Report Dhaval

download Report Dhaval

of 35

Transcript of Report Dhaval

  • 8/9/2019 Report Dhaval

    1/35

    Acknowledgement

    I am very thankful to Kirby Building Systems India Ltd. (KBSIL) for having given

    me the opportunity to undertake my summer training on some of their Mega Projects. It

    was a very good learning experience for me to have worked on theseprojects

    whichinvolved many new and unique construction practices and challenges.

    I would like to convey my heartiest thanks to Mr. G.PrasadRaju, General Manager-

    BTD, who directed mein these projects and gave an insight in to what these projectsare

    all about. I would also like to give my heart-felt thanks to Mr. P.V.Rao, Manager -

    Construction, who guided me all through the summer training and imparted in-depth

    knowledge of the project. I would also extend my sincere thanks to Mr.Philipose, VP,

    Operationsfor inspiring and motivating me through out the training.

    I would also like to thank the entire BTD teamfor their self-less help and knowledge

    sharing, which has helped me immensely in my learning and in the preparation of this

    report. I would also extend my thanks to the entire PMG team, the Design and Drafting

    teamfor their help and guidance during the training.

    Last but not the least; I would like to thank all the staff atKBSIL for being so helpful

    during this summer training.

    Name:Dhaval Gandhi

    Date:25th

    June 2010

  • 8/9/2019 Report Dhaval

    2/35

    2

    CONTENTS

    CHAPTER 1 INTRODUCTION Page No.

    1.1 About the Organization 4

    1.2Product range offered byKirby 4

    1.3 About PEB (Pre engineered building) 5

    1.4 Advantages ofPEB 6

    1.5 Induction Programme at Head Office 6

    1.6 Kirby Flowchart 7

    CHAPTER2 PROJECT DETAILS 9

    2.1 General Details 9

    2.2Paint Shop 9

    2.3 Trims & Chassis Building 10

    2.4 Stamping Building 11

    2.5 Body Shop 12

    2.6 Power Train 13

    CHAPTER3SKILLS LEARNED/KNOWLEDGE

    GAINED DURING THE INTERNSHIP

    3.1 Basics ofPEB 15

    3.2 Material Management 19

    3.3 Erection Process of the buildings 20

    3.4Safetyproceduresinvolved in erection and sheeting 233.5Quality Inspection 23

    3.6 Report Generation 24

    3.7 Obstacles to Progressat site 26

  • 8/9/2019 Report Dhaval

    3/35

    3

    Chapter -1

    Introduction

    1.1 About the Organization:

    Kirby Building Systems India Ltd is an affiliate of Alghanim Industries Kuwait, a

    multinational organization with diverse interests in Industrial and consumer products.

    It launched its technology-driven Pre-Engineered Steel Building Solutions (PEB) in

    India around the dawn of year 2000 with an avowed aim of serving the multifarious

    needs of the Indian construction market. Its over 30 years of experience (in PEB)

    abroad prior to entering the Indian landscape has crystallized into a wide range of

    time-tested innovative solutions to specific needs.

    KIRBY's Product range covers buildings tailored to customers' unique requirements

    with a variety of accessories that go into making the buildings, which are not only

    aesthetically brilliant but also majestic and structurally stable and sturdy. 'Quality' for

    KIRBY epitomizes a combination of speed of construction, safety of the structure,

    sustainability against natural and man-made disasters, suitability to the purpose,

    unmatched pre- and post- sales service, scalability, and substantial savings in terms of

    both time and money.

    While serving the various needs of the customers across a wide spectrum of industries

    in India through its vast network of Sales offices, KIRBY from its inception in India,

    has highly esteemed every stated or implied need of the customers and exemplified

    the "total value" offered to the customers for their money.

    KIRBY'S state of art manufacturing facility was setup in April 2000 at Pashamylaram

    near Hyderabad in Andhra Pradesh spread over sprawling 30,000 meter square and

    over 30 acres of land was commissioned in a record period of seven months is the

    epicenter of all its activities (backed by a highly qualified, dedicated, experienced &

    seasoned pool of engineers, designers, professionals) that synergies to create efficient

  • 8/9/2019 Report Dhaval

    4/35

    4

    need-based permanent building solutions. As a part of its expansion programme,

    KIRBY has setup another plant at Haridwar, Uttaranchal State in April 2006.

    KIRBY is an ISO 9001 certified company and a market leader in Pre Engineered

    Buildings in India. Till date Kirby supplied more than 2500 buildings to 2000

    customers proving its engineering excellence in various projects and over the years

    KIRBY has earned a remarkable reputation for providing cost effective solutions for

    buildings manufactured to the highest standards and suited to all environments. Some

    of the factories constructed in India and abroad using Kirby concept are model by

    themselves.

