Reliance - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/online/... ·...
Transcript of Reliance - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/online/... ·...
• Reliance.
' . ..... j . ... ... ,. ~ . ,., .
Gas Pipelhi~s Limited . l, . ' . :1'\ ~ -~ .....
· I
""· ..... ~---~ ~ M~by_._....~~
Letter No. DNEPL/MoEFCC/EC/01 ~~-~---~~te: 29.06.2015
To, !:~~~--The Member Secretary .0.. ·~ . 0! "·,.,....J' . . : • ... ""'~ lA Division, lndustry-11 , .,,, · ~ Ministry of Environment, Forests and Climate Change, -1!> Indira Paryavaran Bhawan, ...,-'\ \ ~ Aliganj, Jorbagh Road, a1(\ <S \ · · New Delhi-11 0 003. ---
Sub: Request for grant of Environmental Clearance for the proposed Dahej Nagothane Ethane Pipeline (DNEPL} Project of Reliance Gas Pipelines Limited (RGPL}.
Ref: MoEFCC F.No. J-11011/226/2014 - lA II (I} dated 15.10.2014
Dear Sir,
With reference to the above subject, we are pleased to submit one hard and soft copy in CD of the Final Environmental Impact Assessment (EIA) Report for obtaining Environmental
Clearance for the proposed Dahej Nagothane Ethane Pipeline (DNEPL) Project, for your kind perusal. This report has been prepared as per the TORs issued to RGPL vide MoEF letter dated 151
h October, 2014 and has been updated after completion of Public
Consultation in all seven districts viz. Bharuch, Surat, Navsari, Valsad in Gujarat and
Palghar, Thane and Raigad in Maharashtra, through which the pipeline passes.
We request you to kindly process our application and grant Environmental Clearance to the
project at the earliest.
Thanking you,
Yours Sincerely,
For Reliance Gas Pipelines Limited
Registered Office: 9th Floor, Maker Chambers IV, 222, Narimnn Point, Mumbai - 400 021. Phone: +91 -·~2-2278 sooo.
CJN: U60300MH1991PLCos9678
GOVERNMENT OF GUJARAT FORESTS & ENVIRONMENT DEPARTMENT BLOCK NO. 14, gTn FLOOR, SACHIVALAYA
GANDHINAGAR- 382 010.
NILESH TRIVEDI DIRECTOR (ENVIRONMENT) & MEMBERSECRETARY,GCZMA
Ref. No.ENV-10-2015-162-E
To, ~r. Ranjini Wan·ier
Director,
Ph : (079) 2325106f
Fax: (079)23252156 E-mail. [email protected] July1 , 2015
Ministry of Environment, Forests & Climate Change Indira Paryavaran Bhavan, Jor Bugh, Aliganj Road New Delhi - 110 003
Sub: CRZ Clearance for proposed Dahej Nagothane Ethane Pipeline project at Dahej, Dist: Bharuch by MIS Reliance Gas Pipeline Limited(RGPL) regarding
Dear Madam,
M/s Reliance Gas Pipelines Limited(RGPL ), has approached this Department seeking
recommendations from the Gujarat Coastal Zone Management Authority to Ministry
of Environment, Forests and Climate Change, Government of India to grant CRZ
clearance for proposed Dahej Nagothan Etahne Pipeline (DNEPL) at Dahej , Dist:
Bharuch, vide application dated 05-02-2015 .
It is submitted that Reliance Gas Pipelines Limited , a wholly owned subsidiary of
Reliance Industries Limited (RGPL) proposes to lay a pipeline of 440 Km (12" dia)
from RGPL's Dahej Manufacturing Division (DMD) , Gujarat to RGPL's Nagothane
Manufacturing Division (NDM), Maharashtra and a 46 Km (8'' dia) spur pipeline to
RGPL's Hazira Manufacturing Division(HMD) for transportation ofupto 1.4 MMTPA
of liquid Ethane. Out of total 486 Km pipeline, approximately 256 km passes through
State of Gujarat
M/s Reliance Gas Pipeline Limited (RGPL) has submitted following documents
alongwith application:
1) A copy of the TORs issued by the MOEF&CC, GOI dated 15th October, 2014
2) Form 1 as per CRZ Notification 2011
3) Overall route map
4) List of villages through which proposed pipeline passes in Gujarat
5) A report for demarcation of High Tide Line, Low Tide Line, CRZ Boundary, etc.
