Rate analsis Chapter No. 23 (Tube Wells)

142
1 1- Boring for tube well in all types of soil except shingle and rock from ground level to 100 Ft (30 Metre) depth including sinking and with-drawing of casing pipe complete. S. Dia of ime (Day Daily Labour Hire charges Loading Expenses Repair Petty store Total Contractor Total Grand Total Rs. per No. bore equired t labour per foot of boring Per Foot charges bolts & Column (6, Profit 10% Rate per Ft foot complete charges material No. of Rate per Amount of T & P nuts etc. 9, 10, 11) on Column 100' (30M) installation day day No.12 (12 + 13) (5 + 14) Say and carriage 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 1 3" 3 930.60 27.92 4.00 0.02 40.00 0.80 - - 4.80 0.48 5.28 33.20 33.20 2 4" 4 930.60 37.22 8.00 0.04 40.00 1.60 - - 9.60 0.96 10.56 47.78 47.80 3 5" 6 1353.00 81.18 12.00 0.10 40.00 4.00 1.00 1.00 18.00 1.80 19.80 100.98 101.00 4 6" 9 1353.00 121.77 18.00 0.20 40.00 8.00 2.00 2.00 30.00 3.00 33.00 154.77 154.75 5 8" 11 1775.40 195.29 22.00 0.30 40.00 12.00 6.00 3.00 43.00 4.30 47.30 242.59 242.60 6 10" 13 1960.20 254.83 26.00 0.40 40.00 16.00 7.00 4.00 53.00 5.30 58.30 313.13 313.15 7 12" 14 1960.20 274.43 33.60 0.40 40.00 16.00 8.00 5.00 62.60 6.26 68.86 343.29 343.30 8 15" 17 2382.60 405.04 44.20 0.50 40.00 20.00 9.00 6.00 79.20 7.92 87.12 492.16 492.15 9 18" 18 2382.60 428.87 50.40 0.50 40.00 20.00 10.00 7.00 87.40 8.74 96.14 525.01 525.00

Transcript of Rate analsis Chapter No. 23 (Tube Wells)

Page 1: Rate analsis Chapter No. 23 (Tube Wells)

1

1- Boring for tube well in all types of soil except shingle and rock from ground level to 100 Ft (30 Metre) depthincluding sinking and with-drawing of casing pipe complete.

S. Dia of Time (Day) Daily Labour Hire charges Loading Expenses Repair Petty store Total Contractor Total Grand Total Rs. per Rate perNo. bore required to labour per foot of boring Per Foot charges bolts & Column (6, Profit 10% Rate per Ft/ foot Metre

complete charges material No. of Rate per Amount of T & P nuts etc. 9, 10, 11) on Column

100' (30M) installation day day No.12 (12 + 13) (5 + 14) Sayand carriage

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

1 3" 3 930.60 27.92 4.00 0.02 40.00 0.80 - -

4.80 0.48 5.28 33.20 33.20 108.89

2 4" 4 930.60 37.22 8.00 0.04 40.00 1.60 - -

9.60 0.96 10.56 47.78 47.80 156.73

3 5" 6 1353.00 81.18 12.00 0.10 40.00 4.00 1.00 1.00 18.00 1.80 19.80 100.98 101.00 331.21

4 6" 9 1353.00 121.77 18.00 0.20 40.00 8.00 2.00 2.00 30.00 3.00 33.00 154.77 154.75 507.65

5 8" 11 1775.40 195.29 22.00 0.30 40.00 12.00 6.00 3.00 43.00 4.30 47.30 242.59 242.60 795.71

6 10" 13 1960.20 254.83 26.00 0.40 40.00 16.00 7.00 4.00 53.00 5.30 58.30 313.13 313.15 1027.05

7 12" 14 1960.20 274.43 33.60 0.40 40.00 16.00 8.00 5.00 62.60 6.26 68.86 343.29 343.30 1125.98

8 15" 17 2382.60 405.04 44.20 0.50 40.00 20.00 9.00 6.00 79.20 7.92 87.12 492.16 492.15 1614.29

9 18" 18 2382.60 428.87 50.40 0.50 40.00 20.00 10.00 7.00 87.40 8.74 96.14 525.01 525.00 1722.03

Page 2: Rate analsis Chapter No. 23 (Tube Wells)

2

2- Boring for tube well in all types of soil except shingle gravel and rock from a depth of 100.10 to 200 Ft (30 to 60 Metre) below ground level, including sinking and with drawing of casing pipe complete.

S. Dia of Time (Day) Daily Labour Hire charges Loading Expenses Repair Petty store Total Contractor Total Grand Total Rate per Rate perNo. bore required to labour per foot of boring Per Foot charges bolts & Column (6, Profit 10% Rate per Ft/ Rft Metre

complete charges material No. of Rate per Amount of T & P nuts etc. 9, 10, 11) on Column

100' (30M) installation day day No.12 (12 + 13) (5 + 14)

and carriage

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

1 5" 10 1353.00 135.30 20.00 0.30 40.00 12.00 1.00 1.00 34.00 3.40 37.40 172.70 172.70 566.46

2 6" 14 1353.00 189.42 28.00 0.40 40.00 16.00 2.00 2.00 48.00 4.80 52.80 242.22 242.20 794.48

3 8" 15 1775.40 266.31 30.00 0.40 40.00 16.00 6.00 3.00 55.00 5.50 60.50 326.81 326.80 1071.94

4 10" 16 1960.20 313.63 32.00 0.50 40.00 20.00 7.00 4.00 63.00 6.30 69.30 382.93 382.95 1256.02

5 12" 17 1960.20 333.23 40.80 0.50 40.00 20.00 20.00 5.00 85.80 8.58 94.38 427.61 427.60 1402.57

6 15" 20 2382.60 476.52 52.00 0.60 40.00 24.00 9.00 6.00 91.00 9.10 100.10 576.62 576.60 1891.31

7 18" 21 2382.60 500.35 58.80 0.60 40.00 24.00 10.00 7.00 99.80 9.98 109.78 610.13 610.15 2001.21

Page 3: Rate analsis Chapter No. 23 (Tube Wells)

3

3- Boring for tube well in all types of soil except shingle gravel and rock from a depth of 200.10 to 300 Ft (60 to 90 Metre) below ground level including sinking and with drawing of casing pipe complete.

S. Dia of Time (Day) Daily Labour Hire charges Loading Expenses Repair Petty store Total Contractor Total Total Rate per Rate perNo. bore required to labour per foot of boring Per Foot charges bolts & Column (6, Profit 10% Rate per Ft/ Rft Metre

complete charges material No. of Rate per Amount of T & P nuts etc. 9, 10, 11) on Column

100' (30M) installation day day No.12 (12 + 13) (5 + 14) Say

and carriage

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

1 5" 14 1353.00 189.42 28.00 0.40 40.00 16.00 1.00 1.00 46.00 4.60 50.60 240.02 240.00 787.27

2 6" 18 1353.00 243.54 36.00 0.50 40.00 20.00 2.00 2.00 60.00 6.00 66.00 309.54 309.55 1015.29

3 8" 19 1775.40 337.33 38.00 0.50 40.00 20.00 6.00 3.00 67.00 6.70 73.70 411.03 411.05 1348.17

4 Contractor's Profit 20 1960.20 392.04 40.00 0.60 40.00 24.00 7.00 4.00 75.00 7.50 82.50 474.54 474.55 1556.49

5 12" 21 1960.20 411.64 48.00 0.60 40.00 24.00 8.00 5.00 85.00 8.50 93.50 505.14 505.15 1656.87

6 15" 22 2382.60 524.17 56.80 0.70 40.00 28.00 9.00 6.00 99.80 9.98 109.78 633.95 633.95 2079.36

7 18" 23 2382.60 548.00 64.40 0.70 40.00 28.00 10.00 7.00 109.40 10.94 120.34 668.34 668.35 2192.15

Page 4: Rate analsis Chapter No. 23 (Tube Wells)

4

4- Boring for tube well in all types of soil except shingle gravel and rock from a depth of 300.10 to 400 Ft (90 to 120 Metre) below ground level including sinking and with drawing of casing pipe complete.

S. Dia of Time (Day) Daily Labour Hire charges Loading Expenses Repair Petty store Total Contractor Total Grand Total Rate per No. bore required to labour per foot of boring Per Foot charges bolts & Column (6, Profit 10% Rate per Ft/ Metre

complete charges material No. of Rate per Amount of T & P nuts etc. 9, 10, 11) on Column

100' (30M) installation day bag (7 x 8) No.12 (12 + 13) (5 + 14) Say

and carriage

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

1 8" 23 1775.40 408.34 46.00 0.60 40.00 24.00 6.00 3.00 79.00 7.90 86.90 495.24 495.25 1624.39

2 10" 24 1960.20 470.45 48.00 0.70 40.00 28.00 7.00 4.00 87.00 8.70 95.70 566.15 566.15 1856.97

3 12" 25 1960.20 490.05 60.00 0.70 40.00 28.00 8.00 5.00 101.00 10.10 111.10 601.15 601.15 1971.77

4 15" 27 2382.60 643.30 70.20 0.80 40.00 32.00 9.00 6.00 117.20 11.72 128.92 772.22 772.20 2532.89

5 18" 27 2382.60 643.30 75.60 0.80 40.00 32.00 10.00 7.00 124.60 12.46 137.06 780.36 780.35 2559.59

Page 5: Rate analsis Chapter No. 23 (Tube Wells)

5

Daily Labour Charges for :Daily charges for boring of tube well per 100 ft(30 M) depth including sinking and with drawingof casing pipe.

a) For 3" to 4" (75 to 100mm) dia bore.

Detail Unit Rate (British System) per Rft

Qty RatePer Unit (Rs.) Amount (Rs.)

Labour for 30 M

Foreman 1.00 No 170.00 P. Day 170.00 Skilled Cooly 2.00 Nos 160.00 P. Day 320.00 Unskilled Cooly 1.00 No 140.00 P. Day 140.00 Chowkidar 1.00 No 75.00 P. Day 75.00

Total 705.00 Sundries ### Percent 70.50 Total 775.50

Contractor's Profit & Overhea ### Percent 155.10 Total rate for 100 Rft 930.60

Say 930.60

Page 6: Rate analsis Chapter No. 23 (Tube Wells)

6

Daily Labour Charges for :Daily charges for borring of tube well per 100 ft(30 M) depth including sinking and with drawingof casing pipe. 20

b) For 5" to 6" (125 to 150mm) dia bore.

Detail Unit Rate (British System) per Rft

Qty RatePer Unit (Rs.) Amount (Rs.)

Labour

Foreman 1.00 No 170.00 P. Day 170.00 Skilled Cooly 4.00 Nos 160.00 P. Day 640.00 Unskilled Cooly 1.00 No 140.00 P. Day 140.00 Chowkidar 1.00 No 75.00 P. Day 75.00

Total 1,025.00 Contractor's Profit ### Percent 102.50 Total 1,127.50

Contractor's Profit & Overhea ### Percent 225.50 Total rate for 100 feet 1,353.00

Say 1353.00

Page 7: Rate analsis Chapter No. 23 (Tube Wells)

7

Daily Labour Charges for :Daily charges for borring of tube well per 100 ft(30 M) depth including sinking and with drawingof casing pipe.

c) For 8" (200mm) dia bore.

Detail Unit Rate (British System) per Foot

Qty RatePer Unit (Rs.) Amount (Rs.)

Labour

Foreman 1.00 No 170.00 P. Day 170.00 Skilled Cooly 6.00 Nos 160.00 P. Day 960.00 Unskilled Cooly 1.00 No 140.00 P. Day 140.00 Chowkidar 1.00 No 75.00 P. Day 75.00

Total 1,345.00 Sundries ### Percent 134.50 Total 1,479.50

Contractor's Profit & Overhea ### Percent 295.90 Total rate for 100 feet 1,775.40

Say 1,775.40

Page 8: Rate analsis Chapter No. 23 (Tube Wells)

8

Daily Labour Charges for :Daily charges for borring of tube well per 100 ft(30 M) depth including sinking and with drawingof casing pipe.

d) For 10" to 12" (250 to 300mm) dia bore.

Detail Unit Rate (British System) per Foot

Qty RatePer Unit (Rs.) Amount (Rs.)

