Regional Freeway System MAG Management Committee June 15, 2005

5
Regional Freeway System Regional Freeway System MAG Management Committee MAG Management Committee June 15, 2005 June 15, 2005 FY 2006 - 2007 FY 2006 - 2007 MAG Life Cycle Program MAG Life Cycle Program

description

FY 2006 - 2007 MAG Life Cycle Program. Regional Freeway System MAG Management Committee June 15, 2005. PROJECT CHANGES. Red Mountain, Power Rd. – University Dr. Construction Cost Increase. PROJECT CHANGES. The current programmed amount of - PowerPoint PPT Presentation

Transcript of Regional Freeway System MAG Management Committee June 15, 2005

Page 1: Regional Freeway System MAG Management Committee June 15, 2005

Regional Freeway SystemRegional Freeway System

MAG Management CommitteeMAG Management Committee

June 15, 2005June 15, 2005

FY 2006 - 2007 FY 2006 - 2007 MAG Life Cycle ProgramMAG Life Cycle Program

Page 2: Regional Freeway System MAG Management Committee June 15, 2005

PROJECT CHANGESPROJECT CHANGES

Red Mountain, Power Rd. – University Dr.

Construction Cost Increase

Page 3: Regional Freeway System MAG Management Committee June 15, 2005

PROJECT CHANGESPROJECT CHANGES

The current programmed amount of $126.5 million will need to be increased by $17.6 million to a revised cost of $144.1 million.

Approximately 30% of the increase is due to higher materials cost for construction items such as : Cement, Steel, Diesel Fuel and Lumber

Page 4: Regional Freeway System MAG Management Committee June 15, 2005

PROJECT CHANGESPROJECT CHANGES

Increased noise wall quantities $3.6 million

Increased Materials cost $3.5 million

Pavement $3.4 million

Increased retaining wall quantities $3.0 million

Adding pump station storage box $1.5 million

Adding construction of a new maintenance underpass at McKellips Rd

$1.3 million

Increased excavation quantities $0.6 million

Adding McDowell Road detour at Power Rd $0.5 million

Channel Lining $0.2 million

TOTAL INCREASE: $17.6 million

Page 5: Regional Freeway System MAG Management Committee June 15, 2005

Cash FlowCash Flow

A review of the current cash flow indicates funding is available for this cost increase.