    Today, Kirby is well positioned as the global leader of pre-engineered steel buildings

    (PEB). Kirby is well known for providing global customers with customized and cost

    effective solutions.

    Their steel buildings are designed and manufactured to international building

    standards for a wide range of applications such as, industrial, commercial,

    recreational, warehousing and others. Kirby is a wholly owned subsidiary of the

    multi-national conglomerate Alghanim Industries.

    At KBSIL (Kirby Building Systems India Ltd.) all the necessary parts and accessories

    are fabricated at the plants in Hyderabad and Haridwar. The assembling and erection

    works are usually subcontracted. Only monitoring is done by KBSIL and queries so

    arising are handled.

    But the Renault Nissan project was a turnkeyproject handled by Kirby and hence

    they were directly answerable to the clients though the erection works were sub

    contracted like in all projects.

    Kirby India has a total annual installed capacity of 100,000 MTPA expanded to

    175,000 MTPA in July 2007:

    Hyderabad: from 60,000 MT to 100,000 MT, this is the largest PEB plant of

    its kind in the world.

    Haridwar: from 40,000 MT to 75,000 MT

  • 8/9/2019 Report Dhaval

    5/35

    5

  • 8/9/2019 Report Dhaval

    6/35

    6

    Ki Indi S l s Netwo k

    Company has an all India sal s net ork comprising of 25 offices & 110 B ilders who

    have been trained and Certified on Kirbys Erectionprocedures.

  • 8/9/2019 Report Dhaval

    7/35

    7

    1.2Product Range offered byKirby:

    Kirby offers a wide range of solutions tailored to specific needs.

    Kirby solutions caters to applications such as warehouses, factories, showrooms,

    shopping malls, offices, camps, supermarkets, workshops, mosques, aircraft hangars,

    car parks, gas stations, sports complex and schools among many others.

    Their products include low rise and medium rise pre-engineered buildings,

    conventional structural steel buildings, primary and secondary frames, mezzanines,

    fascias, canopies, cranes, open web joists and trusses.Secondary members such as

    purlins, girts and related accessories, either painted or pre-galvanized, are produced

    in-house to complement the whole structure and provide clients with an all inclusive

    package.

    Roof and wall cladding systems can be supplied in a wide range of profiles and

    colours.

    Insulation is also available in single cladding with fibre glass insulation or in

    polyurethane insulated panels.

    Kirby has pioneered the introduction of Industrial racking systems, offering a One

    Stop complete warehousing solution.

    Kirby also offers a wide range of Structural Steel products which covers applications

    in several market segments including

    y Oil & Gas onshore & offshore

    y Heavy IndustryPetrochemicals, Steel, Aluminium smelters, Cement,

    Fertilizers

    y InfrastructureBridges, Power, Desalination plants, Airports, Seaports,

    Railways

    y BuildingsHigh-rise residential and commercial buildings, Malls, Car parks,

    leisure, special purpose/heavy duty factories & warehouses

    Structural Steel products meet the highest design and manufacturing standards in the

    industry.

  • 8/9/2019 Report Dhaval

    8/35

    8

    1.3Pre Engineered Building:

    A Pre engineered building is a steel structure built over a structural concept of

    primary members, secondary members, and the cover sheeting connected to each

    other. The structural members are custom designed to be lighter in weight as well as

    high in strength. For today and in the future, Steel has become the material of choice

    in building construction, compared to concrete and timber. Thus steel building

    designs have become more flexible, durable and adaptable.

    Pre Engineered Steel Buildings (PEB) revolutionized the construction market using

    built-ups in place of conventional Hot Rolled Sections. PEB is a steel structure built

    over a structural concept of primary members, secondary members, and the cover

    sheeting connected to each other. The structural members are custom designed to be

    lighter in weight as well as high in strength. Pre-Engineered Steel Buildings can be

    fitted with different structural additions like trusses, mezzanine floors, fascias,

    canopies and crane systems as per user requirements.

    As a leading PEB manufacturer, Kirby provides the complete service of engineering

    and fabrication thus ensuring better quality control at every stage of the process.

    1.4 Kirby Customer Base:

    Companys customer base include all top MNCs, large industrial houses &

    government

    Select private Sector clients:

    Tatar Power

    Reliance

    General Electric

    Hero Honda

    Nokia

    Suzlon

    Renault Nissan

    A V Birla Group

    Regency Ceramics

  • 8/9/2019 Report Dhaval

    9/35

    9

    Bridgestone

    Pepsi

    Toyota

    Pipavav

    Tata Motors

    It also exported buildings to Mauritius, Turkmenistan, Mozambique, Sierra Leone and

    U.K.

