Reduced cost bases Transportation & Installation merging · PDF fileReduced cost bases...

36
Reduced cost bases Transportation & Installation merging Deep water MPP Umbilical and Structures Installation Moho Nord, Offshore Congo 12 th February 2017

Transcript of Reduced cost bases Transportation & Installation merging · PDF fileReduced cost bases...

Reduced cost bases

Transportation & Installation merging

Deep water MPP Umbilical and Structures Installation

Moho Nord, Offshore Congo

12th February 2017

AGENDA

/ INTRODUCTION

/ BACKGROUND

/ PROJECT EXECUTION

/ PCM INSTALLATION

/ MPP UMBILICAL INSTALLATION

/ QUESTIONS

3

OCEAN INSTALLERAt a glance

4

MOHO NORD DEVELOPMENT

Client: TOTAL

Ownership: TOTAL (~53.5%) – OperatorChevron (~31.5%)Société Nationale des Pétroles du Congo (~15%)

Location: 75km SW of Pointe Noire – Congo

Water Depth: 750 – 1,200m

Subsea Infrastructure:• 28 Subsea wellheads tied back to FPUs• 17 additional wells from new TLP

Production capacity: 140,000 b/d

Moho Phase 1 Bis Scope:• Extension of Moho Bilondo subsea development• Tied back to Alima FPU

Ocean Installer won the MPI Contract

Total © Total ©

Total ©

Total ©

5

TOTAL

OVERVIEW

MOHO NORD CPI

2 x 45Te Transformers

175Te Pump Control Module

70Te SUT

12,5m LongTopside end

6,3km MPP Power & Control Umbilical

Support & Leveling Structure

252 Te Multi Phase Pump Module

Dummy Multi Phase Pump Module

20 x Flying Leads

6

MOHO NORD INSTALLATION VESSELVessels – CSV Normand Vision

Long-term charter from Solstad

Ordered and developed in cooperationbetween OI, Solstad and Vard

Class leading asset design

Tailored for installation offlexible risers and flowlines

Length: 156,7m

Breadth: 27m

VLS: 150t

Crane capacity: 400t

Bunks: 140

Under deck carousel: 3000 ton

On deck carousel: 1800 ton

.

8 OFF VESSELS WITH SAME DESIGN

Skandi Acergy

Skandi Artic (DSV)

Aker Wayfarer

Lewek Connector

Normand Oceanic

Skandi Vitoria

Skandi Niteroi

7

Key Sites

GEOGRAPHICAL OVERVIEW

RosythUmbilical

TotalParis

StordMobilisation

StavangerPM&E

Pointe NoireCongo

Moho NordSite

BergenStructures

AGENDA

/ INTRODUCTION

/ BACKGROUND

/ PROJECT EXECUTION

/ PCM INSTALLATION

/ MPP UMBILICAL INSTALLATION

/ QUESTIONS

2014 2015 2016 2017

Project AwardJuly 2015

ITTDec 2014

Tender Phase7 months

Task 5 Here

Timeline

KEY PROJECT MILESTONES

10

Deck area

NORMAND VISION

Deck area 2100 m2

3000Te Underdeck Carousel

11

EQUIPMENT OVERVIEWInstallation & Tooling

Installation

• 2 x I/O Transformers• PCM• MPP Umbilical• MPP module• 20 x Flying leads

Project equipment

• Project side VLS• Project rigging & tools• Horizontal connection system• Survey• Precommissioning

12

Deck Overview

DECK PLAN

Plan view of deckready for transitfrom Rosyth

13

One trip:• Vessel Mobilisation (personnel, rigging, installation aids and side

VLS)• Ocean Installer – Project Mobilisationo Stord

• One Subsea – Norwayo Loadout MPP moduleo Loadout PCM & Transformers

• Oceaneering – UKo Transit to Rosytho Loadout umbilical

• Moho Nord Field - Congoo Transit to Congoo Installation activities

Installation Approach

ONE TRIP APPROACH

AGENDA

/ INTRODUCTION

/ BACKGROUND

/ PROJECT EXECUTION

/ PCM INSTALLATION

/ MPP UMBILICAL INSTALLATION

/ QUESTIONS

2014 2015 2016 2017

ProjectDemobJan 2017

Project MobOct 2016

Project AwardJuly 2015

ITTDec 2014

Tender Phase7 months

Engineering Phase15 months

InstallationPhase3 months

Task 5 Here

Timeline

KEY PROJECT MILESTONES

ProjectHAZID

Jan 2016

ProjectHAZOP

May 2016

16

CONGO OPERATIONS & PLANNINGLocal support team

Congo services

• Rope Access team on Alima• Provisions• Liftco, rigging• Precom supplies• Pointe Noire project operational office• External and covered storage facilities• Local harbour, Normand Vision Pointe Noire• Welders, on Normand Vision• Burners, on Normand Vision• Translators• Agency

