT-16400
SHIGA ENERGY PVT. LTD. ()
In a recent meeting at CEA, CEA has asked KEC to complete the Tr. line worksby DEC 2016.
17Tashiding - Legship 23 22 20 121 D/C DEC-16220
SIKKIM HYDRO POWER LIMITED (SHPL)
LILO of one ckt of Legship - New Melli at Rangit-II1 D/C 220
SKS POWER GENERATION LTD. (SKS)
Interim arrangement removed.LILO of one ckt of Raigarh - Raipur at Binjkote TPP1 D/C 400
SPECTRUM COAL & POWER LTD. (SCPL)
Trasmission Lines: Page 6 of 11
Legends
TL: Total Location STC: Stubs Cast TE: Towers Erected STG: Stringing Completed
Schedule
1. 2. 5. 6. 7. 8. 9. 10. 12.3.
Revised/Anticipate
d
11.
Construction progress StatusTarget Date
RemarkTowers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hcKM
Ckts(S/C)
&(D/C)
Commissioned.24Ratija - Kasiapalli 241 D/C 132
STERLITE ENERGY LIMITED (SEL)
Tree Enumeration in Forest Land Completed.40Sterlite TPP - Jharsuguda 64 51 9 01 2xD/C 400
STERLITE GRID LTD. (SGL)
Transmission Licensee granted by CERC. Tariff Adoption done by CERC.MAY-19Aligarh - Prithala1 D/C NOV-17400
Change In Law-Additional 0.5% Krishi Kalyaan CESS has been included inService tax w.e.f 1st June 2016 same has been intimated to all LTTCs. Delay ingetting Section 164. PTCC Clearance pending with CEA (PTCC). Facing SevereRoW issues in Multiple Locations Between 57/0 67/0, 83/4 84/2, 91/2, 95/1,128/0 129/0, AP 141,142,143.
AUG-19644Jharsuguda - Raipur 763 310 147 232 D/C JUL-17765
Commissioned 06/16. (NRSs-XXIX.)JUN-17270Jullandhar - Samba line 356 356 356 2703 D/C JUN-16400
Transmission Licensee granted by CERC. Tariff Adoption done by CERC.Kadarpur-Sohna road4 D/C NOV-17400
Commissioned 06/16. (PKTCL)APR-16323Kharagpur (WBSETCL) - Chaibasa (PG) 426 426 426 3235 D/C JUN-16400
Force majeure events due to Bandh, Shutdown, Curfew, Bad Law & OrderSituation in J&K & there has been 58 days execution days lost till date, andsuspension of work due to Armed Conflict & Blockade from 08-07-2016, noticessent to all LTTC's. Wild Life proposal is pending with NBWL. Change in Law- i.Additional Swachh Bharat [email protected]% has been added in Service Tax w.e.f15th Nov.2015 as per Ministry of Finance Govt. of India Gazette Notification21/2015-Service Tax & 22/2015-Service Tax dated 06th Nov. 2015 ii. Additional0.5% Krishi Kalyaan CESS has been included in service tax w.e.f 01.06.2016 iii.Increase in J&K [email protected]% to 14.5% dated w.e.f 01.07.2016; same has beenintimated to LTTC's.
OCT-186LILO of Both ckt Uri - Wagoora at Amargarh6 D/C JUL-17400
Transmission Licensee granted by CERC. Tariff Adoption done by CERC.SEP-19LILO of Gurgaon - Manesar at Sohna Road7 D/C NOV-17400
Change In Law- New Guidelines by MoP No. 3/7/2015- Trans dated 15-10-2015for payment of compensation towards damages in regard to RoW for T/L.Additional Swachh Bharat Cess@ 0.5% has been added in Service Tax w.e.f15th Nov.2015 as per Ministry of Finance Govt. of India Gazette Notification21/2015-Service Tax & 22/2015-Service Tax dated 06th Nov. 2015.Additional0.5% Krishi Kalyaan CESS has been included in Service tax w.e.f 1st June 2016same has been intimated to all LTTCs. PTCC Clearance pending with CEA(PTCC). Facing severe RoW issues in
JUN-18196Maheshwaram(PG) - Mehboob Nagar 252 211 147 748 D/C FEB-17400
Trasmission Lines: Page 7 of 11
Legends
TL: Total Location STC: Stubs Cast TE: Towers Erected STG: Stringing Completed
Schedule
1. 2. 5. 6. 7. 8. 9. 10. 12.3.
Revised/Anticipate
d
11.
