Refuel 17 Plans - Nuclear Regulatory Commission · Refuel 17 Plans Don Shue Manager, Planning &...
Transcript of Refuel 17 Plans - Nuclear Regulatory Commission · Refuel 17 Plans Don Shue Manager, Planning &...
![Page 1: Refuel 17 Plans - Nuclear Regulatory Commission · Refuel 17 Plans Don Shue Manager, Planning & Outage Management. ¾Outage Begins: April 25, 2008 ¾Duration: 38 Days ¾Outage Goals](https://reader036.fdocuments.in/reader036/viewer/2022062604/5fb4516de0de87028d36a1f5/html5/thumbnails/1.jpg)
Refuel 17 Plans
Don Shue Manager, Planning & Outage Management
![Page 2: Refuel 17 Plans - Nuclear Regulatory Commission · Refuel 17 Plans Don Shue Manager, Planning & Outage Management. ¾Outage Begins: April 25, 2008 ¾Duration: 38 Days ¾Outage Goals](https://reader036.fdocuments.in/reader036/viewer/2022062604/5fb4516de0de87028d36a1f5/html5/thumbnails/2.jpg)
Outage Begins: April 25, 2008Duration: 38 DaysOutage Goals Focus:
Nuclear Safety Radiological Safety Industrial Safety
Outage Overview:
![Page 3: Refuel 17 Plans - Nuclear Regulatory Commission · Refuel 17 Plans Don Shue Manager, Planning & Outage Management. ¾Outage Begins: April 25, 2008 ¾Duration: 38 Days ¾Outage Goals](https://reader036.fdocuments.in/reader036/viewer/2022062604/5fb4516de0de87028d36a1f5/html5/thumbnails/3.jpg)
Nuclear Safety Significant Events: 0 Human Performance Events: < 1Recordable Injuries: < 1Dose: 75 REMPost Outage Capacity Factor: 96%
Outage Goals:
![Page 4: Refuel 17 Plans - Nuclear Regulatory Commission · Refuel 17 Plans Don Shue Manager, Planning & Outage Management. ¾Outage Begins: April 25, 2008 ¾Duration: 38 Days ¾Outage Goals](https://reader036.fdocuments.in/reader036/viewer/2022062604/5fb4516de0de87028d36a1f5/html5/thumbnails/4.jpg)
Outage Milestones: 95% On TimeCurrently Met 47 of 48 (98%)
Outage Goals:
![Page 5: Refuel 17 Plans - Nuclear Regulatory Commission · Refuel 17 Plans Don Shue Manager, Planning & Outage Management. ¾Outage Begins: April 25, 2008 ¾Duration: 38 Days ¾Outage Goals](https://reader036.fdocuments.in/reader036/viewer/2022062604/5fb4516de0de87028d36a1f5/html5/thumbnails/5.jpg)
Required Resources:500 General Workers200 Specialty Contractors
Focus Areas:Welders & Pipe Fitters
6 PSNC12 Fossil/Hydro
Crane Operators & RiggersScaffold Builders
Focus Area -
Labor
![Page 6: Refuel 17 Plans - Nuclear Regulatory Commission · Refuel 17 Plans Don Shue Manager, Planning & Outage Management. ¾Outage Begins: April 25, 2008 ¾Duration: 38 Days ¾Outage Goals](https://reader036.fdocuments.in/reader036/viewer/2022062604/5fb4516de0de87028d36a1f5/html5/thumbnails/6.jpg)
New Work Control Process (CMMS)Includes
Danger TaggingWork ControlMaterials Management Condition Reports
Increased Focus By Information Services
Focus Area -
Work Control
![Page 7: Refuel 17 Plans - Nuclear Regulatory Commission · Refuel 17 Plans Don Shue Manager, Planning & Outage Management. ¾Outage Begins: April 25, 2008 ¾Duration: 38 Days ¾Outage Goals](https://reader036.fdocuments.in/reader036/viewer/2022062604/5fb4516de0de87028d36a1f5/html5/thumbnails/7.jpg)
RF-17 Major Projects