Labour

Foreman 1.00 No 170.00 P. Day 170.00 Skilled Cooly 6.00 Nos 160.00 P. Day 960.00 Unskilled Cooly 2.00 Nos 140.00 P. Day 280.00 Chowkidar 1.00 No 75.00 P. Day 75.00

Total 1,485.00 Sundries ### Percent 148.50 Total 1,633.50

Contractor's Profit & Overhea ### Percent 326.70 Total rate for 100 feet 1,960.20

Say 1,960.20

Page 9: Rate analsis Chapter No. 23 (Tube Wells)

9

Daily Labour Charges for :Daily charges for borring of tube well per 100 ft(30 M) depth including sinking and with drawingof casing pipe.

e) For 15" to 18" (375 to 450mm) dia bore.

Detail Unit Rate (British System) per Foot

Qty RatePer Unit (Rs.) Amount (Rs.)

Labour

Foreman 1.00 No 170.00 P. Day 170.00 Skilled Cooly 8.00 Nos 160.00 P. Day 1,280.00 Unskilled Cooly 2.00 Nos 140.00 P. Day 280.00 Chowkidar 1.00 No 75.00 P. Day 75.00

Total 1,805.00 Sundries ### Percent 180.50 Total 1,985.50

Contractor's Profit & Overhea ### Percent 397.10 Total rate for 100 feet 2,382.60

Say 2,382.60

Page 10: Rate analsis Chapter No. 23 (Tube Wells)

10

DESCRIPTION OF ITEM NO 5: Direct rotary/ reverse rotary drilling of bore fortube wells in all type of soil except shingle, graveland rock.

(a) From ground level to 250 ft. below ground level.i) 15" to 18" i/d

Detail Unit Rate (British System) per Foot bore

Qty RatePer Unit (Rs.) Amount (Rs.)

Material

1 Reg pumps etc. 24.00 Hrs 1200.00 Ph 28,800.00 2 Generator set light arrangement 8.00 Hrs 140.00 Ph 1,120.00 3 Carriage from store to site of work for

reverse rotary drilling reg complete setand generator set etc. L. S. 3,000.00

Total 32,920.00 Labour

Foreman for 3 shifts (One No. per shift) 3.00 Nos 170.00 P. Shif 510.00 Driller for 3 shifts (One No. per shift) 3.00 Nos 170.00 P. Shif 510.00 Helper for 3 shifts (One No. per shift) 54.00 Nos 75.00 P. Shif 4,050.00 Electrician for 8 hours 1.00 No 170.00 P. Shif 170.00 Mechanic for 3 shifts 3.00 Nos 170.00 P. Shif 510.00

Total 5,750.00 Sundries ### Percent 575.00 Total 6,325.00

Say 6,325.00

Page 11: Rate analsis Chapter No. 23 (Tube Wells)

11

Detail Unit Rate (British System) per Foot bore

Qty RatePer Unit (Rs.) Amount (Rs.)

H.S.D. for rig for 24 hours ### Ltr 10.00 Ltr 2,179.20 H.S.D. for generator for 8 hours 72.64 Ltr 10.00 Ltr 726.40 Cotton waste for rig for 24 hours 7.90 Kg 16.00 Kg 126.40 Mobil oil 22.70 Ltr 79.00 Ltr 1,793.30 Mix. Expenditure L. S. 600.00

Total 5,425.30

Machinery 32,920.00 Labour 6,325.00 Material (lubricate P.O.L) 5,425.30

Total 44,670.30 Contractor's Profit ### Percent 4,467.03 Total 49,137.33

Daily Expenditure 49,137.33 Daily Progress ### FtCharges Per Feet 49,137 406.09

121 say 406.10

Rate Charges Per Metre 1,331.99 1,332.00

Material ( P.O.L )

Page 12: Rate analsis Chapter No. 23 (Tube Wells)

12

Item No. 5 Direct rotary/ reverse rotary drilling of bore fortube wells in all type of soil except shingle, graveland rock.

a. From ground level to 250 ft. below ground level.( ii) 20" to 26" (500 to 650mm) dia

Detail Unit Rate (British System) per Rft of bore

Qty RatePer Unit (Rs.) Amount (Rs.)

Daily Expenditure 49,137.33

Daily Progress ### Ft

Charges Per Foot 49,137 115

427.28 say 427.30

Rate Per Metre 1,401.48 say 1,401.50

Page 13: Rate analsis Chapter No. 23 (Tube Wells)

13

Item No. 5 Direct rotary/ reverse rotary drilling of bore fortube wells in all type of soil except shingle, graveland rock.

b. Exceeding 250 ft (75 M) below ground level. ( i) 15" to 18" (375 to 450mm) dia

Detail Unit Rate (British System) per Rft of bore

Qty RatePer Unit (Rs.) Amount (Rs.)

Daily Expenditure 49,137.33

Daily Progress 92.00 Ft

Rate Per Rft 49,137

92 534.10 say 534.10

Rate Per Metre 1,751.85 say 1,751.85

Page 14: Rate analsis Chapter No. 23 (Tube Wells)

14

Item No. 5 Direct rotary/ reverse rotary drilling of bore fortube wells in all type of soil except shingle, graveland rock.

b. Exceeding 250 ft (75 M) below ground level.(ii) 20" to 26" (500 to 650mm) dia

Detail Unit Rate (British System) per Rft of bore

Qty RatePer Unit (Rs.) Amount (Rs.)

Daily Expenditure 49,137.33

Daily Progress 88.40 Ft

Boring Charges Per Foot 49,137 88.40

555.85 say 555.85

Rate Per Metre 1,823.20 say 1,823.20

Page 15: Rate analsis Chapter No. 23 (Tube Wells)

15

DESCRIPTION OF ITEM NO 6: Boring for tube well in shingle, gravel and rock,including sinking and with drawing of casingpipe.

a. From ground level to 200 ft (60 M) below ground level.

(i) 12" to 18" (300 to 450mm) dia

Detail Unit Rate (British System) per Ft of bore

Qty RatePer Unit (Rs.) Amount (Rs.)

Daily Expenditure as per Item No. 5 49,137.33

Daily Progress 46.00 Ft

Charges Per Foot 49,137 46

1,068.20 say 1,068.20

Rate Per Metre 3,503.71 say 3,503.70

Page 16: Rate analsis Chapter No. 23 (Tube Wells)

16

Item No. 6 Boring for tube well in shingle, gravel and rock,including sinking and with drawing of casingpipe.

a. From ground level to 200 ft (60 M) below ground level.

(ii) 20" to 26" (500 to 650mm) dia

Detail Unit Rate (British System) per Ft of bore

Qty RatePer Unit (Rs.) Amount (Rs.)

Daily Expenditure as per Item No. 5 49,137.33

Daily Progress 42.58 Ft

Charges Per Foot 49,137 42.58

1,154.00 say 1,154.00

Rate Per Metre 3,785.20 say 3,785.20

Page 17: Rate analsis Chapter No. 23 (Tube Wells)

17

Item No. 6 Boring for tube well in shingle, gravel and rock,including sinking and with drawing of casingpipe.

b. Exceeding 200 ft depth (70 M) below ground level.(i) 12" to 18" (300 to 450mm) dia

Detail Unit Rate (British System) per Ft of bore

Qty RatePer Unit (Rs.) Amount (Rs.)

Daily Expenditure 49,137.33

Daily Progress 38.68 Ft

Boring Charges Per Foot 49,137 38.68

1,270.35 say 1,270.35

Rate Per Metre 4,166.76 say 4,166.75

Page 18: Rate analsis Chapter No. 23 (Tube Wells)

18

Item No. 6 Boring for tube well in shingle, gravel and rock,including sinking and with drawing of casingpipe.

b. Exceeding 200 ft depth (70 M) below ground level.(ii) 20" to 26" (500 to 650mm) dia

Detail Unit Rate (British System) per Ft of bore

Qty RatePer Unit (Rs.) Amount (Rs.)

Daily Expenditure as per Item No. 5 49,137.33

Daily Progress 28.73 Ft

Charges Per Foot 49,137 28.73

1,710.31 say 1,710.30

Rate Per Metre 5,609.83 say 5,609.85

Page 19: Rate analsis Chapter No. 23 (Tube Wells)

19

DESCRIPTION OF ITEM NO 7: Providing strong substantially built box of deodarwood (2nd class) 4'x2½'x9' (1.22x0.76x0.228)with compartments, lock and locking arrangementfor preserving samples of strata from bore hole.

Detail Unit Rate (British System) per Job for CompleteBore.

Qty RatePer Unit (Rs.) Amount (Rs.)

Material

Deodar Wood (2nd Class)Top and bottom 2x4'x2.5'x1/12' 1.66 Cft

Sides 2(4'+2'-4")x1/12'x¾' 0.79 Cft

Partition 9x2'-4"x½'x1/24' 0.44 Cft

Strips 6x3'x6"x½x1/24 0.44 Cft

3.33 CftWastage 15% 0.50 CftTotal 3.83 Cft 3.83 Cft 500.00 P. Cft 1,915.00 Lock 1.00 No 40.00 Each 40.00 Hinges 2.00 No. 8.00 Each 16.00 Steel Handle 4" (100mm) 2.00 Nos 8.00 Each 16.00

Total 1,987.00 Contractor's Profit ### Percent 198.70 Total 2,185.70

Labour

Sawing charges (3.83Cft x 10) 38.30 Sft 0.80 Sft 30.64 Carpenter 0.75 No 300.00 P. Day 225.00

Page 20: Rate analsis Chapter No. 23 (Tube Wells)

20

Detail Unit Rate (British System) per Job for CompleteBore.

Qty RatePer Unit (Rs.) Amount (Rs.)

Taking and preserving box 2 lbssample of strata. L. S. 47.20

Total 302.84 Sundries ### 120.00 24.00 Total 326.84

Contractor's Profit ### Percent 32.68 Total 359.52

Labour Rate Per Job for complete bore. Rs. 359.52

say 359.50 Composite Rate per Job for complete bore. Rs. 2,545.22

Say 2,545.20

Page 21: Rate analsis Chapter No. 23 (Tube Wells)

21

DESCRIPTION OF ITEM NO 8: Furnishing Sample of Water from Bore Hole.

Detail Unit Rate (British System) per Set of 2 bottles

Qty RatePer Unit (Rs.) Amount (Rs.)

MaterialBottle 2 lbs capcity 2.00 Nos 20.00 Each 40.00

Total 40.00 Contractor's Profit ### Percent 4.00 Total 44.00

LabourTaking samples of water from borehole including bailing or pumping. L. S. 40.00 Sealing the water sample andproviding necessary packing etc. L. S. 20.00 Handling charges L. S. 30.00

Total 90.00 Contractor's Profit ### Percent 9.00 Total 99.00

Labour Rate Per Set of 2 bottles Rs. 99.00 say 99.00

Composite Rate per Set Rs. 143.00 Say 143.00

Page 22: Rate analsis Chapter No. 23 (Tube Wells)

22

9- Providing and installing Brass Strainer in Tube Well Bore Hole including Socket, special Socket, Studs

etc. complete.