17

General field overview

MPP STATION

Ca. 5,7km

INSTALLATION SITES

FPU Alima

18

FPU Alima

Location: Moho Nord Field – Congo

Moored on fixed heading (12 Mooring lines)

L: 188.5m

B: 34m

Slot 5: Umbilical Pull-in

M41C: PCM Installation

M51A: Transformer Installation (2x)

INSTALLATION SITES

AGENDA

/ INTRODUCTION

/ BACKGROUND

/ PROJECT EXECUTION

/ PCM INSTALLATION

/ MPP UMBILICAL INSTALLATION

/ QUESTIONS

20

PCM INSTALLATIONOverview – PCM Lift

Crane Curve – Sealift Mode

Radius – 19m

Available Lifting Height – 38.5 m

Capacity – 265 Te

Utilisation (Dyn.) – Approx 75%

21

DYNAMIC ANALYTICAL ANALYSISRelease of Load

LOSE CA. 60Te DURING ROTATION

LOSE CA. 100Te ON CONTACT OF LOWER SUPPORT

CA. 9DEG DYNAMIC ROLL ON VESSEL

22

PCM INSTALLATIONWeather Criteria – Head Seas

Relative Vertical Motion [m]

TP [s]

HS [m]6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

2,1 0,4 0,6 0,9 1,2 1,9 2,1 2,5 2,9 3,9 5,4 5,7 6,1 8,5 7,5 5,1

1,8 0,3 0,6 0,8 1,0 1,5 1,7 2,1 2,4 3,4 4,5 5,8 5,4 4,8 4,1 3,9

1,5 0,3 0,4 0,6 0,8 1,2 1,4 1,8 2,2 3,2 3,8 4,4 4,6 4,4 3,5 2,7

1,1 0,2 0,3 0,5 0,6 0,9 1,0 1,3 1,7 2,8 3,6 3,4 3,4 2,9 3,3 2,0

Acceptable for 1.7m of Relative Vertical Motion

Acceptable for 2.5m of Relative Vertical Motion

Acceptable for 3.5m of Relative Vertical Motion

Not Acceptable

23

PCM INSTALLATIONKey Challenge is tolerances Vrs Motion

24

PCM INSTALLATIONCLEARANCE

25

PCM INSTALLATIONOverboarding Sequence

26

PCM INSTALLATIONWeather Criteria – Head Seas

27

PCM INSTALLATIONWeather Criteria +/-30deg

28

SIMULATIONS

• Real time simulation

• Vessel crew

• Operational experience

• Crane and Moored FPU simulation

• Crane Controls as per vessel

• Tugger functionality as per vessel

DP System

29

INSTALLATIONPCM operations

AGENDA

/ INTRODUCTION

/ BACKGROUND

/ PROJECT EXECUTION

/ PCM INSTALLATION

/ MPP UMBILICAL INSTALLATION

/ QUESTIONS

31

Product loadout

UMBILICAL OPERATIONS

32

Handling operations

UMBILICAL OPERATIONS

Topside Endloadout fromhandoverlocation

Transpoolingproduct loading intounderdeck carousel

SUT lift fromhandoverlocation

SUT landed onseafastening.Product stored inunderdeckcarousel

33

The MPP umbilical is to be installed betweenthe MPP location and FPU Alima.

Main umbilical data:Length: 6260mOD: 230.5mmWeight: 101.1kg/mMBR: 6.7m (load controlled)MBR: 4.8m (discplacement controlled)

Introduction

MPP UMBILICAL INSTALLATION

34

Sim Vrs Installation

MPP UMBILICAL INSTALLATION

35

MOHO NORD MPI PROJECTOverview

Total split Project Overall SURF SOW

SOW tailored to a Mid Size Deep Water ConstructionVessel such as Normand Vision

Optimization of the execution plan (Transport &Installation in one phase)

Very competitive pricing of relevant SOW

Adding to our strong and successful track record inSURF projects

Systematic and meticulous approach to new countriesentry

Safe, on time, on budget project execution

Sucessful for Total and Ocean Installer

SAME CAN BE DONE FOR DEEP WATER SOW’s IN EGYPT

36CONTACTS

Technical

Iarla Lewis

Project Technical Manager

Mobile +47 901 28 341

[email protected]

Egypt Contact

PATRICK CHAPALAIN

MANAGING DIRECTOR AFMED & MIDDLE EASTREGION

Mobile +971 566 800 972

[email protected]