Renewable energy and grid integration energy transition

28
The Biogas Thailand Forum 2015 "Renewable Energy and Grid Integration / Energy transition" 25 November 2015 in Chiang Mai

Transcript of Renewable energy and grid integration energy transition

Page 1: Renewable energy and grid integration   energy transition

The Biogas Thailand Forum 2015

"Renewable Energy and Grid Integration / Energy transition"

25 November 2015 in Chiang Mai

Page 2: Renewable energy and grid integration   energy transition

Revise Connecting Code & Set up an inspection and standard certification agent

IMPACT of Renewable Connection

Tasks -ENERGY AND ENVIRONMENTAL ENGINEERING DEPARTMENT

CONTENTS

Page 3: Renewable energy and grid integration   energy transition

Structure of Power Sector: Enhanced Single Buyer Model

IPP SPP VSPP Import

(34%) (12%) (4%) (7%)

EGAT

MEA PEA

(42%)

(100%)

(30%) (70%)

Generation Capacity

(35,329 MW*)

Transmission Network

(32,503 Circuit-km)

Distribution& Retail

(168,650 GWh)(20.5 Million Customers)

(99.8% access)

Private Power Producers

State Owned Enterprises (SOEs)

As of December 2013

* Contracted Capacity

EGAT

Voltage Level 500 kV 300 kV 230 kV 132 kV** 115 kV 69 kV Total

Transmission Line (circuit-km)

4,167 23 14,505 9 13,780 19 32,503

Transmission Line Length by Voltage

** Thailand-Malaysia Transmission Line

Source: Electricity Generating Authority of Thailand 3

Network System

Operator & Single Buyer

IPPs = Independent Power Producers

(Capacity sold to EGAT > 90 MW)

SPPs = Small Power Producers

(Capacity sold to EGAT ≤ 90 MW)

VSPPs = Very Small Power Producers

(Capacity sold to MEA/PEA ≤10 MW)

Page 4: Renewable energy and grid integration   energy transition

Main responsibilities

of ERC

Granting of license/and develop operate tracking scheme

Price regulation :

Fuel Adjustment Charge (FT) and pipeline tariff

Regulating competition

Assurance of sufficient supply of energy

Promotion of participation of energy consumers: to further develop rural

areas and communities

Organizational Development

Engineering Standard for:

Regulations/Standardization, Interoperability

Safety , Alleviate Environmental impact for construction &

operation

ensure fair rates to consumers

Settling disputes between consumers and operators

Power Development Fund and 13Regional Energy Consumer Committee

4

Engineering standard for supply and system

operation:

Access Code

Dispatching

Energy Regulatory Commission (ERC): Energy-Related Policies and Activities

seeks to create a new dialogue between civil society and sector actors: Representatives of

Government, Utilities, NGO

Ensure that all license holders are capable of

financing the undertaking of their licensed activities

Tasks -ENERGY AND ENVIRONMENTAL ENGINEERING DEPTMENT

-Establishment of Technical Standards and Safety of the Energy Industry Operation.-Review and Analysis of Efficiency of Power Plant Operating Data (Licensees proposed investments).

-Preparing Specific Requirements for Connection of Renewable Energy Power Systems (REPS).-Supporting steering committee and working group for revision Grid Code Connecting Code and Distribution Code.

Page 5: Renewable energy and grid integration   energy transition

Energy Industry Act 2007

DIVISION 3 REGULATION OF THE ENERGY INDUSTRY OPERATION

PART 4 THE ENERGY NETWORK SYSTEM AND THE ENERGY NETWORK SYSTEM OPERATOR

(Section 79 – Section 88)

Section 81 A licensee who owns an energy network system must allow other licensees or energy industry operators to utilize or connect to his system in accordance with terms stipulated and announced by the licensee who owns the energy network system.

The terms under paragraph one shall comprise term on connection of an energy network system, term on utilization of energy network system facilities and term on energy network system operation, such terms shall be based on the following principles:

(1) They must not adversely affect security, safety and quality of energy system.

(2) They must not disadvantage energy consumers and the public.(3) They must not discriminate or hinder other licensees or energy industry operators.

(4) The technical specifications at the end-use points or at the point of connection to an energy network system must be clear, technically feasible and must not impose an undue burden on the person who requests utilization of or connection to the energy network system.(5) They must have a clear description of duty and responsibility of a person who requests utilization of and connection to an energy network system and a person who allows utilization of or connection to the system.

