RELIANCE INDUSTRIES LIMITED NAGOTHANE MANUFACTURING...
Transcript of RELIANCE INDUSTRIES LIMITED NAGOTHANE MANUFACTURING...
190
First Prize
Petrochemicals
RELIANCE INDUSTRIES LIMITED
NAGOTHANE MANUFACTURING DIVISION
Raigad (Maharashtra)
Unit Profile
Nagothane Manufacturing Division (NMD) is one of the six major manufacturing sites
of RIL, located in Raigad district of Maharashtra. NMD is a petrochemical complex
commissioned in the year 1989. Various production units in the complex are
producing Polyethylene, Polypropylene, EO and MEG totaling 600 KTA per year.
Production Capacity of the plant
Product Capacity Capacity Utilization in %
KTA 2012-13 2013-14
Ethylene + Propylene 560 78 79
EO+MEG 81 91 114
LDPE 110 102 90
LLDPE/HDPE 240 80 96
PP 120 86 85
BUTENE-1 15 0 0
Energy Consumption
Energy requirement of the complex is met by captive generation of steam & power
in Captive Power Plant (CPP) with the help of Gas Turbine Generators, Steam
Generators and Steam Turbine Generators. CPP imports power from MSEDCL
(Maharashtra State Electricity Distribution Company Limited) distribution grid as per
operation philosophy.
Energy Index for last four years
191
Energy Conservation Measures Taken
1. Up-rate of GTG- 50: Saving in fuel & Power cost by: Improved heat rate, higher
efficiency (by load transfer from ST to GT) & avoiding power
2. Small air compressor installed
3. CCC implementation in CG and C3R compressors
4. Lighting modification in all plants
5. ONE SEAL oil pump stoppage in LLDPE –tr1
6. STG overhaul and performance restoration
7. Replacement of 2 SL steam float traps and 15 passing by pass valve
replacement
8. Instrument air leak rectification during April'13 turn around
Other Initiatives taken for achieving Energy Excellence
1. ISO 50001 certification received in the year 2013. Group of engineers have
been trained and certified as ISO 50001 auditors.
2. Fuel hierarchy published monthly for optimization of CPP operation.
3. Maximum utilization of the cracker generated waste fuel gas in CPP.
4. Optimization of power import w.r.t site demand and fuel scenario.
5. Efficient operation of furnaces
6. Better Steam trap management. Periodic surveys conducted and attending
losses.
7. Identification, accounting and reduction of complex hydrocarbon loss.
8. Energy efficiency as a criterion during procurement of equipment or service.
9. Minimum power generation from condensing steam turbine.
10. Periodical audits of highly Energy intensive equipments are done and taking
action on the gaps.
11. Site Energy Cell Engineers have been trained for Prosteam software which is
helpful for utility balance and Super-target software which is helpful for heat
exchanger network and heat integration study based on Pinch concept.
12. Participation in Global benchmarking activities and taking actions to minimize
the gaps with respect to global/national level.
13. Prosteam optimizer has been developed. By taking real time data, the optimizer
gives recommendations to minimize total operating cost of the site by reducing
letdowns and vents, and loading more efficient equipments within the given
constraints. It also optimizes between purchased power and the power
generated captively. The optimizer runs every hour in auto mode. It fetches
data from IP21 for 15 mins. average time span and gives recommendations.
14. Energy Consultant has been engaged for revolutionizing the Energy
Management System in Reliance. Engaged with SME experts for energy areas
like Process, Power, and HVAC.
15. Energy management consultant for studying opportunities in heat integration.
192
Energy Policy
193
Certificate of Merit
Petrochemicals
PANIPAT NAPHTHA CRACKER
Panipat (Haryana)
Unit Profile
Panipat Naphtha Cracker, the largest Naphtha Cracker in India, was commissioned
in March 2010. There are five main Process units in the Naphtha Cracker Complex:
Naphtha Cracker & Associated units, Polypropylene Unit, LLDPE/HDPE Swing Unit,
HDPE Unit and MEG Unit.
NCU produce mainly Polymer Grade Ethylene and Polymer Grade Propylene. It also
produces Hydrogen, Methane off gas, Pyrolysis Fuel Oil (PFO) and other products
like raw C4 mix, raw Pyrolysis Gasoline that are further processed in Associated
Units.
