Reduced cost bases
Transportation & Installation merging
Deep water MPP Umbilical and Structures Installation
Moho Nord, Offshore Congo
12th February 2017
AGENDA
/ INTRODUCTION
/ BACKGROUND
/ PROJECT EXECUTION
/ PCM INSTALLATION
/ MPP UMBILICAL INSTALLATION
/ QUESTIONS
4
MOHO NORD DEVELOPMENT
Client: TOTAL
Ownership: TOTAL (~53.5%) – OperatorChevron (~31.5%)Société Nationale des Pétroles du Congo (~15%)
Location: 75km SW of Pointe Noire – Congo
Water Depth: 750 – 1,200m
Subsea Infrastructure:• 28 Subsea wellheads tied back to FPUs• 17 additional wells from new TLP
Production capacity: 140,000 b/d
Moho Phase 1 Bis Scope:• Extension of Moho Bilondo subsea development• Tied back to Alima FPU
Ocean Installer won the MPI Contract
Total © Total ©
Total ©
Total ©
5
TOTAL
OVERVIEW
MOHO NORD CPI
2 x 45Te Transformers
175Te Pump Control Module
70Te SUT
12,5m LongTopside end
6,3km MPP Power & Control Umbilical
Support & Leveling Structure
252 Te Multi Phase Pump Module
Dummy Multi Phase Pump Module
20 x Flying Leads
6
MOHO NORD INSTALLATION VESSELVessels – CSV Normand Vision
Long-term charter from Solstad
Ordered and developed in cooperationbetween OI, Solstad and Vard
Class leading asset design
Tailored for installation offlexible risers and flowlines
Length: 156,7m
Breadth: 27m
VLS: 150t
Crane capacity: 400t
Bunks: 140
Under deck carousel: 3000 ton
On deck carousel: 1800 ton
.
8 OFF VESSELS WITH SAME DESIGN
Skandi Acergy
Skandi Artic (DSV)
Aker Wayfarer
Lewek Connector
Normand Oceanic
Skandi Vitoria
Skandi Niteroi
7
Key Sites
GEOGRAPHICAL OVERVIEW
RosythUmbilical
TotalParis
StordMobilisation
StavangerPM&E
Pointe NoireCongo
Moho NordSite
BergenStructures
AGENDA
/ INTRODUCTION
/ BACKGROUND
/ PROJECT EXECUTION
/ PCM INSTALLATION
/ MPP UMBILICAL INSTALLATION
/ QUESTIONS
2014 2015 2016 2017
Project AwardJuly 2015
ITTDec 2014
Tender Phase7 months
Task 5 Here
Timeline
KEY PROJECT MILESTONES
11
EQUIPMENT OVERVIEWInstallation & Tooling
Installation
• 2 x I/O Transformers• PCM• MPP Umbilical• MPP module• 20 x Flying leads
Project equipment
• Project side VLS• Project rigging & tools• Horizontal connection system• Survey• Precommissioning
13
One trip:• Vessel Mobilisation (personnel, rigging, installation aids and side
VLS)• Ocean Installer – Project Mobilisationo Stord
• One Subsea – Norwayo Loadout MPP moduleo Loadout PCM & Transformers
• Oceaneering – UKo Transit to Rosytho Loadout umbilical
• Moho Nord Field - Congoo Transit to Congoo Installation activities
Installation Approach
ONE TRIP APPROACH
AGENDA
/ INTRODUCTION
/ BACKGROUND
/ PROJECT EXECUTION
/ PCM INSTALLATION
/ MPP UMBILICAL INSTALLATION
/ QUESTIONS
2014 2015 2016 2017
ProjectDemobJan 2017
Project MobOct 2016
Project AwardJuly 2015
ITTDec 2014
Tender Phase7 months
Engineering Phase15 months
InstallationPhase3 months
Task 5 Here
Timeline
KEY PROJECT MILESTONES
ProjectHAZID