(6) Any other characteristic as announced by the Commission.

The term under paragraphs one and two shall not cause a licensee who owns an energy network system to lose benefits or to be at a disadvantage in

Page 6: Renewable energy and grid integration   energy transition

renewable energy

Status of renewable energy in Year 2014 compare with the target in Alternative Energy Development Plan: AEDP of 20% for 20 years as follows

Year SOLAR WIND HYDRO MSW BIOMASS BIOGASENERGY CROPS

TOTAL (MW)

2014 1,298.5 224.5 3,048.4 65.7 2,541.8 311.5 - 7,490.4

2036 6,000.0 3,002.0 3,282.4 500.0 5,570.0 600.0 680.0 19,634.4

REMARK: * INSTALLED CAPACITYSOURCE: POWER DEVELOPMENT PLAN 2015

YEAR 2014 YEAR 2026 YEAR 2036

IMPORT 7 10 - 15 15 - 20

COAL AND LIGNITE 20 20 - 25 20 - 25

RE AND HYDRO POWER 8 10 – 20 15 - 20

NATURAL GAS 64 45 -50 30 - 40

NUCLEAR - - 0 -5

DIESEL/FUEL OIL 1 - -

Page 7: Renewable energy and grid integration   energy transition

Security Energy System & Reverse Power Flow from

RENEWABLE ENERGY

77

Page 8: Renewable energy and grid integration   energy transition

Reverse Power Flow can make Margin Reducing in

Transmission System, Contingency Reserves are

designed for only EMERGENCY CASE.

Otherwise, Reverse Power Flow can be cause reliability

reducing in the power system and might occur missing

N-1 Criterion and the black out.

SECURITY ENERGY SYSTEMThe N-1 Criterion

8

Page 9: Renewable energy and grid integration   energy transition

22/33 kV

115 kV

.

./ .

Generator

Transmission LineTransmission Line

Length > 60 km.

RE

RE

RE

RE

RE

115 kV

22/33 kV

.

./ .

DS switch

Tie Feeder

ความมัน่คงระบบไฟฟ้า ระบบไฟฟ้าไมร่องรับ N-1

เม่ือเกิดเหตุขัดข้องระบบไม่รองรับ N-1

9

ศักยภาพของสายส่งลดลง เน่ืองจาก REที่ไหลย้อน

ระบบส่งไฟฟ้าของประเทศไทยไม่ได้ถูกออกแบบมาเพื่อรองรับ Source จาก Distribution Feeder

Page 10: Renewable energy and grid integration   energy transition

ค่าความสญูเสียของระบบไฟฟ้า (Loss)

CASE STUDY RE 75% of each Transformer

Power Demand การเกิดไฟไหลยอ้น (Reverse Power)

Load 100% Not Occur (Receive from Transmission System)

Load 75% Not Occur

Load 50% Power Reverse Flow 12.5 MVAเกิดไฟไหลยอ้น 12.5 MVA

75% of Transformer 115/22-33 kV Size 50MVA = 37.5 MVA

10

Page 11: Renewable energy and grid integration   energy transition

IMPACT of Renewable Connection

IMPACT of Renewable Connection• FULL GRID CONNECTION CAPACITIES• REVERSE POWER FLOWS• VOLTAGE CONTROL IN DISTRIBUTION

GRID• PROTECTION COORDINATION IN

DISTRIBUTION GRID

Develop real time data monitoring

forecast for dispatchable VSPP

Use smart grid device & equipment

(Move to smart grid)

Revise Connecting Code

Energy mix and Asset planning

Plan for using renewable energy

(Find exactly RE potential area)

Redesign power grid for RE connection

(Expand grid to RE area)

Revise Power Purchase

Agreement & Contract

Feeder Management

Centralized/Distributed Operation Model and

business modelsBalancing Technology in various

time ranges

Page 12: Renewable energy and grid integration   energy transition

IMPACT of Renewable Connection

Revise Connecting Code & Set up an inspection and standard certification agent

A (Draft)Requirements on Power Network System Connection with Distribution Authority(MEA/PEA) B.E. 2558 (Old B.E. 2551)

B Regulation for an Invertor Used in Grid – Connected Power Generating System

C Set up a license as an inspection and standard certification agent for equipment connected to an energy network system

Section 76 Any person wishing to become an inspection and standard certification agent for equipment connected to an energy network system shall have to acquire a license as an inspection and standard certification agent from the Commission.

