Recommendations of the EAP - CESNET WEF Draft Scoping...Environmental Affairs North Region Dr LW...

33
EOH Coastal & Environmental Services Waaihoek Wind Energy Facility 124 Increases in the demand for electricity as the South African economy grows will increase the amount of fossil fuels required to generate this electricity. 11.5 Opinion of the EAP The proposed Waaihoek WEF is consistent with South African and KwaZulu-Natal renewable energy and climate change policies. Although a number of significant impacts are associated with the project, it is the professional opinion of CES and the specialists that: The vast majority of environmental impacts identified can be adequately mitigated to reduce the impacts to an acceptable level, provided mitigation measures recommended in this report are implemented and maintained throughout the life of the project. The implementation of mitigation measures and recommendations must be consistently monitored by an independent Environmental Control Officer (ECO) during construction. In particular, the implementation of measures suggested by the Bat specialist to mitigate the effect of the WEF, during both construction and operation, is particularly important. The recommendations made by all specialists and the EAP in the EMPr (Appendix F, Section 14.6) must be implemented The information in the report is sufficient to allow DEA to make an informed decision. It is the opinion of Coastal & Environmental Services (CES) that NO FATAL FLAWS are associated with the proposed Waaihoek WEF and associated infrastructure (including powerline). 11.6 Recommendations of the EAP It is the opinion of CES that the proposed development should be approved provided that appropriate mitigation measures are implemented and that the Environmental Management Programme (EMPr) is implemented, maintained and adapted to incorporate relevant legislation, standard requirements and audit reporting, throughout the life of the development. The mitigation measures for all impacts identified in the EIA are provided in the detailed assessment in Appendix D and have been incorporated into the EMPr. The EMPr must be implemented by the relevant parties during all phases of the WEF development of the project, viz. Planning & Design, Construction, Operational and Decommissioning phase. Inclusions, additions and adaptations of the EMPr, as well as all final plan drawings and maps must be submitted to DEA (Pretoria) for final approval.

Transcript of Recommendations of the EAP - CESNET WEF Draft Scoping...Environmental Affairs North Region Dr LW...

Page 1: Recommendations of the EAP - CESNET WEF Draft Scoping...Environmental Affairs North Region Dr LW Mngoma Department of Agriculture & Environment (DAE) KZN: Environmental Services District

EOH Coastal & Environmental Services Waaihoek Wind Energy Facility 124

• Increases in the demand for electricity as the South African economy grows will increase the amount of fossil fuels required to generate this electricity.

11.5 Opinion of the EAP The proposed Waaihoek WEF is consistent with South African and KwaZulu-Natal renewable energy and climate change policies. Although a number of significant impacts are associated with the project, it is the professional opinion of CES and the specialists that: • The vast majority of environmental impacts identified can be adequately mitigated to reduce

the impacts to an acceptable level, provided mitigation measures recommended in this report are implemented and maintained throughout the life of the project.

• The implementation of mitigation measures and recommendations must be consistently monitored by an independent Environmental Control Officer (ECO) during construction.

• In particular, the implementation of measures suggested by the Bat specialist to mitigate the effect of the WEF, during both construction and operation, is particularly important.

• The recommendations made by all specialists and the EAP in the EMPr (Appendix F, Section 14.6) must be implemented

• The information in the report is sufficient to allow DEA to make an informed decision. It is the opinion of Coastal & Environmental Services (CES) that NO FATAL FLAWS are associated with the proposed Waaihoek WEF and associated infrastructure (including powerline).

11.6 Recommendations of the EAP It is the opinion of CES that the proposed development should be approved provided that appropriate mitigation measures are implemented and that the Environmental Management Programme (EMPr) is implemented, maintained and adapted to incorporate relevant legislation, standard requirements and audit reporting, throughout the life of the development. The mitigation measures for all impacts identified in the EIA are provided in the detailed assessment in Appendix D and have been incorporated into the EMPr. The EMPr must be implemented by the relevant parties during all phases of the WEF development of the project, viz. Planning & Design, Construction, Operational and Decommissioning phase. Inclusions, additions and adaptations of the EMPr, as well as all final plan drawings and maps must be submitted to DEA (Pretoria) for final approval.

Page 2: Recommendations of the EAP - CESNET WEF Draft Scoping...Environmental Affairs North Region Dr LW Mngoma Department of Agriculture & Environment (DAE) KZN: Environmental Services District

EOH Coastal & Environmental Services Waaihoek Wind Energy Facility 125

12 INFORMATION REQUIRED BY COMPETENT AUTHORITY

In terms of Section 31(2) of the EIA Regulations (2010), an Environmental Impact Assessment Report must contain all the information necessary for the competent authority to consider the application and to reach a decision contemplated in regulation 35, and must include–

(r) Any specific information required by the competent authority;

12.1 General Site Information

Description of affected farm portions

Farm Name Farm number 21 digit SG Code Size (ha)

Goedgeloof 180/1 NOHT00000000007700000 353.72

180/RE NOHT00000000007700001 887.72

Waaihoek

173/9 NOHT00000000015200001 240.64

173/11 NOHT00000000015200002 23.34

173/3 NOHT00000000015200003 1443.85

173/4 NOHT00000000015200005 481.28

173/5 NOHT00000000015200007 224.28

173/6 NOHT00000000015200010 217.30

Groothoek

152/1 NOHT00000000015200013 265.52

152/3 NOHT00000000017300006 346.69

152/2 NOHT00000000017300009 579.33

152/5 NOHT00000000017300011 463.07

152/7 NOHT00000000017700003 463.07

152/10 NOHT00000000017700006 579.33

152/13 NOHT00000000018000000 347.31

Goedehoop 177/3 NOHT00000000018000001 1087.80

177/6 NOHT00000000018200001 214.09

Weltevreden 182/1 NOHT00000000018200002 1001.90

182/2 NOHT00000001706800001 457.70

Wijdgelegen

17068/1 NOHT00000001706800002 1100.00

17068/2 NOHT00000001706800003 808.82

17068/5 NOHT00000001706800004 386.11

17068/3 (RE) NOHT00000001706800005 422.71

17068/4 NOHT00000001706900009 428.27

Paardepoort 77/RE NOHT00000000007700000 1001.80

77/1 NOHT00000000007700001 1072.22

Bloedrivier 17069/9 NOHT00000001706900009 455.2

Page 3: Recommendations of the EAP - CESNET WEF Draft Scoping...Environmental Affairs North Region Dr LW Mngoma Department of Agriculture & Environment (DAE) KZN: Environmental Services District

EOH Coastal & Environmental Services Waaihoek Wind Energy Facility 126

Location of the Waaihoek Wind Energy Facility

Photographs of the site

Page 4: Recommendations of the EAP - CESNET WEF Draft Scoping...Environmental Affairs North Region Dr LW Mngoma Department of Agriculture & Environment (DAE) KZN: Environmental Services District

EOH Coastal & Environmental Services Waaihoek Wind Energy Facility 127

Turbine design specifications

Nacelle height/Hub height Max. 140m

Blade Diameter Max. 140m

Foundation dimensions Max. 20m x 20m x 5m

Laydown area dimensions 10 000m2

Generation Capacity Max. 4 MW each

Onsite measured wind parameters

This information is considered, by the developer, to be confidential because of its commercial sensitivity. The preferred site was chosen based on an in-house study on the wind resource in the broader area. The findings of this study were supported by historic data from a local weather station. Together this research provided a comprehensive macro wind model of the area, which clearly illustrated the preferred site as an optimal site for a wind farm. A met mast which was subsequently installed on site has confirmed the expected wind resource. In addition to the wind resource, other key factors which indicated that the site is potentially suitable for a wind farm included but were not limited to proximity to and availability of Eskom grid, site access and constructability, and potential environmental and social sensitivities.

Generation capacity of the facility at delivery point

Delivery point 88kV/275kV bay at Bloedrivier Substation

Eskom Bloedrivier Substation 140 MW

Page 5: Recommendations of the EAP - CESNET WEF Draft Scoping...Environmental Affairs North Region Dr LW Mngoma Department of Agriculture & Environment (DAE) KZN: Environmental Services District