![Page 8: Refuel 17 Plans - Nuclear Regulatory Commission · Refuel 17 Plans Don Shue Manager, Planning & Outage Management. ¾Outage Begins: April 25, 2008 ¾Duration: 38 Days ¾Outage Goals](https://reader036.fdocuments.in/reader036/viewer/2022062604/5fb4516de0de87028d36a1f5/html5/thumbnails/8.jpg)
Reactor Core Offload & Reload:•
Assemblies:
68 New Assemblies89 Visually Inspected Reinsert Assemblies
•
Install New RCCAs
•
Lead Test AssemblyVisual InspectionCladding OxidationAssembly & Rod Growth
•
Increased FME Focus
![Page 9: Refuel 17 Plans - Nuclear Regulatory Commission · Refuel 17 Plans Don Shue Manager, Planning & Outage Management. ¾Outage Begins: April 25, 2008 ¾Duration: 38 Days ¾Outage Goals](https://reader036.fdocuments.in/reader036/viewer/2022062604/5fb4516de0de87028d36a1f5/html5/thumbnails/9.jpg)
Reactor Core Offload & Reload:•
Baffle Jetting
Clipped 8 AssembliesVisual Inspection of 32 Outer Assemblies
•
Contingencies:In Mast Sipping, UT, ReconsitutionAdditional ClippingCore Redesign
![Page 10: Refuel 17 Plans - Nuclear Regulatory Commission · Refuel 17 Plans Don Shue Manager, Planning & Outage Management. ¾Outage Begins: April 25, 2008 ¾Duration: 38 Days ¾Outage Goals](https://reader036.fdocuments.in/reader036/viewer/2022062604/5fb4516de0de87028d36a1f5/html5/thumbnails/10.jpg)
Required By Material Reliability Program Number 139 (MRP-139).VC Summer Allowed Deviation to 2008Will Overlay Six Nozzles
Surge Line (1)Safety Valves (3) Spray Line (1)Power Operated Relief (1)
WSI Will Be Repair Vendor
Pressurizer Weld Overlay:
![Page 11: Refuel 17 Plans - Nuclear Regulatory Commission · Refuel 17 Plans Don Shue Manager, Planning & Outage Management. ¾Outage Begins: April 25, 2008 ¾Duration: 38 Days ¾Outage Goals](https://reader036.fdocuments.in/reader036/viewer/2022062604/5fb4516de0de87028d36a1f5/html5/thumbnails/11.jpg)
“C”
RCP Flange Gasket Replacement:Slow Weep on Startup Under Cold ConditionsDoes Not Weep Under Hot Conditions
Will Upgrade Flange Using HydranutsAREVA Will Be Repair Vendor
![Page 12: Refuel 17 Plans - Nuclear Regulatory Commission · Refuel 17 Plans Don Shue Manager, Planning & Outage Management. ¾Outage Begins: April 25, 2008 ¾Duration: 38 Days ¾Outage Goals](https://reader036.fdocuments.in/reader036/viewer/2022062604/5fb4516de0de87028d36a1f5/html5/thumbnails/12.jpg)
![Page 13: Refuel 17 Plans - Nuclear Regulatory Commission · Refuel 17 Plans Don Shue Manager, Planning & Outage Management. ¾Outage Begins: April 25, 2008 ¾Duration: 38 Days ¾Outage Goals](https://reader036.fdocuments.in/reader036/viewer/2022062604/5fb4516de0de87028d36a1f5/html5/thumbnails/13.jpg)
![Page 14: Refuel 17 Plans - Nuclear Regulatory Commission · Refuel 17 Plans Don Shue Manager, Planning & Outage Management. ¾Outage Begins: April 25, 2008 ¾Duration: 38 Days ¾Outage Goals](https://reader036.fdocuments.in/reader036/viewer/2022062604/5fb4516de0de87028d36a1f5/html5/thumbnails/14.jpg)
B.5.B Large Area Fire Enhancements•
Completed Online Plant Changes in 2007
•
Will Complete Physical Changes During Refueling
•
System Modifications:Main FeedwaterCondensateReactor Building Spray
