Report IDP material analysis
-
Upload
suhaimi-alhakimi -
Category
Technology
-
view
368 -
download
1
description
Transcript of Report IDP material analysis
TAKE NOTE: 20% PRESENTATION, 40% PRODUCT TANGIBLE/INTANGIBLE, 40% FINAL REPORT.
PROJECT: DESIGN A PORTABLE DRINKING
WATER SYSTEM FOR A GROUP IN THE
VILLAGE /JUNGLE.
PART ->
MOHD SUHAIMI AL HAKIMI B ARIFIN
1012799
INTRODUCTION
PROBLEM STATEMENT
OBJECTIVE
SCOPE
EXPECTED RESULTS
Integration Design Project Requirement and Consideration
Step 1 – Special Services include feasibility and pre-design investigations to determine the best
alternative approach to meet the project objectives.
Step 2 – Preliminary Design and Reports, should include preliminary design information and
reports in the form of drawings and documents outlining the nature of the project, a summary of
the basis of the engineering design, a preliminary cost estimate and a description of the extent of
services and recommendations.
TAKE NOTE: 20% PRESENTATION, 40% PRODUCT TANGIBLE/INTANGIBLE, 40% FINAL REPORT.
Step 3 – Detailed Design, Final Drawings and Specifications, includes preparation of a design
brief; final plans (detailed engineering drawings); specifications (construction requirements,
materials and equipment); a final cost estimate; and documents required for approval or permit
applications
Design consideration
1. Routine of certain place to implement our water system
COMMERCIAL AND INSTITUTIONAL USE WATER USE (ROUTINE DAILY AVERAGE)
Shopping Centres (based on total floor area) 2500-5000 L/(m2·day) [60-120 USgal/(ft2·day)]
Hospitals 900-1800 L/(bed·day) [240-480 USgal/(bed·day)]
Schools 70-140 L/(student·day) [20-40 USgal/(student·day)]
Travel Trailer Parks (min.with separate hook-ups) 340 L/(space·day) [90 USgal/(space·day)] 800
L/(space·day) [210 USgal/(space·day)]
Campgrounds 225-570 L/(campsite·day) [60-150
USgal/(campsite·day)]
Mobile Home Parks 1000 L/(space·day) [260 USgal/(space·day)]
Motels 150-200 L/(bed-space·day) [40-50 USgal/(bed-
space·day)]
Hotels 225 L/(bed-space·day) [60 USgal/(bed-space·day)]
2. Fire protection
The decision as to whether or not fire protection will be provided via the communal water supply
system is a municipal responsibility. In deciding upon the need for such protection, the
municipality should consider such factors as the:
Availability of adequate supply of water;
Additional capital and operating costs associated with such a system;
Availability of an adequate fire department, fire service communication and fire safety
control facility; and
Alternatives to a piped communal fire facility such as residential sprinkler systems.
3. Site selection criteria
Preparation for separation from residential area or non-compatible land use.
Optimized the raw water source and certain area to be serviced.
Ability of site to experience flooding.
Suitability of subsurface and soil condition.
Future expansion of the site land.
Waste disposal consideration.
TAKE NOTE: 20% PRESENTATION, 40% PRODUCT TANGIBLE/INTANGIBLE, 40% FINAL REPORT.
Product modeling (Internal part)
[Muhammad khairi]
TAKE NOTE: 20% PRESENTATION, 40% PRODUCT TANGIBLE/INTANGIBLE, 40% FINAL REPORT.
Material Analysis for Casing.
TAKE NOTE: 20% PRESENTATION, 40% PRODUCT TANGIBLE/INTANGIBLE, 40% FINAL REPORT.
1. Casing desired.
2. Properties (Using ANSYS 14.5, Finite Element Analysis software)
Analysis type Static
Mesh type Solid mesh
Thermal effect ON
Thermal option Include temperature loads
Zero strain temperature 298 Kelvin
Include fluid pressure effects from SolidWorks
Flow Simulation
Off
Solver type FFEPlus
Inplane Effect: Off
Soft Spring: Off
Inertial Relief: Off
Incompatible bonding options Automatic
Large displacement Off
Compute free body forces ON
Friction Off
Use Adaptive Method: Off
3. Unit of the measurement of the product to be designed.
Unit system: SI (MKS)
Length/Displacement mm
Temperature Kelvin
Angular velocity Rad/sec
4. Properties of the product desired.
Figure 1 : Designed water system carrier / casing
TAKE NOTE: 20% PRESENTATION, 40% PRODUCT TANGIBLE/INTANGIBLE, 40% FINAL REPORT.