Energy Consumption
Specific Electricity Consumption in kWh/Ton of Product
Units 2012-13 2013-14
Naphtha Cracker Unit 113 109
Poly Propylene 331 320
SWING 196 196
High Density Polyethylene 502 468
Mono Ethylene Glycol 338 338
194
Specific Thermal Energy Consumption in M kCal/Ton of Product
Units 2012-13 2013-14
Naphtha Cracker Unit 4.9 4.7
Poly Propylene 0.3 0.3
SWING 1.2 1.2
High Density Polyethylene 0.3 0.3
Mono Ethylene Glycol 1.2 1.1
Energy Conservation Measures Taken
1. Interconnection between HSD pump discharge headers of individual Gas
Turbines (GTs)
An interconnection has been provided between HSD pump discharge headers of
individual GTs resulting in stoppage of 2 nos. of HSD pumps of power rating
9.33 kWh each.
Investment : Rs. 1.72 Lakh.
Electricity saving : 0.41 Lakh kWh.
0
100
200
300
400
500
600
Naphtha Cracker
Unit
Poly Propylene SWING High Density
PolyEthylene
Mono Ethylene
Glycol
Specific Electrical Energy Consumption in
KWHr/Ton of Product 2012-13
Specific Electrical Energy Consumption in
KWHr/Ton of Product 2013-14
0.00.51.01.52.02.53.03.54.04.55.05.5
Naphtha
Cracker Unit
Poly Propylene SWING High Density
PolyEthylene
Mono Ethylene
Glycol
Specific Thermal Energy Consumption
Million kCal/ tonne 2012-13
Specific Thermal Energy Consumption
Million kCal/ tonne 2013-14
195
2. Routing of NCU’s FCC C3 dryer Bed changeover’s Residual Propylene to
Fuel Gas header
In NCU FCC C3 dryer, during bed changeover residual Propylene was earlier
flared, which has been routed now to Fuel Gas header in controlled manner
avoiding low-temperature in downstream piping thereby leading to savings of
300 MT/month of Hydrocarbon using existing dryer depressurizing line to Fuel
gas.
Investment : Nil
Fuel saving : 3795 MTOE
3. Steam trap survey for CPP and NCU
Steam trap survey for CPP and NCU was conducted in June’13 & identified traps
were replaced in Sept’13 resulting in saving of 2 TPH steam loss.
Investment : Rs. 1.55 Lakh
Fuel saving : 1125 MTOE.
4. Utilizing ETP slop oil as a PFO blending component.
At PNC ETP, slop oil is being recovered as a side stream from waste water
through OWS and CRWS treatment process and based on the experimental
results at lab, it was proposed to mix the slop oil maximum up to 5% with PFO
(Flash Pt. of blend – 56 °C).
Hence, 418 Tonnes of Slop Oil has been blended with PFO from Jan'14 till
March'14 resulting into saving of Rs. 1.69 Cr./year. The issue of Slop Oil
disposal has also been resolved effectively.
Investment : Rs. 7.61 Lakh
Fuel saving : 395 MTOE.
5. Change of Operation philosophy of Poly Propylene extruders
PP unit has two extruders, each one operated by 12.5 MW Motor. Extruder can
be operated in two speeds (190/243 rpm) by means of lever arrangement.
Since commissioning it was being operated at high speed. As a pellet cutting
improvement measure, the operation philosophy was changed to low speed
from high speed operation. It yielded energy saving to the tune of 600-700 kWh
(Both lines total).
Investment : Nil
Electricity saving : 30.66 Lakh KWh.
196
Energy Policy
197
Certificate of Merit
Petrochemicals
ASIAN PAINTS
PHTHALIC DIVISION Ankleshwar (Gujarat)
Unit Profile
Asian Paints is India's largest paint company and ranked among the top ten
Decorative coatings companies in the world. Asian Paints along with its subsidiaries
have operations in 17 countries across the world with 23 paint manufacturing
facilities, servicing consumers in over 65 countries.
Vertical integration has seen Asian Paints diversity into products such as
Pentaeryttritol (Penta) manufactured at Cuddalore in Tamil Nadu (India) in 1987
and Phthalic Anhydride 'PAN' at Ankleshwar in Gujarat in 1990. Both these
chemicals are key raw materials for paint production.
Manufacturing of Phthalic Anhydride involves high temperature oxidation of Ortho
Xylene generating large amounts of heat recovered in the form of 22 bar steam.
This is in turn used for generating power making the plant self-sustained on power
front.
198
During full capacity plant operation, power consumption from external source i.e
grid or DG sets is zero units now and the natural gas consumption is 2000 m3/day.
This was mainly achieved through innovative and one of its kind energy
conservation schemes.
The initial steam turbine of KKK, Germany make, designed for 1190 kW , 20 bar,
340 °C superheated steam with specific steam consumption 8.5 kg/kW, was
replaced by Triveni make steam turbine in December, 2000 for a specific steam
consumption of 7.1 kg/kW for same steam conditions.