EOH Coastal & Environmental Services Waaihoek Wind Energy Facility 128

13 REFERENCES Amajuba District Municipality Integrated Development Plan (IDP). Amajuba District Municipality Spatial Development Frameworks (SDF). Aviation Act (No. 74 of 1962): 13th Amendment of the Civil Aviation Regulations 1997. Branch, B., 2001. A Photographic Guide to: Snakes and other reptiles of Southern Africa. Random House Struik, South Africa. Breen, C.M. and Begg, G.W., (1989). Conservation status of southern African Wetlands. In: Biotic diversity in Southern Africa; Concepts and conservation, ed BJ Huntley. Oxford University Press, Cape Town. Carruthers, V. & du Preez, L., 2011. Frogs and Frogging in South Africa. Random House Struik, South Africa. Conservation of Agricultural Resources Act (No. 43 of 1983). Constitution Act (No. 108 0f 1996). EKZNW (2010) Terrestrial Systematic Conservation Plan: Minimum Selection Surface (MINSET), unpublished GIS Coverage (tscp_minset_dist_2010_wll.zip), Biodiversity Conservation Planning Division, Ezemvelo KZN Wildlife, P.O. Box 13053, Cascades, Pietermaritzburg, 3702. Electrical Regulation Act (No. 4 of 2006). Emadlangeni Local Municipality Integrated Development Plan (IDP). Emadlangeni Local Municipality Spatial Development Frameworks (SDF). IUCN, (1980). World Conservation strategy: Living resource conservation for sustainable development, International Union for the Conservation of Nature and Natural Resources. KwaZulu-Natal Department of Economic Development (2007) Feasibility of a Renewable/Alternate Energy Cluster in KwaZulu-Natal, LINDON, Umbogintwini. KwaZulu-Natal Department of Economic Development (2007) Overview and Analysis of Alternative and Renewable Energy Sources as Applicable to KwaZulu-Natal: Report II: Renewable Resources, best applicable technology and policy considerations for KZN, Nkadlane, La Lucia. KwaZulu-Natal Heritage Act (No. 4 of 2008). KwaZulu-Natal Planning and Development Act (No. 6 of 2008). Mineral and Petroleum Resources Development Act (No. 28 of 2002). Mucina, L. & Rutherford, M.C. (eds) 2006. The vegetation of South Africa, Lesotho and Swaziland. Strelitzia 19. South African National Biodiversity Institute, Pretoria. National Environmental Management Act (No. 107 of 1998). National Environmental Management: Air Quality Act (No. 39 of 2004). National Environmental Management: Biodiversity Act (No. 10 of 2004).

Page 6: Recommendations of the EAP - CESNET WEF Draft Scoping...Environmental Affairs North Region Dr LW Mngoma Department of Agriculture & Environment (DAE) KZN: Environmental Services District

EOH Coastal & Environmental Services Waaihoek Wind Energy Facility 129

National Environmental Management: Protected Areas Act (No. 57 of 2003) National Environmental Management: Waste Management Act (No. 59 of 2008). National Forest Act (No. 48 of 1998) National Heritage Resource Act (No. 25 of 1999). National Road Traffic Act (No. 93 of 1996) National Veld and Forest Fire Act (No. 101 of 1998) National Water Act (No. 36 of 1998). Occupational Health and Safety Act (No. 85 of 1993). SANBI (2009). Further Development of a Proposed National Wetland Classification System for South Africa. Primary Project Report. Prepared by the Freshwater Consulting Group (FCG) for the South African National Biodiversity Institute (SANBI). Stuart, C. & Stuart, T., 2007. Field Guide to Mammals of Southern Africa. Random House Struik, South Africa. Subdivision of Agricultural Land Act (No. 70 of 1970).

Page 7: Recommendations of the EAP - CESNET WEF Draft Scoping...Environmental Affairs North Region Dr LW Mngoma Department of Agriculture & Environment (DAE) KZN: Environmental Services District

Coastal & Environmental Services Waaihoek Wind Energy Facility 130

14 APPENDICES

14.1 Appendix A: Public Participation Documents 14.1.1 Newspaper advert:

Advert from newspaper (Published on the 25th October 2013 in the Vryheid Herald and 18th October in the Natal Witness.

Proposed Waaihoek Wind Energy Facility

(Emadlangeni Local Municipality, Amajuba District Municipality, KwaZulu-Natal)

NOTICE OF ENVIRONMENTAL IMPACT ASSESSMENT

AND INVITATION TO REGISTER AS AN I&AP Notice is hereby given in terms of Regulation 54(2) published in Government Notice No. R543 under Chapter 5 of the National Environmental Management Act (No. 107 of 1998), of the intent to submit an Environmental Impact Assessment application to the National Department of Environmental Affairs (DEA). Proponent and Location: South Africa Mainstream Renewable Power Developments (Pty) ltd. is proposing to construct a Wind Energy Facility with a maximum capacity of 140 MW, to be developed approximately 8km east and south-east of Utrecht in the Emadlangeni Local Municipality, KwaZulu Natal Province. Project Activities: The proposed project will entail the construction and operation of up to 90 wind turbines each generating between 1.5 – 4 M.W of power. Two overhead powerline corridor alternatives are proposed to transmit the electricity from the WEF to the Eskom Bloedrivier substation. In addition, the option of utilising an abandoned 88kV powerline servitude to the south of the site is also being considered. Listed Activities: The proposed project is a listed activity in terms of GN R 545, activity (1): “The construction of facilities or infrastructure for the generation of electricity where the electricity output is 20 megawatts or more’” and GN R 545, activity (8) “The construction of facilities or infrastructure for the transmission and distribution of electricity with a capacity of 275 kilovolts or more, outside an urban area or industrial complex” which require a full Scoping and EIR. Other listed activities in terms of GN R 544 include activities (10), (11), (18); GN R 545 activity (15) and GN R546 activities (4) and (13). Coastal & Environmental Services has been commissioned by South Africa Mainstream Renewable Power Developments (Pty) ltd. to undertake the Environmental Impact Assessment. You are hereby invited to register as an Interested & Affected Party (I&AP). Please submit your name, contact information and any comments to the contact person below.

For more information, registration as an I&AP or submission of written comments contact by post, phone, fax or e-mail:

Contact details: Mr Roy de Kock, PO Box 8145, East London, 5210, Tel: 043 726 7809/8313, Fax: 043 726 8352, e-mail: [email protected]

Page 8: Recommendations of the EAP - CESNET WEF Draft Scoping...Environmental Affairs North Region Dr LW Mngoma Department of Agriculture & Environment (DAE) KZN: Environmental Services District

EOH Coastal & Environmental Services Waaihoek Wind Energy Facility 131

NATAL WITNESS

Page 9: Recommendations of the EAP - CESNET WEF Draft Scoping...Environmental Affairs North Region Dr LW Mngoma Department of Agriculture & Environment (DAE) KZN: Environmental Services District

EOH Coastal & Environmental Services Waaihoek Wind Energy Facility 132

VRYHEID HERALD

Page 10: Recommendations of the EAP - CESNET WEF Draft Scoping...Environmental Affairs North Region Dr LW Mngoma Department of Agriculture & Environment (DAE) KZN: Environmental Services District

EOH Coastal & Environmental Services Waaihoek Wind Energy Facility 133

14.1.2 On-site notice boards

Page 11: Recommendations of the EAP - CESNET WEF Draft Scoping...Environmental Affairs North Region Dr LW Mngoma Department of Agriculture & Environment (DAE) KZN: Environmental Services District

EOH Coastal & Environmental Services Waaihoek Wind Energy Facility 134

Page 12: Recommendations of the EAP - CESNET WEF Draft Scoping...Environmental Affairs North Region Dr LW Mngoma Department of Agriculture & Environment (DAE) KZN: Environmental Services District

EOH Coastal & Environmental Services Waaihoek Wind Energy Facility 135

Page 13: Recommendations of the EAP - CESNET WEF Draft Scoping...Environmental Affairs North Region Dr LW Mngoma Department of Agriculture & Environment (DAE) KZN: Environmental Services District

EOH Coastal & Environmental Services Waaihoek Wind Energy Facility 136

Page 14: Recommendations of the EAP - CESNET WEF Draft Scoping...Environmental Affairs North Region Dr LW Mngoma Department of Agriculture & Environment (DAE) KZN: Environmental Services District

EOH Coastal & Environmental Services Waaihoek Wind Energy Facility 137

14.2 Appendix B: Interested and Affected Parties Database

STAKEHOLDERS

Stakeholder Contact Person

SANRAL Ms Nanna Gouws

Department of Agriculture, Forestry & Fisheries: Land Use & Soil Management Ms Anneliza Collett

Eskom: Renewable Energy Mr Kevin Leask

Eskom Ms Tshililo Nekhalali

Eskom: Land & Rights Section Ms Michelle Nicol

Department of Water Affairs Ms Zethu Makwabasa

Department of Energy Ms Mokgadi Mathekgana

Department of Environmental Affairs: General Enquiries Mr Albi Modise

Department of Environmental Affairs: Project Enquiries Ms Mmatlala Rabothata

Department of Agriculture & Environment (DAE) KZN: Senior Manager Environmental Affairs North Region Dr LW Mngoma

Department of Agriculture & Environment (DAE) KZN: Environmental Services District Manager Mr Zama Mathenjwa

Department of Agriculture & Environment (DAE) KZN: Amajuba District Agriculture District Manager Mr John Nhleko

Department of Agriculture & Environment (DAE) KZN: HOD EIA Mr Poovey Moodley

Amajuba DM Manager Mr Linda Africa

Emadlangeni LM Manager Ms GP Ntshangase

Emadlangeni Technical Services Mr Khumbulani Gwala

Emadlangeni Ward 1 councillor Cllr V. Ndlovu

Emadlangeni Ward 3 councillor Cllr B.M Phenyane

Renewable energy forum in KZN: Chairperson Ms Abigail Knox

Telkom Mr Raymond Couch

Sentech Ms Alishea Viljoen

Vodacom Mr Andre Barnard

Civil Aviation Authority Ms Lizelle Stroh

Air Traffic and Navigation Services (ATNS): Vryheid and Newcastle airports Mr Dylan Fryer