    1.5 Kirby Manualsand Brochures

    Kirby offers a wide array of metal building products and it also provides

    Catalogues and manuals which may be used as ready reckoner by existing as well asnew customers. The main purpose of these manuals and brochures is to provide

    necessary information and to clear the queries of Builders and customers.

    Kirby Corporate Brochure

    Kirby Technical Hand Book

    Erection Manual

    Product Guide

    Kirby Safety Manual

    These manuals and brochures may also be directly downloaded from the

    official website of KBSIL.

    1.6 QualityPolicy

    KBSIL is committed to design, manufacture and supply quality products

    conforming to Global Standards, with the state of art technology and equipments

    to ensure total customer satisfaction. It also aims to maintain leadership in this

    industry by continuously upgrading its technology, Quality management

    systems and skills of its Employees.

  • 8/9/2019 Report Dhaval

    10/35

    10

    1.7 Health, Safetyand Environment (HSE) Policy

    KBSIL is committed to provide safe and healthy environment during design,

    manufacture and supply of building systems.

    Objectives:

    KBSIL strongly believes that good health and safety performance is an integral

    part of efficient business.

    To ensure compliance to all statutory rules on health safety and environment.

    To train all builders and employees in advance on erection, sheet laying,

    operations of material handling equipments and latest techniques on safety.

    To provide appropriate training and information to enable all employees and

    builders to appreciate and accept individual responsibility for Health and Safety.

    To provide and maintain facilities and working conditions which are safe for

    employees, visitors and customers at the project premises.

    To be a leader in Health Safety and Environment practices through

    continual improvement in its HSE performance.

    1.8 HRPolicy:

    Kirby provides an environment where human resources are nurtured and

    developed to achieve organizational goals, while in the process providing

    adequate scope for individual growth. Kirby takes pride in saying We build

    careers as strongly as we make our buildings .

    Kirby gives importance to:

    Career Management

    Training and development programs

    Equal opportunity

    Communication channels and feedback

    mechanisms Activities promoting work -

    life balance

  • 8/9/2019 Report Dhaval

    11/35

    11

    1.9 KirbyValues:

    Straight Talking: They encourage open debate where the best ideas win

    Customer Centric: They put the customers at the Centre of their focus and

    initiatives with the objective of providing them with unmatchable levels of services

    and products.

    Teamwork: They actively share information and ideas; enthusiastically work

    to make those around them better

    Diversity and Respect: The diversity of their workforce is an asset and they treat

    everyone with dignity and respect regardless of status, gender, education, ethnicity or

    religion

    Empowerment: They empower people to make decisions with a bias for action

    Employees as core assets: They believe that their employees are the most valuableresource and do whatever it takes for their continuous training, development and

    motivation.

    Meritocracy: The reward and career advancements of their people are

    based on their performance and capabilities, not on theirwasta (influence).

    The work environment is based on their corporate values---- straight talking,

    customer centric, teamwork, diversity and respect, empowerment, employees as

    core assets and meritocracy.

    1.10 Advantages ofPEB:

    Reduced construction time

    Lower cost

    Flexibility of expansion.

    Large clear spans

    Higher quality control.

    Lower maintenance or high durability Energy efficient roofing and wall systems (very well insulated)

    Architectural versatility.

    Single source responsibility(single vendor supplies all members)

  • 8/9/2019 Report Dhaval

    12/35

    12

    1.11 Induction Programme at Head Office:

    The induction programme was held from 3rd

    May 2010 to 7th

    May 2010 and during

    this programme, we were briefed about the organization, its extent, its structure, its

    scope of work and its working culture. Further, we were detailed about the role of

    Builders Training Department (BTD) in the organization as we were to be associated

    with it for the coming days.

    On the first day, we met Mr. Ramchandra Rao(HR Manager) who further introduced

    us to Mr. Prasada Raju (GM BTD) who is the head of the Builders Training

    Department. Initially for the first two days we studied the Technical Handbook and

    Erection Manual in detail. Our familiarisation with the manual was very important

    before we moved ontoour projects as the manual included the basics of PEB, its

    erection procedure and Kirby terminology so used.

    After this, our visits to various departments in the organization were arranged. We

    visited almost all the departments of the organization (Design, Drafting, Production,

    Shipping, PMG, Quality and Safety) and everywhere we were given all possible

    information by the concerned official. Then we had a plant visit wherein we got to

    know about the entire fabrication process in detail.

    Also, we got an opportunity to learn about the SAP module in which the company hasinvested a huge amount to monitor all the projects running round the globe.