Name: PET
Model type: Linear Elastic Isotropic
Default failure criterion: Unknown
Tensile strength: 5.73e+007 N/m^2
Compressive strength: 9.29e+007 N/m^2
Elastic modulus: 2.96e+009 N/m^2
Poisson's ratio: 0.37
Mass density: 1420 kg/m^3
5. Mesh information.
Mesh type Solid Mesh
Mesher Used: Standard mesh
Automatic Transition: Off
Include Mesh Auto Loops: Off
Jacobian points 4 Points
Element Size 4.20455 mm
Tolerance 0.210227 mm
Mesh Quality High
Figure 3 : Von MisesStress analysis. Figure 2 : Mesh in high quality.
TAKE NOTE: 20% PRESENTATION, 40% PRODUCT TANGIBLE/INTANGIBLE, 40% FINAL REPORT.
Figure 5 : Strain Analysis. Figure 4 :Displacement analysis
Figure 6 : Deformed shape Figure 7 : Force and Pressure from top (RED) and constraint from all Degree of Freedom at the bottom (GREEN)
TAKE NOTE: 20% PRESENTATION, 40% PRODUCT TANGIBLE/INTANGIBLE, 40% FINAL REPORT.
Water Filtration System inside the Casing Bottle
General method to use our product.
1. Take out the condensor container from the outer most casing, unscrew the cap and open the
condensor.
2. Condensation process starts, water rains down the drain channels and bottle fills up.
3. When filled up, psh back the condensor –elements back into the bottle and close it.
4. When we wanna drink the water, just unscrew the cap and ENJOY it!
Our filtration water system technology could be used by top up the water by loose the bottle
itself, rather than loosening the cap. This method will ensure the phenomena of condensation.
The air will blow through the condenser element which is installing on the bottle. The trapped
water will drain through a channel into the container of water system. The water condenses on
the filtration of our coated element of filter component.
TAKE NOTE: 20% PRESENTATION, 40% PRODUCT TANGIBLE/INTANGIBLE, 40% FINAL REPORT.
PUMPING FACILITIES
1.Importance of pumping facilities.
To raw and treated water pumping stations and booster pumping stations. Pumping facilities
should be designed to maintain the quality of pumped water, for example, by minimizing
retention time and ensuring adequate flows and velocities in the distribution system. Appropriate
design measures to help ensure the security of water pumping facilities should also be
incorporated.
The three types of pumping facilities addressed in this chapter are raw water pumping
(commonly called low lift pumping), treated water pumping (commonly called high lift
pumping) and booster pumping stations.
Pumping stations commonly use either horizontal centrifugal pumps, vertical turbine pumps or
submersible pumps. Typically, horizontal split case centrifugal pumps are equipped with side
suction and side discharge, while larger units may have bottom suction. Refer to the Hydraulic
Institute (HI) ANSI/HI Pump Standards for appropriate uses of different pump types.
INSTRUMENTATION AND CONTROL
1. Introduction
The objectives of instrumentation and control are to support the continuous production of high
quality drinking water in an efficient manner in terms of staff and resources used, and to satisfy
the regulatory requirements for monitoring and recording operational data in accord with a
control philosophy document prepared by the designer. For information regarding monitoring
and control systems for poisonous gases such as chlorine or ozone, the designer should refer to
the supplier or manufacturer recommendations for health and safety.
2. Basis of control
Control systems should be designed with a user-friendly human-machine interface (HMI) system
to facilitate plant operation and on-line monitoring. Equipment status, flow rates, water levels,
pressures and chemical feed rates should all be displayed via an HMI. All automated systems
should be designed with a manual override or another form of redundancy to allow safe
operation in the event of a hardware or communication failure.
Process and instrumentation diagrams (P&ID) should be developed for all drinking-water system
facilities and should include all major and minor processes along with all ancillary process
equipment.
TAKE NOTE: 20% PRESENTATION, 40% PRODUCT TANGIBLE/INTANGIBLE, 40% FINAL REPORT.
3. Control system
Manual Control Systems: Are simpler to maintain and repair than automatic systems and are lower in initial cost, but
require the on-site presence of an operator when producing drinking water; and
The initial low costs may be outweighed by high labour and operating costs including, chemical
and energy costs incurred by poorer process control.
Automatic Control Systems:
Provide a more consistent product with lower labour costs;
Require skilled maintenance;
Should provide a level of reliability appropriate for the control function; and
Should be designed to have the capability to manage any set of conditions which may occur.
PREVIEW FOR APPLICATION OF THE DESIGN WATER SYSTEM
<- Imagination of the water system complete with filtration
technology.
The plastic straw will be connected to the top of the water carrier. Instead of opening the cap to
drink, user might also suck the water from the water carrier. This will ease them to drink.
REFERENCE
TAKE NOTE: 20% PRESENTATION, 40% PRODUCT TANGIBLE/INTANGIBLE, 40% FINAL REPORT.
1. www.bottlematerial5678910.com.uk/physic/internalInk/pprp
2. www.ANSYS.com.uk