Redevelopment of Jama Masjid Precinct
Transcript of Redevelopment of Jama Masjid Precinct
Project Detail: The Jama Masjid Redevelopment plan includes proposal for
redevelopment of the peripheral roads and the precinct within it. The Plan of precinct covers an area of around 12.7 Hectares around the Jama Masjid, and includes the peripheral streets of about 3kms, starting from Subhash Marg to back of Jama Masjid till Subhash Marg at Parade Ground car parking.
Issues Identified: Spatial organisation, Commercial activities, Circulation, Facilities for the worshippers of Jama Masjid, Present infrastructure utilities, Civic amenities
Redevelopment of Jama Masjid Precinct
Project Aim: Identifiable urban form for the
Precinct Contemporary environment befitting
the heritage of this Precinct Open up a visual and physical link to
the Red Fort Create democratic multi use civic
space and streetscapes Development of a new physical plan,
incorporating modifications in: Land use Built fabric Movement networks &
parking Urban infrastructure
services Rationalization of spaces
for commercial and other uses
Plan showing the precinct. 1850 AD
Redevelopment of Jama MasjidPrecinct
Proposed Master Plan as submitted by the consultant Shri Pradeep Sachdeva
Meena Bazar
Area of Intervention
Satellite Image of the Precinct
21st Century
Issues
Commercial activity spilling on public right of way
Visual corridor blocked by Meena Bazaar
Unregulated traffic and parkingInappropriately sited urban infrastructure
Present: Shahi entry to Jama Masjid
Proposed: Shahi entry to Jama Masjid
View of precinct from Minar Present
Proposed
Way Forward
Master Plan Approved
Master Plan Review and
Update
Approval of Revised
Master Plan
Detailed Design of Individual
Components
Operations and Maintenance
INPUTS FROM USERS, RESIDENT COMMUNITIES, CITY AGENCIES, UTILITY PROVIDERS, EXPERTS AND OTHER
STAKEHOLDERS
Bidding Process for Construction
Preparation of Estimates and
Tender Documents/
DPRs
Appointment of Consultant for Detailed
Design
Setting-up of Co-
ordination/ Monitoring
Group
CURRENT STATUS OF PROJECT
Construction and Supervision
Preparation of Working Drawings
Finalization of Implementation Framework