Ray Holsheimer - Aurizon - Major occurrence Central Queensland
-
Upload
informa-australia -
Category
Business
-
view
326 -
download
11
description
Transcript of Ray Holsheimer - Aurizon - Major occurrence Central Queensland
Derailment : Epala – Ambrose Central Queensland Ray Holsheimer Principal Adviser Rail Safety (Derailment Prevention) Aurizon 30th April, 2014 Sydney Harbour Marriot
Introduction • At 12:11, 8th February 2013, a fully
loaded coal train (9F24) derails on the Epala – Ambrose section of the North Coast Line (NCL)/ Blackwater System
• 9F24 – 10,359t, 1,685m, TDO
• 36 Wagons and 2 Locomotives derailed • 1.2km track and overhead damage • 150 services delayed or cancelled
2 + 2 DP 4000/4100 49 x 106t “VC/VS” Wagon Pairs
Introduction (cont.)
• Investigators POV
• What happened?
• Why did it happen?
• Share learnings • Derailment Investigation
• Immediate and Basic Causation
• Preventing a Recurrence
North Coast Line (NCL) and Blackwater System
(Including Site based Evidence)
Investigation • Need to solve the right
problem to prevent recurrence
• Critical to find the POD and what acts or conditions existed
• Use facts based systems approach to discover basic causation
• Learning – Having available networked capability is important
RISSB COP and Guideline outline “Best Practice”
approach
Systems Approach
What Happened • Blackwater system is affected
by heavy rain (ex Tropical Cyclone Oswald)
• 825mm rain, 24th _ 27th January • NCL closed 24th at 20:10 • 9F24 stowed at Rangal
• Learning – Investigation boundaries need to be broad enough to “discover” causation
Flood Damage • Blackwater system and NCL
is shut down for 13 days • 153 sites suffer flood damage • Client Requirement Brief
(CRB) process invoked to manage recovery operations
Learning – Helicopter flyovers invaluable to determine scope of works on this scale
NCL – 4 View looking South
Recovery and Resumption of Operation • Track restoration begins on 30th
January • Track is ballasted, resurfaced and
stress tested (multiple workgroups) • Track inspected and handed back at
normal operational speed – 15:10, 5th February
• 42 services (32 loaded UP direction totalling 174,000 tonnes)
• 9F24 derails at 12:12, 8th February, UP line, UP direction
The Site and Factual Evidence
Wagon #29 – 720m towards Epala
Lead wheel, lead bogie, first to derail
8mm flat LH Rail - Trapped sideframe and wheel
Increasing intensity – Wagons 18 through 28
Other Impacts/Learnings • Fire • Check rails do their job at bridge
Direction of Travel 9F24
Lead Locos + 28 Wagons 572.321 km
Wagon #98 574.206 km
#29
#64
Direction of Travel 9F24
Heat Marks Sideframe Wagon #28
Rolled Rail
All Clips Dislodged
#28
Continuous Flange Mark
Tread Marks
Direction of Travel of 9F24
Failed Knuckle
Ballast Marks
Mark from rail foot
#29 #3629
Direction of Travel
Right hand rail
9F24 Direction of Travel
of
#32 #31
#29 #30
Sleeper impact marks
Direction of Travel
#34
Bogies missing
Continuous Flange Marks
Police Photo
Photographs • Learning - Aerial
photography invaluable
• Take “lots” of photos – evidence lost on recovery
• Safety Advise Travelling in cabs Remote Locomotives
30
36
29
34
Direction of Travel 31
32
35
63
64
4128
4020
Initial position of Wagon 36 following roll
sequence
33
Flange Marks on web RH Rail - Gauge Side
Direction of Travel
Direction of Travel
277 mm
The “C” Shaped Buckle
• 29 metres long • 60 meters from
the end of the pile-up
• Drivers report seeing a buckle
• No derailed running evidence
Learning – “Track Survey” is critical in determining immediate causation
Learnings – The “C” Shaped Buckle
573.698 km 573.727 km
573.638 km 573.698 km Misalignment (Buckle)
573.633 km
25mm Design Cant (LH Rail DOT) 0 mm CantCurve - Design Radius 3708 m Straight
670 740680 690 730720710700660650640630
83 Metres ( 4 seconds at 74 kph) Length 29 Metres ( 277mm Lateral -‐ Static )
Towards Epala
No evidence of Derailed Running to this point
There is no loss of detection prior to derailment.Signal detection circuit is active on RH Rail DOT.
