Refractory Dry Out Procedures

download Refractory Dry Out Procedures

of 18

description

Refractory Dry Out Procedures

Transcript of Refractory Dry Out Procedures

  • Refractory Dry Out ProceduresPage: 1 of 11 TAM/GPOS - 02

    Document Class 1

    PT TRUBA ALAM MANUNGGAL ENGINEERING CHINA SFECO

    PT.GLOBAL POWER SERVICES

    B Revised as comments

    A For approval

    Rev. Description Date Prepared Checked Reviewed Approved

    PT. PLN (PERSERO)PEMBANGKIT SUMATERA II

    OWNERSNO.

    PT. PLN (PERSERO)JASA SERTIFIKASI (LMK)

    ClientPLTU 3 BANGKA BELITUNG

    Bangka, Bangka-Belitung, Republic of IndonesiaDOC. NO. TAM01-NW0095-BB-0001

    Electronic File Name: Date of Issue: Revision No.

  • Refractory Dry Out Procedures

    Page 2 of 11

    1.0 SCOPE

    This procedure covers the general requirements for boiler refractory dry out.

    2.0 PURPOSE

    During the installation of refractory, its humidity and size is relevantly larger than the size after it

    is dried up. So that it shall be driying up before it is put into high temperature during boiler

    normal operation to eliminate natural water and crystal water.The remained water evaporation

    will cause cracks, protrusion, displacement or even worse falling off. In order to lengthen

    refractory lifespan and prevent boiler part abrasion, the curing process is necessary.

    3.0 REFERENCE

    3.1 VENDOR REFRACTORY DATA SHEET

    4.0 GENERAL DESCRIPTION OF THE SYSTEM

    4.1 Data of the boiler

    Type of the boiler : CFB

    Max steam capacity : 130t/hr

    Steam outlet temperature : 540 C

    Steam outlet pressure : 9.81 MPa

    5.0 IMPLEMENTATION OF METHODE

    5.1 High velocity gas firing is proposed to effect the dry-out of the component by : Internal

    vessel firing. The thermal input will be supplemented with the use of 1 or 2 Under Bed

    Burners for the High Temperature segment of the process (*if wood firing not reach the

    temp.)

    5.2 It is assumed that the low temperature a n d high temperature dry-out operations will be

    undertaken in one stage for the item parts of the site integrated plant.

    5.3 Salient Details for RDO

    5.3.1 Furnace5.3.2 Cyclone Inlet Duct / Crossover5.3.3 Cyclone5.3.4 Cyclone Outlet Duct5.3.5 Seal Pot5.3.6 Ash Return Duct

  • Refractory Dry Out Procedures

    Page 3 of 11

    5.4 Temperature Profile References

    5.4.1 Great Wall Refractory data sheet for low temperature RDO5.4.2 Owner Engineering Department.

    6.0 SAFETY PRECAUTION

    6.1 All staff shall wear helmet correctly before entering the site.

    6.2 All staff shall well familiar with Electric Power Construction Safe Working Regulation.

    6.3 Field apparatus and valve shall have nameplate. Work yard shall have security facilities

    and warning logo. Holes, channels and cavities shall be covered with board parallel with

    the ground or the reliable fence and red lamp shall be set in the dangerous place at night.

    6.4 Refractory devices are put in to use with abundant equipments.

    6.5 Sufficient lighting and emergency lighting can be used at any time.

    6.6 Complete footpath, crawling ladder and fence with unimpeded passageway, fire goods

    and trash shall be totally cleaned.

    6.7 Warning board of No Open Flames shall be hanging out in the operating region of fuel

    equipment. Tinder taking is strictly forbidden for entering this region and special person

    shall be arranged to take good care of that.

    6.8 Oil box and running pipe shall be kept strictness without oil leaking. If there has oil leak,

    it shall be repaired in time and clean up the oil in time.