S. Dia of Thickness Rate of Contractor's Total L A B O U RNo. Strainer of strainer Profit Material Daily Daily Labour Lowering Contractor's Total Labour Composite Labour Composite

Strainer (Per Ft i/c 20.00 Progress Expenses Per Ft Equipment Profit Labour Rate Rate/Ft Rate Rate

Specials Percent 4 + 5 in Ft Rs. Charges 20.00 9 + 10 Per Ft. 6 + 12 per Metre per Metre

Stud, and Percent + 11

Socket)

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

1 2" 5/32" 250.00 12.50 262.50 200.00 1,273.80 6.37 2.00 0.10 8.47 8.45 270.97 27.72 888.78

2 3" 5/32" 350.00 17.50 367.50 200.00 1,273.80 6.37 2.00 0.10 8.47 8.45 375.97 27.78 1233.18

3 4" 3/16" 450.00 22.50 472.50 150.00 1,273.80 8.49 2.52 0.13 11.14 11.15 483.64 36.53 1586.33

4 5" 3/16" 488.00 24.40 512.40 130.00 1,273.80 9.80 2.52 0.13 12.44 12.45 524.84 40.82 1721.49

5 6" 3/16" 525.00 26.25 551.25 120.00 1,273.80 10.62 3.56 0.18 14.35 14.35 565.60 47.08 1855.18

6 7" 3/16" 612.00 30.60 642.60 100.00 1,273.80 12.74 3.56 0.18 16.48 16.50 659.08 54.04 2161.77

7 8" 3/16" 700.00 35.00 735.00 80.00 1,273.80 15.92 4.16 0.21 20.29 20.30 755.29 66.55 2477.35

8 9" 3/16" 825.00 41.25 866.25 80.00 1,273.80 15.92 4.16 0.21 20.29 20.30 886.54 66.55 2907.85

9 10" 3/16" 950.00 47.50 997.50 70.00 1,273.80 18.20 4.16 0.21 22.57 22.55 1020.07 74.01 3345.81

10 10" 1/4" 1050.00 52.50 1102.50 70.00 1,273.80 18.20 4.16 0.21 22.57 22.55 1125.07 74.01 3690.21

11 12" 1/4" 1140.00 57.00 1197.00 70.00 1,273.80 18.20 5.00 0.25 23.45 23.45 1220.45 76.91 4003.07

12 15" 1/4" 1250.00 62.50 1312.50 60.00 1,273.80 21.23 5.00 0.25 26.48 26.50 1338.98 86.85 4391.85

13 18" 1/4" 1300.00 65.00 1365.00 60.00 1,273.80 21.23 5.00 0.25 26.48 26.50 1391.48 86.85 4564.05

14 20" 1/4" 1625.00 81.25 1706.25 50.00 1,273.80 25.48 5.00 0.25 30.73 30.75 1736.98 100.78 5697.28

15 22" 1/4" 1950.00 97.50 2047.50 50.00 1,273.80 25.48 6.00 0.30 31.78 31.80 2079.28 104.23 6820.03

Page 23: Rate analsis Chapter No. 23 (Tube Wells)

23

20

Contractor's Profit

Page 24: Rate analsis Chapter No. 23 (Tube Wells)

24

Daily Labour Charges

Detail Unit Rate (British System) per day

Qty RatePer Unit (Rs.) Amount (Rs.)

Labour

Foreman 1.00 No 170.00 P. Day 170.00 Skilled Coolies 1.00 No 160.00 P. Day 160.00 Unskilled Coolies 4.00 Nos 140.00 P. Day 560.00 Chowkidar 1.00 No 75.00 P. Day 75.00

Total 965.00 Sundries ### Percent 96.50 Total 1,061.50

Contractor's Profit & Overhea ### Percent 212.30 Total 1,273.80

Daily Labour Charges P. Day Rs. 1,273.80

Page 25: Rate analsis Chapter No. 23 (Tube Wells)

25

Daily Labour Charges

Detail Unit Rate (British System) per Day Charges

Qty RatePer Unit (Rs.) Amount (Rs.)

20

Labour

Foreman 1.00 No 170.00 P. Day 170.00 Skilled Coolies 2.00 Nos 160.00 P. Day 320.00 Unskilled Coolies 6.00 Nos 140.00 P. Day 840.00 Chowkidar 1.00 No 75.00 P. Day 75.00

Total 1,405.00 Sundries 10.00 140.50 Total 1,545.50

Contractor's Profit 20.00 309.10 Total 1,854.60

Daily La Rs. 1,854.60

Contractor's Profit

Page 26: Rate analsis Chapter No. 23 (Tube Wells)

26

10 - Providing and Installing M. S. Bail Plug in Tube Well Bore Hole (Each).

M A T E R I A LS. Dia of Plug Rate Total Wt. of Size of Wt. of Total Wastage Total Wt. in Rate Amount Material

No. bore Length Per Foot Disc Bars Bars Wt. Wt. Kg Per Kg Rs. Bolts &

Lbs. (Lbs.) (Lbs.) in Lbs Nuts

(3 x 4) (6 + 8) (9 + 10)

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15

1 2" 1.50 110.00 165.00 0.14 1/4" 0.53 0.67 0.07 0.74 0.33 17.00 5.68 4.00

2 3" 1.50 150.00 225.00 0.30 1/4" 0.53 0.83 0.08 0.91 0.41 17.00 7.04 4.00

3 4" 2.00 280.00 560.00 0.51 3/8" 1.50 2.01 0.20 2.21 1.00 17.00 17.05 4.00

4 5" 2.00 370.00 740.00 1.22 3/8" 1.50 2.72 0.27 2.99 1.36 17.00 23.07 4.00

5 6" 2.00 430.00 860.00 1.72 3/4" 6.00 7.72 0.77 8.49 3.85 17.00 65.48 8.00

6 7" 2.00 228.89 457.78 2.30 3/4" 6.00 8.30 0.83 9.13 4.14 17.00 70.40 8.00

7 8" 2.00 251.79 503.58 2.97 3/4" 6.00 8.97 0.90 9.87 4.48 17.00 76.09 8.00

8 9" 2.00 286.12 572.24 3.72 3/4" 6.00 9.72 0.97 10.69 4.85 17.00 82.45 8.00

9 10" 2.00 396.75 793.50 6.23 3/4" 6.00 12.23 1.22 13.45 6.10 17.00 103.74 8.00

10 12" 2.00 480.67 961.34 8.83 3/4" 6.00 14.83 1.48 16.31 7.40 17.00 125.79 8.00

Page 27: Rate analsis Chapter No. 23 (Tube Wells)

27

11 15" 2.00 601.10 1202.20 13.57 3/4" 6.00 19.57 1.96 21.53 9.76 17.00 166.00 8.00

12 18" 2.00 686.67 1373.34 19.34 3/4" 6.00 25.34 2.53 27.87 12.64 17.00 214.94 8.00

13 20" 2.00 778.74 1557.48 23.74 3/4" 6.00 29.74 2.97 32.71 14.84 17.00 252.26 8.00

14 22" 2.00 852.80 1705.60 28.60 3/4" 6.00 34.60 3.46 38.06 17.26 17.00 293.49 8.00

Page 28: Rate analsis Chapter No. 23 (Tube Wells)

28

20

Page 29: Rate analsis Chapter No. 23 (Tube Wells)

29

Contractor's Profit

Page 30: Rate analsis Chapter No. 23 (Tube Wells)

30

M A T E R I A L L A B O U R C O S T (Rs.)Material Welding Cutting Total Grand Say Contra- Total Labour for Labour Total Progr- Daily Rate Say Rate Labour Compo-

Total Threading Disc Disc Total ctor's Lowering Contra- ess Charges Per Rft Per Plug Rate siteClamp Profit Equip- ctor's Daily @ Rs. of Each Length

(5 + 14 (18 + 19) (16 + 20) 20.00 (22 + 23) ment Profit (25 + 26) 1,854.6 Plug (31 x 3) (24 + 33)

+ 15) 20.00 per No. (27 + 29)

Percent

16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34

174.68 4.00 30.80 15.40 46.20 220.89 221 11.04 231.93 3.73 0.75 4.48 100 18.55 23.03 23.05 34.54 34.54 266.47

236.04 4.00 40.82 20.40 61.22 297.26 297 14.86 312.12 3.73 0.75 4.48 100 18.55 23.03 23.05 34.54 34.54 346.66

581.05 4.00 53.20 26.68 79.88 660.93 661 33.05 693.98 4.70 0.94 5.65 80 23.18 28.83 28.85 57.66 57.66 751.63

767.07 4.00 65.52 33.76 99.28 866.35 866 43.32 909.67 4.70 0.94 5.65 80 23.18 28.83 28.85 57.66 57.66 967.33

933.48 4.00 80.48 40.00 120.48 1053.96 1054 52.70 1106.66 4.78 0.96 5.74 56 33.12 38.85 38.85 77.71 77.71 1,184.37

536.18 6.00 92.64 46.32 138.96 675.15 675 33.76 708.90 4.78 0.96 5.74 56 33.12 38.85 38.85 77.71 77.71 786.61

587.67 6.00 105.20 52.60 157.81 745.47 745 37.27 782.74 7.77 1.55 9.32 48 38.64 47.96 47.95 95.92 95.92 878.67

662.69 6.00 117.80 58.88 176.68 839.37 839 41.97 881.34 7.77 1.55 9.32 48 38.64 47.96 47.95 95.92 95.92 977.26

905.24 6.00 133.00 66.00 199.00 1104.24 1104 55.21 1159.45 7.77 1.55 9.32 48 38.64 47.96 47.95 95.92 95.92 1,255.37

1095.13 6.00 157.12 78.56 235.68 1330.81 1331 66.54 1397.35 9.33 1.87 11.20 40 46.36 57.57 57.55 115.13 115.13 1,512.48

Page 31: Rate analsis Chapter No. 23 (Tube Wells)

31

1376.20 6.00 194.88 97.44 292.32 1668.52 1669 83.43 1751.95 9.33 1.87 11.20 40 46.36 57.57 57.55 115.13 115.13 1,867.08

1596.28 6.00 232.60 116.32 348.92 1945.20 1945 97.26 2042.46 9.33 1.87 11.20 32 57.96 69.16 69.15 138.31 138.31 2,180.77

1817.74 6.00 257.68 128.84 386.52 2204.26 2204 110.21 2314.48 11.20 2.24 13.44 30 61.82 75.26 75.25 150.52 150.52 2,465.00

2007.09 6.00 282.00 141.44 423.44 2430.53 2431 121.53 2552.05 11.20 2.24 13.44 30 61.82 75.26 75.25 150.52 150.52 2,702.57

Page 32: Rate analsis Chapter No. 23 (Tube Wells)

32

11- Providing and installing PVC Strainer BSS Class "B" in Tube Well Bore Hole including Sockets and Solvents etc. complete.

S. Dia of Rate Contractor's Total Daily Labour Labour Solvent Lowering Contractor's Total Say Rate per Rft Rate per MetreNo. Strainer Per Ft Profit Progress Charges Cost Charges Profit (8 + 9 + Labour Composite Labour

20.00 (3 + 4) in Ft Per Day Per Ft 20.00 10 + 11) (5 + 14)

Percent Percent

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

1 3" 64.00 3.20 67.20 200.00 567.60 2.84 1.00 1.84 0.14 5.82 5.80 5.80 73.02 19.08

2 4" 80.00 4.00 84.00 180.00 567.60 3.15 1.12 2.24 0.17 6.69 6.70 6.70 90.69 21.93

3 5" 130.00 6.50 136.50 180.00 567.60 3.15 1.12 2.60 0.19 7.06 7.05 7.05 143.56 23.16

4 6" 185.00 9.25 194.25 160.00 567.60 3.55 1.20 3.28 0.22 8.25 8.25 8.25 202.50 27.07

5 8" 450.00 22.50 472.50 128.00 706.20 5.52 2.08 3.76 0.29 11.65 11.65 11.65 484.15 38.20

6 10" 450.00 22.50 472.50 128.00 706.20 5.52 2.08 4.00 0.30 11.90 11.90 11.90 484.40 39.02

7 12" 650.00 32.50 682.50 104.00 706.20 6.79 2.64 5.00 0.38 14.81 14.80 14.80 697.31 48.58

8 14" 800.00 40.00 840.00 104.00 706.20 6.79 2.64 5.00 0.38 14.81 14.80 14.80 854.81 48.58

Page 33: Rate analsis Chapter No. 23 (Tube Wells)

33

12- Providing and installing PVC Strainer BSS Class "D" in Tube Well Bore Hole including Sockets and Solvents etc. complete.

M A T E R I A L L A B O U R E Rate per Rft Rate per MetreS. Dia of Rate for Contractor's Total Daily Labour Labour Solvent Lowering Total Contractor's Total Labour Composite Labour

No. Pipe Per Ft Profit Progress Charges Cost Charges Labour Profit (8 + 11 (5 + 13)

20.00 3 + 4 Per Day Per Ft (9 + 10) 20.00 + 12)

Percent Percent

1 2 3 4 5 6 7 8 9 10 11 4 13 14 15 16

1 1¼" 24.00 1.20 25.20 200.00 522.70 2.61 0.64 1.07 1.71 0.09 4.41 4.40 29.61 14.46

2 1½" 29.50 1.48 30.98 200.00 522.70 2.61 0.72 1.16 1.88 0.09 4.58 4.60 35.56 15.03

3 2" 40.00 2.00 42.00 200.00 522.70 2.61 0.76 1.19 1.95 0.10 4.66 4.65 46.66 15.29

4 3" 103.00 5.15 108.15 200.00 567.60 2.84 1.00 1.84 2.84 0.14 5.82 5.80 113.97 19.09

5 4" 170.00 8.50 178.50 180.00 567.60 3.15 1.12 2.23 3.35 0.17 6.67 6.65 185.17 21.87

6 5" 245.00 12.25 257.25 180.00 567.60 3.15 1.28 2.60 3.88 0.19 7.23 7.25 264.48 23.70

7 6" 350.00 17.50 367.50 160.00 567.60 3.55 1.60 20.00 21.60 1.08 26.23 26.25 393.73 86.03

Page 34: Rate analsis Chapter No. 23 (Tube Wells)

34

13 - i -Providing and installing PVC Bail/ End Plug in Tube Well Bore Hole: BSS Class "B".