![Page 15: Refuel 17 Plans - Nuclear Regulatory Commission · Refuel 17 Plans Don Shue Manager, Planning & Outage Management. ¾Outage Begins: April 25, 2008 ¾Duration: 38 Days ¾Outage Goals](https://reader036.fdocuments.in/reader036/viewer/2022062604/5fb4516de0de87028d36a1f5/html5/thumbnails/15.jpg)
Generic Letter 2008-01 ItemsGas Accumulation In:
ECCSDecay Heat RemovalContainment Spray
RF-17 Actions:Laser Templating of Susceptible LinesPiping Ultrasonic ExamsProcedure Changes To Ensure System Flow & Remove Potential Voids
![Page 16: Refuel 17 Plans - Nuclear Regulatory Commission · Refuel 17 Plans Don Shue Manager, Planning & Outage Management. ¾Outage Begins: April 25, 2008 ¾Duration: 38 Days ¾Outage Goals](https://reader036.fdocuments.in/reader036/viewer/2022062604/5fb4516de0de87028d36a1f5/html5/thumbnails/16.jpg)
High Pressure Turbine Inspection:•
Double Axial Six Stage Monoblock Turbine
•
Rotor Installed in Refuel-11 (April 1999)
•
Inspection IncludesCleaningInspectionNDE
![Page 17: Refuel 17 Plans - Nuclear Regulatory Commission · Refuel 17 Plans Don Shue Manager, Planning & Outage Management. ¾Outage Begins: April 25, 2008 ¾Duration: 38 Days ¾Outage Goals](https://reader036.fdocuments.in/reader036/viewer/2022062604/5fb4516de0de87028d36a1f5/html5/thumbnails/17.jpg)
Main Generator Inspection:•
First Inspection Since Generator Rewind In Refuel-15
•
Assessment of Stator and Rotor
•
Robot Inserted Into Generator
•
Performs Wedge Tapping On Stator
![Page 18: Refuel 17 Plans - Nuclear Regulatory Commission · Refuel 17 Plans Don Shue Manager, Planning & Outage Management. ¾Outage Begins: April 25, 2008 ¾Duration: 38 Days ¾Outage Goals](https://reader036.fdocuments.in/reader036/viewer/2022062604/5fb4516de0de87028d36a1f5/html5/thumbnails/18.jpg)
Secondary FAC Inspections:•
Inspecting Multiple Locations (165 Total)
•
Some May Require Component Replacement
![Page 19: Refuel 17 Plans - Nuclear Regulatory Commission · Refuel 17 Plans Don Shue Manager, Planning & Outage Management. ¾Outage Begins: April 25, 2008 ¾Duration: 38 Days ¾Outage Goals](https://reader036.fdocuments.in/reader036/viewer/2022062604/5fb4516de0de87028d36a1f5/html5/thumbnails/19.jpg)
Feedwater Booster Pump Repairs:•
“A”
Pump Will Have
Seals Replaced•
“B”
Pump Will Be
Refurbished Including New Seals
•
PSE and Vendor Designed New Seal
•
“C”
& “D”
Pumps Previously Refurbished
![Page 20: Refuel 17 Plans - Nuclear Regulatory Commission · Refuel 17 Plans Don Shue Manager, Planning & Outage Management. ¾Outage Begins: April 25, 2008 ¾Duration: 38 Days ¾Outage Goals](https://reader036.fdocuments.in/reader036/viewer/2022062604/5fb4516de0de87028d36a1f5/html5/thumbnails/20.jpg)
Circulating Water Pump Motors:•
Began Purchase of New Motors Over 2 Years Ago
•
Install New Motor Onto “B”
CW Pump
•
The “Old”
CW Motor Will Now Be A Spare
•
New Motors Will Be More Reliable
![Page 21: Refuel 17 Plans - Nuclear Regulatory Commission · Refuel 17 Plans Don Shue Manager, Planning & Outage Management. ¾Outage Begins: April 25, 2008 ¾Duration: 38 Days ¾Outage Goals](https://reader036.fdocuments.in/reader036/viewer/2022062604/5fb4516de0de87028d36a1f5/html5/thumbnails/21.jpg)
Questions?Questions?