RENO CONSOLIDATED 20-01 PROJECT...May – Virtual Project Presentation 2020 December – Final...
Transcript of RENO CONSOLIDATED 20-01 PROJECT...May – Virtual Project Presentation 2020 December – Final...
![Page 1: RENO CONSOLIDATED 20-01 PROJECT...May – Virtual Project Presentation 2020 December – Final Design 2021 Construction – Late Summer SCHEDULE 2020 - 2021 Total Project Budget $4.4](https://reader033.fdocuments.in/reader033/viewer/2022050122/5f523acf44263538dc720b71/html5/thumbnails/1.jpg)
RENO CONSOLIDATED20-01 PROJECTCalifornia Ave.: Booth St. to Hunter Lake Dr.Mayberry Dr.: Memory Ln. to California Ave. First St.: Sierra St. to Virginia St.Virtual Project Presentation| May 27, 2020
In Partnership with
Consultant
![Page 2: RENO CONSOLIDATED 20-01 PROJECT...May – Virtual Project Presentation 2020 December – Final Design 2021 Construction – Late Summer SCHEDULE 2020 - 2021 Total Project Budget $4.4](https://reader033.fdocuments.in/reader033/viewer/2022050122/5f523acf44263538dc720b71/html5/thumbnails/2.jpg)
PROJECT PURPOSE AND GOALS
Pavement Preservation Generally Deficient
Roadway SurfacesMulti Modal Access New and Improved
Connectivity Inclusive Transport
Modes
![Page 3: RENO CONSOLIDATED 20-01 PROJECT...May – Virtual Project Presentation 2020 December – Final Design 2021 Construction – Late Summer SCHEDULE 2020 - 2021 Total Project Budget $4.4](https://reader033.fdocuments.in/reader033/viewer/2022050122/5f523acf44263538dc720b71/html5/thumbnails/3.jpg)
Mem
ory
Ln.
LegendProject Limits
California Avenue and Mayberry Drive Roadway Rehabilitation ADA Improvements Bicycle and Pedestrian
Connectivity Improved Safety
PROJECT AREA
![Page 4: RENO CONSOLIDATED 20-01 PROJECT...May – Virtual Project Presentation 2020 December – Final Design 2021 Construction – Late Summer SCHEDULE 2020 - 2021 Total Project Budget $4.4](https://reader033.fdocuments.in/reader033/viewer/2022050122/5f523acf44263538dc720b71/html5/thumbnails/4.jpg)
Before: Free right-turn
encourages speeding No Crosswalks Eastbound-thru
challenging sight distance
Northbound-thru & eastbound left-turn movements prohibited
PROJECT SCOPECalifornia Avenue and Mayberry Drive Intersection
![Page 5: RENO CONSOLIDATED 20-01 PROJECT...May – Virtual Project Presentation 2020 December – Final Design 2021 Construction – Late Summer SCHEDULE 2020 - 2021 Total Project Budget $4.4](https://reader033.fdocuments.in/reader033/viewer/2022050122/5f523acf44263538dc720b71/html5/thumbnails/5.jpg)
PROJECT SCOPECalifornia Avenue and Mayberry Drive Intersection
After: Reconfigure to 4-way
intersection with crosswalks
Reduced speeds entering neighborhood
Less conflict points between pedestrians, bicycles, & vehicles
Safer Roadway
![Page 6: RENO CONSOLIDATED 20-01 PROJECT...May – Virtual Project Presentation 2020 December – Final Design 2021 Construction – Late Summer SCHEDULE 2020 - 2021 Total Project Budget $4.4](https://reader033.fdocuments.in/reader033/viewer/2022050122/5f523acf44263538dc720b71/html5/thumbnails/6.jpg)
RTC RIDE Route 16 - Idlewild Westbound Route Stripe wider travel lane
Bus Stop on California Avenue Relocate 200’ east to Arbutus Street/Forson Drive Intersection Widen sidewalk for ADA Compliance Add Street Lighting
Bus Stop on Hunter Lake Drive at California Avenue Widen sidewalk for ADA Compliance
PROJECT SCOPETransit Improvements
![Page 7: RENO CONSOLIDATED 20-01 PROJECT...May – Virtual Project Presentation 2020 December – Final Design 2021 Construction – Late Summer SCHEDULE 2020 - 2021 Total Project Budget $4.4](https://reader033.fdocuments.in/reader033/viewer/2022050122/5f523acf44263538dc720b71/html5/thumbnails/7.jpg)
Bus Stop Improvements
Tie-In to Recently Constructed sidewalk & street improvements at
Booth Street
Adjustment to Width of Westbound Travel Lane to Better Accommodate
BusesVarying Sidewalk Widths
to Minimize Impact to Existing Utility Poles
Adding Sidewalk and Bike Facilities along both
sides of California Avenue for connectivity from Hunter Lake Drive
to Booth Street
PROJECT SCOPE
![Page 8: RENO CONSOLIDATED 20-01 PROJECT...May – Virtual Project Presentation 2020 December – Final Design 2021 Construction – Late Summer SCHEDULE 2020 - 2021 Total Project Budget $4.4](https://reader033.fdocuments.in/reader033/viewer/2022050122/5f523acf44263538dc720b71/html5/thumbnails/8.jpg)
HUN
TER
LAKE
DR
WES
TFIE
LD A
VE
CONCEPTUAL DESIGNCalifornia Avenue: Hunter Lake Drive to Arbutus Street/Forson Drive IntersectionMayberry Drive: Memory Lane to California Avenue
![Page 9: RENO CONSOLIDATED 20-01 PROJECT...May – Virtual Project Presentation 2020 December – Final Design 2021 Construction – Late Summer SCHEDULE 2020 - 2021 Total Project Budget $4.4](https://reader033.fdocuments.in/reader033/viewer/2022050122/5f523acf44263538dc720b71/html5/thumbnails/9.jpg)
CONCEPTUAL DESIGNCalifornia Avenue: Forson Drive to Booth Street
![Page 10: RENO CONSOLIDATED 20-01 PROJECT...May – Virtual Project Presentation 2020 December – Final Design 2021 Construction – Late Summer SCHEDULE 2020 - 2021 Total Project Budget $4.4](https://reader033.fdocuments.in/reader033/viewer/2022050122/5f523acf44263538dc720b71/html5/thumbnails/10.jpg)
Village Shopping Center
California Ave.H
unte
r Lak
e D
r.