M A T E R I A L L A B O U R E RateS. No. Dia of Cost of Contractor's Total Solvent Contractor's Total Lowering Total Labour Composite

Bail / Bail/ Profit Profit Charges Labour

End Plug End Plug 20.00 (3 + 4) 20.00 6 + 7 8 + 9 5 + 10

Percent Percent say1 2 3 4 5 6 7 8 9 10 11 12

1 3" 40.00 2.00 42.00 1.00 0.05 1.05 2.60 3.65 3.65 45.65 45.65

2 4" 55.00 2.75 57.75 1.12 0.06 1.18 2.99 4.17 4.15 61.92 61.90

3 5" 86.00 4.30 90.30 1.28 0.06 1.34 3.32 4.66 4.65 94.96 94.95

4 6" 125.00 6.25 131.25 1.60 0.08 1.68 4.11 5.79 5.80 137.04 137.05

5 8" 250.00 12.50 262.50 2.08 0.10 2.18 5.07 7.25 7.25 269.75 269.75

Contractor's Profit 6 10" 356.00 17.80 373.80 2.08 0.10 2.18 5.40 7.58 7.60 381.38 381.40

7 12" 480.00 24.00 504.00 2.64 0.13 2.77 6.07 8.84 8.85 512.84 512.85

8 14" 506.00 50.60 556.60 2.64 0.26 2.90 6.07 8.97 8.95 565.57 565.55

Page 35: Rate analsis Chapter No. 23 (Tube Wells)

35

13 - iiProviding and installing PVC Bail/ End Plug in Tube Well Bore Hole: BSS Class "D".

M A T E R I A L L A B O U R E RateS. No. Dia of Cost of Contractor's Total Solvent Contractor's Total Lowering Total Labour Composite

Bail / Bail/ Profit Profit Charges Labour

End Plug End Plug 20.00 (3 + 4) 20.00 (6 + 7) (8 + 9) (10 + 5) say

Percent Percent

1 2 3 4 5 6 7 8 9 10 11 12

1 1¼" 20.00 1.00 21.00 0.80 0.04 0.84 1.60 2.44 2.45 23.44 23.45

2 1½" 30.00 1.50 31.50 0.88 0.04 0.92 1.72 2.64 2.65 34.14 34.15

3 2" 45.00 2.25 47.25 0.92 0.05 0.97 1.80 2.77 2.75 50.02 50.00

4 3" 60.00 3.00 63.00 1.00 0.05 1.05 2.60 3.65 3.65 66.65 66.65

5 4" 80.00 4.00 84.00 1.12 0.06 1.18 3.00 4.18 4.20 88.18 88.20

6 5" 115.00 5.75 120.75 1.28 0.06 1.34 3.32 4.66 4.65 125.41 125.40

7 6" 150.00 7.50 157.50 1.60 0.08 1.68 4.12 5.80 5.80 163.30 163.30

Page 36: Rate analsis Chapter No. 23 (Tube Wells)

36

14- Providing and installing M.S. blind pipe socketed/ welded joint M.S. reducer (where necessary) in

Tube Well Bore Hole including jointing/ welding with strainer etc. complete.

S. Dia of Thickness Rate Contractor's Total Daily Daily Lowering Contractor's Total Grand Rate per Rft Rate per MetreNo. Pipe of Pipe Per Ft Profit Progress Charges Charges Profit 10% Total Labour Composite Labour Composite

20.00 (4 + 5) Rs. (9 + 10) (8 + 11) (6 + 13)

Percent 1854.60

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

1 2" 1/8" 50.34 2.52 52.86 100 18.55 2.00 0.20 2.20 20.75 20.75 73.61 68.06 241.43

2 3" 1/8" 82.45 4.12 86.57 100 18.55 2.00 0.20 2.20 20.75 20.75 107.32 68.06 352.02

3 4" 1/8" 119.06 5.95 125.01 80 23.18 2.52 0.25 2.77 25.95 25.95 150.96 85.12 495.16

4 5" 3/16" 160.27 8.01 168.28 80 23.18 2.52 0.25 2.77 25.95 25.95 194.23 85.12 637.09

5 6" 3/16" 190.79 9.54 200.33 56 33.12 3.56 0.36 3.92 37.03 37.05 237.38 121.52 778.60

6 7" 3/16" 228.89 11.44 240.33 56 33.12 3.56 0.36 3.92 37.03 37.05 277.38 121.52 909.82

7 8" 3/16" 251.79 12.59 264.38 48 38.64 4.16 0.42 4.58 43.21 43.20 307.58 141.70 1008.86

8 9" 3/16" 286.12 14.31 300.43 48 38.64 4.16 0.42 4.58 43.21 43.20 343.63 141.70 1127.09

9 10" ¼" 396.75 19.84 416.59 48 38.64 4.16 0.42 4.58 43.21 43.20 459.79 141.70 1508.10

10 12" ¼" 480.67 24.03 504.70 40 46.36 5.00 0.50 5.50 51.86 51.85 556.55 170.07 1825.50

11 15" ¼" 601.10 30.05 631.15 40 46.36 5.00 0.50 5.50 51.86 51.85 683.00 170.07 2240.26

12 18" ¼" 686.67 34.33 721.00 32 57.96 5.00 0.50 5.50 63.46 63.45 784.45 208.12 2573.01

13 20" ¼" 778.24 38.91 817.15 30 61.82 6.00 0.60 6.60 68.42 68.40 885.55 224.35 2904.61

14 22" ¼" 852.80 42.64 895.44 30 61.82 6.00 0.60 6.60 68.42 68.40 963.84 224.35 3161.40

Page 37: Rate analsis Chapter No. 23 (Tube Wells)

37

Rate per MetreComposite

17

239.49

297.45

470.88

664.21

1588.00

1588.82

2287.18

2803.78

Page 38: Rate analsis Chapter No. 23 (Tube Wells)

38

Rate per MetreComposite

17

97.12

116.63

153.05

373.82

607.35

867.48

1291.43

Page 39: Rate analsis Chapter No. 23 (Tube Wells)

39

say

73.60

107.30

150.95

194.25

237.40

277.40

307.60

343.65

459.80

556.55

683.00

784.45

885.55

963.85

Page 40: Rate analsis Chapter No. 23 (Tube Wells)

40

Daily Labour Charges3" - 6" dia

Detail Unit Rate (British System) per day

Qty RatePer Unit (Rs.) Amount (Rs.)

Labour

Plumber 1.00 No 170.00 P. Day 170.00 Skilled Coolies 0.50 Nos 160.00 P. Day 80.00 Unskilled Coolies 0.75 Nos 140.00 P. Day 105.00 Chowkidar 1.00 No 75.00 P. Day 75.00

Total 430.00 Sundries 10.00 Percent 43.00 Total 473.00

Contractor's Profit & Overhea 20.00 Percent 94.60 Total 567.60

Daily Labour Charges P. Day Rs. 567.60 say 567.60

Page 41: Rate analsis Chapter No. 23 (Tube Wells)

41

Daily Labour Charges8" - 14" dia

Detail Unit Rate (British System) per day

Qty RatePer Unit (Rs.) Amount (Rs.) 20

Labour

Plumber 1.00 No 170.00 P. Day 170.00 Skilled Coolies 0.50 Nos 160.00 P. Day 80.00 Unskilled Coolies 1.50 Nos 140.00 P. Day 210.00 Chowkidar 1.00 No 75.00 P. Day 75.00

Total 535.00 Sundries 10.00 Percent 53.50 Total 588.50

Contractor's Profit & Overhea 20.00 Percent 117.70 Total 706.20

Contractor's Profit & Overheads Rs. 706.20 say 706.20

Page 42: Rate analsis Chapter No. 23 (Tube Wells)

42

Daily Labour Charges

Detail Unit Rate (British System) per day

Qty RatePer Unit (Rs.) Amount (Rs.)

Labour

Plumber 0.50 No 170.00 P. Day 85.00 Skilled Coolies 0.60 Nos 160.00 P. Day 96.00 Unskilled Coolies 1.00 Nos 140.00 P. Day 140.00 Chowkidar 1.00 No 75.00 P. Day 75.00

Total 396.00 Sundries 10.00 Percent 39.60 Total 435.60

Contractor's Profit & Overhea 20.00 Percent 87.12 Total 522.72

Daily Labour Charges P. Day Rs. 522.72 522.70

11/4" - 3" dia

Page 43: Rate analsis Chapter No. 23 (Tube Wells)

43

Daily Labour Charges

Detail Unit Rate (British System) per day

Qty RatePer Unit (Rs.) Amount (Rs.)

Labour

Foreman 1.00 No 170.00 P. Day 170.00 Skilled Coolies 2.00 Nos 160.00 P. Day 320.00 Unskilled Coolies 6.00 Nos 140.00 P. Day 840.00 Chowkidar 1.00 No 75.00 P. Day 75.00

Total 1,405.00 Sundries 10.00 Percent 140.50 Total 1,545.50

Contractor's Profit & Overhea 20.00 Percent 309.10 Total 1,854.60

Daily Labour Charges P. Day Rs. 1,854.60

Page 44: Rate analsis Chapter No. 23 (Tube Wells)

44

15- Providing and installing PVC blind pipe BSS Class "B" in Tube Well Bore Hole including Sockets and

Solvents and jointing with strainer etc. complete.

S. Dia of Rate Contractor's Total Daily Labour Labour Lowering Solvent Total Contractor's Total Rate per Rft Rate per MetreNo. Strainer Per Ft Profit Progress Charges Per Ft Charges Profit (8 + 11 Labour Composite Labour Composite

20.00 (3 + 4) Per Day (9 + 10) 20.00 + 12) (5 + 13)

Percent Percent

1 2 3 4 5 6 7 8 9 10 11 4 13 14 15 16 16

1 3" 36.59 1.83 38.42 200 930.60 4.65 1.84 1.00 2.84 0.14 7.64 7.65 46.05 25.04 151.06

2 4" 54.88 2.74 57.62 180 930.60 5.17 2.24 1.12 3.36 0.17 8.70 8.70 66.32 28.53 217.54

3 5" 76.22 3.81 80.03 180 930.60 5.17 2.60 1.12 3.72 0.19 9.08 9.10 89.11 29.77 292.27

4 6" 109.76 5.49 115.25 160 930.60 5.82 3.48 1.20 4.68 0.23 10.73 ### 125.98 35.20 413.21

5 8" 161.59 8.08 169.67 128 ### 8.71 3.76 2.08 5.84 0.29 14.85 ### 184.52 48.70 605.21

6 10" 253.05 12.65 265.70 128 ### 8.71 4.32 2.08 6.40 0.32 15.43 ### 281.14 50.62 922.13

7 12" 353.66 17.68 371.34 104 ### 10.73 5.00 2.64 7.64 0.38 18.75 ### 390.09 61.49 1279.50

8 14" 423.78 21.19 444.97 104 ### 10.73 5.00 2.64 7.64 0.38 18.75 ### 463.72 61.49 1520.99

Page 45: Rate analsis Chapter No. 23 (Tube Wells)

45

20

Contractor's Profit

Page 46: Rate analsis Chapter No. 23 (Tube Wells)

46

Daily Labour Charges

a) 3" to 6" (75mm to 150mm) dia.

Detail Unit Rate (British System) per day

Qty RatePer Unit (Rs.) Amount (Rs.)

Labour

Plumber 1.00 No 170.00 P. Day 170.00 Skilled Coolies 2.00 Nos 160.00 P. Day 320.00 Unskilled Coolies 1.00 No 140.00 P. Day 140.00 Chowkidar 1.00 No 75.00 P. Day 75.00

Total 705.00 Sundries 10.00 Percent 70.50 Total 775.50

Contractor's Profit 20.00 Percent 155.10 Total 930.60

Daily Labour Charges P. Day Rs. 930.60

Page 47: Rate analsis Chapter No. 23 (Tube Wells)

47

Daily Labour Charges

b) 8" to 14" (200mm to 350mm) dia.

