Reducing waste in building and civil engineering projects ... Guide to cost saving...
date post
15-Apr-2018Category
Documents
view
216download
3
Embed Size (px)
Transcript of Reducing waste in building and civil engineering projects ... Guide to cost saving...
00 Good Practice Guide
Reducing waste in building and civil engineering projects
Guide to cost saving and client cost saving strategies
Guidance for construction clients and their advisers on how to encourage cost savings through waste reduction on their projects and share in these savings
WRAP helps individuals,businesses and local authoritiesto reduce waste and recycle more,making better use of resources andhelping to tackle climate change.
Contents
1.0 Reducing the cost of waste in construction: guidance for construction clients 012.0 What are the cost savings? 023.0 Reducing wastage allowances and wastage rates 064.0 Incorporating reused and/or recycled materials (on site reuse and imported materials) 115.0 Reduce total waste (in design and on site) 16 6.0 Reduce unit cost of disposal 237.0 Sharing the savings 27 7.1 Traditional procurement single stage 28 7.2 Traditional procurement two stage 29 7.3 Design and Build 30 7.4 Collaborative procurement 30 7.5 PFI/PPP contracts 31 7.6 Management Contracting and Construction Management 318.0 Where should I focus? 329.0 Guidance and tools 34
By taking action on waste, your projects can reduce costs in two ways:n spending less on materials; andn spending less on waste disposal.
Spending less on materialsPurchase costs can be cut by:1. taking positive steps to reduce wastage allowances and achieve
lower wastage rates on major components; and2. reusing/reprocessing demolition, excavation and construction
materials on site (in place of imported materials); using materials in-situ (e.g. following remediation); and purchasing recovered and/or recycled materials which are less expensive than primary products.
Spending less on waste disposalDisposal costs can be cut by:1. reducing the total amount of waste produced (e.g. through
designing out waste, improving site storage of materials, off site construction, reuse of demolition and excavation materials on site etc); and
2. reducing the unit cost of disposal (e.g. by segregating out the most valuable / high cost waste streams).
Use the table below to access further guidance for building and infrastructure projects.
Use the following links to:n learn how the client can share in these savings;n identify where to focus efforts;n find case study evidence on potential savings; andn access WRAPs free tools and resources to help quantify waste and cost savings.
1.0 Reducing the cost of waste in construction: guidance for construction clients
Guide to cost saving and client cost saving strategies 01
Waste is expensive and often under-estimated as a construction cost.
This guidance identifies how projects can cut the costs of waste, and what actions you (as the client) can take to increase and share in these savings.
Spending less on materials
Spending less on waste disposal
Reduce wastage rates
Incorporate reused / recycled materials(on site reuse and imported materials)
Reduce total waste (in design and on site)
Reduce unit cost of disposal
WRAP (Waste & Resources Action Programme) has conducted studies into the potential for cost savings from taking action to reduce waste through design and on site. In addition, WRAP has published case studies on projects (buildings and civils) which demonstrate actual money savings. Clients, design teams and contractors can review these case studies to learn from good practice.
Cost savings from reducing wastage rates and segregating waste streamsWRAP has estimated for a range of building types the savings available if wastage rates on a few key materials are reduced from typical industry baseline practice to good practice rates (as identified by major contractors), and if waste is segregated on site rather than going off site in mixed waste skips. The calculations are made using the Net Waste Tool, which applies wastage rates to cost plan information. The analysis identifies which components and specifications offer the greatest opportunities for waste/cost saving, and proposes a least-cost segregation strategy. The results include both the value of materials that are wasted, and the cost of waste disposal. The analysis does not include further savings from more fundamental design changes at an earlier stage, or savings from reuse of demolition and excavation materials.