Section 73 Standards of equipment used to connect an energy network system of a licensee who has its own system, including methods of inspection and certification of inspection results, shall be in conformity with the regulations prescribed by the Commission.

Regulations under paragraph one may require that certain types of equipment used to connect to an energy network system be inspected and certified prior to their utilization in energy industry operation.

In preparation of regulations under paragraph one, a licensee who has an energy network system shall prepare the details for consideration to the Commission.

Section 82 In the case where the Commission views that the term on connection of an energy network system, the term on utilization of

energy network system facilities and the term on energy network system operation do not comply with the principles under Section 81, the Commission shall have the power to order the licensee who issues such terms to revise or improve the terms to comply with the principles under Section 81.

Page 13: Renewable energy and grid integration   energy transition

Your personal experiences with renewable energy

Revise Connecting Code & Set up an inspection and standard certification agent

A (Draft)Requirements on Power Network System Connection with Distribution Authority(MEA/PEA) B.E. 2558 (Old B.E. 2551)

B Regulation for an Invertor Used in Grid – Connected Power Generating System

C Set up a license as an inspection and standard certification agent for equipment connected to an energy network system

Different inverter testing procedures for MEA and PEA //Type testing for selected inverter of a defined series to certify all inverters of the same series //Routine testing for all applied inverters required //Confusion as to the “official bodies” that are allowed to perform testing

Harmonize testing procedures between both authorities (PEA/MEA)

Limitation for grid connection capacity/Supervisory Control And Data Acquisition/Distribution Management System (DMS)/P.F. Control

/Dispatching for RE-VSPP/Voltage Control/Grid-connected Inverter/etc.

Page 14: Renewable energy and grid integration   energy transition

Your personal experiences with renewable energy

(Draft)Requirements on Power Network System Connection with Distribution Authority

(MEA/PEA) B.E. 2558 (Old B.E. 2551)0

Regulation for an Invertor Used in Grid – Connected Power Generating System

Page 15: Renewable energy and grid integration   energy transition
Page 16: Renewable energy and grid integration   energy transition
Page 17: Renewable energy and grid integration   energy transition

ส ำนักงำนคณะกรรมกำรก ำกบักจิกำรพลงังำน319 อำคำรจัตรัุสจำมจรุ ีชัน้ 19 ถนนพญำไท แขวงปทมุวัน เขตปทมุวัน กรงุเทพ 10330โทร : 0-2207-3599 http://www.erc.or.th

THANK YOU

The Office of the Energy Regulatory Commission of Thailand (OERC)

Telephone 0-2207-3599Facsimile 0-2207-3502Website: www.erc.or.th

Page 18: Renewable energy and grid integration   energy transition

BACK UP

Page 19: Renewable energy and grid integration   energy transition

Back UpEnergy Industry Act 2007

Page 20: Renewable energy and grid integration   energy transition

Energy Industry Act 2007

DIVISION 3

REGULATION OF THE ENERGY INDUSTRY OPERATION

PART 3

ESTABLISHMENT OF STANDARDS AND SAFETY OF THE ENERGY INDUSTRY OPERATION

PART 4

THE ENERGY NETWORK SYSTEM AND THE ENERGY NETWORK SYSTEM OPERATOR

Page 21: Renewable energy and grid integration   energy transition

Energy Industry Act 2007

DIVISION 3 REGULATION OF THE ENERGY INDUSTRY OPERATION

PART 3 ESTABLISHMENT OF STANDARDS AND SAFETY OF THE ENERGY INDUSTRY OPERATION

( Section 72 - Section 78 )

Section 72 Energy industry operation shall comply with engineering standards and shall ensure safety pursuant to the regulations prescribed by the Commission which are as follows:

(1) shall not impose an undue burden on the licensees;

(2) shall not be so rigid that they would limit or hinder competition;

(3) shall not offer benefits to any particular licensee; and

(4) shall be transparent.

In the event that energy industry operation of a licensee fails to comply with the regulations under paragraph one, the Commission shall have the authority to order the licensee to improve or to rectify the operation.