  • 8/9/2019 Report Dhaval

    13/35

    13

    1.12Kirby Flow Chart:

    Down Payment

    Credit

    Release

    Design Sketch with details

    Shipper List

    Erection Drawings

    Shop Drawings

    Shipper List

    Erection Drawings

    Shop Drawings

    Fabricated building material

    Shipper list

    Shipping advice / shipper list / erection dwg

    To inform the customer

    Customer / Job site

    Area Sales office, Kirby

    Design Dept / Pace II

    Estimating

    Customer Service Dept

    (Master File)

    Design Department

    Drafting Department

    Production Control

    Plant / Q.C.

    Shipping & Packing

    Dept. / Transport

    Credit Department

    Enquiry Proposal contract

    QRF sketch Book pricerecommendations

    SignedOrder

    ErectionDrawing

    ShippersLists

    Signed

    Offer/D

    P

    ShippingDocuments

    Sales Office

    ErectionDrawing

    ShippersLists

  • 8/9/2019 Report Dhaval

    14/35

    14

    The roles of the various departments are as under:

    1. CSD Customer Service Department This department is the single point

    contact for the client and all the queries are directed over here. Thus, it is that part

    of the organization which co-ordinates all the activities of other departments. They

    are responsible for executing the project as per the time frame.

    2. Sales & Marketing Department They book jobs i.e. they get customers/clients.

    They target the clients and get work orders. It is one of the largest departments at

    KBSIL. Kirbys market segment is a niche market. They have grown very much

    in the past four years with major breakthroughs in the automobile sector.

    3. Quality Department They take care of the quality of the materials which are

    being supplied. They perform various tests on the lots randomly (1 in 10) and

    certify the material as OK. Quality inspection at Kirby is done in three stages:

    a. Raw Material stage inward stage

    b. In process stage

    c. Outward Shipping stage

    4. Drafting Department. They prepare detailed drawings and drawings which are

    to be sent on the site. They prepare three types of drawings:

    a. Approval Drawings meant for the approval from the clients

    b. Fabrication Drawings element wise drawings meant for the fabrication in the

    plant.

    c. Erection Drawings detailed drawings to be provided to the erection

    engineers at the site for the purpose of execution.

    5. Design Department They design the building based on the data of the site

    available and by keeping other standards, rules and customer requirements in

    mind. They use design packages such as STAAD Pro at the job stage and

    SMARTEST at the quote stage.

    6. Credit Department - They take care of all the financial aspects of the

    organisation. Kirby extends credit to its customers by accepting a letter of credit

    or a bank guarantee.They give open credit to bigger companies such as Nokia,

    Suzlon etc. and to obtain this type of credit, prior approval is required from the

    Kuwait head office of Kirby building systems.

  • 8/9/2019 Report Dhaval

    15/35

    15

    Chapter - 2

    Project Details

    2.1 General Details:

    The following projects were undertaken during the summer training period.

    1. Toshiba JSW - Chennai

    2.

    MRF Ltd. - Trichy

    3. Star Panel Boards Ltd. - Bangalore

    4. Sterilite Infra Tech Ltd. - Aurangabad

  • 8/9/2019 Report Dhaval

    16/35

    16

    Project 1 - Toshiba JSW

    Project Details:-

    Bldg A - Main Building # 10

    Job No : - 2619

    Location :- Chennai, Tamil Nadu.

    Client :- Toshiba JSW Turbine & Generators Ltd.

    Total Quantity of Steel : -5413 MT.

    Total area of the building : - 42,240sq.m(C/C)

    TentativeFabricationand ErectionSchedule.

    Revised Fabrication and Erection Schedule.

    Bldg B Blade Shop Building # 50

    Job No :- 1004U

    Location :- Chennai, Tamil Nadu

    Client :- Toshiba JSW Turbine & Generators Ltd.

    Total Quantity of Steel : - 213 MT.

    Total area of the building : - 1964.16sq.m(C/C)

    Tentative Fabrication and Erection Schedule.

    Revised Fabrication and Erection Schedule.

  • 8/9/2019 Report Dhaval

    17/35

    17

    Project 2 - M/s MRF Limited, Trichy

    Bldg A1: Truck Radial Plant

    Project Details:-Job No :- 2683

    Location :- Trichy, Tamilnadu.

    Client :- M/s. MRF Ltd.

    Sub-Contractors :- 1. Sree Building Solutions Package I2. Pearl City Engineering Builders Package II

    Total Quantity of Steel is 6412MT.

    Total area of the building is 53692.20sq.m(C/C)

    Current Status:-y The start of the project has been delayed and the revised schedule has been

    prepared.

    y The type of contract is Lump Sum contract.

    Bldg B1: Non Truck BiasPlant

    Project Details:-

    Job No : - 2687

    Location : - Trichy, Tamilnadu.

    Client : - M/s. MRF Ltd.

    Sub-Contractors : - SS Constructions package III

    Total Quantity of Steel is 3627MT.

