Replacement of N. Carlin Springs Road Bridge over George Mason Dr. Approximate schedule with phases and proposed Maintenance of Travel (MOT) plans February 2017

Transcript of Replacement of N. Carlin Springs Road Bridge over George ... · Replacement of N. Carlin Springs...

Page 1: Replacement of N. Carlin Springs Road Bridge over George ... · Replacement of N. Carlin Springs Road Bridge over George Mason Dr. Approximate schedule with phases and proposed Maintenance

Replacement of N. Carlin Springs Road Bridge over George Mason Dr.

Approximate schedule with phases and proposed Maintenance of Travel (MOT) plans

February 2017

Page 2: Replacement of N. Carlin Springs Road Bridge over George ... · Replacement of N. Carlin Springs Road Bridge over George Mason Dr. Approximate schedule with phases and proposed Maintenance

Project Elements

• Removal of existing bridge span over George Mason Drive

• Construction of new bridge with four travel lanes, bike lanes, wider sidewalks, jointless deck, higher clearance and refurbished bridge abutments

• Installation of new sanitary sewer line under N. Abingdon Street and Carlin Springs Road

• Site restoration & enhancement

Page 3: Replacement of N. Carlin Springs Road Bridge over George ... · Replacement of N. Carlin Springs Road Bridge over George Mason Dr. Approximate schedule with phases and proposed Maintenance

5’ 25.5’ 4’ 25.5’ 5’

8’ 5’ 11’ 10.5’ 10.5’ 11’ 5’ 8’

Existing Cross Section – 65’ Wide

Existing Centerline

Final Centerline

Planned Cross Section – 69’ Wide

Page 4: Replacement of N. Carlin Springs Road Bridge over George ... · Replacement of N. Carlin Springs Road Bridge over George Mason Dr. Approximate schedule with phases and proposed Maintenance

New Bridge’s Design

Page 5: Replacement of N. Carlin Springs Road Bridge over George ... · Replacement of N. Carlin Springs Road Bridge over George Mason Dr. Approximate schedule with phases and proposed Maintenance

Projected Schedule

• Spring 2017 – Advertisement for contractor bids on project

• Summer 2017 – Award of contract• Fall 2017 – Construction begins• Winter 2018/19 – Construction

complete• Summer 2019 – Landscape

restoration

Page 6: Replacement of N. Carlin Springs Road Bridge over George ... · Replacement of N. Carlin Springs Road Bridge over George Mason Dr. Approximate schedule with phases and proposed Maintenance

Permitted work times

• Most work in the roadway will take place during weekdays between 9:00 AM and 4:00 PM

• Work outside of the roadway can begin at 7:00 AM on weekdays

• If needed, work may take place on weekends or overnight (but only with special permission) to address significant tasks that must be expedited.

• There will be two periods of total roadway closures; each is anticipated to be five days or less in duration. County will work with contractor to expedite.

• Vehicle and pedestrian access to/from adjacent properties will be maintained at all times

Page 7: Replacement of N. Carlin Springs Road Bridge over George ... · Replacement of N. Carlin Springs Road Bridge over George Mason Dr. Approximate schedule with phases and proposed Maintenance

Phases of Bridge Replacement

• Phase 1 – The center median and existing southern span (currently northbound lanes) are removed. A temporary edge barrier is installed. Approximate duration is one month.

• Phase 2 – All vehicle & pedestrian traffic is shifted to northern span (currently southbound lanes). There will be one travel lane per direction plus the existing sidewalk. New southern span is built. Approximate duration is 6 months.

• Phase 3- After new southern span is built, all traffic is shifted to it. Again one travel lane per direction plus a temporary walkway. Existing northern span is removed. New northern span is built. Approximate duration is 6 months.

• Phase 4 – After the northern span is built the two halves are joined. All four vehicular traffic lanes are restored. Temporary sidewalks and barriers are replaced by permanent sidewalks and railings. Approximate duration is 2 months.

Page 8: Replacement of N. Carlin Springs Road Bridge over George ... · Replacement of N. Carlin Springs Road Bridge over George Mason Dr. Approximate schedule with phases and proposed Maintenance

Phase 1 Work & Maintenance of Traffic

• Set up work site

• Removal of roadway median; existing bridge is split into two parallel bridge spans. A temporary barrier is installed between the spans.

• Southern span (northbound lanes) is removed.

• During median removal, traffic is reduced to one lane per direction

• When south span is removed, all traffic on Carlin Springs and George Mason must be rerouted via detours (up to five days duration)

Page 9: Replacement of N. Carlin Springs Road Bridge over George ... · Replacement of N. Carlin Springs Road Bridge over George Mason Dr. Approximate schedule with phases and proposed Maintenance

Detours - Used for up to 5 days during Phases 1 and 3

Page 10: Replacement of N. Carlin Springs Road Bridge over George ... · Replacement of N. Carlin Springs Road Bridge over George Mason Dr. Approximate schedule with phases and proposed Maintenance

Phase 2 Work & Maintenance of Traffic

• Construction of new south side bridge section

• All traffic (vehicles and pedestrians) is shifted to the north span

Page 11: Replacement of N. Carlin Springs Road Bridge over George ... · Replacement of N. Carlin Springs Road Bridge over George Mason Dr. Approximate schedule with phases and proposed Maintenance

Phase 3 Work & Maintenance of Traffic

• Removal of existing north side span

• Construction of new north side bridge span

• Construction of new sewer line in Carlin Springs Rd and Abingdon Street.