Speed of Last Upright Wagon (Position 68) is20.49 kph as it traverses the misalignment.
• Stay facts focused
• Open questions
• Learning - Proving “what is not” can be important to “what is” on the basis of fact
• Within limits, harmonic roll will not “feed” forward
These witness marks cannot be made by the “C” shaped buckle
29 m 29 m
NUCARS® and Engineering Analysis
Determination of the POD – Facts Based
573.638 km 573.698 km
573.633 km
25mm Design Cant (LH Rail DOT)Curve - Design Radius 3708 m
610 670590 600 680 690660650640630620
POD : 573.615 (+/-‐ 0.005) kmNCL -‐ UP Line
83 Metres ( 4 seconds at 74 kph)
Wagon 28 (VCAL 55055)
T=0 UTC 12:11:048th February, 2013Speed = 74 kph
Leading Wheelset Derails to Right in DOT
Most Likely PODError Bar
POD - Event Recorders
NUCARS
POD - Observed On-Site Factual Evidence No evidence of Derailed Running to this point
Legend
: Dragging Equipment Detector
: Mast (OHLE Equipment)
: Flood Recovery Works
: NUCARS - Predicted POD
: Most Likely POD - Consolidated Evidence - Lag Adjusted
Direction of Travel EF24
What was the Immediate Causation • Most evidence at
the POD is destroyed
• Based on fact, 9F24 encounters an “S” shaped buckle
• Drivers confirm the shape
• There is “too much steel”
NUCARS® Analysis On the basis of fact
The only possible shape
Marks laterally displaced indicating bogie yaw
L/V =1.12 Headstock Strike
Sequence The “Rolled” Rail
Why was there “Too much Steel” • Need to be mindful of the
environment
• Standards & Procedures exist, are adequate, have been communicated and understood
• Independent workgroups carry out tasks within competency
• CRB process is ineffective in delivering the required interdependent process control
Why was there “Too much Steel” (cont.)
• Ballasting performed • Lift and Line (Resurfacing) • Stress Testing
• Design Neutral Temperature (DNT) 38ºC (-7/+8) - CETS
• Tested OK at 34ºC • Max temp daytime 31.2ºC
• Further ballasting • Lift and Line (Resurfacing) • No TSR – Loaded trains at
operational speed, UP direction
Pro
cess
Ano
mal
y
CETS Mod 2
Stress Testing at NCL - 4
Rail Buckles
• Most likely, a smaller “S” shaped buckle is left behind the previous train Loaded Coal Train EF32, 11:30
Scope Variation and Stabilisation • Variation to “Scope of
Work” ineffective with the CRB process (at the time)
• Learning - Once regulated, it is impossible to tell where ballasting has been performed
• Learning - Interdependence between resurfacing, stress testing, restressing and stabalisation
Authority Gradient and Norms • No speed restriction (TSR)
applied on resumption of operation
• Driver Interviews • track rough - not reported • “no worse than usual”
• Learning – Forward facing camera provides valuable information
Basic Causation • Adequate Standards and Procedures exist to
complete the work • Independent workgroups perform competently
• Insufficient control over process at NCL – 4 • independent work groups require
interdependence for successful delivery
• Change management of the CRB process
• Communications and authority gradient – seeking a “Zero Harm” outcome
Discovery of Basic Causation is the key to preventing a
recurrence
Other Organisational Responses • Blanket speed restriction was applied to the
Blackwater network
• Safety Advice communicated regarding appropriate responses to infrastructure defects
• Rail Stress Management review
• Change management of CRB process to prepare for potential future scenarios
• Continuing journey to “Zero Harm” by sharing and leading cultural change
Final Thoughts • Have team presence during recovery to
quarantine evidence
• Investigation team “war room” near site
• Importance of these forums to share, learn and grow as industry
• Ensure you have access to appropriate capability to get a quality investigation
• Quality investigations take time and resources
Questions
Thank You