20

Detail Unit Rate (British System) per day

Qty RatePer Unit (Rs.) Amount (Rs.)

Labour

Plumber 1.00 No 170.00 P. Day 170.00 Skilled Coolies 2.00 Nos 160.00 P. Day 320.00 Unskilled Coolies 2.00 Nos 140.00 P. Day 280.00 Chowkidar 1.00 No 75.00 P. Day 75.00

Total 845.00 Sundries 10.00 Percent 84.50 Total 929.50

Contractor's Profit 20.00 Percent 185.90 Total 1,115.40

Daily Labour Charges P. Day Rs. 1,115.40

Page 48: Rate analsis Chapter No. 23 (Tube Wells)

48

16- Providing and installing PVC blind pipe BSS Class "D" in Tube Well Bore Hole including Sockets and Solvents

and jointing with strainer etc. complete.

S. Dia of Rate Contractor's Total Daily Daily Labour Solvent Lowering Total Contractor's Total Rate per Rft Rate per MetreNo. Strainer Per Ft Profit Progress Charges Rate Charges Profit (8 + 11 Labour Composite Labour Composite

20.00 (3 + 4) Per Ft (9 + 10) 20.00 12) (5 + 13)

Percent Percent

1 2 3 4 5 6 7 8 9 10 11 4 13 14 15 16 17

1 1¼" 13.90 0.69 14.59 260 719.40 2.77 0.64 1.08 1.72 0.09 4.57 ### 19.17 15.00 62.87

2 1½" 17.77 0.89 18.66 260 719.40 2.77 0.72 1.16 1.88 0.09 4.74 ### 23.40 15.55 76.75

3 2" 26.83 1.34 28.17 240 719.40 3.00 0.76 1.20 1.96 0.10 5.06 ### 33.23 16.58 108.98

4 3" 56.40 2.82 59.22 200 719.40 3.60 1.00 1.84 2.84 0.14 6.58 ### 65.80 21.58 215.82

5 4" 92.99 4.65 97.64 180 930.60 5.17 1.12 2.24 3.36 0.17 8.70 ### 106.34 28.53 348.79

6 5" 140.24 7.01 147.25 180 930.60 5.17 1.28 2.60 3.88 0.19 9.24 ### 156.50 30.32 513.31

7 6" 201.22 10.06 211.28 160 930.60 5.82 1.60 3.48 5.08 0.25 11.15 ### 222.43 36.57 729.57

Page 49: Rate analsis Chapter No. 23 (Tube Wells)

49

20

Contractor's Profit

Page 50: Rate analsis Chapter No. 23 (Tube Wells)

50

Daily Labour Charges

a) 1¼" to 3" (32mm to 75mm) dia.

Detail Unit Rate (British System) per day

Qty RatePer Unit (Rs.) Amount (Rs.)

Labour

Plumber 1.00 No 170.00 P. Day 170.00 Skilled Coolies 1.00 No 160.00 P. Day 160.00 Unskilled Coolies 1.00 No 140.00 P. Day 140.00 Chowkidar 1.00 No 75.00 P. Day 75.00

Total 545.00 Sundries 10.00 Percent 54.50 Total 599.50

Contractor's Profit & Overhe 20.00 Percent 119.90 Total 719.40

Daily Labour Charges P. Day Rs. 719.40

Page 51: Rate analsis Chapter No. 23 (Tube Wells)

51

Daily Labour Charges

b) 4" to 6" (100mm to 150mm) dia.

20

Detail Unit Rate (British System) per day

Qty RatePer Unit (Rs.) Amount (Rs.)

Labour

Plumber 1.00 No 170.00 P. Day 170.00 Skilled Coolies 2.00 Nos 160.00 P. Day 320.00 Unskilled Coolies 1.00 No 140.00 P. Day 140.00 Chowkidar 1.00 No 75.00 P. Day 75.00

Total 705.00 Sundries 10.00 Percent 70.50 Total 775.50

Contractor's Profit & Overhea 20.00 Percent 155.10 Total 930.60

Daily Labour Charg Rs. 930.60

Page 52: Rate analsis Chapter No. 23 (Tube Wells)

52

DESCRIPTION OF ITEM NO 17: Testing and developing of tube well of size6" (150mm) inner dia and above Continuously.

i) Upto 1.5 cusacs Discharge.

Detail Unit Rate (British System) per Hours

Qty RatePer Unit (Rs.) Amount (Rs.)

Diesel Oil 2.50 gallon per hourfor 3 days (72 Hours). ### Ltr 10.00 P. Ltr 8,172.00 Mobil Oil 3 gallon (for 72 hrs.) 13.62 Ltr 79.00 P. Ltr 1,075.98 Grease 2.5 Lbs 1.13 Kg 25.00 P. Kg 28.25 C. Oil L.S. 20.00

Total 9,296.23 Contractor's Profit & Overhe 20.00 Percent 1,859.25 Total 11,155.48

Composite Rate Pe Rs. 11155.48 111.55 100

Say 111.55

Material (P. O. L.) For 100 Hours

Page 53: Rate analsis Chapter No. 23 (Tube Wells)

53

Item No. 17 Testing and developing of tube well of size6" innner dia and above Continuously.

ii) Upto 1.5 cusacs Discharge.

Detail Unit Rate (British System) per Hour

Qty RatePer Unit (Rs.) Amount (Rs.)

Diesel Oil 3 gallon per hourfor 3 days (72 Hours). ### Ltr 10.00 P. Ltr 9,806.40 Mobil Oil 4 gallon (for 72 hrs.) 18.16 Ltr 79.00 P. Ltr 1,434.64 Grease 3 Lbs (for 72 hrs.) 1.36 Kg 25.00 P. Kg 34.00 C. Oil L.S. 20.00

Total 11,295.04 Contractor's Profit & Overhe 20.00 Percent 2,259.01 Total 13,554.05

Composite Rate Pe Rs. 13554.05 135.54 100

Say 135.55

Material (P. O. L.) For 100 Hours

Page 54: Rate analsis Chapter No. 23 (Tube Wells)

54

DESCRIPTION OF ITEM NO 18: Shrouding with graded pea gravel 3/8" - 1/8"(10-3mm) around tube well in bore hole.

Detail Unit Rate (British System) per Cft

Qty RateAnalysis for 100 Cft Per Unit (Rs.) Amount (Rs.)

MaterialBajri 3/8" - 1/8" (10-3mm) Bajri 3/8" - 1/8" ( ### Cft 1500.00 % Cft 1,500.00 Wastage 5% Wastage 5% 75.00

Total 1,575.00 Contractor's Profit & Overhe 20.00 Percent 315.00 Total 1,890.00

LabourWashing and Pouring bagSkilled Coolies 3.30 Nos 160.00 P. Day 528.00 Unskilled Coolies 1.00 No 140.00 P. Day 140.00

Total 668.00 Sundries 10.00 Percent 66.80 Total 734.80

Contractor's Profit & Overhe 20.00 Percent 146.96 Total 881.76

Labour Rate Per Cf Rs. 8.82 8.80 Labour Rate Per C Rs. 310.82 310.80

Composite Rate Per Rs. 27.70 27.70 Composite Rate Pe Rs. 978.36 978.35

Page 55: Rate analsis Chapter No. 23 (Tube Wells)

55

19- Laying, cutting, jointing, testing and disinfecting cast iron pipe line in trenches with spigot and socket

caulked lead joint, including cost of materials, such as lead, yarn, etc. complete in all respects.

S. Internal Weight of Weight of Carriage of Lowering Cutting Pluging Testing Jointing Total Composite CompositeNo. dia of 18' length 100' length 100' pipe into ends with and with lead charges for rate Per Ft rate Per

pipe of pipe in of pipe in from field trenches chipping, temporary disinfecting joint 100' (30 M) Metre

lbs ton store to site strin- ging & fini- shing wooden (5 + 6 + 7 +

lead four laying to surface to plug + 8 + 9 +

chain @ Rs. correct uniform 10)

48.27 alignment finish

Tons and grade

1 2 3 4 5 6 7 8 9 10 11 12 13

1 3" 170.00 0.429 4.07 148.50 37.13 4.99 46.44 1151.21 1392.33 13.92 45.67

2 4" 190.00 0.48 4.55 148.50 32.27 6.72 50.03 1170.61 1412.68 14.13 46.34

3 5" 324.00 0.82 7.76 198.00 74.25 9.36 53.71 1829.17 2172.25 21.72 71.25

4 6" 410.00 1.03 9.82 198.00 99.00 12.73 59.41 1742.61 2121.57 21.22 69.59

5 8" 591.00 1.49 14.16 264.00 148.50 18.80 68.61 2337.88 2851.95 28.52 93.54

6 10" 794.00 2.00 19.02 339.45 198.00 35.31 81.87 3960.25 4633.90 46.34 151.99

7 12" 1018.00 2.57 24.38 396.00 237.60 49.74 91.79 4646.31 5445.82 54.46 178.62

8 15" 1389.00 3.50 33.27 475.20 270.00 92.26 119.75 6044.72 7035.21 70.35 230.75

9 18" 1834.00 4.62 43.93 594.00 297.00 131.94 131.01 8060.91 9258.79 92.59 303.69

Page 56: Rate analsis Chapter No. 23 (Tube Wells)

56

19 - a - Lowering into trenches, stringing and laying C.I. pipe line to correct alignment and gradient.

S. Internal L A B O U RNo. dia Daily Daily Amount per Rate 100 ft

Progress Charges 100 ft Analysis for daily charges

1 3" 400 594.00 148.50 148.50 Plumber 1 No 170.00 170.00

2 4" 400 594.00 148.50 148.50 Coolies 2 Nos 140.00 280.00

3 5" 300 594.00 198.00 198.00 Total 450.00

4 6" 300 594.00 198.00 198.00 Sundries 10.00 Percent 45.00

5 8" 225 594.00 264.00 264.00 Total 20.00 495.00

6 10" 175 594.00 339.43 339.45 Contractor's Profit & Overheads 20.00 Percent 99.00

7 12" 150 594.00 396.00 396.00 Total 594.00

8 15" 125 594.00 475.20 475.20

9 18" 100 594.00 594.00 594.00

Page 57: Rate analsis Chapter No. 23 (Tube Wells)

57

19 - Cutting cast iron pipe, chipping & finishing the face to uniform finish = Cut at every 200ft (60 M)For 200' (60 M)

S. I/D Labour for Cutting & finishing Rate per

No. of No. of Daily Rate per 100 ft

Pipe cut P. day Charges 200 ft per cut

per cut

1 2 3 4 5 6

1 3" 8.00 594.00 74.25 37.13 Analysis of Daily Charges

2 4" 6.00 387.20 64.53 32.27 LABOUR

3 5" 4.00 594.00 148.50 74.25 Pipe fitter 1 No 170.00 170.00

4 6" 3.00 594.00 198.00 99.00 Unskilled Cooly 2 Nos 140.00 280.00

5 8" 2.00 594.00 297.00 148.50 Total 450.00

6 10" 1.50 594.00 396.00 198.00 Sundries 10.00 Percent 45.00

7 12" 1.25 594.00 475.20 237.60 Total 495.00

8 15" 1.10 594.00 540.00 270.00 Contractor's Profit & Overheads 20.00 Percent 99.00

9 18" 1.00 594.00 594.00 297.00 594.00

Page 58: Rate analsis Chapter No. 23 (Tube Wells)

58

19 - c Providing and fixing temporary wooden tapered plug of hard wood to each end of pipe line.Assume for 500 ft. Rate for 100 ft.

