Region 3 SHADY BRIDGE Project consists of replacing 3 bridges with 4 ~ hanging a pedestrian bridge...
-
Upload
piers-watkins -
Category
Documents
-
view
213 -
download
0
Transcript of Region 3 SHADY BRIDGE Project consists of replacing 3 bridges with 4 ~ hanging a pedestrian bridge...
Region 3
SHADY BRIDGESHADY BRIDGEProject consists of replacing 3 bridges with 4 ~ hanging a Project consists of replacing 3 bridges with 4 ~ hanging a
pedestrian bridge under the new SB River bridge and NB and pedestrian bridge under the new SB River bridge and NB and SB off ramp modifications.SB off ramp modifications.
Region 3
Original Project TimelineOriginal Project Timeline
• Project Bid ~ February 2004
• Contract Completion ~ January 31, 2008
• Stem Wall Issues ~ June 2006– Stem Wall Repairs ~ October 2007– Repairs Complete ~ February 2008
Region 3
Stem Wall Damage Stem Wall Damage InvestigationInvestigation
• Ground Penetrating Radar
• Impact Echo Hammer
• Impulse Resonance
• Core Drilling
Region 3
Ground Penetrating RadarGround Penetrating Radar
Region 3
Core DrillingCore Drilling
Region 3
Stem Wall Damage PicturesStem Wall Damage Pictures
Region 3
Stem Wall Damage PicturesStem Wall Damage Pictures
Region 3
Stem Wall Damage PicturesStem Wall Damage Pictures
You can note that the rebar is pushed away from the concrete stem wall.
Region 3
Stem Wall Damage PicturesStem Wall Damage Pictures
Region 3
Overview of Stem Wall DamageOverview of Stem Wall Damage
Region 3
Duct Bundling Allowance –vs- Duct Bundling Allowance –vs- BR130BR130
Region 3
Duct Bundling AllowanceDuct Bundling Allowance
Region 3
Stem Wall PT Duct Install PicturesStem Wall PT Duct Install Pictures
Region 3
Duct and Bundling PicturesDuct and Bundling Pictures
Region 3
Duct and Bundling PicturesDuct and Bundling Pictures
Region 3
Duct and Bundling PicturesDuct and Bundling Pictures
Region 3
Repair DetailsRepair Details
Region 3
Another IssueAnother Issue
The bottom of Deck is The bottom of Deck is corrugated!corrugated!
Region 3
Bottom of DeckBottom of Deck
Region 3
Bottom of DeckBottom of Deck
Region 3
Bottom of DeckBottom of Deck
Concrete Dobie Blocks
The bottom of deck buckled between dobies
Region 3
Deck Form BoardsDeck Form Boards
Contractor used 11/32” plywood. Requirement is now 5/8” nominal thickness.
Region 3
Warpage:Warpage:
Contractor was required to remove this plywood on the remaining spans; 3 and 4.
Region 3
Where we are now.Where we are now.
• July 12, 2008 ~ Sent Ross Bros. a letter of Termination for Default.
• July 21, 2008 ~ ODOT received proposals from both the contractor and the surety.
• July 24, 2008 ~ ODOT rejected Ross’ proposal, but agreed to pursue Safeco’s 2nd proposed option.
Per the Standard Specifications, the contractor and their surety have the ability to propose a cure to the project with in 10 days of the notice.
Ross’ proposal kept them as the Prime Contractor. Safeco’s proposal had 2 options; 1) keeping Ross as the prime and 2) Safeco taking over the contract and hiring a completion contractor.
Region 3
Where we are now.Where we are now.• September 15, 2008 ~ ODOT signed a
Takeover Agreement with Safeco.
• Highlights of Takeover Agreement– Safeco is now the Prime Contractor;– Safeco is allowed to use Ross Brothers;– Safeco will provide on-sight Project Manager– Safeco will assume Superintendent
responsibilities per the STD Specs 150 section;– Safeco will reimburse ODOT ± $2M for stem wall
repairs and investigation;– Safeco will reimburse ODOT ± $1.1M for
continued CEI costs;– Safeco will reimburse ODOT ± $426K for LD’s;
After 7 weeks of back and forth negotiations, ODOT and Safeco came to agreement.
Region 3
Where we are now.Where we are now.• Highlights of Takeover Agreement; (cont)
– Agreement established a new interim and new completion date;
• October 31, 2010 – All work complete except for site restoration, clean up, punch list, pier and falsework removal, planting, etc.
• August 31, 2011 – Final completion – All work must be complete.
• September 29, 2008 ~ Safeco was provided an NTP to proceed with the work under the new agreement.
• October 31, 2008 ~ The NB South Umpqua River Bridge was open to traffic.