Boot
h St
.
Hunter LakeElementary
Raley’sM
emor
y Ln
.
![Page 11: RENO CONSOLIDATED 20-01 PROJECT...May – Virtual Project Presentation 2020 December – Final Design 2021 Construction – Late Summer SCHEDULE 2020 - 2021 Total Project Budget $4.4](https://reader033.fdocuments.in/reader033/viewer/2022050122/5f523acf44263538dc720b71/html5/thumbnails/11.jpg)
West First Street Roadway Rehabilitation ADA Improvements Sidewalk Replacement
PROJECT AREALegend
Project Limits
![Page 12: RENO CONSOLIDATED 20-01 PROJECT...May – Virtual Project Presentation 2020 December – Final Design 2021 Construction – Late Summer SCHEDULE 2020 - 2021 Total Project Budget $4.4](https://reader033.fdocuments.in/reader033/viewer/2022050122/5f523acf44263538dc720b71/html5/thumbnails/12.jpg)
PROJECT SCOPEWest First Street
Sidewalks & Ramps: ADA Improvements
Sierra Street Intersection: Full Reconstruct
Sierra Street to Virginia Street: Grind and Overlay
![Page 13: RENO CONSOLIDATED 20-01 PROJECT...May – Virtual Project Presentation 2020 December – Final Design 2021 Construction – Late Summer SCHEDULE 2020 - 2021 Total Project Budget $4.4](https://reader033.fdocuments.in/reader033/viewer/2022050122/5f523acf44263538dc720b71/html5/thumbnails/13.jpg)
2020 February – Preliminary Design
2020 May – Virtual Project Presentation
2020 December – Final Design
2021 Construction – Late Summer
SCHEDULE 2020 - 2021
![Page 14: RENO CONSOLIDATED 20-01 PROJECT...May – Virtual Project Presentation 2020 December – Final Design 2021 Construction – Late Summer SCHEDULE 2020 - 2021 Total Project Budget $4.4](https://reader033.fdocuments.in/reader033/viewer/2022050122/5f523acf44263538dc720b71/html5/thumbnails/14.jpg)
Total Project Budget $4.4 Million Investment in our Community
Funded with RTC-5 Fuel Tax
Next Steps Preliminary and Final Design Right-of-Way Utilities Construction!
BUDGET AND NEXT STEPS
![Page 15: RENO CONSOLIDATED 20-01 PROJECT...May – Virtual Project Presentation 2020 December – Final Design 2021 Construction – Late Summer SCHEDULE 2020 - 2021 Total Project Budget $4.4](https://reader033.fdocuments.in/reader033/viewer/2022050122/5f523acf44263538dc720b71/html5/thumbnails/15.jpg)
Complete a comment/question form and mail to:Judy Tortelli, RTC Project Manager1105 Terminal Way, Suite #108Reno, NV 89502
Email: [email protected] Phone: (775) 335-1824 Visit our website at rtcwashoe.com and search Reno
Consolidated 20-01 Project ***Comments Due by June 30, 2020*** Comment Matrix Posted on Website Follow RTC on Social Media
COMMENTS OR QUESTIONS?
![Page 16: RENO CONSOLIDATED 20-01 PROJECT...May – Virtual Project Presentation 2020 December – Final Design 2021 Construction – Late Summer SCHEDULE 2020 - 2021 Total Project Budget $4.4](https://reader033.fdocuments.in/reader033/viewer/2022050122/5f523acf44263538dc720b71/html5/thumbnails/16.jpg)
Thank you forWatching!Judy Tortelli – RTC Project Manager
Your RTC. Our Community.rtcwashoe.com
In Partnership with
Consultant