Page 22: Renewable energy and grid integration   energy transition

Energy Industry Act 2007

DIVISION 3 REGULATION OF THE ENERGY INDUSTRY OPERATION

PART 3 ESTABLISHMENT OF STANDARDS AND SAFETY OF THE ENERGY INDUSTRY OPERATION

( Section 72 - Section 78 )

Section 73 Standards of equipment used to connect an energy network system of a licensee who has its own system, including methods of inspection and certification of inspection results, shall be in conformity with the regulations prescribed by the Commission.

Regulations under paragraph one may require that certain types of equipment used to connect to an energy network system be inspected and certified prior to their utilization in energy industry operation.

In preparation of regulations under paragraph one, a licensee who has an energy network system shall prepare the details for consideration to the Commission.

Page 23: Renewable energy and grid integration   energy transition

Energy Industry Act 2007

DIVISION 3 REGULATION OF THE ENERGY INDUSTRY OPERATION

PART 3 ESTABLISHMENT OF STANDARDS AND SAFETY OF THE ENERGY INDUSTRY OPERATION

( Section 72 - Section 78 )

Section 74 A licensee shall have to maintain, repair and improve an energy network system, equipment or other devices used for energy industry operation to ensure that their operating efficiency and standards comply with the regulations under Section 72, paragraph one. In the case of any damage or breakdown, repair must be expeditiously taken to restore the operation.

Section 75 In establishing the standards under Section 72, paragraph one, and Section 73, paragraph one, the Commission may refer to the standards prescribed by other agencies having authority and duties under the law on those respective matters.

Section 76 Any person wishing to become an inspection and standard certification agent for equipment connected to an energy network system shall have to acquire a license as an inspection and standard certification agent from the Commission.

The qualifications of an applicant for a license to be an inspection and standard certification agenty, submission of application for a license, issuance of a license, extension of a license, term of a license, fees for issuance and extension of a license, including fee for the inspection and certification, shall be in conformity with the criteria, procedures and conditions prescribed by theCommission.

Page 24: Renewable energy and grid integration   energy transition

Energy Industry Act 2007

DIVISION 3 REGULATION OF THE ENERGY INDUSTRY OPERATION

PART 3 ESTABLISHMENT OF STANDARDS AND SAFETY OF THE ENERGY INDUSTRY OPERATION

( Section 72 - Section 78 )

Section 77 The Commission shall have the authority to revoke a license for inspection and standard certification agent for equipment used to connect an energy network system in the following cases:

(1) lack of qualifications as stipulated in the announcement issued under Section 76, paragraph two;

(2) dishonest inspection, reporting of inspection result, or certification of inspection results;

(3) delay in inspection, report of inspection results or certification of inspection results, with undue reasons, causing serious damage to a person requesting inspection; or

(4) having inspectors whose qualifications do not meet standards or whose numbers are less than requirement as stipulated in the announcement issued under Section 76, paragraph two.

Section 78 Revocation of a license for an inspection and standard certification agency under Section 77 shall not affect standard certification undertaken by the agency prior to the revocation of the license except that the certification previously made was below the standards specified by the Commission, in which case the Commission may consider ordering revocation of such certification.

In the case where any person is affected by damage from standard certification which is below standards and has been revoked under paragraph one, the inspection and standard certification agency whose license is revoked shall be liable for the compensation for such damages.

Page 25: Renewable energy and grid integration   energy transition

Energy Industry Act 2007

DIVISION 3 REGULATION OF THE ENERGY INDUSTRY OPERATION

PART 4 THE ENERGY NETWORK SYSTEM AND THE ENERGY NETWORK SYSTEM OPERATOR

(Section 79 – Section 88)

Section 79 A licensee who owns an energy network system shall carry out the operation in line with what is stipulated in the energy network

system expansion plan.

A licensee who owns an energy network system and is a government agency as determined by the Commission shall develop an energy network system expansion plan and present it to the Minister for further submission to

the Cabinet for approval.

In considering of the energy network system expansion plan under paragraph two, the Commission shall provide comments on the subject. In this regard, if the mentioned plan has significant impacts on general public, the Commission shall organize an opinion hearing process in accordance with Section 26.

A licensee who owns an energy network system and is not a government agency under paragraph two shall develop an energy network system expansion plan for submission to the Commission for approval in compliance with the scope and criteria specified by the Commission.