prepared by the Institute ofRemote Sensing, Anna University, Chennai
6) CRZ maps alongwith demarcation of High Tide Line, Low Tide Line, CRZ
Boundary, etc. prepared by the Institute of Remote Sensing, Anna University ,
Chennai
7) Acknowledgement copy of the CTE application submitted to GPCB
8) Various undertakings as per this Department ' s guidelines
9) EIA report, prepared by the Bhagwati Anna Labs Pvt Limited, Hyderabad
The EIA report prepared by Bhagwati Anna Labs Pvt Limited, Hyderabad includes the
details like Project Description (chapter - 2), Baseline Environment Status( Chapter 3),
Anticipated Environmental Impact and its mitigation measures( Chapter 4 ), Analysis of
Alternatives(Chapter 5), Environmental Monitoring Program(Chapter 6),
Environmental Management Plan(Chapter 8) .The Bhagwati Anna Labs Pvt Ltd has
also included one chapter as Summary and Conclusion(Chapter 10)
The main findings of the EIA report prepared by the Bhagwati Anna Labs Pvt Ltd,
Chennai are summarized as follows:-
!. The project activities include excavation of soil in the ROU for laying of the
pipeline and construction of the pump station/delivery stations. Excavation
activities ('dig-ups ') undertaken to expose a section of pipe requiring repair or
replacement. Excavations are generally performed for corrosion or stress
corrosion cracking (SCC) repair activities, coating refurbishment work,
installation of new anode beds and projects requiring new tie in facilities.
Excavations usually occur on the pipeline easement or in designated compounds
and are a short term, temporary event.
II. Movement of vehicles along the pipeline corridor and associated access tracks.
Vehicles regularly travel along access tracks and the pipeline easement while
undertaking inspection and maintenance activities. Theses unsealed tracks are
predominantly located on station properties where public access is restricted.
III. Storage, use, collection and transport of hydrocarbons and chemicals. A variety of
hydrocarbons and chemicals are used for maintenance activities (e.g. diesel fuel ,
lubricants for machinery, degreasing agents, paints, etc.) . Waste hydrocarbons are
also generated via the collection and removal of product contaminants in the
pipeline (via filters or 'pigging' operations) and maintenance activities on
machinery and vehicles . All waste hydrocarbons are collected and removed for
2
disposal at a licensed waste facility. All maintenance and collection activities are
undertaken in accordance with APA procedures which include spill prevention
measures.
IV. Operation and maintenance of the pipeline may result in potential adverse effects
to soil and terrain like soil inversion and resulting loss in soil fertility or structure,
erosion of disturbed sandy soils and the fine powdery sub-soils, particularly by
wind, erosion of banks and channels of watercourses, compaction of soils and
contamination of soils by oil or chemicals. It is considered that these impacts can
be appropriately managed through the implementation of the mitigation measures
like preserving top soil and restoration of the area to near original conditions after
completion of construction, reinstating surface contours and natural drainage
patterns, reinstating watercourse banks as soon as practicable and applying bank
stabilization techniques as necessary, restricting the use of heavy machinery to the
minimum necessary to complete the task, restricting vehicle use in wet or boggy
conditions, monitoring for erosion, evidence of inversion and compaction and
minimizing oil spills, chemicals and wastes in a manner that minimizes the risk of
spills to the environment. Thus, the impact on the land environment during the
construction phase is reversible and insignificant. During the operation phase of
the project, the presence of the pump stations/delivery stations will be the only
visible impact on the existing flat/barren topography. As the pipeline will be
underground no impact is envisaged on the topography along the pipeline
alignment during the operational phase of the project.
V. The impact on ambient air quality is assessed hereunder considering the existing
baseline air quality. The ambient air quality levels along the proposed pipeline
corridor and around the pumping station/terminal stations are observed to be well
within the stipulated standards applicable for residential/rural and sensitive areas.