    Total area of the building is 28207.62sq.m (C/C)

    Tentative Schedule for Fabrication and erection.

    Revised Schedule for Fabrication and erection.

    Note: This Schedule is for both the Buildings.

  • 8/9/2019 Report Dhaval

    18/35

    18

    Project 3 - StarPanel Boards Limited, Bangalore

    Project Details:-

    Location :-Karnataka, Bangalore.

    Client :-Star Panel Boards Ltd.

    Sub-Contractor :- M/s. Hi-Tech Builders (For Painting and Erection works).

    Total Quantity of Steel is 1523 MT.

    Total area of the building is 38,837.30 sq.m (C/C)

    Present Status:-y The project is in the initial stages.

    y There has been a delay in the start of the project.

    y It is due to delay in final approval of G.A. drawings as well as delay in release

    of shop drawings for fabrication.

    y The current status as on 17/05/2010 is that the anchor bolt casting is 100%

    complete.

    y The sheeting material is yet to be received as there was a change in the

    profile.

    y 34 loads of Red Steel (693 tonnes) has already been sent to the site as on

    12/05/2010. Out of which 9 loads of steel is yet to be unloaded.y The erection operation is yet to begin.

    y The fabrication and dispatch of the sheeting is expected to be completed as

    scheduled.

    Schedule for Fabrication and Erection.

  • 8/9/2019 Report Dhaval

    19/35

    19

    Project 4 - Sterilite Infra Tech Limited, Aurangabad.

    Project Details:-

    Location :- Aurangabad, Maharashtra.

    Client :- M/s Sterilite Infra Tech Limited.

    Sub-Contractor :- Sangha Erectors.

    Total Quantity of Steel is 1428 MT.

    Total area of the building is 32,854.48sq.m (C/C)

    Schedule for Fabrication and Erection.

  • 8/9/2019 Report Dhaval

    20/35

    20

    Chapter 3

    Skills Learnt/Knowledge gained during the internship

    The following areas were focused upon during the internship:

    3.1 Basics ofPEB:

    A Pre engineered building consists of following components:

    a. Structural Systems

    b. Secondary members

    c. Cladding

    d. Accessories

    a) Structural systems (Primary members):

    They are the main load carrying and support members of a pre- engineered

    building.The shape and size vary based on application and requirements. The main

    frame is the main load carrying member of a structural system which includes

    columns, end wall posts, rafters and other main support members.

    All structural steel sections and welded plate members shall be designed in

    accordance with the applicable sections, relating to design requirements and allowable

    stresses, of the latest edition of the American Institute of Steel Construction

    Specification for the Design of Cold Formed Steel Structural Members. The

    following are the structural systems used by Kirby according to the requirement and

    the type of the building:

    Rigid Frame

    Beam & Column

    Lean to

    Space Saver

    L Canopy

    Butterfly Canopy

    Single Slope

    Multi-Span

  • 8/9/2019 Report Dhaval

    21/35

    21

    b) Secondary members:

    The secondary members are load carrying members suitable to ensure the stability of

    the building against forces in any direction. They primarily include purlins and girts,

    eave struts, cable bracing and open steel web joists.

    i) Purlins & Girts:These are structural members made up of cold formed steel Zsections. They are supported on columns, rafters or building walls. The girts

    and purlins can be lapped and nested at the supports which creates a

    continuous beam configuration. They are placed on the roof and perimeter of

    the building. Hence they serve as a support to the roof sheeting and wall

    cladding.

    ii) Eave struts:Structural members located along the sidewall; at the intersectionof the planes of the roof and wall. It is constructed from cold formed ' C'

    sections and is rolled to suit the roof slope.

    Application: Joins the roof and wall cladding.

    iii)Cable bracing: This member is designed to ensure the stability of the buildingagainst forces in the longitudinal direction due to wind, cranes, earthquakes. It

    is made of a cable which is forged into a rod terminal and this arrangement is

    then fixed on a structure using a hill side washer, nut washer and a nut.

  • 8/9/2019 Report Dhaval

    22/35

    22

    c) Cladding:

    Kirbys pre- painted sheeting is a multi-layer coating system to ensure long life and

    optimum coating adherence. The steel substrate is hot dipped galvanized zinc or hot

    dipped zinc / aluminium coated. The surface of the metal coatings is then given a

    series of pre treatments to ensure that they are completely clean. Kirby claddings can

    be used for roofs and walls and are available with or without insulation.

    i) Kirby RibProduct Description:This type of panel has coverage of 1 m. It ismade up of major ribs and minor ribs so placed as seen in the diagram below.