2.0 What are the cost savings?
02 Guide to cost saving and client cost saving strategies
HousingHouses (20, masonry construction)Houses (20, timber-framed)Residential block (concrete-framed)Halls of residence (steel-framed)
CommercialSupermarket (steel-framed)Distribution centre (steel-framed)Office (concrete-framed)
PublicHospital (in-situ concrete-framed)Secondary school (steel-framed)Primary school (steel-framed)Prison (pre-cast concrete-framed)
RefurbishmentSocial housing refurbishmentSmall office refurbishment (Cat A)Large office refurbishment (Cat B)Small retail refurbishment
1.0 1.3 7.1 9.8
3.8 11.0 23.0
178.0 22.5 1.5 4.9
1.5 0.7 3.3 1.4
Reduction in value of materials wasted (A)
7,60014,40026,20057,800
20,70044,500
101,700
446,600125,900
8,2008,700
3,3002,600
12,7007,300
9,2007,1006,100
18,600
5,80028,60024,100
109,10034,700
2,7001,200
10,3001,3004,4004,800
10,70010,80019,70024,300
16,20016,60029,700
64,80028,900
8,4008,200
6,3002,3005,9008,700
6,10010,700
8,60052,100
10,30056,50096,100
490,900131,700
2,5001,700
7,3001,600
11,2003,400
Reduction in disposal
cost(B)
Cost of implement-
ation(C)
Net Benefit
(A+B)-C
Summary of net cost savings on different types of project as a result of reducing wastage rates from baseline to good practice levels on a few major components1
()(M)
Project construction
value
1For example, the quoted savings on the timber-framed house example are from the seven components where lower wastage has the biggest impact in reducing material purchase costs: brickwork, blockwork, plasterboard, insulation, roof tiles, ground slab and chipboard flooring.
Guide to cost saving and client cost saving strategies 03
HousingCommercialPublicRefurbishment
Cost savings from lower wastage rates and waste segregation in construction averaged across a number of project analyses
Saving as % of construction cost
Saving on cost of materials
(A)
0.550.440.290.24
Reduction in disposal cost
(B)
0.020.160.070.44
Total saving(A+B)
0.760.060.360.68
Cost of implement-
ation(C)
0.340.170.050.34
Net Benefit
(A+B)-C
1.420.430.300.34
The results indicate that projects can save 0.2% to 2% of construction value by reducing wastage and the cost of its disposal. These savings are stated after subtracting the costs of implementing good practice (such as additional planning, monitoring, training, materials storage etc). The case studies also illustrate the associated reductions in landfill and carbon emissions.
The following tables list the cost savings for various building types. For more examples, visit www.wrap.org.uk/constructioncba or the sector-specific pages on WRAPs web site.
Brick and block wall with insulationFlooringBoard insulationTimber stud partitioning
Construction value
100100100100
Total saving(A)
8,4302,520
2,540
Cost of implementation
(B)
1,0601,0601,0601,060
Net Benefit(A B)
7,3701,4609,5601,480
Summary of net cost savings on different trade packages (each 100k value) as a result of reducing wastage rates from baseline to good practice levels on a few major components
()Trade package
10,620
(k)
04 Guide to cost saving and client cost saving strategies
Cost savings from designing out wasteWRAP has conducted studies that identified and quantified opportunities to design out waste on several projects (mainly buildings). These opportunities were discussed with the design teams at RIBA stages C/D, and selected actions were approved as real solutions that might be considered on these or future projects.
Colchester & Chelmsford CourtsPre-fabricated concrete stairwells
Queenshill CourtSavings from use of prefabricated bathroom pods
Southgate CollegeModular classroom construction
Pre-cast concrete columns
Tate Modern 2Material re-use for landscaping
Fair-faced finish internal walls
Saving in the cost of construction
(A)
17,800
78,800
52,300
40,700
78,000
49,400
Construction Value(m)
30
6.8
20
118
Saving in the cost of waste disposal
(B)
900
3,000
9,100
600
11,200
400
Total savings(A+B)
18,700
81,800
61,400
41,300
89,200
49,800
Cost savings from reducing waste in design
()
Guide to cost saving and client cost saving strategies 05
Cost savings from material re-useOpportunities for material re-use are more common in civil engineering projects and building projects with significant ground/site works. This is due to the fact that materials reuse is most commonly in the form of recycled aggregates and reprocessed materials that have applications in infrastructure and civil works, and building substructure, rather than building superstructures. Savings from material re-use can be very significant. On average, 50% of the cost of certain packages can be saved by incorporated recycled materials, whethe