• All traffic (vehicles and pedestrians) is shifted onto the new south side span.

• When north span is removed, all traffic on Carlin Springs & George Mason Drive must be rerouted via detours (up to five days duration)

• Abington Street within sewer line construction zone is reduced to one lane (Northbound only)

Page 12: Replacement of N. Carlin Springs Road Bridge over George ... · Replacement of N. Carlin Springs Road Bridge over George Mason Dr. Approximate schedule with phases and proposed Maintenance

Sewer Line Construction

Page 13: Replacement of N. Carlin Springs Road Bridge over George ... · Replacement of N. Carlin Springs Road Bridge over George Mason Dr. Approximate schedule with phases and proposed Maintenance

Phase 4 Work & Maintenance of Traffic

• Refurbishment of bridge abutments and wing walls

• Completion of permanent sidewalks on new bridge

• Vehicular traffic on Carlin Springs Road will be returned to two lanes per direction across bridge

• Pedestrian traffic will be restored as permanent sidewalks are completed

Page 14: Replacement of N. Carlin Springs Road Bridge over George ... · Replacement of N. Carlin Springs Road Bridge over George Mason Dr. Approximate schedule with phases and proposed Maintenance

Completion

• Removal of construction trailer, temporary signage and building materials

• Restoration of site and planting of new landscaping

• No impacts on traffic movement (vehicles or pedestrians)

Page 15: Replacement of N. Carlin Springs Road Bridge over George ... · Replacement of N. Carlin Springs Road Bridge over George Mason Dr. Approximate schedule with phases and proposed Maintenance

Expected Construction Concerns

• Noise & dust from demolition and construction

• Cut-through traffic as a result of short-term lane closures and traffic detours

• Potential traffic congestion from lane reductions & detours during construction

• Some access restriction on N. Abingdon Street

• Pedestrian crossings of N. Carlin Springs Road at N. Wakefield and N. Edison streets

• Rerouting or disruptions to Metrobus Route 25 service

Page 16: Replacement of N. Carlin Springs Road Bridge over George ... · Replacement of N. Carlin Springs Road Bridge over George Mason Dr. Approximate schedule with phases and proposed Maintenance

Landscaping – Tree Removal & Replacement

Page 17: Replacement of N. Carlin Springs Road Bridge over George ... · Replacement of N. Carlin Springs Road Bridge over George Mason Dr. Approximate schedule with phases and proposed Maintenance

Community Preconstruction Meeting to be held in late summer or early fall

• Community members to meet with Contractor and key County staff

• Will provide more details about schedules, detours and process

• Civic associations and all nearby properties will receive invites

• Updates to be provided on County’s project webpage

• Date and location TBD

• Web page: www.arlingtonva.us/projects/carlin-springs-road-bridge/

Page 18: Replacement of N. Carlin Springs Road Bridge over George ... · Replacement of N. Carlin Springs Road Bridge over George Mason Dr. Approximate schedule with phases and proposed Maintenance

Contacts:

Web page: www.arlingtonva.us/projects/carlin-springs-road-bridge/

• Bridge Engineer – Ravinder Singh, 703 228-3661,

[email protected]

• Sanitary Sewer Engineer – Jaime Rojas, [email protected]

• Project Manager – Richard Viola, 703 228-3699, [email protected]

Page 19: Replacement of N. Carlin Springs Road Bridge over George ... · Replacement of N. Carlin Springs Road Bridge over George Mason Dr. Approximate schedule with phases and proposed Maintenance

Details of Maintenance of Traffic (MOT) Phases

Page 20: Replacement of N. Carlin Springs Road Bridge over George ... · Replacement of N. Carlin Springs Road Bridge over George Mason Dr. Approximate schedule with phases and proposed Maintenance

MOT Phase 1- Full Closure with Detours

Page 21: Replacement of N. Carlin Springs Road Bridge over George ... · Replacement of N. Carlin Springs Road Bridge over George Mason Dr. Approximate schedule with phases and proposed Maintenance

MOT Phase 2 – Travel on North Side Only

Page 22: Replacement of N. Carlin Springs Road Bridge over George ... · Replacement of N. Carlin Springs Road Bridge over George Mason Dr. Approximate schedule with phases and proposed Maintenance

MOT Phase 3 – Travel on South Side Only

Page 23: Replacement of N. Carlin Springs Road Bridge over George ... · Replacement of N. Carlin Springs Road Bridge over George Mason Dr. Approximate schedule with phases and proposed Maintenance

MOT Phase 4 – Completion of Sidewalks