    The main purpose of this type of panel is for roof cladding.

    ii) Kirby Wall Product Description:As the name would suggest; this type of panel is used for wall panelling purpose. Its profile is as shown above. In

    between the major ribs, the panels have a valley like shape. Each panel shall

    provide one meter coverage.

    iii)Kirby Decking Product Description:Typical applications of decking panelsare in high rise buildings, office buildings and mezzanine floors in industrial

    buildings and warehouses. Decks can be used as a permanent shuttering to

    support the wet concrete and help in creating composite slabs and floor beams.

    The continuous flange stiffeners and deep embossments increase the load

    carrying capacities. They provide for a stable and rigid working platform

    without any need of propping.

  • 8/9/2019 Report Dhaval

    23/35

    23

    d) Accessories:

    In addition to the main building components, Kirby provides a wide range of building

    accessories. They are s follows:

    Walk doors

    Sliding Doors

    Aluminium Windows

    Insulation

    Louvers

    Fasteners

    Power Ventilators

    Skylights & Wall Lights

    Ridge Ventilators

    Roof Jacks

    RoofCurbs

    The following figure shows the various elements of a PEB:

  • 8/9/2019 Report Dhaval

    24/35

    24

    3.2 Material Management:

    This was the main responsibility that was assigned to me at the site. Kirby being the

    supplier of the materials had to maintain perfect records of the material available on

    site and the material which is to be shipped. Especially the material required for the

    priority area had to be shipped on time so that the erection process is not delayed.

    The materials received were updated in an excel sheet and the balance materials to be

    received were kept track. The shipping department in Kirby released the list of

    materials required for the project; building wise in different phases and revisions.

    These lists were termed as Shippers lists which were sent to us via e-mail. These

    lists were used to update the required quantity of materials in the excel sheet.

    The materials were shipped to the site in trucks and each load of materials had a

    packing list attached to it which carried a unique load number and L.R. (Lorry

    Receipt) number. These packing lists were arranged in files according to the load

    number and according to the building for which it has been sent. Each material had a

    unique Piece Mark number attached to it and this was also updated on the excel sheet

    in order to retrieve the status of the material quickly.

    The materials which arrived in trucks were unloaded directly at the material storage

    yard of the respective builder or subcontractor.

    A material storage yard adjacent to the building

  • 8/9/2019 Report Dhaval

    25/35

    25

    Suggestions forimprovement in thisaspect:

    The subcontractors had dumped the material in their yard in a haphazard manner

    as shown in the picture. This resulted in a lot of wastage of time in searching for

    the appropriate material. Instead the materials can be unloaded and stacked

    according to their load numbers so that they can be retrieved easily when required.

    The builders need to keep track of the materials required in the priority areas and

    maintain separate lists for those materials which would help in preparing the list

    of balance materials to be received.

    Sometimes the shippers lists were not available till the latest date of revision and

    this posed problems during the updating process. A proper communication

    between the shippers department personnel and the site personnel would help

    avoid this problem.

    3.3 Erection Process of the buildings:

    The buildings were erected in accordance with the erection manual provided by

    Kirby. This manual had the detailed procedure to be followed for safe erection at the

    site. Safety is always given utmost importance by Kirby and they followed stringent

    safety rules and practices on the site.

    The erection sequence is as follows:

    y Anchorbolt testing Pedestal testing: The foundation part is generally not

    executed by Kirby. It is carried out by a civil contractor. In our site, it was

    carried out by CCCL, a Chennai based company. Only the testing for the

    alignment of the anchor bolts is done by Kirby. This is termed as the Pedestal

    testing. In this test, the anchor bolts are checked for their alignment and for

    their levels so that there is no problem when the column is placed over the

    bolts.

    y Primary elements erection: Once the pedestal test has been performed, the

    erection of the primary elements is started. The primary erection includes the

    main frame elements such as columns, beams and rafters. These elements are

    erected with the help of cranes and ropes. Once the columns have been

  • 8/9/2019 Report Dhaval

    26/35

    26

    erected, their stability becomes very important and hence they should be

    fastened with ropes so that they do not sway in the wind.

    One of the Raftersbeing erected.

    y Secondary elements erection: Once the primary elements are erected, the

    secondary elements such as purlins, girts, bracings and others should be

    erected. Some purlins and girts are erected along with the primary members

    for the stability of the columns and beams.

    Erection of Bracings with the help ofa crane.

  • 8/9/2019 Report Dhaval

    27/35

    27

    y Roofsheeting and wall cladding:The roof sheeting and wall cladding are the

    final stages of erection. The wall cladding operation is carried out after a

    proper arrangement has been made for the scaffolding. The workers are

    instructed to wear the safety gear which includes safety ropes and helmets

    before carrying out this operation as it is done at great heights. Any fall from

    such a height would result in fatal injuries to the victim. Hence Kirby takes no

    chances in this aspect of safety.