Ezemvelo KZN Wildlife Ms Dinesree Thambu

Ezemvelo KZN Wildlife Ms Felicity Elliott

Ezemvelo KZN Wildlife: Integrated Environmental Management Mr Andy Blackmore

Ezemvelo KZN Wildlife: District Conservation Officer, Underberg Region Mr Richard Schutte

Ezemvelo KZN Wildlife: Regional Ecologist Ms Sonja Kruger

Ezemvelo KZN Wildlife: Ecological Advice Division Mr Ian Rushworth

Ezemvelo KZN Wildlife: KZN Biodiversity Stewardship Programme Mr Greg Martindale

Ezemvelo KZN Wildlife: Avifaunal unit Mr Athol Marchant

Ezemvelo KZN Wildlife: District Ecologist Mr Petros Ngwenya

AMAFA / Heritage KwaZulu Natal Ms Annie van der Venter

AMAFA / Heritage KwaZulu Natal Mr James van Vuuren

Birdlife South Africa Mr Daniel Marnewick

Birdlife South Africa Dr Hanneline Smit-Robinson

Page 15: Recommendations of the EAP - CESNET WEF Draft Scoping...Environmental Affairs North Region Dr LW Mngoma Department of Agriculture & Environment (DAE) KZN: Environmental Services District

EOH Coastal & Environmental Services Waaihoek Wind Energy Facility 138

Birdlife South Africa: Birds and Renewable Energy Manager Ms Samantha Ralson

Endangered Wildlife Trust: CEO Ms Yolan Friedman

Endangered Wildlife Trust: Head of Conservation Science Dr Harriet Davies-Mostert

Endangered Wildlife Trust: African Crane Conservation Programme Manager Ms Kerryn Morrison

Endangered Wildlife Trust: African Crane Conservation Programme Field Officer Ms Glenn Ramke

Endangered Wildlife Trust: Senior Field Officer KZN Ms Tanya Smith

Endangered Wildlife Trust: Wildlife & Energy Programme Mr Lourens Leeuwner

WESSA KZN Region Ms Jenny Duvenage

WESSA KZN Region: Conservation Project Manager Mr Chris Galliers

WESSA KZN Region: Conservation Director Mr Garth Barnes

WWF: Enkangala Grasslands Project South Africa Mr Angus Burns

The Bat Interest Group of KwaZulu-Natal Ms Wendy White

Utrecht Farmers Association Ms Michelle van Staden

Ingogo Farmers Association Mr Jan Smit

Groenvlei Farmers Association Mr Christoff Joubert

Dejagersdrift Farmers Association Mrs Patricia Strauss

Vryheid Farmers Association Ms Lurien Jacobsz

Battlefields Route Association KZN Mr Dave Sutclifft

LANDOWNERS

Farm Number/Portion

Farm

Contact Person Name

180/1 Goedgeloof Mr Charles Johan de Villiers

180/RE Goedgeloof

Mr Petrus Stephanus Fourie 173/9 Waaihoek

173/11 Waaihoek

173/3 Waaihoek

Waaihoek Community Trust 173/4 Waaihoek

173/5 Waaihoek

173/6 Waaihoek Mr Job Dube

152/1 Groothoek Mr Greyling

152/3 Groothoek

152/2 Groothoek

152/5 Groothoek

152/7 Groothoek

152/10 Groothoek

152/13 Groothoek

177/3 Goede Hoop Ms Marina Theron (Goedehoop Number 177 Farming)

177/6 Goede Hoop Mr Craig de Oliviera (Counterpoint Trading 402 BK)

182/2 Weltevreden Mr Koos Uys (Jurust EDMS BPK Pty Ltd.)

182/1 Weltevreden

17068/1 Wijdgelegen

Mr Karel Landman (Fanie Landman Family Trust) 17068/2 Wijdgelegen

17068/5 Wijdgelegen

17068/3 Wijdgelegen Mr David Stock; Mr Kobus vd Bank (Knights Farm Pty Ltd)

Page 16: Recommendations of the EAP - CESNET WEF Draft Scoping...Environmental Affairs North Region Dr LW Mngoma Department of Agriculture & Environment (DAE) KZN: Environmental Services District

EOH Coastal & Environmental Services Waaihoek Wind Energy Facility 139

17068/4 Wijdgelegen Mr Lafras Uys (Jutein EDMS BPK)

77/RE Paardepoort Mr Inus Davel (Davelhoek Trust)

77/1 Paardepoort

17069/9 Bloedrivier Mr Robert Stannard

ADJACENT LANDOWNERS

Farm Number/Portion

Farm

Contact Person Name

17064 Stuurmanskraal Mr Inus Davel (Davelshoek Trust)

160/3 Twijfelfontein Mr Graystock Rudolf Naude

17071/4 Tigerfontein

17069/3 Bloedrivier

Mr Robert Stannard 17069/2 Bloedrivier

17069/4 Bloedrivier

17069/10 Bloedrivier

78/2 Blaauwstroom

Blaauwstroom Trust 78/3 Blaauwstroom

159/1 Vryheid

107/2 Vergenoegd Mr Johannes Davel

107/3 Vergenoegd

122/RE Weltevreden Ms Susanna Margaretha Hunter

122/2 Weltevreden Government of South Africa

123/7 Holdkrans

152/12 Groothoek Mr Hennie Boshoff (LAM Boerdery Trust)

173/3 Waaihoek

Waaihoek Community Trust 173/4 Waaihoek

173/5 Waaihoek

173/12 Waaihoek

173/13 Waaihoek Mr Job Dube

160/1 Twijfelfontein Mr Greyling

160/2 Twijfelfontein

17274/RE Gumtree Grove

122/1 Weltevreden

Mr Willem Adriaan Human 177/RE Goede Hoop

177/1 Goede Hoop

177/2 Goede Hoop Mr Moses Mahlinza

177/7 Goede Hoop

177/5 Goede Hoop Mr Craig de Oliviera (Counterpoint Trading 402 BK)

177/8 Goede Hoop Mr William Peter Fogarty

180/2 Goedeloof Mr Nhlanhla Nhleko (Masibambani Communal Land)

150/RE Spartelspruit Mr Koot Smit (Spartelspruit Trust)

182/RE Weltevreden Mr Koos Uys (Jurust EDMS BPK Pty Ltd)

424/1 Gumstreespruit Mr Jan Harm Steenkamp

177/4 Goede Hoop

Mr Andries de Villiers 434 Rusthof

152/6 Groothoek

435/RE Oldeani Mr Dieter Louis Muhl

Page 17: Recommendations of the EAP - CESNET WEF Draft Scoping...Environmental Affairs North Region Dr LW Mngoma Department of Agriculture & Environment (DAE) KZN: Environmental Services District

EOH Coastal & Environmental Services Waaihoek Wind Energy Facility 140

SURROUNDING LANDOWNERS

Farm Number/Portion

Farm

Contact Person Name

83/4 Vlakplaats

Mr Andries De Villiers

83/6 Vlakplaats

124/11 Klipspruit

152/4 Groothoek

152/6 Groothoek

83/2 Vlakplaats Ms Annie Jacoba Mans

66/2 Grootvlei

Mr Lourens Greyling (Baltus Spruit Eiendomme Cc) 66/7 Grootvlei

83/5 Vlakplaats

83/9 Vlakplaats

123/2 Holdkrans

Blaauwstroom Trust

159/RE Vryheid

159/2 Vryheid

159/3 Vryheid

159/5 Vryheid

107/1 Vergenoegd

Mr Christoffel Boshoff Davel 107/4 Vergenoegd

107/7 Vergenoegd

107/8 Vergenoegd

61/2 Waterhoek Mr Cornelis Moll

152/9 Groothoek Ms Nelisiwe Elsie Dhlamini

104/5 Suikerhoek Mr Robert Tobias Oostehuizen (Gleimius Trading Cc)

104/6 Suikerhoek

150/1 Spartelspruit

Mr Gunther August Wolters Muhl 460

180/3 Goedeloof

180/4 Goedeloof

61/3 Waterhoek Ms Jacoba Alberta Johanna Taljard

124/6 Klipspruit Mr Jan Harm Steenkamp

53/4 Wydgelegen Mr Johannes Adam Wilken

107/5 Vergenoegd

Mr Johannes Davel 107/6 Vergenoegd

6/1 Hammar

6/2 Hammar

83/3 Vlakplaats

Mr Hennie Boshoff (Lam Boerdery Trust) 83/10 Vlakplaats

83/11 Vlakplaats

53/2 Wydgelegen Mr Willy Leeuw (Leeuw Mining & Exploration Pty Ltd)

66/RE Grootvlei Mr Moshaedi Hendry Motloung

124/8 Klipspruit

Mr Levy Mpheni Ngcobo (Brothers Property Holdings KZN CC) 124/9 Klipspruit

173/10 Waaihoek

Page 18: Recommendations of the EAP - CESNET WEF Draft Scoping...Environmental Affairs North Region Dr LW Mngoma Department of Agriculture & Environment (DAE) KZN: Environmental Services District

EOH Coastal & Environmental Services Waaihoek Wind Energy Facility 141

66/10 Grootvlei Mr Nicolaas Smuts

66/16 Grootvlei

124/12 Klipspruit Mr Pieter Breytenbach

86/1 Zoetmelksrivier Ms Senta Klingenberg

83/8 Vlakplaats Mr TL Mnguni (Siyanqobaazwelethu Community Trust)