Section 80 A licensee who owns an energy network system shall carry out energy industry operation fairly without unjust discrimination.

Page 26: Renewable energy and grid integration   energy transition

Energy Industry Act 2007

DIVISION 3 REGULATION OF THE ENERGY INDUSTRY OPERATION

PART 4 THE ENERGY NETWORK SYSTEM AND THE ENERGY NETWORK SYSTEM OPERATOR

(Section 79 – Section 88)

Section 81 A licensee who owns an energy network system must allow other licensees or energy industry operators to utilize or connect to his system in accordance with terms stipulated and announced by the licensee who owns the energy network system.

The terms under paragraph one shall comprise term on connection of an energy network system, term on utilization of energy network system facilities and term on energy network system operation, such terms shall be based on the following principles:

(1) They must not adversely affect security, safety and quality of energy system.

(2) They must not disadvantage energy consumers and the public.

(3) They must not discriminate or hinder other licensees or energy industry operators.

(4) The technical specifications at the end-use points or at the point of connection to an energy network system must be clear, technically feasible and must not impose an undue burden on the person who requests utilization of or connection to the energy network system.

(5) They must have a clear description of duty and responsibility of a person who requests utilization of and connection to an energy network system and a person who allows utilization of or connection to the system.

(6) Any other characteristic as announced by the Commission.

The term under paragraphs one and two shall not cause a licensee who owns an energy network system to lose benefits or to be at a disadvantage in

Page 27: Renewable energy and grid integration   energy transition

Energy Industry Act 2007

DIVISION 3 REGULATION OF THE ENERGY INDUSTRY OPERATION

PART 4 THE ENERGY NETWORK SYSTEM AND THE ENERGY NETWORK SYSTEM OPERATOR

(Section 79 – Section 88)

Section 82 In the case where the Commission views that the term on connection of an energy network system, the term on utilization of

energy network system facilities and the term on energy network system operation do not comply with the principles under Section 81, the Commission shall have the power to order the licensee who issues such terms to revise or improve the terms to comply with the principles under Section 81.

Section 83 In the case where a licensee or an energy industry operator, wishing to utilize or connect an energy network system, views that

a term on connection of energy network system connection, term on utilization of energy network system facilities and term on energy network system operation do not comply with the principles under Section 81, the licensee or the energy industry operator can make a request to the Commission for consideration.

In the case where the Commission views that the terms do not comply with the principles under Section 81, the Commission shall have the

power to order the licensee who issues such terms to revise or improve the terms to comply with the principles under Section 81.

Section 84 In the case that a licensee who owns an energy network system refuses to allow utilization of or connection to his system, the person who has been refused has the right to make a request to the Commission for consideration. When the Commission has made a decision on the request under paragraph one hereof, the concerned parties shall abide by the decision.

Section 85 A licensee who owns an energy network system must provide a person who requests the utilization of or connection to his system with accurate information necessary for utilization of or connection to the system. He shall not take any action that would disrupt the normal utilization of and connection to an energy network system of other licensee or energy industry operator.

Page 28: Renewable energy and grid integration   energy transition

Energy Industry Act 2007

DIVISION 3 REGULATION OF THE ENERGY INDUSTRY OPERATION

PART 4 THE ENERGY NETWORK SYSTEM AND THE ENERGY NETWORK SYSTEM OPERATOR

(Section 79 – Section 88)

Section 86 A licensee who owns an energy network system must disclose contracts, agreements, conditions and tariffs for the utilization of or connection to his system, according to the criteria, procedures and conditions announced by the Commission.

Section 87 A licensee with an energy network system operator shall be responsible for control, management and overseeing of energy system to ensure balance, security, stability, efficiency and reliability of overall system, and shall have authority and duties to execute other tasks as specified by the Commission under conditions of the license issuance. The licensee with an electricity system operator shall order licensees who operate electricity industry to generate electricity fairly without unjust discrimination.

Section 88 In the case that a person makes a complaint to the Commission that a licensee with an electricity system operator has breached Section 87, paragraph two, the Commission shall make decision on the complaint within thirty days as from the date of receipt of written complaint. In the case where the Commission considers that the licensee with the electricity system operator has breached Section 87, paragraph two, causing damage to the complainant, the Commission shall preliminarily determine amount of compensation for such damage.