VI. During the construction phase of the project, the major impacting activities
includes, earth work excavation, embankment formation, handling, laying and
jointing of pipelines - these activities would cause a general increase in levels of
dust and suspended particulate matter in the ambient air. However, this increase in
concentration would be of temporary nature and localized. Water sprinkling will
be carried out for dust suppression. Movement of vehicles for transpm1ation of
construction material and usage of diesel generators - These activities would
cause a marginal increase in the levels of oxides of nitrogen, carbon monoxide
3
and hydrocarbons. The construction vehicles would have a valid PUC certificate
and the DG sets would be provided with stack of adequate height.
VII. There will be no air emissions during the operation phase from pipeline operation.
Thus, the impact on air quality during pipeline operations is negligible. Dust
generation from light vehicles and activities associated with the maintenance and
monitoring of the pipeline does occur. Minor emissions from the pipeline are
likely at above-ground facilities during maintenance operations. Remote operation
of valves (in the event of damage or programmed maintenance) uses Ethane
pressure to drive valve actuators and will result in the release of small amounts of
Ethane. Minor emissions from scraper stations will occur during loading and
removal of the pipeline pigs, which would normally occur once every five to ten
years. Fugitive emissions are extremely low from pipeline operations. The risk of
pipeline ruptures or leaks is also extremely low due to the implementation of
protection measures and the routine monitoring, inspection and maintenance that
will be carried out. Given the isolated nature of potential emission generation,
impacts on air quality associated with the pipeline are expected to be low.
VIII. Activities related to transportation, operation of construction plant and machinery,
operation of DG sets etc. add noise to the ambient levels. The noise levels due to
construction activities are estimated to be around 70-90 dB(A). Such onetime
exposure is not expected to last for more than few weeks and shall not exceed the
stipulated standards of CPCB. However, base camp will be established away from
habitation area to reduce the noise impact. Major construction work will be
carried out during the daytime. Noise generation is temporary and is restricted to
construction site.
IX. Most of the pipeline IS passmg through open area with sparse or negligible
population within the pipeline corridor (200m on either side) it is expected that
the noise exposure to the workers will be at levels well below the stipulated
norms. Impacts of noise on surrounding population due to construction activities
are expected to be insignificant and will be only temporary.
X. Due to the proposed pumping/delivery stations operation, there may be marginal
increase in noise levels in the immediate vicinity of the pumping stations. Such
marginal increase in the resultant noise levels would not alter the noise
environment significantly and in any case the noise levels beyond the pumping
station boundary would be below the permissible limits. The nearest settlement
4
would be at least 500 m away from the pumping/delivery station, where the
impact due to proposed operations at the pumping/delivery stations would be very
less. Thus no significant impact on the ambient noise quality is envisaged. The
pumps will be provided with enclosures to reduce the noise. People working at the
pumping station will be provided with PPE. There is an existing green belt at
DMD where the pump station will be located, which will reduce the impact of
noise due to operation of pumps on the surrounding areas around the pumping
station/terminal stations.
XI. Most of the rivers encountered enroute the pipeline alignment are seasonal and
will be crossed by open cut method. Horizontal Direction DRGPLling (HDD) will
be used for all crossings involving perennial rivers and major lined canals. Block
valves will also be provided at regular intervals to sectionalize the mainline and at
major river/canal crossings. Due to these measures no impact is envisaged on the
present water quality of the major river/canal crossing the pipeline alignment
during construction phase. Hence, there will not be any impact on the river water
quality of the major rivers and canals coming across the pipeline alignment.
XII . Drinking water required at the base camps during construction phase - The water
will be made available through local supply system. The domestic sewage from
the construction camps will be either disposed off into soak-pits/in consultation
with local authorities. Wastewater generation during construction phase of the
pipeline will be minimal and temporary in nature.
XIII. Water required during hydrostatic testing of pipeline - There will be one time
water requirement for hydrostatic testing. Efficient use of water will be made to
reuse the test water in different test sections. Water will be tapped from different
sources along the pipeline route, without unduly disturbing its normal users .
XIV. The total water requirement during construction phase is 491 KLD. There will be
a one-time requirement of 4,800 m3 of water per section of hydrostatic testing ( ~
30 km). This water will be reused in different test sections to an extent practically
feasible. The magnitude of impact on water environment during construction
phase will be minor and temporary. The water requirement will be only at Pump
Station at the starting location, intermediate ML V s, IPSs and termination
locations. For Pump station and M&R Station, water will be used from RGPL's
respective manufacturing division plant, as applicable. Local water sources with
due permissions from relevant authorities for ML V, IPS & pipeline laying.