    6.9 Making good protection to avoid scald and burn in the site.

    7.0 REFRACTORY DRY OUT PREPARATIONS

    7.1 According to various boiler construction materials, fabricate 3 groups of relevant

    standard test blocks (160 40 40mm). Put them into relevant positions during

    curing: furnace lower part, cyclone separator and Wind box, for the convenience

    of calculating material water content. The water content shall be lower than 0.5%

    after the curing.

    7.2 Finish the installation work of boiler proper, loop sealing system and flue gas system.

    Air leakage and air pressure tests shall be qualified.

    7.3 Check and clean the inside of furnace, flue/air duct, cyclone separator, loop seal, air

    pre-heater and dust remover.

  • Refractory Dry Out Procedures

    Page 4 of 11

    7.4 Complete the installation of boiler expansion indicator and adjust the needle to

    zero.

    7.5 Complete the installation of fuel oil system. After water pressure test, clean it and put

    into pre-commissioning and then supply oil to the boiler formally.

    7.6 Install and pre-commission boiler relevant thermal instruments and electrical

    instruments. Put into operation after colligation.

    7.7 Finish the installation of boiler inside. Drum water level shall be clear and accurate.

    Lighting condition shall be good.

    7.8 Make sure the availability of woods or other material as fuel media for low

    temperature curing program

    7.9 Make sure all the supporting system for RDO must be ready, such as : Drain Pump,

    Boiler Fans, and Cooling System

    7.10 Supply softened water or chemical demineralized water until normal water level.

    Water temperature shall follow design requirement. Clean the water level gauge.

    7.11 Set a certain amount of bed materials in boiler air distribution grid and open back

    opening man hole for the convenience of hot flue gas flowing through air distribution

    device evenly.

    7.12 Reserve humidity exhausting hole at the proper position of furnace wall to make sure

    that the steam can be exhausted freely during curing.

    7.13 Install temporary thermocouple for burner area ( burner 1 and 2 )

    7.14 Install temporary line from drain wind box to drain seal pot

    7.15 Temperature rising rate, insulation temperature and insulation duration shall be in

    consistent with possible dehydration and other physical variation and deformation.

    Curing process can be divided into the following two classes:

    The first stage (Phase 1) : carry out mid-low temperature curing at approximately

    150C and 250C stages according to water discharge law. The main purpose of this

    stage is to discharge free water in the castables. There is a large amount of free water

    in the castables that using cement as combining agent. So that the insulation time for

    this stage shall be long enough to eliminate free water completely.

    The second stage (phase 2) : high temperature curing combining with boiler pre-

    commissioning. The main purpose for this stage is to discharge structural water in

    the refractory materials. Structural water refers to H-O-H. Eliminate H- and -O-H to

    increase refractory intensity.

  • Refractory Dry Out Procedures

    Page 5 of 11

    8.0 REFRACTORY CURING PROGRAM

    8.1 Low-temperature curing program

    Temperature

    (C)

    Temperature rising

    speed C /h

    Time

    (hr)Remarks

    Normal temperature 150 5 17 Remove free water150 C maintain 32

    150 - 250 C 5 16Remove structure water

    250 C maintain 32

    Total minimum curing timeShutdown the boiler and check low temperature curing condition

    7.2 High temperature curing program (combine with pre-commissioning)

    Temperature

    (C)

    Temperature rising

    speed C /hTime (hr) Remarks

    Normal temperature - 150 10 20 5 - 10Remove free water150 maintain temp. 10

    150 - 250 10 20 16

    250 Maintain temp. 16Remove structure water and

    Heat Balance Stage250 350 15 25 16

    350 Maintain temp. 48

    Cooling Down

    Total minimum curing time

    After finish, natural cooling down

  • Refractory Dry Out Procedures

    Page 6 of 11

    9.0 REFRACTORY DRY OUT OPERATION METHOD

    9.1 Low temperature

    1) Startup Burner and Hot Primary Air :

    Gas flow:

    Hot Primary Air Start up Burner Seal Pot and Separator Separator Outlet

    Flue Duct ID fan

    Operation method:

    In the initial stage, remove start up oil gun, open ID fan inlet and Outlet dumper. Open

    man hole, set the fire wood, cover the primary air nozzle at bed furnace with rockwoll

    and Supervise burner wall and wind box temperature during baked period. The

    temperature rising rate shall strictly follow the requirement in the curve.