124/RE Klipspruit Mr Thomas Frederick Klopper

61/1 Waterhoek Vidroforte Africa Pty Ltd

61/8 Waterhoek N&H Boerdery Trust

123/RE Holdkrans Mr Willem Adriaan Human

123/4 Holdkrans

78/1 Blaauwstroom Mr Petrus Jacobus Claassen (Winlake Trading 22 Pty Ltd)

123/1 Oudehoutdraai

17069/5 Mr Josef Johannes Benjamin Greyling

159/4 Vryheid Steftraco BK

160/3 Twijfelfontein Mr Graystock Rudolf Naude

17071/3 Tigerfontein

173/8 Waaihoek Mr Inus Davel (Davelshoek Trust)

173/14 Waaihoek Pinelands Stud Pty Ltd

180/5 Goedeloof

Mr Pieter Carel Hanekom

181/RE Lijnspruit

Mr Erasmus Jacobus Petrus Smit 181/4 Lijnspruit

181/8 Lijnspruit

17069/1 Bloedrivier

Mr Robert Stannard 17069/6 Bloedrivier

17069/7 Bloedrivier

17069/8 Bloedrivier

17071/RE Tigerfontein Mr Leonhard Daniel Malan

17071/1 Tigerfontein Ms Cornelia Albertha Johanna Hatting

17071/2 Tigerfontein

REGISTERED I&APs

Stakeholder Name

Endangered Wildlife Trust Mr Bradley Gibbons

Leads 2 Business Ms Bianca Torré

Ngcobo Bros. Property Holdings C.C Mr G Usher

Ngcobo Bros. Property Holdings C.C Mr LM Ngcobo

Independent Mrs AJ Mans

McCarthy Cruywagen Attorneys Mr Dennis McCarthy

Naudé Boerdery Mr GR Naudé

Richardson & Peplow Environmental Ms Kate Richardson

Page 19: Recommendations of the EAP - CESNET WEF Draft Scoping...Environmental Affairs North Region Dr LW Mngoma Department of Agriculture & Environment (DAE) KZN: Environmental Services District

Coastal & Environmental Services Waaihoek Wind Energy Facility 142

14.3 Appendix C: Public Participation Documents The following documentation is provided: Scoping and EIR notification, proof and correspondence for all IAPs (including neighbouring landowners) per phase of the EIA. Sequential correspondence sent and received throughout the EIA per Stakeholder, which include:

Ezemvelo

BirdlifeSA

Eskom

Dept. of Energy

WESSA

Emadlangeni Local Municipality

Amajuba District Municipality

Dept. of Agriculature

Dept of Mineral Resources

Dept of Water Affairs and Sanitation

Endangered Wildlife Trust

WWF

SANRAL

KZN DAE

ATNS

Civil Aviation Authority

BatsKZN

AMAFA

Sentech, Telkom, Vodocom See attached.

Page 20: Recommendations of the EAP - CESNET WEF Draft Scoping...Environmental Affairs North Region Dr LW Mngoma Department of Agriculture & Environment (DAE) KZN: Environmental Services District

EOH Coastal & Environmental Services Waaihoek Wind Energy Facility 143

14.4 Appendix D: Focus group meetings The information includes focus group meetings that were held during the Scoping and EIR phase of the EIA.

Page 21: Recommendations of the EAP - CESNET WEF Draft Scoping...Environmental Affairs North Region Dr LW Mngoma Department of Agriculture & Environment (DAE) KZN: Environmental Services District

EOH Coastal & Environmental Services Waaihoek Wind Energy Facility 144

Page 22: Recommendations of the EAP - CESNET WEF Draft Scoping...Environmental Affairs North Region Dr LW Mngoma Department of Agriculture & Environment (DAE) KZN: Environmental Services District

Coastal & Environmental Services Waaihoek Wind Energy Facility 145

14.5 Appendix E: Impact Assessment Tables Table 14-1. General Impacts Associated with the WEF

ISSUE DESCRIPTION OF IMPACT NATURE OF IMPACT

SPATIAL SCALE (EXTENT)

TEMPORAL SCALE (DURATION)

CERTAINTY SCALE (LIKELIHOOD)

SEVERITY / BENEFICIAL SCALE

SIGNIFICANCE PRE-MITIGATION

MITIGATION MEASURES SIGNIFICANCE POST-MITIGATION

PLANNING & DESIGN PHASE

GENERAL IMPACTS

Traffic & Transport

Inadequate planning for the transportation of turbine parts and specialist construction equipment to the site by long and/or slow moving vehicles could cause traffic congestion, especially if temporary road closures are required.

DIRECT Regional Short-term Possible Moderately Severe MODERATE • Project planning must include a plan for traffic control that will be implemented, especially during the construction phase of the development. Consultation with the local Road Traffic Unit in this regard should be done early in the planning phase. The necessary road traffic permits should be obtained for transporting parts, containers, materials and construction equipment to the site.

LOW

The integrity of existing highway infrastructure such as bridges and barriers may be compromised by the heavy vehicle traffic delivering components to the site.

DIRECT CUMULATIVE

Regional Short-term Possible Slight LOW • Careful planning of the routes taken by heavy vehicles must highlight areas of road that may need to be upgraded in order to accommodate these vehicles. Once identified, these areas must be upgraded if necessary.

LOW

Inappropriate planning for road construction can increase the risk of surface water run-off, loss of biodiversity, soil erosion, etc.

DIRECT CUMULATIVE

Localised Medium-term Possible Severe HIGH • It is recommended that strip access roads should be used to maintain ecosystem integrity as much as possible. Strip roads should not be tarred. Limit the number of strip roads on site to minimise their overall footprint.

LOW

Road modifications which may be necessary to allow for the delivery of components to site via heavy vehicles could have long lasting traffic benefits.

INDIRECT CUMULATIVE

Regional Long-term Probable Slightly beneficial LOW POSITIVE

• If roads are upgraded, this should improve the conditions for all users of the roads.

LOW POSITIVE

Storage of hazardous substances

Inappropriate planning for the storage of hazardous substances such as diesel, paint, pesticides, etc, tools and equipment used on site could lead to surface and ground water pollution e.g. due to oil leaks, spillage of diesel etc. In addition, these hazardous substances could be washed off into nearby drainage lines. The mixing of cement on site could result in ground water contamination from compounds in the cement. In addition, a large number of cement mixing stations on site could increase the presence of impermeable areas of hard standing which in turn could increase rates of run-off and thereby increasing the risk of localized flooding, soil erosion, silting, gullies, etc.

DIRECT CUMULATIVE

Localised/ Nearby river and

water systems

Short-term Possible Moderate MODERATE • All hazardous substances such as paints, diesel and cement must be stored in a bunded area with an impermeable surface beneath them.

• Cement mixing must be conducted at a single location which should be centrally located, where practical.

LOW

Environmental Legal and Policy

Compliance

Failure to adhere to existing policies and legal obligations could lead to the project conflicting with local, provincial and national policies, legislation etc. This could result in lack of institutional support for the project, overall project failure and undue disturbance to the natural

DIRECT CUMULATIVE

Municipal Long-term Possible Severe HIGH • Ensure that all relevant legislation and policy is consulted and further ensure that the project is compliant with such legislation and policy.

• These should include (but not restricted to): o Local and District Spatial Development

Frameworks

LOW

Page 23: Recommendations of the EAP - CESNET WEF Draft Scoping...Environmental Affairs North Region Dr LW Mngoma Department of Agriculture & Environment (DAE) KZN: Environmental Services District

EOH Coastal & Environmental Services Waaihoek Wind Energy Facility 146

environment. o KwaZulu-Natal Biodiversity Conservation Plan

o Local Municipal bylaws • In addition, planning for the construction and

operation of the proposed energy facility should consider available best practice guidelines.

Stormwater Management and Erosion

The introduction of roads and impermeable areas of hard standing could increase rates of run-off and therefore the risk of localised flooding.

INDIRECT Localised/ Nearby river and

water systems

Long-term Possible Severe HIGH • Structures must be located at least 32 m away from identified drainage lines.

• A Stormwater Management Plan must be designed and implemented to ensure maximum water seepage at the source of water flow.

• The plan must also include management mitigation measures for water pollution, waste water management and the management of surface erosion e.g. by considering the applicability of contouring, etc.

LOW

Inappropriate storm water management will lead to damage, pollution and potential flooding of the site.

DIRECT Study Area Medium-term Possible Severe HIGH • A stormwater management plan must be developed and implemented

LOW

Management of general waste

Inappropriate planning for management and disposal of waste e.g. storage disposal could result in surface and ground water contamination.

DIRECT INDIRECT

CUMULATIVE

Localised Long-term Possible Severe HIGH • Develop and implement a waste management plan for handling on site waste.

• Designate an appropriate area where waste can be stored before disposal.

LOW

Electromagnetic Interference

(EMI)

WEFs can cause television, radio and microwave interference by blocking and / or causing part of the signal to be delayed.

DIRECT Regional Long-term Probable Moderately Severe MODERATE • Accurate siting of wind turbines in the planning and design phase should reduce these effects.