5
XV. The domestic sewage will be disposed off into soak-pits/septic tanks. Water
required for ML V s, IPSs and M&R during operation phase is estimated to be
approximately 500 litres I day I per station, which will be primaRGPLy met by
providing tube well at respective location.
XVI. During construction, solid waste generated wi ll include packaging and wrapping
material, stubs of spent welding electrodes, used rags and housekeeping waste
from the construction camps etc. Site Contractors will be responsible for disposal
I resale of the wastes and these shall be disposed off at Municipality/ Local Body
approved sites.
XVII. All the non-hazardous wastes will be land filled or disposed off in municipality
facilities at approved sites. All the hazardous wastes generated will be disposed
off as per CPCB/State PCB guidelines at nearest TSDF sites. Recyclable wastes
will be sold off to CPCB/ local PCB authorized vendors. Hence impact on the
surrounding environment during construction and operation phase of the project
is not envisaged due to solid waste generation
XVIII. Most ofthe river crossing will be resorted during dry season when majority of the
riverbeds will be dry facilitating construction and minimizing impact. The impact
in the context of biota and fishery resources in the area is not considered to be
significant as most of the rivers are observed to be dry for major part of the year
except during monsoon season. As explained earlier, at the perennial
rivers/canals, Horizontal Direction DRGPLling (HDD) will be done to avoid the
impact on the biotic environment. There will be no discharge of the wastewater to
any water body from the pumping/delivery stations during the operational phase
of the project. The impact of buried pipeline passing through the fresh water
bodies would have least impact on the aquatic ecological status of these water
bodies.
XIX. The present land use of proposed pumpmg station/delivery station area is
uncultivable waste type. There will be positive impact on the present land use as
there will be structures and greenery on this type of land during the operation of
the project. The impact on the land use along the pipeline corridor will be
minimum and temporary as the excavated earth will be refilled back and efforts
will be made to bring back the original land use of the area. After completion of
pipeline construction, the ground will be restored to near original condition and
handed over back to the landowner to continue their regular activities. All sites
6
used for temporary works shall also be restored and returned to the original
landowner.
XX. The proposed land of the pumping station is mostly barren land with less fertility .
Top soil will be removed during the excavation for laying of the pipeline. This
soil cover will be restored back after laying of the pipeline. Hence no negative
impact is envisaged on the top soil cover all along the pipeline alignment.
XXI. The proposed activities will generate indirect employment in the region due to the
requirement of workers in site preparation activities, supply of raw material,
auxiliary and anci llary works, which would marginally improve the economic
status of the people. The activities would result in an increase in local ski ll levels
through exposure to site activities and technology. Residential/bui lt-up land will
not be acquired for the proposed pipeline; hence rehabilitation and resettlement
will not be associated with the project. The pipeline is proposed to be laid in the
RoU of existing pipelines. There will not be major changes in the land use pattern.
The proposed project activities do not involve loss or disturbance to sensitive areas
and cultural heritage.
The proposal of the RGPL was scrutinized by the Technical Committee in its 16th
meeting, which was held on 04-04-2015 , wherein the representative of RGPL made a
presentation about various activities to be carried out in the CRZ area, EIA report
prepared by the Bhagvati Ana Labs Private Limited, Hyderabad, and CRZ map
prepared by the Institute of Remote Sensing, Anna University, Chennai
After detailed discussion and deliberation on the presentation made by the
representative of the RGPL, during the presentation, the Technical Committee asked
the RGPL to submit various details including existence of Forests land involved in the
project
The RGPL submitted details vide its letter dated 11-05-2015 and submitted that the
pipeline will be laid across the CRZ area using horizontal direction drilling (HDD)
Technique at least 5 m below the river bed and there will be no impact on the river
regime. Regarding the existing forest land involved in the project, it is submitted that
the project involved reversion of diverted forest land in RoU of existing pipelines, and
a small section of fresh forest diversion, forest re-diversion ( -0.9 ha) proposal
submitted to State Forest Dept. on 3-Nov-2014 and fresh diversion (-0.2 ha) proposal
submitted on 28-oct-20 14 Application are in advanced stages of approval process.