    In order to make hot flue gas reach the loop seal connect the temporary thin pipe of

    drain wind box to drain of seal pot for flue emission.

    When baked for period, then the natural cooling to ambient temperature install the

    start up burner back for the high temperature curing period.

    2) Furnace Dense-Phase Zone

    Gas flow:

    Furnace dense-phase zone Loop seal and cyclone separator outletflue ductID fan

    Loop seal

    Operation method:

    In the initial period, bake the furnace from thermal firewood and the temperature

    rising rate shall follow the curve. If the firewood heat quantity cannot meet

    temperature rising requirement, input burner into service to continue heating up.

    Closely supervise wall temperature metering point until the first stage of curing is

    finished.

  • Refractory Dry Out Procedures

    Page 7 of 11

    9.2 High-temperature Refractory Dry Out (*if wood firing methode not reach temp.)

    After the first stage of Refractory Dry Out remove all temporary facilities, recover

    formal system and start the second stage of curing, that is, high temperature curing stage.

    High-temperature curing stage is boiler formal operation stage. Start up ID fan and

    primary fan. Ignite under burner and Control air room temperature rising rate with

    primary air flow rate and oil flow rate. At this time all the systems are in normal

    operation status. Control Burner and primary air flow rate to meet temperature rising

    curve requirement.

    As the steam parameter is very high at the later stage of phrase 2 curing, so this time

    boiler blow pipe shall be kept on executed through Boiler Blow Pipe Measures. Carry out

    the moisture content test of presetting model after its natural cooling.

    10.0 REFRACTORY DRY OUT CAUTIONS

    10.1 Curing shall be executed before activate combustion furnace and the curing of hearth,

    separator and return value shall be carried out thereupon after that and the curing of

    activate combustion furnace shall finished before the phase 2 curing. Detection point

    and temperature rising rate in any region shall not exceed the requirement of heating

    curve rate and thermal insulation of curing. Temperature rising rate and boiler

    temperature shall not over the standard when the curing temperature is in 110 - 350C

    periods and 10C tolerance is permitted in other temperature period. According to the

    actual craft condition, partial short time over-heating is permitted with 30Ctolerance,

    but it would be better if the temperature can be controlled well in accordance with the

    standard.

    10.2 Because the warming regions are connected during the curing period, which will

    interfere temperature and the heating curve in different regions at the same time, so

    adding temperature-keeping time of heating curves in different regions during the

    curing process is permitted to secure the temperature-keeping time in all parts of boiler.

    10.3 Interruption during the curing process caused by the craft, the speed of temperature

    rising and dropping shall in accordance with the related standard.

    10.4 Air bleeder shall be preset on furnace wall and combustor, etc, which covered the

    castables and one air bleeder, shall be made on the fender apron of separator for 5 m2

    intervals at least.

  • Refractory Dry Out Procedures

    Page 8 of 11

    10.5 Steam that produced during the curing process will eject from the exhaust gate. The

    temperature tolerance of steam pocket wall shall be no more than 50C during warming

    and boosting process. In order to control the temperature, the wall temperature of super

    heater shall be closely monitored at the later stage of curing process. The water level

    tolerance shall be opened occasionally to feed water for the boiler.

    10.6 After low-temperature curing, the moisture content test will be carried out in the related

    region of anti-friction and refractory matter; the high-temperature curing will be

    conducted once the test is qualified.

    10.7 Temperature rising shall be stable during the curing process, and the furnace wall

    situation shall be always checked to avoid flow and transformation.

    10.8 Open vent properly in order to eject moisture during curing process.

    10.9 Flame must be small at the beginning of curing, or else partial temperature rising speed

    too fast will cause the negative effects.

    10.10 Sewerage under boiler circuit shall be kept totally open to avoid thermal shock and

    water attack.

    10.11 Set exhausting system shall be connected to keep smooth water in order to avoid the

    water attack that caused by water trapped.