    Wall cladding along withscaffolding.

    The roof sheeting is carried out in three stages. Initially the wire mesh is laid and then the

    insulation is laid on top of this. Finally the roof sheeting panels are laid and bolted. The

    wire mesh acts as a support to the insulation and the roof sheets.

    Roofsheeting in progress Picture showing wire mesh & Insulation

  • 8/9/2019 Report Dhaval

    28/35

    28

    3.4 Safetyproceduresinvolved in the Erection and sheeting:

    As mentioned earlier, safety is given utmost importance by Kirby and also the

    clients. The safety supervisors were appointed by Kirby who used to keep a

    constant check on the safety aspects in the various buildings.

    The roof sheeting is usually done at great heights and hence the appropriate

    safety harness is to be worn. PPEs such as helmets and safety ropes were

    mandatory for the laborers who used to climb on the roof.

    Even for the wall cladding, the safety ropes were mandatory and these were

    attached to the scaffolding erected for this purpose.

    A safety supervisor was appointed by the client as well and he used to conduct

    frequent checks on the site and provide any suggestions if required. If there

    was any discrepancy in this regard, strict action was taken against the safety

    engineer in charge on the site.

    3.5 Qualityinspection:

    Generally quality inspections are not carried out by Kirby on the site. It is done only

    at the plant before the material is shipped. Since this project is of a bigger nature in

    terms of built up area and tonnage of steel, the clients have made a special request to

    provide a quality inspector on the site to perform the inspection during the painting of

    the members.

    y Paint inspection using WFT gauge to test the WFT(Wet film thickness).

    o This test can be performed when the paint is applied fresh, i.e. before the

    paint gets dried.

    o The gauge is placed on the freshly painted metal and the thickness is

    checked based on the readings available on the teeth of the gauge. In this

    project, Kirby maintains the WFT at 120 microns.

    y Paint inspection using Elcometer to test the DFT (dry film thickness) of the

    paint.

    o This test is performed 8 hours after the painting operation is completed.

  • 8/9/2019 Report Dhaval

    29/35

    29

    o To perform this test, the knob of the Elcometer is wound to a particular level

    and then the Elcometer is placed on the metal which is painted.

    o The knob gets rewound automatically and stops at the exact thickness level

    of the paint on the metal.

    y Alignment and plumb testing for the columns:

    o A plumb bob is suspended on a fulcrum and the verticality of the columns is

    checked on the flange as well as the web.

    y Torque tightening test using torque tightening machine:

    o The torque to be maintained depends on the diameter of the bolt used. The

    torque tightening machine is set to the required torque and then the bolts are

    tightened.

    o For e.g.: A torque of 431 Nm is maintained for 20 mm diameter High

    Strength Bolts.

    3.6 Report generation:

    Along with material management, emphasis was given on report generation

    during the training. I was involved in the preparation of various reports such as Daily

    manpower report, Daily Progress Report, Sheeting and cladding progress report.

    y DailyProgress Report (DPR):

    o This report was to be submitted by KBSIL to the client (RNAIPL) on a daily

    basis and it consisted of all the details of the work done on site relating to

    various activities going on at site like Roof Sheeting, Wall Cladding,

    Downspout fixing, window and door fixing etc.

    o It was prepared daily and handed over to the client. It was prepared by the

    erection engineers on the site and I was involved in this process.

    o Each building had a separate engineer in charge and hence separate DPRs

    were prepared by them and a copy was forwarded to the head office, to keep

    them informed about the activities which weregoing on at the site.

    o This DPR is a very important report as it depicts the current status of the

    project and also gives an idea about the pace at which the work is being

    carried out.

  • 8/9/2019 Report Dhaval

    30/35

    30

    y Daily Manpower Report:

    o Since the availability of adequate strength of labour was extremely vital for

    the smooth progress of the project, a daily manpower report was prepared

    and maintained in order to have an idea about the labour strength on the site.

    o This proves to be extremely helpful in planning the progress of the various

    activities as the amount of labourers available would determine the pace at

    which the work can be carried out.

    o This report was prepared on a daily basis by the Project Manager at the site

    and I was also involved in this report generation.

    o The number of labourers present in each building was reported by the

    engineer in charge of that building and this was put together to form the

    manpower report.

    o A copy was sent daily to the client as well as the head office in order to keep

    them updated about the situation at the site.

    o The format of the manpower report so generated is as follows:

    KIRBY DAILY MANPOWER REPORT DT 25-06- 2009

    Stamping Bodyshop Paintshop T&C Powertrain

    BUILDING C E A B F UTILITY TOTAL

    UNLOADING & SHIFTING 4 11 15

    PAINTING 5 6 31 8 50

    ERECTION PRIMARY 12 8 20

    ERECTION SECONDREY 59 10 33 62 19 8 191

    MONITOR ERECTION 12 8 41 61

    PROCESS

    BEAM&MEZZANINE 28 10 25 63

    ROOF SHEETING 44 62 38 144

    MONITOR SHEETING 11 6 17

    WALL CLADDING 16 25 10 8 59

    GENERAL & ALIGNMENT 3 12 15

    TOTAL 124 126 70 256 43 16 635

    y Sheeting and cladding progressreport:

    o This report was prepared to depict the progress of the roof sheeting and wall

    cladding for each building.

    o Since these two activities were the major activities carried out on the site, a

    separate report was prepared for this purpose.