7
The representative of RGPL made a presentation before the GCZMA in its 26th
meeting, which was held on 15-05-2015 , and submitted that they have proposed to lay
a pipeline of 440 Km (12 " dia.) from RGPL's Dahej Manufacturing Division , Gujarat
to RGPL 's Nagothane Manufacturing Division, Maharashtra and 46 Km (8 " dia.)
spur pipeline to RGPL ' s Hazira Manufacturing Division for transportation of upto 1.4
MMTPA of liquid Ethane . Out of total 486 Km pipeline, approximately 256 Km
passes through the State of Gujarat. The proposed pipeline passes through tidal
influenced water bodies in Gujarat viz. Bhukhi, Narmada, Purna , Mindhola, Kim-main
line and Kim - Hazira and it is falls under purview of CRZ Notification 2011. The
total length of pipeline passes through CRZ area would be 4864m. Horizontal
Directional Drill (HDD) techniques shall be used for laying of the pipeline across the
water bodies, without disturbing water courses. HDD is a trenchless method with no
impact in the river regime. There is no excavation in the river regime and possible in
soft and hard strata. HDD would be started from outside CRZ Limit. Waste drilling
mud and drill cutting will be disposed off at nearby TSDF. Construction camp will be
located outside the CRZ area. No domestic solid waste /liquid waste will be disposed
off in CRZ water bodies. Construction labours would be provided with septic tank and
soak pit system or portable sewage treatment plants. Treated Sewage water will be used
for dust suppression. All construction equipment will comply with the emission and
noise standards. No construction activities will be undertaken during night time.
The representative of RGPL submitted that the maximum overall risk due to the Dhej
Nagothane Ethane Pipeline facility is found to be 1.0 x 10-5 /year, which is
inacceptable region (ALARP level) as per HSE UK risk acceptance criteria. The
societal risk for overall DNEPL pipeline facility is observed to be in acceptable region
as per the HSE UK Risk acceptable criteria. The impact of thermal radiation on
adjacent buried pipeline will not have potential impact due to adequate soil cover and
separation distance. It was further submitted that installation of SCADA dedicated
optical fibre cable based telecommunication system, leak detection system, Pipeline
Application Software etc would be used as Risk Prevention and mitigation measures.
Forests re-diversion (0.9 ha) proposal submitted to Forests Department on 03-11-2014
and for fresh diversion (0.2 ha) on 28th October, 2014
The representative of the RGPL submitted that the pipeline will be laid across the water
bodies using Horizontal Directional Drilling (HOD) technique, wherein there is no
excavation in the river regime. The pipeline will be laid at a depth of minimum 5 m
8
below the nver bed. Also, no domestic or solid waste, generated during the
construction phase, will be disposed of in the CRZ water bodies. Thus, there will be no
impact on the marine environment. It was further submitted that the Pipeline is the
safest mode transportation of hydrocarbons. Being buried underground, there is no
interference in the existing land usage. They have submitted detail analysis regarding
waste drilling mud & drill cutting and also stated that, Bentonite (natural clay) in dry
(powder) or slurry (mixed with water) form, a non-hazardous, environmentally friendly
and non-toxic in nature, is used during the drilling operation to take ground cuttings out
of the hole. Certificate from Bentonite Supplier M/s Trishul Industries with chemical
composition of Bentonite powder is obtained. It is submitted that the drill cuttings are
also non-hazardous and are recycled and reused and it is proposed to dispose of the
waste drilling mud in nearby low lying areas outside of the CRZ limits, in consultation
with concerned authorities. The representative of the RGPL submitted that the
proposed pipeline will be located upstream of the Kalpasar barrage at a distance of
approximately 4.4 km and they are in the process of filing application for obtaining
NOC from the concerned department.