Jan 2016
ProjectHAZOP
May 2016
16
CONGO OPERATIONS & PLANNINGLocal support team
Congo services
• Rope Access team on Alima• Provisions• Liftco, rigging• Precom supplies• Pointe Noire project operational office• External and covered storage facilities• Local harbour, Normand Vision Pointe Noire• Welders, on Normand Vision• Burners, on Normand Vision• Translators• Agency
18
FPU Alima
Location: Moho Nord Field – Congo
Moored on fixed heading (12 Mooring lines)
L: 188.5m
B: 34m
Slot 5: Umbilical Pull-in
M41C: PCM Installation
M51A: Transformer Installation (2x)
INSTALLATION SITES
AGENDA
/ INTRODUCTION
/ BACKGROUND
/ PROJECT EXECUTION
/ PCM INSTALLATION
/ MPP UMBILICAL INSTALLATION
/ QUESTIONS
20
PCM INSTALLATIONOverview – PCM Lift
Crane Curve – Sealift Mode
Radius – 19m
Available Lifting Height – 38.5 m
Capacity – 265 Te
Utilisation (Dyn.) – Approx 75%
21
DYNAMIC ANALYTICAL ANALYSISRelease of Load
LOSE CA. 60Te DURING ROTATION
LOSE CA. 100Te ON CONTACT OF LOWER SUPPORT
CA. 9DEG DYNAMIC ROLL ON VESSEL
22
PCM INSTALLATIONWeather Criteria – Head Seas
Relative Vertical Motion [m]
TP [s]
HS [m]6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
2,1 0,4 0,6 0,9 1,2 1,9 2,1 2,5 2,9 3,9 5,4 5,7 6,1 8,5 7,5 5,1
1,8 0,3 0,6 0,8 1,0 1,5 1,7 2,1 2,4 3,4 4,5 5,8 5,4 4,8 4,1 3,9
1,5 0,3 0,4 0,6 0,8 1,2 1,4 1,8 2,2 3,2 3,8 4,4 4,6 4,4 3,5 2,7
1,1 0,2 0,3 0,5 0,6 0,9 1,0 1,3 1,7 2,8 3,6 3,4 3,4 2,9 3,3 2,0
Acceptable for 1.7m of Relative Vertical Motion
Acceptable for 2.5m of Relative Vertical Motion
Acceptable for 3.5m of Relative Vertical Motion
Not Acceptable
28
SIMULATIONS
• Real time simulation
• Vessel crew
• Operational experience
• Crane and Moored FPU simulation
• Crane Controls as per vessel
• Tugger functionality as per vessel
DP System
AGENDA
/ INTRODUCTION
/ BACKGROUND
/ PROJECT EXECUTION
/ PCM INSTALLATION
/ MPP UMBILICAL INSTALLATION
/ QUESTIONS
32
Handling operations
UMBILICAL OPERATIONS
Topside Endloadout fromhandoverlocation
Transpoolingproduct loading intounderdeck carousel
SUT lift fromhandoverlocation
SUT landed onseafastening.Product stored inunderdeckcarousel
33
The MPP umbilical is to be installed betweenthe MPP location and FPU Alima.
Main umbilical data:Length: 6260mOD: 230.5mmWeight: 101.1kg/mMBR: 6.7m (load controlled)MBR: 4.8m (discplacement controlled)
Introduction
MPP UMBILICAL INSTALLATION
35
MOHO NORD MPI PROJECTOverview
Total split Project Overall SURF SOW
SOW tailored to a Mid Size Deep Water ConstructionVessel such as Normand Vision
Optimization of the execution plan (Transport &Installation in one phase)
Very competitive pricing of relevant SOW
Adding to our strong and successful track record inSURF projects
Systematic and meticulous approach to new countriesentry
Safe, on time, on budget project execution
Sucessful for Total and Ocean Installer
SAME CAN BE DONE FOR DEEP WATER SOW’s IN EGYPT