• If complaints are received from surrounding landowners regarding this issue, the developer must investigate and mitigate these issues to the best of their abilities.

LOW

Vegetation Clearing

Risk of designing long and wide access roads that would require wide scale vegetation stripping on site thereby compromising local biodiversity.

DIRECT CUMULATIVE

Localised Long-term Possible Severe HIGH • It is recommended that internal roads should comprise of strip roads to maintain ecosystem integrity as much as possible.

• Strip roads should not be tarred.

LOW

Risk that digging the trenches for an underground connecting cables could adversely affect surface vegetation and damage soil structure.

DIRECT Study Area Medium-term Probable Severe HIGH • Route determination for the underground connecting cables should consider the shortest possible routes.

• The size of the underground trenches for the connecting cables must be limited to the minimum acceptable dimensions appropriate for laying down the cables.

MODERATE

Landscape and Visual

Design and siting of the wind turbines could result in an alteration of the landscape character and sense of place

DIRECT Localised Long-term Probable Severe HIGH • The facility should be designed to minimise visual intrusion.

HIGH

Shadow Flicker The movement of the turbine blades across the direction of sunlight causes a phenomenon called shadow flicker, which can result in health problems if people are regularly exposed to it.

DIRECT Localised Long-term Possible Severe HIGH • The layout of wind turbines should be designed in order to minimize the effects of shadow flicker on surrounding landowners.

• Recommendations made by the visual impact assessor with regard to the identification of landowners who may be within range of the shadow flicker caused by the turbines, should be implemented.

• If surrounding landowners complain of shadow flicker-related issues, these must be investigated and mitigated to the best of the developers’ ability.

LOW

Page 24: Recommendations of the EAP - CESNET WEF Draft Scoping...Environmental Affairs North Region Dr LW Mngoma Department of Agriculture & Environment (DAE) KZN: Environmental Services District

EOH Coastal & Environmental Services Waaihoek Wind Energy Facility 147

ISSUE DESCRIPTION OF IMPACT NATURE OF IMPACT

SPATIAL SCALE (EXTENT)

TEMPORAL SCALE (DURATION)

CERTAINTY SCALE (LIKELIHOOD)

SEVERITY / BENEFICIAL SCALE

SIGNIFICANCE PRE-MITIGATION

MITIGATION MEASURES SIGNIFICANCE POST-MITIGATION

CONSTRUCTION PHASE

GENERAL IMPACTS

Socio-economic During construction, the development could have a beneficial local economic effect, supporting companies manufacturing turbine parts and providing work for construction and haulage contractors, for example.

DIRECT INDIRECT

CUMULATIVE

Municipal Short-term Possible Slightly Beneficial LOW POSITIVE

• Local companies should be given the opportunity to tender for the provision of locally-sourced materials, labour, plant, transport, etc.

LOW POSITIVE

The construction phase will create temporary jobs for local communities. It will thereby have positive impacts by creating short term employment within the affected communities.

DIRECT CUMULATIVE

Study Area Short-term Probable Beneficial MODERATE POSITIVE

• No mitigation required MODERATE POSITIVE

Visual intrusion Visual disturbance of the landscape during construction will be caused by the construction activity, and the presence and use of very large machinery.

DIRECT Localised Short-term Probable Slight LOW • It is not practical to mitigate the visual intrusion of construction vehicles and construction equipment on site.

LOW

Nuisance dust Dust is likely to be a potential nuisance due to the construction activities.

DIRECT Localised Short-term Probable Moderately Severe LOW • Fugitive/nuisance dust could be reduced by implementing the following: · o Damping down of un-surfaced and un-

vegetated areas; o Retention of vegetation where possible;

o Excavations and other clearing activities

must only be done during agreed working times and permitting weather conditions to avoid drifting of sand and dust into neighbouring areas;

o A speed limit of 30km/h must not be exceeded on dirt roads;

• Any complaints or claims emanating from the lack of dust control should be attended to immediately by the Contractor.

LOW

Construction camp

Unnecessary disturbance of vegetation due to sprawl of campsite can cause loss of biodiversity.

DIRECT Localised Short-term Possible Moderately Severe MODERATE • The ECO must assist in the siting of structures and supervise any bush clearing (although this is not anticipated) for the construction camp. Construction camp should be fenced to avoid sprawl.

LOW

Vegetation clearing

Unnecessary disturbance of vegetation from construction of ancillary structures i.e. control building, toilet facilities, etc. can cause loss of biodiversity.

DIRECT Localised Short-term Possible Moderately Severe MODERATE • Vegetation clearing must be restricted to the identified sites for the construction camp, cement mixing areas, ancillary infrastructure lay down areas, underground power cable route, control cabin and other activities on site that have been identified as necessary for development of the project.

• There must be no unnecessary disturbance of natural vegetation. Where unavoidable, such disturbed areas must be rehabilitated.

LOW

Access roads Unnecessary disturbance of habitats during road construction could cause loss of biodiversity.

DIRECT Localised Short-term Possible Moderately Severe MODERATE • Construction vehicles and machinery should only access the site using existing tarred roads to minimise disturbance on the receiving environment.

LOW

Alien and invasive plants

Unnecessary disturbance of the areas within the site could increase the risk of spreading noxious weeds, invasive and alien plants.

INDIRECT CUMULATIVE

Localised Short-term Possible Severe HIGH • Alien plants should be removed from the site through appropriate methods e.g. hand pulling, chemical, cutting, etc. under supervision from the ECO.

• Disturbed areas must be rehabilitated.

MODERATE

Page 25: Recommendations of the EAP - CESNET WEF Draft Scoping...Environmental Affairs North Region Dr LW Mngoma Department of Agriculture & Environment (DAE) KZN: Environmental Services District

EOH Coastal & Environmental Services Waaihoek Wind Energy Facility 148

Fire Risk of runaway fires from cooking on the construction camp might lead to the burning of surrounding vegetation.

DIRECT Localised Short-term Possible Severe VERY HIGH • There should be no burning of construction waste or debris onsite.

MODERATE

Noise Adverse noise effects will occur during the construction of the development, e.g. from the movement of heavy goods vehicles and the use of heavy duty construction equipment for excavation of foundations, vegetation stripping, etc.

DIRECT Localised Short-term Probable Moderately Severe MODERATE • Machinery that causes noise must only be operated at appropriate times (during the day and at normal working hours).

LOW

Stormwater management

Sediment is likely to be created during construction. This could be washed off into the nearby drainage line e.g. during the excavation of foundations, the laying of access roads within the site, digging of cable runs and soil stripping and stockpiling to create foundations and temporary areas of hard-standing, such as the construction camp.

DIRECT CUMULATIVE

Localised Short-term Possible Moderately Severe MODERATE • The recommendations of the stormwater management plan must be implemented to avoid soil erosion and siltation of drainage line.

LOW

Degradation of drainage lines

from earthworks

Unplanned construction activities or earthworks that occur close to onsite drainage lines could cause adverse impacts such as soil erosion, siltation, and blockage of the drainage line.

DIRECT Localised Short-term Possible Severe HIGH • There must be no earthworks within 32 m of the drainage lines so as to avoid contamination of water sources.

LOW

Soil erosion Soil could wash out of bare slopes before natural regeneration has established.

DIRECT Study Area Short-term Possible Moderately Severe MODERATE • Vegetation must be retained where possible to avoid soil erosion.

• If slopes are cleared during construction, these must be rehabilitated as soon as possible to minimize soil erosion losses.

LOW

Management of general waste

Littering by construction workers could cause surface and ground water pollution.

INDIRECT CUMULATIVE

Study Area Long-term Possible Moderately Severe MODERATE • Littering must be avoided and litter bins must be made available at various strategic points on site. Refuse from the construction site must be collected on a regular basis and deposited at an appropriate landfill.

LOW

Hazardous substances

Onsite maintenance of construction vehicles/machinery and equipment could result in oil, diesel and other hazardous chemicals contaminating surface and ground water. Surface and ground water pollution could arise from the spillage or leaking of diesel, lubricants and cement during construction activities.

DIRECT CUMULATIVE

Study Area Long-term Possible Moderately Severe MODERATE • The storage of fuels and hazardous materials must be located away from sensitive water resources.

• All hazardous substances (e.g. diesel, oil drums, etc.) must be stored in a bunded area.

• The recommendations of the stormwater management plan must be implemented during construction.

LOW

Management of construction

waste

Waste from construction activities e.g. excess concrete and cement mixture, empty paint containers, oil containers, etc, could cause pollution of ground and surface water when they come into contact with run-off water.

DIRECT CUMULATIVE

Study Area Short-term Possible Moderately Severe MODERATE • An environmental management programme (EMPr) incorporating waste management issues during the construction phase of the project must be developed and implemented.

• All excess waste must be disposed of at an appropriately licensed landfill site.

• All construction materials must be stored in a central and secure location with controlled access with an appropriate impermeable surface.

• The recommendations of the Stormwater Management Plan must be implemented to mitigate the impacts of run-off water on pollution.