    10.12 Expansion indicators in all parts of boiler shall be calibrated zero.

    10.13 During curing process, blow-off pipe shall be always checked and dealt with the blow

    down valve if there has something abnormal.

    10.14 All connected drain valve of header can be adjusted according to the curing situation.

    11.0 INSPECTION METHOD

    11.1 At the beginning of curing, the wall temperature in all points of steam pocket shall be

    monitored at any time and record every 1 hour and every 2 hours after the completely

    preheat with record other monitoring points every 1 hour.

    11.2 At initial stage every 1 hour and then every 2 hours checking the expansion indicator

    and make records. If there has any abnormal situation, report shall be made at once,

    decrease the temperature and checking then curing again after the problem found and

    solved.

  • Refractory Dry Out Procedures

    Page 9 of 11

    12.0 APPENDIX12.1 General Arrangement of High Velocity Gas Flow12.2 Temperature Rise Curve

  • Refractory Dry Out Procedures

    Page 10 of 11

    APPENDIX 1

    TO FLUE DUCT

    Firewood Combustion

    Temporary Line ( drain windbox to drain seal pot)

  • Refractory Dry Out Procedures

    Page 11 of 11

    APPENDIX 2

  • FIELD INSPECTION AND TESTING REPORT

    Form No. :

    Drawing No. :

    Tested by

    SignaturePrint nameDate

    No Subject

    1Check and clean the inside of furnace, flue/air duct,cyclone separator, loop seal, air preheaterburner and dust remover

    2 Complete the installation of boiler expansionindicator and adjust the needle to zero3 Completion of fuel oil system

    4 Completion of Combustion system and Feed WaterSystem5 Drum water level shall be clear and accurate

    6Install and pre-commission boiler relevantthermal instruments and electrical instruments.Put into operation after colligation

    7 Supply demineralized water until normal waterlevel.Clean the water level gauge

    8 Make sure manhole at backposition9 Availability of fire woods and other material as fuel

    10 Interconnection temporary line between drainwindbox and drain sealpot

    11 Tool, Instrumentation, and communicationequipment related to the test shall be12 Fire fighting equipment should be ready on area

    FIELD INSPECTION AND TESTING REPORT

    REFRACTORY DRY OUT

    Responsible by Witness and Approved by

    TAME - SFECO CONSULTANT PLN

    Subject Yes No N/ACheck and clean the inside of furnace, flue/air duct,cyclone separator, loop seal, air preheater, wind box,

    Complete the installation of boiler expansionindicator and adjust the needle to zero

    fuel oil system and burnerCompletion of Combustion system and Feed Water

    Drum water level shall be clear and accuratecommission boiler relevant

    thermal instruments and electrical instruments.Put into operation after colligation.Supply demineralized water until normal waterlevel.Clean the water level gauge

    manhole at back opening on open

    ire woods and other material as fuelInterconnection temporary line between drainwindbox and drain sealpotTool, Instrumentation, and communicationequipment related to the test shall be furnished.Fire fighting equipment should be ready on area

    CHECK LIST

    Page No.

    Witness and Approved by

    PLN COMM.

    Remarks

  • FIELD INSPECTION AND TESTING REPORT

    Form No. :

    Drawing No. :

    Tested by

    SignaturePrint nameDate

    Area : Furnace / Wind Box / Cyclone

    No Area Time

    FIELD INSPECTION AND TESTING REPORT

    REFRACTORY DRY OUT

    Responsible by Witness and Approved by

    TAME - SFECO CONSULTANT PLN

    RDO Process Report

    Area : Furnace / Wind Box / Cyclone (L/R) Date : ....................

    Parameter

    Temp Temp Rising

    Page No.

    Witness and Approved by

    PLN COMM.