Construction progress StatusTarget Date
RemarkTowers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hcKM
Ckts(S/C)
&(D/C)
multiple locations i.e. between 9/1 15/1, 17/1, 20/12, 20/18, 26/1-26/5, 32/8 33/3 and 40/0 41/0 in Tehsil Kandukur, Thalakondapalli, Midjil, Ghanpur,Kothakota.Transmission Licensee granted by CERC. Tariff Adoption done by CERC.MAY-19Neemrana(PG) - Dhanonda(HVPNL)9 D/C NOV-17400
Change In Law- New Guidelines by MoP No. 3/7/2015- Trans dated 15-10-2015for payment of compensation towards damages in regard to RoW for T/L.Additional Swachh Bharat Cess@ 0.5% has been added in Service Tax w.e.f15th Nov.2015 as per Ministry of Finance Govt. of India Gazette Notification21/2015-Service Tax & 22/2015-Service Tax dated 06th Nov. 2015.Additional0.5% Krishi Kalyaan CESS has been included in Service tax w.e.f 1st June 2016same has been intimated to all LTTCs. PTCC Clearance pending with CEA(PTCC). Facing severe RoW issues in multiple Locations i.e. between 1/0 4/2,29/4 35A/0, 42/0 46/2 in Dist. Nizamabad, Medak and Sangareddy.
JUN-18277Nizamabad - Shankarpalli 355 277 178 6610 D/C FEB-17400
Change In Law-Additional 0.5% Krishi Kalyaan CESS has been included inService tax w.e.f 1st June 2016 same has been intimated to all LTTCs. Delay ingetting Section 164. PTCC Clearance pending with CEA (PTCC). Severe RoWissues in Loc No. between 32/0 33/1 and 58/0 61/0 in Tehsil Jharsuguda andLakhanpur in Dist Jharsuguda.
JUL-17110OPGC - Jharsuguda 152 36 811 D/C JUL-17400
Transmission Licensee granted by CERC. Tariff Adoption done by CERC.MAY-19Prithala - Kadarpur12 D/C NOV-17400
Line Commissioned on 7th Jan 2017.APR-16223Purulia PSP (WB) - Ranchi (PG) 301 301 301 22313 D/C DEC-16400
Ready for Commissioning 06/16. (RTCL).FEB-16402RAPP - Shujalpur line 521 521 521 40214 D/C JUN-16400
Force majeure events due to Bandh, Shutdown, Curfew, Bad Law & OrderSituation in J&K & there has been 58 days execution days lost till date, andsuspension of work due to Armed Conflict & Blockade continued from 08-07-2016, notices sent to all LTTC's. Wild Life proposal is pending with NBWL.Change in Law- i. Additional Swachh Bharat [email protected]% has been added inService Tax w.e.f 15th Nov.2015 as per Ministry of Finance Govt. of IndiaGazette Notification 21/2015-Service Tax & 22/2015-Service Tax dated 06thNov. 2015 ii. Additional 0.5% Krishi Kalyaan CESS has been included in servicetax w.e.f 01.06.2016 iii. Increase in J&K [email protected]% to 14.5% dated w.e.f01.07.2016; same has been intimated to LTTC's.
OCT-18574Samba - Amargarh line 783 658 458 21415 D/C JUL-17400
Shekhawati Transmission Service Company Limited (SKHWTTSCL)
Trasmission Lines: Page 8 of 11
Legends
TL: Total Location STC: Stubs Cast TE: Towers Erected STG: Stringing Completed
Schedule
1. 2. 5. 6. 7. 8. 9. 10. 12.3.
Revised/Anticipate
d
11.
Construction progress StatusTarget Date
RemarkTowers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hcKM
Ckts(S/C)
&(D/C)
court case pending, severe ROW problem, Railway crossing pending.Funds problem from PFC.
FEB-1532Jhunjhunu - Nawalgarh line 108 77 73 01 S/C DEC-17220
court case pending, severe ROW problem, Railway crossing pending.Fund problem from PFC.
FEB-1522Sikar - Nawalgarh line 76 55 48 02 S/C DEC-17220
South East UP Power Transmission Company Limited (SEUPPTCL)
Karchana gantry not finalised80Bara - Karchana 124 0 0 01 D/C JUN-16400
442Gonda - Shahjanpur 542 295 140 02 D/C JUL-16400
2/0 2A/0 stringing under hold due to construction of engineering college in theline corridor. Matter is pending with DM Mainpuri.
92LILO 400 Orai - Mainpur at Bah 135 135 135 893 D/C JUN-16400
1LILO of Obra - Sultanpur at Aurai 5 0 0 04 S/C JUN-16400
Ready for commissioning 12/201693LILO of Orai - Mainpuri line at Mainpuri 135 135 135 935 2xD/C DEC-17400
Completed and commissioned1LILO of Panki - Obra at Rewa Road 2 2 2 16 S/C FEB-16400
14LILO of Sarojini Nagar - Kursi RD at Sultanpur RD 187 D/C JUL-16400
Ckt-I commissioned 12/2016 and Ckt-II Ready for commissioning 12/2016186Mainpuri - Aligarh 219 219 219 1868 D/C DEC-16400
375Mainpuri - Bara Ckt-I 889 613 346 09 S/C MAR-17765
Ready for commissioning 12/2016377Mainpuri - Bara Ckt-II 899 899 899 37710 S/C DEC-16765
188Mainpuri - Unnao (Quad) 449 380 274 011 S/C MAY-16765
Completed and commissioned64Meja - Bara 83 83 83 6412 D/C FEB-16400
Karchana gantry not defined.58Rewa Road - Karchana 10213 D/C OCT-16400
188Tanda - Gonda line 241 97 54 014 D/C JUL-16400
TALCHER TRANSMISSION CO. LTD. (TTCL)
OCT-12290Behrampur - Gazuwaka1 D/C SEP-13400
OCT-12220Talcher II - Behrampur2 D/C SEP-13400
OCT-12161Talcher II - Rourkela3 D/C SEP-13400
TEESTA URJA LTD. (TUL)
RoW matter of balance stringing of 0.5 km of priority portion up to Rangpo S/S,the matter has been taken up with the state govt and a committee headed byDistrict Commissioner is working on resolution of
430Teesta III - Kishanganj 591 501 458 2481 D/C MAY-17400
Trasmission Lines: Page 9 of 11
Legends
TL: Total Location STC: Stubs Cast TE: Towers Erected STG: Stringing Completed
Schedule
1. 2. 5. 6. 7. 8. 9. 10. 12.3.