As per the CRZ map prepared and duly imposed for the proposed route of pipeline,
prepared by the Anna University, Chennai, proposed activities falls in CRZ-I(B), CRZ
III categories
The Authority deliberated the proposal of Reliance Gas Pipelines Limited and
after detailed discussion, it is decided to recommend to the Ministry of
Environment, Forests and Climate Change, Government of India to grant CRZ
Clearance for proposed Dahej- Nagothane Ethane Pipeline (DNEPL)Project of
Reliance Gas Pipelines Limited at Dahej, Dist: Bharuch with some specific
conditions
In view of above, the State Government hereby recommends to the Ministry of
Environment, Forests and Climate Change, Government of India to grant CRZ
clearance for proposed Dahej- Nagothane Ethane Pipeline (DNEPL)Project of
Reliance Gas Pipelines Limited at Dahej, Taluka: Vagra Dist: with the strict
compliance of the following conditions:
Specific Conditions :
1. The RGPL shall strictly adhere to the provisions of the CRZ Notification, 2011
issued by the Ministry of Environment, Forests and Climate Change, GOI,
9
2. The RGPL shall obtain all necessary clearances permissions from different
Government Departments I Agencies before commencing any construction
activity related to the proposed project.
3. The RGPL shall ensure that the pipeline will be laid across the CRZ area using
horizontal direction drilling (HDD) Technique at last 5 mt below the river bed
and there will be no impact on the river regime.
4. The RGPL shall obtain necessary permission from the Forests Department
under FCA Act before carrying out any enabling activity for this project.
5. The RGPL shall ensure that no domestic or solid waste is generated during the
construction phase, and if any such waste is generated, it will be not be disposed
off in the CRZ water bodies.
6. The RGPL shall ensure that drilling cutting muds/ materials shall be disposed
off in environmental friendly manner after consultation and obtaining
necessary permission from the concerned authority/ies.
7. The RGPL shall obtain NOC from the Narmada, Water Resources, Water * Supply & Kalpasar Department for the proposed project before the
commencement of the project
8. The RGPL shall strictly implement the measures suggested in the EIA by the M/s
Bhagwati Anna Labs Pvt Ltd, Chennai for mitigation of likely adverse impacts
on coastal and marine environment.
9. There shall no discharge of any kind of wastewater I sewage I effluent into the
creek I sea or in the CRZ areas.
10. No groundwater shall be taped to meet with the water requirements during the
construction and/or operation phases.
11. The RGPL shall participate financially for any common facility that may be
established or any common study that may be carried out for the Gulf of
Khambhat region for environmental protection and/or management purpose.
12. The RGPL shall have to face the consequences whatsoever due to implementation
of the Kalpsar Project proposed by the Government of Gujarat and shall have to
take all necessary actions as may be desired by the Government.
13 . The RGPL shall prepare and furnish the detailed Disaster Management Plan to the
concerned offices including the District Authorities and this Department.
14. The RGPL shall ensure that the construction camps are kept outside the CRZ
areas and the construction labour are provided with adequate amenities like
10
drinking water, fuel , sanitation, etc. to ensure that the existing environmental
condition is not deteriorated by them.
15. The RGPL shall bear the cost of the external agency that may be appointed by this
Department for supervision I monitoring of proposed activities.
16. The RGPL shall ensure that the Corporate Social Responsibility (CSR) activities
shall be carried out on need base ofthe local people.
17. The RGPL shall take up socio-economic upliftment activities in consultation with
the District Collector I DDO. A separate budget shall be provided for this purpose.
18. An Environmental Cell shall be constituted with technically qualified staff to
implement the Environment Management Plan. A separate budget shall be
earmarked annually for this purpose and the details shall be furnished to various
regulatory authorities from time to time.
19. The RGPL shall furnish the environmental audit report including the aspects on
coastal and marine environment, to this Department every year.
20. The RGPL shall regularly submit the half-yearly compliance report on the
conditions stipulated by this Department/ Ministry of Environment and Forests,
Government of India.
21. Any other condition that may be stipulated by this Department/ MOEF&CC, GOI
from time to time for environmental protection I management purpose, shall be
complied with by the RGPL.
Thanking you
Yours sincerely,
~v~' (Nilesh Trivedi ).
Encl: As above
II
Minutes of 105'"meetingof Maharashtra Coastal Zone Management Authority {MCZMA) held on 15"'& 16'" October, 2015
Taking into consideration reports and CRZ map of IRS, Chennai, Hon'ble Supreme Court order dated 19.11.2014 in SLP No. 30128/2014, NHO letter recognizing Mahim Bay as 'Bay' and opinion of Advocate General, GaM, the Authority after deliberation decided to confirm that the plot bearing F P no. 205 of TPS III Mahim Division, situated at Lady Jamsetji Road in "G/N" Ward, Mumbaiis beyond 100 m CRZ setback line.