Description KKK Turbine
Triveni Turbine
Duration 1990-2000 2000-till date
Steam consumption, kg/hr 9000 9000
Specific consumption, kg/kW 8.5 7.1
Power generated, kW 1058 1267
This energy efficiency scheme along with various energy saving schemes like AC
drives in centrifugal pumps, FRP blades in cooling towers, etc. has saved steam of
1000 kg/hr at 22 bar pressure. An innovative idea for converting the energy from
this excess steam was developed for heating thermic fluid oil (Ilexan) used in the
oxidation section up to 200 °C and reduced natural gas consumption by 2000
m3/day.
The Triveni make turbine was further upgraded in the year 2012 by increasing the
number of steam stages and increased the efficiency from 7.1 kg/kW to 6.3 kg/kW
resulting into reduction of steam consumption by 1000 kg/hr. Again this excess
steam was used for pre heating Therminol -66 oil used in the distillation up to
199
270 °C. This scheme has reduced the natural gas consumption from 3500 m3/day to
2000 m3/day as on today.
The compressed air system for instrument air, nitrogen and plant air for ejectors
were being met by operating two compressors at 7 bar discharge pressure. By
segregating the different users at different pressure level and by replacing the air
compressors, 20% reduction in power (30 kW) is achieved. In addition higher air
discharge temperature (150 °C) is now used directly in ejectors and reduced steam
consumption 100 kg/hr at 6 bar pressure.
Energy indices e.g. Specific Energy Consumption, MTOE (Million Tonnes of
Oil Equivalent) and company’s efforts to improve energy conservation.
Plant operation is greatly affected in terms of energy during catalyst replacement
year due to plant operation on lower capacity due to process of catalyst activation.
Year 2010-11 & 2012-13 were catalyst replacement year.
Normal capacity operation years are non-catalyst replacement years i.e. 2009-10,
2011-12 & 2013-14.
0.000
0.020
0.040
0.060
0.080
0.100
2009-10 2010-11 2011-12 2012-13 2013-14
Specific Energy Consumption
TOE / MT
1100
1120
1140
1160
1180
1200
1220
1240
1260
1280
1300
APR MAY JUNE JUL AUG SEP OCT NOV DEC JAN FEB MAR
Plant load (KW) 2013-14
Modification
in Ilexan
system - 10
New AIS
Blower with
VFD , Saving-
5.5 KW
Plant air
compressor
replaced with
screw - comp. -
30 KW
Reduction by 30%
wrt year 2009-10
200
I. Basic concept on the modified energy plant related to specific measures
Natural gas prices have been increased by 184% in last 3 years. So, since last three
years, unit endeavour was to reduce the natural gas consumption by efficiency
enhancement in plant and machineries & by effective utilization of steam energy.
Unit adopted total energy integration strategy approach (point c.) and could reduce
natural gas consumption significantly. Unit could reduce the specific natural gas
consumption by 28% on annual average basis wrt year 2009-10. Current level of
specific natural gas consumption is 46% lower than year 2009-10.
II. Effective reduction in energy consumption, both, in absolute terms of inputs for given unit of output & overall saving realized qualitatively and quantitatively.
Year
Specific
consumption
Sp. Natural gas
consumption
TOE / MT SM3/MT
2009-10 0.052 54.19
2010-11 0.062 62.04
2011-12 0.050 53.13
2012-13 0.077 68.74
2013-14 0.036 39.20
Major Energy conservation projects
Year Actions Effect
2013-14 Replacement of plant air compressor 34 kW power saving
Modification of Ilexan hot oil circulation
system
10 kW power saving
Replacement of pumps and motor with energy efficient equipment (Turbine cw pump, cold oil pump-2)
12 kW power saving
Process flow control through VFD (Therminol circulation pump, HP BFW
11 kW power saving
82032
93165
105732
114199
106334
9174588810
77515
62289
5724251711
62050
50000
60000
70000
80000
90000
100000
110000
120000
N. Gas Consumption
201
Year Actions Effect
pump, Hot oil pump), AIS blower flow control through VFD
Replacement of light fittings with LED 9 kW power saving
Process optimization of thermic fluid heat duty in distillation
1500 sm3/day natural gas
III. Greenhouse Gas inventorization and changes in last 2/3 years
IV. Specific power and fuel consumption
At normal capacity of plant operation, our plant is power free from external sources
also and further we have reduced our fuel consumption also significantly:
Sr. No. Parameters Unit of measure
Design Parameters
Current Parameters
1.
Specific power
consumption from external sources
Units / MT 31 0.0
2. Specific fuel consumption for
thermic fluid heaters
Kg / MT 85 29
0
500
1000
1500
2000
2500
3000
3500
4000
4500
2009-10 2010-11 2011-12 2012-13 2013-14
Total Equiavalent CO2 Emmision
(in MT / annum)
Reduction by
923 MT wrt
As per US EPA calculation