Revised/Anticipate
d
11.
Construction progress StatusTarget Date
RemarkTowers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hcKM
Ckts(S/C)
&(D/C)
these issues and the portions of site area are being cleared one by one.GOKE Territorial Forest, MANJHA UCC Reserve Forest, GHUM SIMANAReserve Forest (Darjeeling & Kurseong division) - " In principle Approval (Stage-I)" has been accorded by MoEF, New Delhi on 28.05.2013. (30 Towers, TotalArea 47.4932 Ha.)
One ckt of Teesta-III - Rangpo completed by TVPTL, IInd ckt is expected to becompleted soon. Work at one location is affected due to RoW issue.
71Teesta III - Rangpo line 98 98 98 702 D/C NOV-16400
TORRENT POWER LTD (TOR. POW. (UNOSUGEN))
Work awarded to M/s Instalaciones. Inabemsa. Spian on May 2014. Routechanged after survey observations.
DGEN - Vadodara1 D/C 400
.DGEN TPS - Bharuch/Dahej Pooling Station2 D/C 400
Work awarded to M/s Instalaciones. Inabemsa. Spian on May 2014. Routechanged after survey observations.
Navseri - Bhasten3 D/C 220
Sandila TPP - ATS not defind4 D/C 400
VANDANA VIDYUT LTD. (VVL)
Target Commissioning date will be provided after approval/receipet of loan fromlenders.
60Salora TPS - Dharamjaigarh (Korba) (PGCIL) PoolingStation
841 D/C MAR-17400
VEMAGIRI TRANSMISSION SYSTEM LIMITED (VTSL)
Bidding process to be taken upAPR-15410Khammam - Hyderabad line -I1 D/C 765
Bidding process to be taken upAPR-15455Vemagiri Pooling Station - Khammam line -I2 D/C 765
VISA POWER LTD (VISA)
Work is under Construction.26Visa Power TPP - Raigarh Pooling Station 37 33 26 01 D/C JUN-15400
WESTERN U.P. POWER TRANSMISSION CO. LTD. (WUPPTCL)
One loc. is in 5th Res. Bn. CISF compound which is crucial and approval isawaited
16Ataur-Indirapuram 54 38 36 61 D/C MAY-17400
41Greater Noida-Noida (Sec -148) 131 127 127 272 D/C MAY-17400
Commissioned 04/16.34Greater Noida-Sikandrabad 53 53 53 343 D/C APR-16400
53Hapur-Ataur 155 150 129 304 D/C JUL-16400
Trasmission Lines: Page 10 of 11
Legends
TL: Total Location STC: Stubs Cast TE: Towers Erected STG: Stringing Completed
Schedule
1. 2. 5. 6. 7. 8. 9. 10. 12.3.
Revised/Anticipate
d
11.
Construction progress StatusTarget Date
RemarkTowers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hcKM
Ckts(S/C)
&(D/C)
Foundation & Erection work complete, Stringing in progress.66Hapur-Greater Noida 187 187 187 635 S/C JUL-16765
14Hapur-dasna 44 34 32 76 D/C JUL-17400
Commissioned 04/16.11LILO of Agra - Meerut line at Greater Noida 35 35 35 117 2xS/C APR-16765
Ready for Commissioning 08/16.2LILO of Moradabad-Muzzafarnagar at Hapur 7 7 7 28 D/C AUG-16400
15LILO of Muradnagar -Muzzafarnagar at Ataur 48 41 23 09 D/C MAY-16400
15LILO of Rishikesh -Kashipur at Nehtaur (Bijnor) 44 44 44 310 D/C JUL-16400
Ready for commissioning 08/16.181Mainpuri-Greater Noida 494 494 494 18111 S/C AUG-16765
ROW at few locs.217Mainpuri-Hapur 602 598 597 20912 S/C JUL-16765
Trasmission Lines: Page 11 of 11
Legends
TL: Total Location STC: Stubs Cast TE: Towers Erected STG: Stringing Completed