S. Size PLUG LABOUR FOR MAKING PLUG LABOUR FOR FIXING Grand Rate for

No. of Area of Length Content Rate Per Amount Daily Daily Amount L. S. Sundries Total Total 100'

plug plug in Cft Progress Charges 10.00 for 500'

Cft (5 X 6) in No. (9 / 8) (11+12) (15+10

+ 7)

1 2 3 4 5 6 7 8 9 10 11 12 13 16 17 18

1 3" 0.50 0.02 300.00 6.00 34.00 620.40 18.25 0.60 0.06 0.66 24.94 4.99 Rate of Hard Wood

2 4" 0.50 0.04 300.00 12.00 30.00 620.40 20.68 0.80 0.08 0.88 33.60 6.72

3 5" 0.50 0.07 300.00 21.00 25.00 620.40 24.82 0.84 0.08 0.92 46.79 9.36 250.00 250.00

4 6" 0.50 0.10 300.00 30.00 19.00 620.40 32.65 0.88 0.09 0.97 63.67 12.73 20.00 50.00

5 8" 0.50 0.17 300.00 51.00 15.00 620.40 41.36 1.40 0.14 1.54 93.98 18.80 Total 300.00

6 10" 0.75 0.41 300.00 123.00 12.00 620.40 51.70 1.60 0.16 1.76 176.55 35.31 Daily Charges

7 12" 0.75 0.59 300.00 177.00 9.00 620.40 68.93 2.40 0.24 2.64 248.71 49.74 300.00 300.00

8 15" 1.00 1.23 300.00 369.00 7.00 620.40 88.63 3.20 0.32 3.52 461.32 92.26 170.00 170.00

9 18" 1.00 1.77 300.00 531.00 5.00 620.40 124.08 4.00 0.40 4.40 659.70 131.94 Total 470.00

Sundries 10.00 47.00

Total 517.00

20.00 103.40

Total 620.40

9x(3)2

4x144

9x(4)2

4x144

9x(5)2

4x144

Hard Wood 1 Cft @ Rs.

9x(6)2

4x144

Contractor's Profit & Overheads

9x(8)2

4x144

9x(10)2

4x144

9x(12)2

4x144Carpenter 1

9x(15)2

4x144Turner 1

9x(18)2

4x144

Contractor's Profit

Page 59: Rate analsis Chapter No. 23 (Tube Wells)

59

19 - d Testing and disinfecting C.I. Pipe. Assume for 1000' (300 M) Rate for 100 ft.

S. I/D of Volume Amount Disin- Amount Hire Total Contra- Total LABOUR Rate Charges

No. pipe in of Water @ Rs fecting @ Rs. Charges ctor's Plugging Labour for Total for 200 Rft

Inch required 12.00 Agent 20.00 of testing (7 + 6 Profit (8 + 9) of Pipe testing &

in Gallon Per ‰ Lbs/Kg Per Lbs/Kg operatus + 4) 20.00 disinfecting (11 + 12)

Gallons Percent

1 2 3 4 5 6 7 8 9 10 11 12 13 16

1 3" 310.00 3.72 0.50 10.00 100.00 113.72 5.69 119.41 48.00 297.00 345.00 Mechanic 1 No. 170.00 170.00

2 4" 720.00 8.64 1.20 24.00 100.00 132.64 6.63 139.27 64.00 297.00 361.00 Coolies 2 Nos 140.00 280.00

3 5" 850.00 10.20 1.40 28.00 100.00 138.20 6.91 145.11 95.00 297.00 392.00 Total 450.00

4 6" 1830.00 21.96 2.00 40.00 100.00 161.96 8.10 170.06 127.00 297.00 424.00 Sundries 10.00 Percent 45.00

5 8" 2180.00 26.16 3.65 73.00 100.00 199.16 9.96 209.12 180.00 297.00 477.00 Total 495.00

6 10" 3410.00 40.92 5.70 114.00 100.00 254.92 12.75 267.67 254.00 297.00 551.00 Contractor's 20.00 Percent 99.00

7 12" 4910.00 58.92 8.00 160.00 100.00 318.92 15.95 334.87 286.00 297.00 583.00 Total 594.00

8 15" 8730.00 104.76 14.50 290.00 100.00 494.76 24.74 519.50 381.00 297.00 678.00 297.00

9 18" 11000.00 132.00 18.50 370.00 100.00 602.00 30.10 632.10 381.00 297.00 678.00

Rate per 100 Rft

Page 60: Rate analsis Chapter No. 23 (Tube Wells)

60

19 - e Jointing cast iron pipe line in trenches with spigot and socket. Caulked lead joints

including cost of material such as lead, yarn etc., complete in all respect.

Length of pipe 18' (6 M) P. Joint.Detail per joint = Unit of Rate 100'S. I/D of Material Per Joint Fuel Total Contra- Total Labour Per JointComposite Composite Composite Composite

No. pipe in Lead Rate Amount Yarn Rate P. Amount ctor's Material No. of rate for 18' rate for rate for rate for

Inch Lbs/Kg Lbs/Kg 3 x 4 Lbs Lbs 6 x 7 5 + 8 Profit Per Joint Days length in 100' length Rft Metre

+ 9 20.00 10 + 11 P. Joint 16 x 100

Percent 12 + 15 18

1 2 3 4 5 6 7 8 9 10 11 12 13 16 17 18 181 3" 4.10 16.00 65.60 0.25 16.00 4.00 4.00 73.60 3.68 77.28 0.15 207.22 1,151.21 11.51 37.76 2 4" 5.20 16.00 83.20 0.38 16.00 6.08 5.00 94.28 4.71 98.99 0.19 210.71 1,170.61 11.71 38.40 3 5" 6.30 16.00 100.80 0.44 16.00 7.04 6.00 113.84 5.69 121.35 0.24 329.25 1,829.17 18.29 60.00 4 6" 7.90 16.00 126.40 0.44 16.00 7.04 7.40 140.84 7.04 147.88 0.28 313.67 1,742.61 17.43 57.16 5 8" 10.80 16.00 132.80 0.63 16.00 10.08 10.40 153.28 7.66 160.94 0.30 420.82 2,337.88 23.38 76.68 6 10" 15.00 16.00 240.00 0.75 16.00 12.00 14.40 266.40 13.32 279.72 0.50 712.85 3,960.25 39.60 129.90 7 12" 17.30 16.00 276.80 1.06 16.00 16.96 16.00 309.76 15.49 325.25 0.59 836.34 4,646.31 46.46 152.40 8 15" 23.00 16.00 368.00 1.50 16.00 24.00 17.00 409.00 20.45 429.70 0.76 1088.05 6,044.72 60.45 198.27 9 18" 31.50 16.00 504.00 2.07 16.00 33.12 28.00 565.12 28.26 593.38 0.99 1450.96 8,060.91 80.61 264.40

Daily ChargesPlumber 1 No 170.00 170.00 Sundires 75.00Cooly 3 Nos 140.00 420.00 Total 825.00Assistant Plumber (skilled cooly) 1 No 160.00 160.00 Contractor's Profit & Overheads 41.25

Total 750.00 Total 866.25

Page 61: Rate analsis Chapter No. 23 (Tube Wells)

61

20- Laying cutting, jointing, testing and disinfecting cast iron pipe line in trenches with flanged and flanged

complete in all respects.

S. Internal Weight of Weight Carriage of Lowering into Cutting ends Pluging Testing and Jointing Total charges Composite CompositeNo. dia of 12' length of 100' 100' pipe trenches strin- chipping, fini- with disinfecting with lead for 100' rate per Ft rate per

pipe of pipe in length from field storeging & laying to shing surface temporary joint (30 M) Metre

lbs of pipe to site lead correct alignment to uniform wooden plug (5 + 6 + 7 +

in ton. four chain Ton and grade finish 8 + 9 + 10)

@ of Rs.

48.27

1 2 3 4 5 6 7 8 9 10 11 12 13 say say

1 3" - 0.50 4.75 148.50 37.13 4.99 46.44 576.78 818.58 8.19 26.85 8.20 26.85 2 4" - 0.65 6.18 148.50 49.50 6.52 50.03 636.45 897.17 8.97 29.43 8.95 29.45 3 5" - 0.85 8.08 198.00 74.25 9.01 53.71 1014.02 1357.07 13.57 44.51 13.55 44.50 4 6" - 1.05 9.98 198.00 99.00 12.23 59.41 1093.26 1471.88 14.72 48.28 14.70 48.30 5 8" - 1.49 14.16 264.00 148.50 17.95 68.61 1254.97 1768.19 17.68 58.00 17.70 58.00 6 10" - 2.05 19.48 339.45 198.00 33.26 81.87 1834.82 2506.87 25.07 82.23 25.05 82.25 7 12" - 2.60 24.71 396.00 237.60 46.79 91.79 2068.84 2865.73 28.66 94.00 28.65 94.00 8 15" - 3.55 33.73 475.20 270.00 86.11 119.75 2861.47 3846.27 38.46 126.16 38.45 126.15 9 18" - 4.70 44.66 594.00 297.00 123.09 131.01 3470.08 4659.84 46.60 152.84 46.60 152.85

20 - a Lowering into trenches, stringing and laying C.I. pipe line to correct alignment and gradient.

S. Internal L A B O U RNo. dia Daily Daily Amount per Rate 100 ft

Progress Charges 100 ft Analysis for daily charges

1 3" 400 594.00 148.50 148.50 Plumber 1 No 170.00 170.00 2 4" 400 594.00 148.50 148.50 Coolies 2 Nos 140.00 280.00 3 5" 300 594.00 198.00 198.00 Total 450.00

4 6" 300 594.00 198.00 198.00 Sundries 10.00 Percent 45.00 5 8" 225 594.00 264.00 264.00 Total 495.00

6 10" 175 594.00 339.43 339.45 Contractor's Profit & Overheads 20.00 Percent 99.00 7 12" 150 594.00 396.00 396.00 Total 594.00

8 15" 125 594.00 475.20 475.20 9 18" 100 594.00 594.00 594.00

Page 62: Rate analsis Chapter No. 23 (Tube Wells)

62

20 - b Cutting cast iron pipe, chipping & finishing the face to uniform finish = Cut at every 200ft (60 M)For 200' (60 M)

S. I/D Labour for Cutting & finishing Rate per

No. of No. of Daily Rate per 100 ft

Pipe cut P. day Charges 200 ft per cut

per cut

1 2 3 4 5 61 3" 8.00 594.00 74.25 37.13 Analysis of Daily Charges2 4" 6.00 594.00 99.00 49.50 LABOUR3 5" 4.00 594.00 148.50 74.25 Pipe fitter 1 No 170.00 170.004 6" 3.00 594.00 198.00 99.00 Unskilled Cooly 2 Nos 140.00 280.005 8" 2.00 594.00 297.00 148.50 Total 450.00

6 10" 1.50 594.00 396.00 198.00 Sundries 10.00 Percent 45.00 7 12" 1.25 594.00 475.20 237.60 Total 495.00

8 15" 1.10 594.00 540.00 270.00 Contractor's Profit & Overheads 20.00 Percent 99.00 9 18" 1.00 594.00 594.00 297.00 594.00

20 - c - Providing and fixing temporary wooden tapered plug of hard wood to each end of pipe line.Detail 500' Rate for 100'

S. Size PLUG LABOUR FOR MAKING PLUG LABOUR FOR FIXING Grand Rate for

No. of Area of Length Contant Rate Per Amount Daily Daily Amount L. S. Sundries Total Contra- Total Total 100'

plug plug in Cft Progress Charges 10.00 ctor's for 500'

Cft (5 X 6) in No. (9 / 8) (11+12) profit (13+14) (15+10

20.00 + 7)

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18

1 3" 0.50 0.02 300.00 6.00 34.00 620.40 18.25 0.60 0.06 0.66 0.03 0.69 24.94 4.99 Daily Charges

2 4" 0.50 0.04 275.00 11.00 30.00 620.40 20.68 0.80 0.08 0.88 0.04 0.92 32.60 6.52

3 5" 0.50 0.07 275.00 19.25 25.00 620.40 24.82 0.84 0.08 0.92 0.05 0.97 45.04 9.01 250.00 250.00

4 6" 0.50 0.10 275.00 27.50 19.00 620.40 32.65 0.88 0.09 0.97 0.05 1.02 61.17 12.23 Contractor's Profit & Overheads 20.00 50.00

5 8" 0.50 0.17 275.00 46.75 15.00 620.40 41.36 1.40 0.14 1.54 0.08 1.62 89.73 17.95 Total 300.00

6 10" 0.75 0.41 275.00 112.75 12.00 620.40 51.70 1.60 0.16 1.76 0.09 1.85 166.30 33.26

7 12" 0.75 0.59 275.00 162.25 9.00 620.40 68.93 2.40 0.24 2.64 0.13 2.77 233.96 46.79 Carpenter 1 No. 300.00 300.00

8 15" 1.00 1.23 275.00 338.25 7.00 620.40 88.63 3.20 0.32 3.52 0.18 3.70 430.57 86.11 Turner 1 No. 170.00 170.00

9 18" 1.00 1.77 275.00 486.75 5.00 620.40 124.08 4.00 0.40 4.40 0.22 4.62 615.45 123.09 Total 470.00

Sundries 10.00 Percent 47.00 Total 517.00

20.00 Percent 103.40 Total 620.40

ãx(3)2

4x144

ãx(4)2

4x144

ãx(5)2

4x144Hard Wood Cft @ Rs.