LOW

Page 26: Recommendations of the EAP - CESNET WEF Draft Scoping...Environmental Affairs North Region Dr LW Mngoma Department of Agriculture & Environment (DAE) KZN: Environmental Services District

EOH Coastal & Environmental Services Waaihoek Wind Energy Facility 149

ISSUE DESCRIPTION OF IMPACT NATURE OF IMPACT

SPATIAL SCALE (EXTENT)

TEMPORAL SCALE (DURATION)

CERTAINTY SCALE (LIKELIHOOD)

SEVERITY / BENEFICIAL SCALE

SIGNIFICANCE PRE-MITIGATION

MITIGATION MEASURES SIGNIFICANCE POST-MITIGATION

OPERATIONS PHASE

GENERAL IMPACTS

Ecology The maintenance of the WEF could cause disturbance to local wildlife, especially breeding birds.

INDIRECT Localised Short-term Probable Slight LOW • Any maintenance staff must remain on designated roads and paths within the site., where possible

• The unnecessary disturbance of existing bush/forest patches must be avoided.

LOW

Air quality Climate change

The electricity generated by the development will displace some of that produced by fossil fuel based forms of electricity generation. The scheme, over its lifetime, will therefore avoid the production of a significant amount of CO2, SO2 and NO2 that would otherwise be emitted to the atmosphere.

DIRECT CUMULATIVE

International Long-term Definite Highly Beneficial VERY HIGH POSITIVE

• Enhance this impact by promoting the use of renewable energy locally.

VERY HIGH POSITIVE

Lighting The facility may be lit at night during operation. This could have adverse impacts on the landscape character and sense of place due to long-term visibility of land.

DIRECT Localised Long-term Probable Severe HIGH • Night lighting impacts could be reduced by using shaded lighting and using lights at low levels.

LOW

Architecture of ancillary

infrastructure

Control buildings, toilet facilities and other ancillary infrastructure could cause negative visual intrusion if allowed to fall into disrepair and not maintained properly.

DIRECT Localised Long-term Probable Moderate MODERATE • All project structures and buildings visible to the public must be maintained.

LOW

Hazardous chemical storage

Inappropriate storage of chemical, herbicides, diesel and other hazardous substances on site could result in soil and water contamination and also pose a high accident danger risk.

DIRECT Localised Long-term Possible Severe HIGH • All hazardous substances must be stored in appropriately bunded locations.

MODERATE

Operating equipment

Noise could be generated by transformers from the process of power conversion. The operation of auxiliary equipment needed to cool the transformers, including cooling fans and oil pumps could also generate some noise.

DIRECT Localised Long-term Probable Moderately Severe MODERATE • Lower noise emission levels from inverters and transformers can be achieved by housing them in enclosed structures.

LOW

Increased stormwater run-

off

Failure to maintain the storm water system could increase the risk of surface water damage to the landscape and vegetation from increased rates of run-off and therefore the risk of localised flooding and increased sheet erosion downstream due to the presence of roads and impermeable areas of hard standing.

DIRECT CUMULATIVE

Localised Long-term Possible Moderately Severe MODERATE • Recommendations of the Stormwater Management Plan must be implemented.

LOW

Waste management

There could be littering by maintenance workers and security personnel on site.

DIRECT Localised Medium-term Possible Moderately Severe MODERATE • A waste management plan incorporating recycling and waste minimisation must be implemented. Develop and implement a worker education plan for waste management in the work environment.

LOW

Page 27: Recommendations of the EAP - CESNET WEF Draft Scoping...Environmental Affairs North Region Dr LW Mngoma Department of Agriculture & Environment (DAE) KZN: Environmental Services District

EOH Coastal & Environmental Services Waaihoek Wind Energy Facility 150

ISSUE DESCRIPTION OF IMPACT NATURE OF IMPACT

SPATIAL SCALE (EXTENT)

TEMPORAL SCALE (DURATION)

CERTAINTY SCALE (LIKELIHOOD)

SEVERITY / BENEFICIAL SCALE

SIGNIFICANCE PRE-MITIGATION

MITIGATION MEASURES SIGNIFICANCE POST-MITIGATION

DECOMMISSIONING PHASE

GENERAL IMPACTS

Visual Intrusion Visual disturbance of the landscape during decommissioning will be caused by the presence and use of very large machinery.

DIRECT Localised Short-term Probable Slight LOW • It is not practical to mitigate the visual intrusion of decommissioning vehicles and decommissioning equipment on site.

LOW

Ecology Unnecessary disturbance of vegetation from the decommissioning of ancillary structures i.e. control building, toilet facilities, etc.

DIRECT Localised Short-term Probable Moderately Severe MODERATE • Deconstruction vehicles and machinery should make use of existing infrastructure such as roads as far as possible to minimise disturbance on the receiving environment.

LOW

Risk of spreading noxious weeds, invasive and alien plants due to the increased movement of human traffic and machinery during decommissioning.

INDIRECT CUMULATIVE

Localised Short-term Probable Moderately Severe HIGH • All bare land must be rehabilitated after decommissioning.

LOW

Noise sensitive receptors

Adverse noise effects could potentially occur during the decommissioning of the WEF, for example from the movement of heavy goods vehicles.

DIRECT Localised Short term Probable Moderately severe MODERATE • Machinery that causes noise must only be operated at appropriate times (during the day and at normal working hours).

LOW

Any noise-related impacts caused by the operation of the facility will cease to be of importance.

DIRECT Localised Long-term Definite Beneficial LOW POSITIVE

• No mitigation required LOW POSITIVE

Socio-economic impacts

During decommissioning, the development could have a beneficial local economic effect by providing temporary jobs for local communities.

INDIRECT Localised Short-term Definite Beneficial LOW POSITIVE

• No mitigation required LOW POSITIVE

Pollution Littering by construction workers could cause surface and ground water pollution.

DIRECT Study Area Short-term Possible Moderately Severe MODERATE • Littering must be avoided and litter bins should be made available at various strategic points on site. Refuse from the construction site should be collected on a regular basis and deposited at an appropriate landfill.

LOW

Onsite maintenance of construction vehicles/machinery and equipment could result in oil, diesel and other hazardous chemicals contaminating surface and ground water. Surface and ground water pollution could arise from the spillage or leaking of diesel, lubricants and cement during construction activities.

DIRECT CUMULATIVE

Study Area Short-term Possible Moderately Severe MODERATE • No storage of fuels and hazardous materials should be permitted near sensitive water resources. All hazardous substances (e.g. diesel, oil drums, etc.) to be stored in a bunded area.

LOW

Dust Dust is likely to be a potential nuisance due to the decommissioning activities.

DIRECT Localised Short-term Probable Slight LOW • Fugitive/nuisance dust could be implemented through the following: o Damping down of un-surfaced and un-

vegetated areas; o Retention of vegetation where possible;

Demolitions and other clearing activities must only be done during agreed working times and permitting weather conditions to avoid drifting of sand and dust into neighbouring areas;

o A speed limit of 30km/h must not be exceeded on dirt roads.

• Any complaints or claims emanating from the lack of dust control must be attended to immediately by the Contractor.

LOW

Traffic & Transport

A high number of heavy vehicle movements will occur during the decommissioning phase. This may have a detrimental effect on sensitive receptors, especially on existing vegetation.

DIRECT Localised Short-term Possible Moderately Severe MODERATE • Construction vehicles and machinery should make use of existing infrastructure such as roads as far as possible to minimise disturbance on the receiving environment. There must be no unnecessary disturbance of

LOW

Page 28: Recommendations of the EAP - CESNET WEF Draft Scoping...Environmental Affairs North Region Dr LW Mngoma Department of Agriculture & Environment (DAE) KZN: Environmental Services District

EOH Coastal & Environmental Services Waaihoek Wind Energy Facility 151

extant vegetation.

Soil erosion After the removal of all wind turbine related structures, the disturbed soils could become exposed, unstable and prone to erosion.

DIRECT Localised Short-term Possible Moderately Severe MODERATE • After the removal of all wind turbine-related structures, the disturbed soils must be re-vegetated to avoid unnecessary soil erosion.

LOW

Land-use Land previously unavailable for certain types of land use will now be available for those uses.

DIRECT Localised Long-term Possible Moderately Positive LOW POSITIVE • No mitigation necessary LOW POSITIVE

Table 14-2. Specialist Impacts Associated with the WEF

ISSUE DESCRIPTION OF IMPACT NATURE OF IMPACT

SPATIAL SCALE (EXTENT)

TEMPORAL SCALE (DURATION)

CERTAINTY SCALE (LIKELIHOOD)

SEVERITY / BENEFICIAL SCALE

SIGNIFICANCE PRE-MITIGATION

MITIGATION MEASURES SIGNIFICANCE POST-MITIGATION

PLANNING & DESIGN PHASE

AGRICULTURE & SOILS IMPACT ASSESSMENT

Loss of agricultural land

The loss of large amounts of agricultural land due to inadequate planning could have negative impacts on the agricultural potential of the farms involved in the development.