    Remarks

  • FIELD INSPECTION AND TESTING REPORT

    Form No. :

    Drawing No. :

    Tested by

    SignaturePrint nameDate

    Area :Temperature

    (C)

    1. Low Temperature (at Burner and Windbox)

    Normal temperature 150

    150 C

    150 - 250 C

    250 C

    2. Low Temperature (at Furnace Dense)

    Normal temperature 150

    150 C

    150 - 250 C

    250 C

    3. High Temperature250 350

    350

    4. Natural Cooling DownNote

    FIELD INSPECTION AND TESTING REPORT

    REFRACTORY DRY OUT

    Responsible by Witness and Approved by

    TAME - SFECO CONSULTANT PLN

    RDO Process Report

    TemperatureRising Speed

    (C)

    Time(Duration)

    hr

    Result

    OK

    (at Burner and Windbox)

    5 17

    maintain 32

    5 10

    maintain 36

    Furnace Dense)

    5 17

    maintain 32

    5 10

    maintain 36

    15 25 10

    Maintain temp. 56

    -

    Page No.

    Witness and Approved by

    PLN COMM.

    Result Remarks

    NO

  • FIELD INSPECTION AND TESTING REPORT

    Form No. :

    Drawing No. :

    Tested by

    SignaturePrint nameDate

    Date :

    Activity : Visual Inspection after Refractory Dry Out

    Equipment : Refractory

    No Subject

    1 REFRACTORY FURNACE

    2 REFRACTORY WINDBOX

    3 REFRACTORY LEFT CYCLONE

    4 REFRACTORY RIGHT CYCLONE

    See attachment visual inspection

    Note :

    FIELD INSPECTION AND TESTING REPORT

    REFRACTORY DRY OUT

    Responsible by Witness and Approved by

    TAME - SFECO CONSULTANT PLN

    Visual Inspection after Refractory Dry Out Completed

    Refractory

    ConditionRemarksGood Bad

    REFRACTORY LEFT CYCLONE

    REFRACTORY RIGHT CYCLONE

    See attachment visual inspection report

    Page No.

    Witness and Approved by

    PLN COMM.

    Completed

    Remarks

  • FIELD INSPECTION AND TESTING REPORT

    Form No. :

    Drawing No. :

    Tested by

    SignaturePrint nameDate

    Remarks :

    PICTURE

    BEFORE RDO

    PICTURE

    AFTER RDO

    FIELD INSPECTION AND TESTING REPORT

    REFRACTORY DRY OUT

    Responsible by Witness and Approved by

    TAME - SFECO CONSULTANT PLN

    ATTACHMENT JOINT INSPECTION

    FURNACE

    PICTURE

    BEFORE RDO

    PICTURE

    AFTER RDO

    Page No.

    Witness and Approved by

    PLN COMM.

    PICTURE

    BEFORE RDO

    PICTURE

    RDO

  • FIELD INSPECTION AND TESTING REPORT

    Form No. :

    Drawing No. :

    Tested by

    SignaturePrint nameDate

    Remarks :

    PICTURE

    BEFORE RDO

    PICTURE

    AFTER RDO

    FIELD INSPECTION AND TESTING REPORT

    REFRACTORY DRY OUT

    Responsible by Witness and Approved by

    TAME - SFECO CONSULTANT PLN

    ATTACHMENT JOINT INSPECTION

    WIND BOX

    PICTURE

    BEFORE RDO

    PICTURE

    AFTER RDO

    Page No.

    Witness and Approved by

    PLN COMM.

    PICTURE

    BEFORE RDO

    PICTURE

    RDO

  • FIELD INSPECTION AND TESTING REPORT

    Form No. :

    Drawing No. :

    Tested by

    SignaturePrint nameDate

    Remarks :

    PICTURE

    BEFORE RDO

    PICTURE

    AFTER RDO

    FIELD INSPECTION AND TESTING REPORT

    REFRACTORY DRY OUT

    Responsible by Witness and Approved by

    TAME - SFECO CONSULTANT PLN

    ATTACHMENT JOINT INSPECTION

    CYCLONE L/R

    PICTURE

    BEFORE RDO

    PICTURE

    AFTER RDO

    Page No.

    Witness and Approved by

    PLN COMM.

    PICTURE

    BEFORE RDO

    PICTURE

    RDO