ãx(6)2

4x144

ãx(8)2

4x144

ãx(10)2

4x144

ãx(12)2

4x144

ãx(15)2

4x144

ãx(18)2

4x144

Contractor's Profit &

Overheads

Page 63: Rate analsis Chapter No. 23 (Tube Wells)

63

20 - d - Testing and disinfecting C.I. Pipe.Assume for 1000' (300 M) Rate for 100' Rate for 10'

S. I/D of Volume Amount Disin- Amount Hire Total Contra- Total LABOUR Composite Rate for Rate Charges

No. pipe in of Water @ Rs fecting @ Rs Charges ctor's Plugging Labour for Total for 1000 Rft 100' for 200 Rft

Inch required 12.00 Agent 20.00 of testing (7 + 6 Profit (8 + 9) of Pipe testing &

in Gallon Per ‰ Lbs/Kg Per Lbs/Kg operatus + 4) 20.00 disinfecting (11+12) (10 + 13)

Gallons Percent

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 161 3" 310.00 3.72 0.50 10.00 100.00 113.72 5.69 119.41 48.00 297.00 345.00 464.41 46.44 Mechanic 1 No. 170.00 170.00

2 4" 720.00 8.64 1.20 24.00 100.00 132.64 6.63 139.27 64.00 297.00 361.00 500.27 50.03 Coolies 2 Nos 140.00 280.00

3 5" 850.00 10.20 1.40 28.00 100.00 138.20 6.91 145.11 95.00 297.00 392.00 537.11 53.71 Total 450.00

4 6" 1830.00 21.96 2.00 40.00 100.00 161.96 8.10 170.06 127.00 297.00 424.00 594.06 59.41 Sundries 10.00 Percent 45.00 5 8" 2180.00 26.16 3.65 73.00 100.00 199.16 9.96 209.12 180.00 297.00 477.00 686.12 68.61 Total 495.00

6 10" 3410.00 40.92 5.70 114.00 100.00 254.92 12.75 267.67 254.00 297.00 551.00 818.67 81.87 20.00 Percent 99.00 7 12" 4910.00 58.92 8.00 160.00 100.00 318.92 15.95 334.87 286.00 297.00 583.00 917.87 91.79 Total 594.00

8 15" 8730.00 104.76 14.50 290.00 100.00 494.76 24.74 519.50 381.00 297.00 678.00 1197.50 119.75 297.00

9 18" 11000.00 132.00 18.50 370.00 100.00 602.00 30.10 632.10 381.00 297.00 678.00 1310.10 131.01

20 - e Laying, cutting, jointing, testing & disinfecting C.I. pipe line in trenches with flanged &

flanged joint complete in all respects.

Length of pipe 12' (4 M). Rate for 100'S. I/D of Bolts & Nuts Per Joint Rubber insertion 1/8" Total Contra- Total Labour Composite Rate Per Composite Composite

No. pipe Size No Rate Amount thick per joint. ctor's Material No. of Daily Amount rate 100' pipe rate per rate per

Dia Length of 5 x 6 Weight in Amount 7 + 9 Profit P. Joint Joints in Charges P. Joint length Ft Metre

Bolts Lbs/kg 7 x 8 20.00 10 + 11 One Day 14 / 13 for 12' 16 x 100

Percent 12

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 181 3" 5/8" 2½" 4.00 6.00 24.00 0.46 10.92 34.92 1.75 36.67 11.00 358.05 32.55 69.22 576.78 5.77 18.922 4" 5/8" 2½" 4.00 6.00 24.00 0.61 14.64 38.64 1.93 40.57 10.00 358.05 35.81 76.38 636.45 6.36 20.883 5" 5/8" 3" 6.00 9.00 54.00 1.00 24.00 78.00 3.90 81.90 9.00 358.05 39.78 121.68 1014.02 10.14 33.264 6" 5/8" 3" 6.00 9.00 54.00 1.18 28.32 82.32 4.12 86.44 8.00 358.05 44.76 131.19 1093.26 10.93 35.865 8" 3/4" 3" 8.00 9.00 72.00 1.20 28.80 100.80 5.04 105.84 8.00 358.05 44.76 150.60 1254.97 12.55 41.166 10" 3/4" 3" 12.00 9.00 108.00 1.86 44.86 152.86 7.64 160.50 6.00 358.05 59.68 220.18 1834.82 18.35 60.187 12" 3/4" 3" 12.00 9.00 108.00 2.50 60.24 168.24 8.41 176.65 5.00 358.05 71.61 248.26 2068.84 20.69 67.868 15" 7/8" 4" 12.00 12.00 144.00 2.84 69.36 213.36 10.67 224.03 3.00 358.05 119.35 343.38 2861.47 28.61 93.869 18" 7/8" 4" 12.00 12.00 144.00 3.42 82.08 226.08 11.30 237.38 2.00 358.05 179.03 416.41 3470.08 34.70 113.82

Daily ChargesPlumber 1 No 170.00 Sundires 10.00 Percent 31.00Cooly 1 No 140.00 Total 341.00

310.00 Contractor's Profit & Overheads 20.00 Percent 17.05Total 358.05

Contractor's Profit & Overheads

Rate per 100 Rft

Page 64: Rate analsis Chapter No. 23 (Tube Wells)

64

21- Laying cutting, jointing, testing and disinfecting cast iron pipe line in trenches with Tyton joints,

complete in all respects.

S. Internal Weight of Weight Carriage of Lowering into Cutting ends Pluging Testing and Jointing Total charges Composite CompositeNo. dia of 12' length of 100' 100' pipe trenches strin- chipping, fini- with disinfecting with lead for 100' rate per Ft rate per

pipe of pipe in length from field store ging & laying to shing surface temporary joint (30 M) Metre

lbs of pipe to site lead correct alignment to uniform wooden plug (5 + 6 + 7 +

in ton. four chain Ton and grade finish 8 + 9 + 10)

@ of Rs.

48.27

1 2 3 4 5 6 7 8 9 10 11 12 13 say say

1 3" - 0.47 4.47 148.50 37.13 3.76 43.97 268.33 506.15 5.06 16.60 5.05 16.60 2 4" - 0.48 4.56 148.50 49.50 5.13 47.55 354.67 609.91 6.10 20.00 6.10 20.00 3 5" - 0.80 7.60 198.00 74.25 7.34 51.24 431.67 770.09 7.70 25.26 7.70 25.25 4 6" - 1.02 9.69 198.00 99.00 10.03 56.93 511.00 884.66 8.85 29.02 8.85 29.00 5 8" - 1.47 13.97 264.00 148.50 15.16 66.14 688.33 1196.10 11.96 39.23 11.95 39.25 6 10" - 1.97 18.72 339.45 198.00 29.78 79.39 855.17 1520.50 15.21 49.87 15.20 49.85 7 12" - 2.52 23.95 396.00 237.60 42.15 89.31 1046.50 1835.51 18.36 60.20 18.35 60.20 8 15" - 3.45 32.78 475.20 270.00 80.14 117.27 2020.67 2996.07 29.96 98.27 29.95 98.25 9 18" - 4.55 43.24 594.00 297.00 114.73 128.54 2423.17 3600.67 36.01 118.10 36.00 118.10

21 - a Lowering into trenches, stringing and laying C.I. pipe line to correct alignment and gradient.

S. Internal L A B O U RNo. dia Daily Daily Amount per Rate 100 ft

Progress Charges 100 ft Analysis for daily charges

1 3" 400 594.00 148.50 148.50 Plumber 1 No 170.00 170.00

2 4" 400 594.00 148.50 148.50 Coolies 2 Nos 140.00 280.00

3 5" 300 594.00 198.00 198.00 Total 450.00

4 6" 300 594.00 198.00 198.00 Sundries 10.00 Percent 45.00 5 8" 225 594.00 264.00 264.00 Total 495.00

6 10" 175 594.00 339.43 339.45 Contractor's Profit & Overhe 20.00 Percent 99.00

7 12" 150 594.00 396.00 396.00 Total 594.00

8 15" 125 594.00 475.20 475.20

Page 65: Rate analsis Chapter No. 23 (Tube Wells)

65

9 18" 100 594.00 594.00 594.00

Page 66: Rate analsis Chapter No. 23 (Tube Wells)

66

21 - b Cutting cast iron pipe, chipping & finishing the face to uniform finish = Cut at every 200ft (60 M)For 200' (60 M)

S. I/D Labour for Cutting & finishing Rate per

No. of No. of Daily Rate per 100 ft

Pipe cut P. day Charges 200 ft per cut

per cut

1 2 3 4 5 61 3" 8.00 594.00 74.25 37.13 Analysis of Daily Charges2 4" 6.00 594.00 99.00 49.50 LABOUR3 5" 4.00 594.00 148.50 74.25 Pipe fitter 1 No 170.00 170.004 6" 3.00 594.00 198.00 99.00 Unskilled Cooly 2 Nos 140.00 280.005 8" 2.00 594.00 297.00 148.50 Total 450.00

6 10" 1.50 594.00 396.00 198.00 Sundries 10.00 Percent 45.00 7 12" 1.25 594.00 475.20 237.60 Total 495.00

8 15" 1.10 594.00 540.00 270.00 Contractor's Profit & Overheads 20.00 Percent 99.00 9 18" 1.00 594.00 594.00 297.00 594.00

21 - c - Providing and fixing temporary wooden tapered plug of hard wood to each end of pipe line.

S. Size PLUG LABOUR FOR MAKING PLUG LABOUR FOR FIXING Grand

No. of Area of Length Contant Rate Per Amount Daily Daily Amount L. S. Sundries Total Contra- Total Total

plug plug in Cft Progress Charges 10.00 ctor's for 500'

Cft (5 X 6) in No. (9 / 8) (11+12) profit (13+14) (15+10

20.00 + 7)

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

1 3" 0.50 0.02 300.00 6.00 34.00 411.40 12.10 0.60 0.06 0.66 0.03 0.69 18.79

2 4" 0.50 0.04 275.00 11.00 30.00 411.40 13.71 0.80 0.08 0.88 0.04 0.92 25.64

3 5" 0.50 0.07 275.00 19.25 25.00 411.40 16.46 0.84 0.08 0.92 0.05 0.97 36.68

4 6" 0.50 0.10 275.00 27.50 19.00 411.40 21.65 0.88 0.09 0.97 0.05 1.02 50.17

5 8" 0.50 0.17 275.00 46.75 15.00 411.40 27.43 1.40 0.14 1.54 0.08 1.62 75.79

ãx(3)2

4x144

ãx(4)2

4x144

ãx(5)2

4x144

ãx(6)2

4x144

ãx(8)2

4x144

Page 67: Rate analsis Chapter No. 23 (Tube Wells)

67

6 10" 0.75 0.41 275.00 112.75 12.00 411.40 34.28 1.60 0.16 1.76 0.09 1.85 148.88

7 12" 0.75 0.59 275.00 162.25 9.00 411.40 45.71 2.40 0.24 2.64 0.13 2.77 210.73

8 15" 1.00 1.23 275.00 338.25 7.00 411.40 58.77 3.20 0.32 3.52 0.18 3.70 400.72

9 18" 1.00 1.77 275.00 486.75 5.00 411.40 82.28 4.00 0.40 4.40 0.22 4.62 573.65

ãx(10)2

4x144

ãx(12)2

4x144

ãx(15)2

4x144

ãx(18)2

4x144

Page 68: Rate analsis Chapter No. 23 (Tube Wells)

68

20 - d - Testing and disinfecting C.I. Pipe.Assume for 1000' (300 M)

S. I/D of Volume Amount Disin- Amount Hire Total Contra- Total LABOUR Composite Rate for Rate Charges

No. pipe in of Water @ Rs fecting @ Rs. Charges ctor's Plugging Labour for Total for 1000 Rft 100' for 200 Rft

Inch required 12.00 Agent 20.00 of testing (7 + 6 Profit (8 + 9) of Pipe testing &

in Gallon Per ‰ Lbs/Kg Per Lbs/Kg operatus + 4) 20.00 disinfecting (11+12) (10 + 13)

Gallons Percent

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 161 3" 310.00 3.72 0.50 10.00 100.00 113.72 5.69 119.41 48.00 272.25 320.25 439.66 43.97 Mechanic

2 4" 720.00 8.64 1.20 24.00 100.00 132.64 6.63 139.27 64.00 272.25 336.25 475.52 47.55 Coolies

3 5" 850.00 10.20 1.40 28.00 100.00 138.20 6.91 145.11 95.00 272.25 367.25 512.36 51.244 6" 1830.00 21.96 2.00 40.00 100.00 161.96 8.10 170.06 127.00 272.25 399.25 569.31 56.93 Sundries

5 8" 2180.00 26.16 3.65 73.00 100.00 199.16 9.96 209.12 180.00 272.25 452.25 661.37 66.14

6 10" 3410.00 40.92 5.70 114.00 100.00 254.92 12.75 267.67 254.00 272.25 526.25 793.92 79.39

7 12" 4910.00 58.92 8.00 160.00 100.00 318.92 15.95 334.87 286.00 272.25 558.25 893.12 89.31

8 15" 8730.00 104.76 14.50 290.00 100.00 494.76 24.74 519.50 381.00 272.25 653.25 1172.75 117.279 18" 11000.00 132.00 18.50 370.00 100.00 602.00 30.10 632.10 381.00 272.25 653.25 1285.35 128.54

21 - e - Laying, cutting, jointing, testing & disinfecting cast iron pipe line in trenches with tyton joints

complete in all respect.