DIRECT CUMULATIVE

Localised Long-term Possible Severe HIGH The specialist report has informed the layout to ensure that loss of agricultural land is kept to a minimum

LOW

ECOLOGICAL IMPACT ASSESSMENT

Loss of indigenous vegetation: WEF

The construction of turbine platforms could result in the clearance of approximately 11ha of indigenous vegetation, resulting in permanent loss

DIRECT Localised Long-term Definite Moderate MODERATE During the Planning and Design Phase, the appointed ECO must survey the site, especially during spring and summer, in order to locate protected geophytic plant species that may need to be transplanted to an appropriate nursery, where deemed viable

Ensure during the Planning and Design phase that turbine platforms and access roads located in sensitive areas or the sensitivity buffers, are either moved to a more appropriate location or otherwise be omitted from the layout

The construction of access road 1 is not a preferred route and should be considered with caution

Route access roads to specifically avoid sensitive areas, as much as possible

LOW

Turbine construction within the Northern Interior Macro-Ecological Corridor, will result in the loss of indigenous vegetation forming part of the corridor, which could consequently deter faunal species from utilising it for the intended purpose of the corridor

DIRECT Project Level Short-term Unsure Moderate MODERATE MODERATE

The construction of access road 1 within the Northern Interior Macro-Ecological Corridor, will result in the loss of indigenous vegetation forming part of the corridor, which could consequently deter faunal species from utilising it for the intended purpose of the corridor

DIRECT Project Level Short-term Unsure Moderate MODERATE LOW

The construction of access roads to turbines will result in the clearance of approximately 24ha, resulting in permanent loss

DIRECT Project Level Long-term Definite Moderate MODERATE LOW

Disturbance of sensitive areas:

WEF

Turbines located in areas identified as sensitive (including buffer zones) could result in habitat disturbance/loss of various niche specific species, with specific reference to rocky outcrops for lizards and indigenous forest patches for small mammals

DIRECT Localised Medium-term Possible Severe HIGH LOW

Routing access roads through sensitive areas or the demarcated sensitivity buffers could result in habitat disturbance/loss of various

DIRECT Localised Medium-term Possible Severe HIGH LOW

Page 29: Recommendations of the EAP - CESNET WEF Draft Scoping...Environmental Affairs North Region Dr LW Mngoma Department of Agriculture & Environment (DAE) KZN: Environmental Services District

EOH Coastal & Environmental Services Waaihoek Wind Energy Facility 152

niche specific species, with specific reference to rocky outcrops for lizards and indigenous forest patches for small mammals.

Loss of indigenous vegetation: Powerline

Pylon installation for above-ground powerlines could result in the permanent loss of indigenous vegetation

DIRECT Localised Long-term Definite Moderate MODERATE Ensure during the Planning and Design Phase that the powerline route is placed in previously impacted areas, where possible

Powerline alternative 1 an alternative route is proposed

LOW

Powerline pylons located in areas identified as sensitive (including buffer zones) could result in habitat disturbance/ loss of various niche specific species, with specific reference to rocky outcrops for lizards and indigenous forest patches for small mammals

DIRECT Localised Medium-term Possible Severe HIGH Ensure during the Planning and Design phase that pylons are placed in low sensitivity areas or previously impacted areas

Ensure during the Planning and Design Phase that pylons located in sensitive areas or the sensitivity buffers, are either moved to a more appropriate location or otherwise be omitted from the layout

LOW

Construction within a National

Freshwater Ecosystem Priority

Area (NFEPA)

The route proposed for powerline route 2 travels through a NFEPA wetland, could result in permanent loss of wetland habitat which provide a niche specific habitat to various amphibian species (Refer to Wetland Impact Assessment)

INDIRECT Localised Long-term Probable Severe HIGH This is not a preferred route and should be considered with caution

LOW

Loss of indigenous vegetation: Additional

infrastructure

The layout design of the contractors site office underground powerlines and access roads into the WEF could result in the permanent loss of at least 1 ha of indigenous vegetation

DIRECT Localised Short-term Possible Moderate MODERATE Ensure during the Planning and Design Phase that the contractors office and access roads are placed in previously impacted areas, where possible

The routing of access roads should make use of existing roads as much as possible

Prior to finalising the route of the access road, the appointed ECO must ensure that where possible the route follows existing roads and tracks and avoid sensitive areas. The ECO should recommend a route change, if deemed necessary

LOW

Construction within a National

Freshwater Ecosystem Priority

Area (NFEPA): Additional

infrastructure

The construction of access route 3 through a wetland defined as a NFEPA will result in the habitat destruction of amphibian populations

DIRECT Localised Permanent Definite Severe HIGH This is not a preferred route and should be considered with caution

LOW

Construction of an access road through a

protected area

The construction of access route 3 through a protected area

CUMULATIVE Localised Permanent Possible Moderate MODERATE This is not a preferred route and should be considered with caution

LOW

WETLAND IMPACT ASSESSMENT

Road upgrade crossing a

watercourse

Disturbance of aquatic habitats due to the position and installation of turbine platforms and associated infrastructure such as access roads and power lines.

DIRECT Regional Long-term Possible Severe HIGH The proposed layout should keep the number of watercourse crossings of roads to a minimum.

LOW

Turbine construction

within the 100m wetland buffer

Disturbance of aquatic habitats due to the position and installation of turbine platforms and associated infrastructure within the 100m No-go Zone for wetlands. The current layout places turbines 7, 74 and 77

DIRECT Regional Long-term Possible Severe HIGH It is recommended that these turbines be relocated outside the requisite buffers.

LOW

Page 30: Recommendations of the EAP - CESNET WEF Draft Scoping...Environmental Affairs North Region Dr LW Mngoma Department of Agriculture & Environment (DAE) KZN: Environmental Services District

EOH Coastal & Environmental Services Waaihoek Wind Energy Facility 153

within the 100m No-go buffer for wetlands. This would have negative impacts on the integrity of the wetland system.

Turbine construction

within the 500m wetland buffer

Disturbance of aquatic habitats due to the position and installation of turbine platforms and associated infrastructure within the 500m buffer for wetlands. The current layout places 35 turbines within the 500m buffer for wetlands. Construction activities would have the potential to impact the hydrological functioning of the wetlands.

DIRECT CUMULATIVE

Regional Long-term Possible Severe HIGH It is recommended that these turbines have construction footprints aligned away from wetlands as far as possible. Construction on hillslopes will require management of runoff and sedimentation to reduce the impact on surrounding wetlands.

LOW

Loss of species of special concern due to poor layout planning and design of appropriate management plans to minimise impact.

DIRECT Project area Long-term Possible Severe HIGH LOW

Turbine construction

within the 50m watercourse

buffers

Loss of riparian vegetation due to construction within 50m of a watercourse.

DIRECT Project area Long-term Possible Severe HIGH It is recommended that these turbines have construction footprints aligned away from the watercourse to minimise erosion and sedimentation.

LOW

Powerline construction

within the wetland and watercourse

buffers

Inappropriate power cable and road routes may transect aquatic habitats, damaging vegetation and potentially leading to erosion.

DIRECT Project area Long-term Possible Severe HIGH Ecologically important and sensitive areas should be avoided, in addition: o Access roads and power cable routes must

deviate, avoid or circumvent around highly sensitive habitats.

o Long term access roads should incorporate the use of an eco-friendly specialised design to avoid issues of soil erosion.

MODERATE

Erosion due to removal of vegetation

The surrounding environment exhibits evidence of vulnerability to soil erosion, especially in the transitional section between the low lying areas and the high lying plateau. Construction and operation activities may result in soil destabilisation and contribute towards further significant soil erosion.

CUMULATIVE Regional Long-term Possible Severe HIGH A Stormwater Management Plan must be developed prior to the commencement of the construction phase. Turbine platforms and access road routes must be designed with significant soil stabilisation and stormwater retention measures.

Access road routes and powerline alternatives must be planned with high erosion potential in mind.

MODERATE

AVIFAUNAL IMPACT ASSESSMENT

Loss of priority avifaunal due to

incorrect placement of

turbines

The loss of avifaunal species due to placement of turbines in highly sensitive areas could have severe negative effects on the avifaunal population.

DIRECT CUMULATIVE

Localised Long-term Possible Severe HIGH The specialist report has informed the layout to ensure that loss of avifaunal is mitigated through the correct placement of turbines.

No turbines occur in highly sensitive areas

LOW

BAT IMPACT ASSESSMENT

Loss of bat species due to incorrect

placement of turbines

The loss of bats species due to placement of turbines in highly sensitive areas could have severe negative effects on the bat population.

DIRECT CUMULATIVE

Long-term Regional Probable Severe HIGH Turbines in high sensitivity areas must be removed from the final layout.

Turbines within the medium sensitivity areas must follow a curtailment schedule developed by the bat specialist.

MODERATE

PALEONTOLOGICAL IMPACT ASSESSMENT

Damaging of fossils due to

incorrect placement of

The damage of fossils due to placement of turbines in highly sensitive areas could have negative implications.

DIRECT CUMULATIVE

Localised Long-term Possible Severe HIGH The specialist report has informed the layout to ensure that damage to fossil rich sediments is mitigated through the correct placement of turbines.

LOW

Page 31: Recommendations of the EAP - CESNET WEF Draft Scoping...Environmental Affairs North Region Dr LW Mngoma Department of Agriculture & Environment (DAE) KZN: Environmental Services District

EOH Coastal & Environmental Services Waaihoek Wind Energy Facility 154

turbines No turbines occur in highly sensitive areas

HERITAGE IMPACT ASSESSMENT

Damaging of heritage artefacts

to incorrect placement of

turbines

The damage of heritage features / artefacts due to placement of turbines in highly sensitive areas could have negative implications.