Item No.1: Proposed DahejNagothane Ethane Pipeline (DNEPL) Project byM/s. Reliance Gas Pipelines Ltd.
Representatives of M/s. Reliance Gas Pipelines Ltd. (RGPL) presented the proposal before the Authority. The proposal is for laying of pipeline of 440km (12"dia) from RIL's Dahej manufacturing Division (DMD), Gujrat to RIL's Naothane Manufacturing Division (NMD), Maharashtra and a 46 km (8" dia) spur pipeline to RIL's HaziraManufacturiongDivision (HMD) for transportation of 1.4 MM TPA of liquid Ethane. Out of total 486 km pipeline, approximately 230km passes through State of Maharshtra. Project proponent has submitted CRZ maps (scale 1:4000) indicating HTL as per approved CZMP and HTL as per CRZ notification, 2011 & report prepared by IRS, Chennai. As per the said report, details of pipeline crossing through different CRZ categories falling under Maharashtra State are listed below-
I Sr. I Site CRZ Class I 1 Length Total length
I I I (m) i No. I (m) I 1 I Nigade River CRZ-III
I 218.24 1152.24
' ' i I CRZ-IVB i 66.00
[2 Ambo River Mangrove Area 135.38 851.28 I (CRZ-1A) I I Buffer Area for 260.77
I I Mangroves I I I I (CRZ-1A)
I CRZ-III I
I I 390.34 I I CRZ-IVB I 21.06
I CRZ-IB i 143.74 3 A mba CRZ-IB 95.85 52.16
Tributary CRZ-III 56.31
! ' i '
' !
'
I
I
J
Minutes of 105'"meetingof Maharashtra Coastal Zone Management Authority {MCZMA) held on 15'"& 16'" October, 2015
The Authority after delibeation decided to recommend the proposal from CRZ point of view to MoEFCC, New Delhi with following observations:
1. Project proponent to submit management plan for disposal of excavated material during drilling indicating site of disposal, monitoring plan etc
2. PP to submit chemical charecteristics of mud used for drilling, its disposal and managemet plan
3. PP as committed to ensure that thickness of the pipe is more in CRZ area to ensure foolproof system to avoid accidential leakage in the mangrove area.
4. PP to also ensure that depth of the drilling below the mangroves should not be less than 10 m.
5. PP to also provide details of leakage detection system
Table Item No. 2: Proposed change of user in existing building Commercial to Residential of flat NO. F-2 on the 5th floor known as "Corinthian Condominium" situated at 17, Justice V. Vyas Road, C.S. No. 511 of Colaba, Mumbai
The project propoenent was present in the meeting and presented the proposal before the Authority. The proposal is for additions & alternations and change of user in existing building Commercial to Residential of flat NO. F-2 on the 5th floor known as "Corinthian Condominium" situated at 17, Justice V. Vyas Road, C.S. No. 511 of Colaba, Mumbai. As per approved CZMP of Mumbai, the site falls in CRZ II and situated on landward side of existing ShahidBhagat Singh Road in existence prior to 19.2.1991.
After deliberation Authority decided to recommend the proposal from CRZ point of view to planning authority with following observations:
1. Local body to ensure that proposed alteration from commercial to residential is as per the provisions of DCR existing and inforce as on 19.2.1991 in CRZ II areas.
2. All other permisions as and when required should be obtained prior to commencement of construction activity.
Item No. 3: CRZ status- plot bearing CTS No. 195 B, Tikka No. 8 of area 153.85 Sq.m. MoujePachpakhadi, Thane
The Authority noted that the Revenue Department, GoM has forwarded the matter regarding allotment of land bearing Tikka No. 8, CTS No. 195 B admeasuring 153.85 Sqm along with temple thereon situated at Post Pachpakhadi, Tal. & Dist. Thane to
Jagmata Charitable Trust, Thane to the MCZMA, Environment De~artment for remark oMC Z status of the land underefenrece. ,
~ .., .f
,a::;~reretary 35/36