  • 8/9/2019 Report Dhaval

    31/35

    31

    o This was done exclusively by me in the excel format and I updated the

    report on a daily basis by interacting with the engineers in charge for the

    various buildings. They used to carry out the updating on the drawings

    manually and this was done on the system by me so that a copyofit can be

    sentto the Head Office fortheir reference.

    A lic tion of SA in Ki :

    SAP (Systems Analysis and Programme Development is a business management

    software tool for realtime processing of data and helps to take business decisions.

    It allows for open communication within and between all company functions. It

    provides entire package of ERP Enterprise Resource Planning. SAPs ERP

    solution includes several modules that support key functional areas like Financials,

    logistics, human resource management etc.

  • 8/9/2019 Report Dhaval

    32/35

    32

    In Kirby, SAP is implemented and used effectively for

    Business process

    Inventory reduction

    saving in time

    Improved customer service.

    Kirby as an organisation has invested several crores in purchasing, implementing

    the SAPs ERP tool and also in training its employees to effectively use this

    software. SAP in Kirby is highly confidential and only authorized people with

    passwords may use it.

    3.7 Obstacles to Progressat Site:

    Though I was not present at the site for a longer period, I observed some obstacles

    that were hampering the execution of the project. This was learning on its own. The

    following reasons can be attributed for the slow progress of work at the site:

    y The mid day temperatures soared to 42 degrees Celsius on a daily basis and

    this sweltering heat was a major obstacle for the progress of work, especially

    for roof sheeting since it had to be done in the direct exposure to the sun.

    y The turnover of labour was also a big issue as most of them fell sick due to the

    extreme heat conditions.

    y The material storage yards were not properly maintained by the builders and

    hence a lot of time was wasted in searching for the appropriate materials as

    they were dumped haphazardly.

    y There were frequent dust storms in the region and usually lasted for almost an

    hour in the evening times and this was a huge problem as the work usually

    progressed at the quickest pace only after 4 PM when the heat receded.

  • 8/9/2019 Report Dhaval

    33/35

    33

    A picture showing the dust storm.

    y At times there was rainfall accompanied by heavy winds and this was also a

    major obstacle to progress. There was one such incident when the wind was

    very heavy and this caused a lot of damages to the roof sheeting.

    (i)The scaffolding which collapsed (ii) The roof sheeting which was damaged

    Effects of the wind storm.

  • 8/9/2019 Report Dhaval

    34/35

    34

    CHAPTER 4

    RECOMMENDATIONS FOR IMPROVEMENT

    During my two months of training at Kirby, I totally felt the dedication and

    commitment of the Kirby employees towards improvement a every step. Some of the

    areas in which a lot of improvement is required are:

    1. Even though some amount of discipline was observed in the material

    storage yard in dumping large members like primary and secondary

    members by the builder, the smaller items like the sag rods, nuts and

    bolts were dumped haphazardly. This resulted in a lot of wastage of

    time in searching for the materials. Instead, the builder can take more

    care in staking the materials separately according to material size,

    purpose and frequency of use.

    2. It is important to educate the supervisors and labor about the

    importance of material management which may help to achieve greater

    control over the materials.

    3. It would be better if the materials from the plant are shipped based on

    the priority of phases. Many a times it so happens that the materials

    that are required at a much later stage arrives at the site and those

    which are required at utmost priority.

    4. SAP:

    SAP- ERP software may be upgraded so that it can be used by

    site engineers and managers to update the daily progress of

    various activities which helps the middle and top management

    to get the real time status of various projects at different

    locations. This helps to exercise greater control over the

    projects and in taking strategic decisions.

  • 8/9/2019 Report Dhaval

    35/35

    CHAPTER 4

    CONCLUSION

    It was indeed a wonderful learning experience to be a part of such a huge

    project, be it in terms of tonnage of steel or cost of the project or the manpower

    involved. I have gained a lot of insight into PEB, its functioning and its erection

    process. Also material management is very important in such projects and hence

    utmost importance must be given to this aspect. I was trained very well in this regard

    and I am sure that this experience will help me in the future.