DIRECT CUMULATIVE

Localised Long-term Possible Severe HIGH The specialist report has informed the layout to ensure that damage to heritage features / artefacts is mitigated through the correct placement of turbines.

No turbines occur in highly sensitive areas

LOW

SOCIO-ECONOMIC IMPACT ASSESSMENT

Inadequate social involvement

Inadequate communication throughout the WEF design and planning phase could have negative social and economic implications.

DIRECT CUMULATIVE

Localised Long-term Possible Severe HIGH The public participation process has been an on-going process designed to include, inform and educate individuals who may be impacted by the WEF development.

LOW

VISUAL IMPACT ASSESSMENT

Change in scenery in the WEF area

The landscape features will be altered by the WEF, this may negatively impact individual perceptions in term of sense of place.

DIRECT

Localised Long-term Possible Severe MODERATE No mitigation possible. MODERATE

TOURISM IMPACT ASSESSMENT

Ecotourism Ecotourism in the area may be negatively / positively impacted by the WEF development through the introduction of manmade features to the natural environment.

DIRECT CUMULATIVE

Localised Long-term Possible Moderate MODERATE All local tourism facilities must be made aware of the WEF through the public participation process in order to address any concerns raised by relevant stakeholders.

MODERATE (Can be both negative and

positive depending on the individual)

Heritage tourism The development of the WEF within close proximity of the battlefields memorial sites could negatively affect tourism related to these memorials.

DIRECT Localised Long-term Possible Moderate MODERATE The Heritage Specialist must be consulted during the planning and design phase to ensure that appropriate buffers are set up around battlefield sites.

LOW

NOISE IMPACT ASSESSMENT

Noise generated by turbines close

to sensitive receptors

The noise generated by turbines can impact people living within 500m of an individual turbine.

DIRECT

Localised Long-term Possible Severe HIGH The specialist report has informed the layout to ensure that turbines do not occur within 500m of households.

No turbines occur in highly sensitive areas

LOW

ISSUE DESCRIPTION OF IMPACT NATURE OF

IMPACT SPATIAL SCALE

(EXTENT) TEMPORAL SCALE

(DURATION) CERTAINTY SCALE

(LIKELIHOOD) SEVERITY /

BENEFICIAL SCALE SIGNIFICANCE

PRE-MITIGATION MITIGATION MEASURES SIGNIFICANCE POST-

MITIGATION

CONSTRUCTION PHASE

AGRICULTURE & SOILS IMPACT ASSESSMENT

Management of hazardous chemicals

Soil contamination and a loss of fertile soils as a result of hazardous chemical spills.

DIRECT CUMULATIVE

Study area Long-term Probable Severe MODERATE Machinery must be properly maintained to keep oil leaks in check.

If a spill occurs on a permeable surface (e.g. Soil), a spill kit must be used to immediately reduce the potential spread of the spill.

If a spill occurs on an impermeable surface such as cement or concrete, the surface spill must be contained using oil absorbent materials.

Contaminated remediation materials must be carefully removed from the area of the spill so as to prevent further release of hazardous chemicals to the environment, and stored in adequate containers until appropriate disposal in a licenced landfill site.

LOW

Increased risk of fires from

construction activities

Potential loss of crops, grazing and livestock as a result of fires originating from the construction site.

INDIRECT Regional Long-term Probable Very Severe HIGH Ensure that all personnel are aware of the fire risk and the need to extinguish cigarettes before disposal, in appropriate waste disposal containers.

Smoking will only be allowed in demarcated

LOW

Page 32: Recommendations of the EAP - CESNET WEF Draft Scoping...Environmental Affairs North Region Dr LW Mngoma Department of Agriculture & Environment (DAE) KZN: Environmental Services District

EOH Coastal & Environmental Services Waaihoek Wind Energy Facility 155

areas with easy access to fire-fighting equipment.

Welding and other construction activities requiring open flames shall be done in a designated area containing fire-fighting equipment.

The risk of fire is highest in the late summer and autumn months, during high wind velocities and dry periods. To avoid and manage fire risk the following steps should be implemented: o Have on site fire-fighting equipment and

ensure that all personnel are educated how to use it and procedures to be followed in the event of a fire.

o Identify the relevant authorities and structures responsible for fighting fires in the area and shall liaise with them regarding procedures should a fire commence.

o Ensure that all the necessary telephone numbers etc. are posted at conspicuous and relevant locations in the event of an emergency.

No open fires shall be allowed on site for the purpose of cooking or warmth. Cooking fires must only be lit in designated cooking areas.

The contractor shall take all reasonable steps to prevent the accidental occurrence or spread of fire.

The contractor shall appoint a fire officer who shall be responsible for ensuring immediate and appropriate action in the event of a fire.

The contractor shall ensure that all site personnel are aware of the procedure to be followed in the event of a fire. The appointed fire officer shall notify the Fire and Emergency Services in the event of a fire and shall not delay doing so until such time as the fire is beyond his / her control.

The contractor shall ensure that there is basic fire-fighting equipment on site at all times. This equipment shall include fire extinguishers and beaters.

Any work that requires the use of fire may only take place within designated areas. Fire-fighting equipment shall be available in these areas.

The contractor shall ensure that the correct emergency call numbers for the nearest fire department and the local Farmers Association Fire Marshall are easily accessible at all times, and that in the event that a fire becomes unmanageable, these people are notified as a matter of urgency.

Soil rehabilitation management

Incorrect or insufficient rehabilitation of soil will result in a decrease of agricultural viability/potential especially in Highland Sourveld.

INDIRECT CUMULATIVE

Localised Medium-term May occur Moderate MODERATE Develop and implement a Rehabilitation and Monitoring Plan to monitor rehabilitated areas.

Ensure that topsoil does not get buried by aluminium rich subsoil in Highland Sourveld areas. Failure to comply will result in topsoil sterilisation.

LOW

Page 33: Recommendations of the EAP - CESNET WEF Draft Scoping...Environmental Affairs North Region Dr LW Mngoma Department of Agriculture & Environment (DAE) KZN: Environmental Services District

EOH Coastal & Environmental Services Waaihoek Wind Energy Facility 156

Implement measures such as wind-breaks, swales and watering to aid the initial grown of primary vegetation.

Fertile topsoil must not be stockpiled for periods exceeding 12 months or exceeding 2m in height.

Topsoil may be supplemented with an indigenous seed mix.

ECOLOGICAL IMPACT ASSESSMENT

Loss of vegetation during

construction

The activity during construction of turbine platforms, internal turbine and WEF access roads and underground powerlines could result in the unnecessary loss of habitat as a result of uncontrolled vegetation clearing, equivalent to around 35ha of indigenous grassland, resulting in permanent loss

DIRECT Localised Permanent Definite Moderately Severe MODERATE During the Construction Phase, construction vehicles must make use of existing farm tracks and once constructed, access roads

During the Construction Phase, ensure that roads and turbines are developed in areas of low sensitivity

During the Construction Phase, ensure that roads on slopes incorporate a storm water diversion

During the Construction Phase, where possible, reserve and store natural vegetation cover for re-vegetation post construction

During the Construction Phase, the ECO must ensure the protected plant populations identified during the Planning and Design Phase are relocated to appropriate locations

In the unlikely event that a protected tree species needs to be removed during construction, a permit to do so must be attained from DAFF

Where possible construction should be limited to previously impacted areas

During the Construction Phase, development should where possible be avoided in sensitive areas that may increase the edge effect of the Northern Interior Macro-Ecological Corridor

LOW

Uncontrolled construction activity in the area, could lead to plant community degradation, resulting in the permanent loss of special habitats.

DIRECT Localised Long-term Possible Severe HIGH LOW

Loss of vegetation within a Macro-

Ecological Corridor

Turbine platforms and turbine access road construction within the Northern Interior Macro-Ecological Corridor, will result in the permanent loss of indigenous vegetation forming part of the corridor, which could consequently deter faunal species from utilising it for the intended purpose

CUMULATIVE

Localised Long-term Definite Moderate MODERATE LOW

The construction of WEF proposed access road, route 3 falls within the Northern Interior Macro-Ecological Corridor. If the route is considered, construction activities could result in the unnecessary loss of indigenous vegetation of an area which forms part of the corridor, which may lead to the narrowing of the Northern Interior ecological corridor which could consequently deter faunal species from utilising it for the intended purpose

CUMULATIVE Localised Long-term Definite Moderate MODERATE LOW

Powerline route 1 falls within the Northern Interior Macro-Ecological Corridor. Construction of this route will result in the permanent loss of indigenous vegetation of an area which forms part of the corridor, which may lead to the narrowing of the Northern Interior ecological corridor which could consequently deter faunal species from utilising it for the intended purpose

DIRECT Localised Long-term Definite Moderate MODERATE LOW

Loss of vegetation within a protected

area

Uncontrolled construction could result in the unnecessary loss and disturbance of vegetation in a protected areas

DIRECT CUMULATIVE

Localised Permanent Definite Severe HIGH MODERATE