Length of pipe 18' (5.4 M). Rate for 100'S. I/D of Cost of Ring Total Composite

No. pipe in Rate Amount Contra ctor's Total Material rate per

Inche of ring Profit Material for 100' 100 ft

20.00 P. joint 6 x 100

Percent 18

1 2 3 4 5 6 7 81 3" 46.00 2.30 48.30 268.33 268.332 4" 60.80 3.04 63.84 354.67 354.673 5" 74.00 3.70 77.70 431.67 431.674 6" 87.60 4.38 91.98 511.00 511.005 8" 118.00 5.90 123.90 688.33 688.33

Contractor's Profit & Overheads

Rate per 100 Rft

Page 69: Rate analsis Chapter No. 23 (Tube Wells)

69

6 10" 146.60 7.33 153.93 855.17 855.177 12" 179.40 8.97 188.37 1046.50 1046.508 15" 346.40 17.32 363.72 2020.67 2020.679 18" 415.40 20.77 436.17 2423.17 2423.17

Page 70: Rate analsis Chapter No. 23 (Tube Wells)

70

S. Internal Weight of 100' Carriage of Lowering into Cutting ends Pluging Testing and Jointing Total charges Composite CompositeNo. dia of length of 100' pipe trenches strin- chepping, fini- with disinfecting with rubber for 100' rate Per Ft rate Per

pipe pipe in ton. from field store ging & laying to shing surface temporary ring (30 M) Metre

to site lead correctalignment to uniform wooden plug (4 + 5 + 6 +

four chain @ and grade finish 7 + 8 +9)

Rs. 32/5 Tons

1 2 3 4 5 6 7 8 9 10 11 121 3" 0.47 3.00 96.80 24.20 3.67 36.67 281.60 445.94 4.46 14.632 4" 0.48 3.07 96.80 32.27 5.14 40.35 372.56 550.19 5.50 18.053 5" 0.80 5.12 129.06 48.40 7.59 44.06 453.68 687.91 6.88 22.564 6" 1.02 6.53 129.06 84.53 10.04 49.88 535.88 815.92 8.16 26.765 8" 1.47 9.41 172.09 96.80 15.17 59.27 720.44 1073.18 10.73 35.206 10" 1.97 12.61 221.26 129.07 29.79 72.80 896.08 1361.61 13.62 44.667 12" 2.52 16.13 258.13 154.88 42.17 83.05 1096.16 1650.52 16.51 54.148 15" 3.45 22.08 309.76 176.00 89.53 111.88 2116.96 2826.21 28.26 92.709 18" 4.55 29.12 387.20 193.60 114.77 123.68 2538.60 3386.97 33.87 111.09

Page 71: Rate analsis Chapter No. 23 (Tube Wells)

71

21 - a - Lowering into trenches, stringing and laying C.I. pipe line to correct alignment and gradient.

S. Internal L A B O U RNo. dia Daily Daily Amount per Rate 100 ft

Progress Charges 100 ft Analysis for daily charges

1 3" 400 363.00 90.75 90.75 Plumber 1 No 170.00 160.002 4" 400 363.00 90.75 90.75 Coolies 2 Nos 140.00 140.003 5" 300 363.00 121.00 121.00 Total 300.00

4 6" 300 363.00 121.00 121.00 Sundries 10.00 Percent 30.00 5 8" 225 363.00 161.00 161.00 Total 330.00

6 10" 175 363.00 207.00 207.00 Contractor's Profit & Overhe 20.00 Percent 66.00 7 12" 150 363.00 242.00 242.00 Total 396.00

8 15" 125 363.00 290.00 290.009 18" 100 363.00 363.00 363.00

Page 72: Rate analsis Chapter No. 23 (Tube Wells)

72

21 - b Cutting cast iron pipe, chipping & finishing the face to uniform finish = Cut at every 200ft (60 M)For 200' (60 M)

S. I/D Labour for Cutting & finishing Rate per

No. of No. of Daily Rate per 100 ft

Pipe cut P. day Charges 200 ft per cut

per cut

1 2 3 4 5 6

1 3" 8.00 387.20 48.40 24.20 Analysis of Daily Charges

2 4" 6.00 387.20 64.53 32.27 LABOUR

3 5" 4.00 387.20 96.80 48.40 Pipe fitter 1 No 170.00 170.00

4 6" 3.00 387.20 129.07 64.53 Unskilled Cooly 2 Nos 140.00 280.00

5 8" 2.00 387.20 193.60 96.80 Total 450.00

6 10" 1.50 387.20 258.13 129.07 Sundries 10.00 Percent 45.00

7 12" 1.25 387.20 309.76 154.88 Total 495.00

8 15" 1.10 387.20 352.00 176.00 Contractor's Profit & Overheads 20.00 Percent 99.00

9 18" 1.00 387.20 387.20 193.60 594.00

Page 73: Rate analsis Chapter No. 23 (Tube Wells)

73

Detail 500' Rate for 100'Rate for

100'

17 18

3.76 Daily Charges

5.13

7.34 250.00 250.00

10.03 Contractor's Profit & Ove 20.00 50.00

15.16 Total 300.00

Hard Wood Cft @ Rs.

Page 74: Rate analsis Chapter No. 23 (Tube Wells)

74

29.78

42.15 Carpenter 1 No. 300.00 170.00

80.14 Turner 1 No. 170.00 170.00

114.73 Total 340.00

Sundries 10.00 Percent 34.00 Total 374.00

10.00 Percent 37.40 Total 411.40

Contractor's Profit &

Overheads

Page 75: Rate analsis Chapter No. 23 (Tube Wells)

75

Rate for 100' Rate Charges

for 200 Rft

161 No. 170.00 170.00

2 Nos 140.00 280.00

Total 450.00

10.00 Percent 45.00 Total 495.00

10.00 Percent 49.50 Total 544.50

272.25

Page 76: Rate analsis Chapter No. 23 (Tube Wells)

76

22 Providing, laying, cutting, jointing, testing and disinfecting GI pipeline in trenches, with socket joint, using GI pipes of BSS 1387 - 1967

complete in all respects, with specials and valves.

(I) Light Quality Length of pipe 18' (5.4 M). Rate for 100'

Material Labour Rate Rate per MetreS. Dia of Rate per Adust- Wastage Special Total Contra- Total No of Prog- Daily Cost Total Total Carr- Testing Labour Compo- Labour Composite Labour

No. pipe in 100' for orum 2% 10% ctor's Joints ress Charges per jointing 13 + 14 iage site for for Per ft for per ft

Inche light 1% 3 + 4 + Profit in line Joint material x 10 15 + 16 100'

quality 5 + 6 20.00 + 17 9 + 18 18 / 100 19 / 100

Perfect

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22

1 ½" 1358.00 13.58 27.16 135.80 1534.54 76.73 1611.27 10.00 40.00 648.00 16.20 1.00 172.00 80.00 - 252.00 1863.27 2.52 18.63 8.27

2 ¾" 1893.00 18.93 37.86 189.30 2139.09 106.95 2246.04 10.00 35.00 648.00 18.51 1.52 200.34 80.00 - 280.34 2526.39 2.80 25.26 9.20

3 1" 2627.00 26.27 52.54 262.70 2968.51 148.43 3116.94 9.00 30.00 648.00 21.60 2.00 236.00 80.00 12.00 328.00 3444.94 3.28 34.45 10.76

4 1¼" 3417.00 34.17 68.34 341.70 3861.21 193.06 4054.27 9.00 30.00 648.00 21.60 2.48 240.80 80.00 12.00 332.80 4387.07 3.33 43.87 10.92

5 1½" 4212.00 42.12 84.24 421.20 4759.56 237.98 4997.54 9.00 30.00 648.00 21.60 3.00 246.00 80.00 14.00 340.00 5337.54 3.40 53.38 11.15

6 2" 5144.00 51.44 102.88 514.40 5812.72 290.64 6103.36 8.00 28.00 648.00 23.14 4.00 271.43 94.00 16.00 381.43 6484.78 3.81 64.85 12.51

7 2½" 7249.00 72.49 144.98 724.90 8191.37 409.57 8600.94 8.00 28.00 648.00 23.14 5.00 281.43 100.00 18.00 399.43 9000.37 3.99 90.00 13.10

8 3" 8393.00 83.93 167.86 839.30 9484.09 474.20 9958.29 7.00 25.00 648.00 25.92 6.00 319.20 120.00 24.00 463.20 10421.49 4.63 104.21 15.19

9 4" 12367.00 123.67 247.34 1236.70 13974.71 698.74 14673.45 7.00 23.00 648.00 28.17 8.00 361.74 120.00 28.00 509.74 15183.18 5.10 151.83 16.72

Plumber 1 No. 170.00 170.00

Cooly 2 Nos. 140.00 280.00

Total 450.00

Contractor's Profit & Overheads 20.00 Percent 90.00 Sundries 20.00 Percent 108.00

Page 77: Rate analsis Chapter No. 23 (Tube Wells)

77

Total 540.00 Total 648.00

Page 78: Rate analsis Chapter No. 23 (Tube Wells)

78

22 Providing, laying, cutting, jointing, testing and disinfecting GI pipeline in trenches, with socket joint, using GI pipes of BSS 1387 - 1967

complete in all respects, with specials and valves.

(ii) Medium QualityLength of pipe 18' (5.4 M). 20 Rate for 100'

Material Labour Rate Rate per MetreS. Dia of Rate per Adust- Wastage Special Total Contra- Total No of Prog- Daily Cost Total Total Carr- Testing Labour Compo- Labour Composite Labour

No. pipe in 100' for orum 2% 10% ctor's Joints ress Charges per jointing 13 + 14 iage site for for Per ft for per ft

Inche light 1% 3 + 4 + Profit in line Joint material x 10 15 + 16 100'

quality 5 + 6 20.00 + 17 9 + 18 18 / 100 19 / 100

Perfect

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22

1 ½" 1618.00 16.18 32.36 161.80 1828.34 91.42 1919.76 10.00 40.00 594.00 14.85 1.00 158.50 80.00 - 238.50 2158.26 2.39 21.58 7.82

2 ¾" 2076.00 20.76 41.52 207.60 2345.88 117.29 2463.17 10.00 35.00 594.00 16.97 1.52 184.91 80.00 - 264.91 2728.09 2.65 27.28 8.69

3 1" 3053.00 30.53 61.06 305.30 3449.89 172.49 3622.38 9.00 30.00 594.00 19.80 2.00 218.00 80.00 12.00 310.00 3932.38 3.10 39.32 10.17

4 1¼" 3816.00 38.16 76.32 381.60 4312.08 215.60 4527.68 9.00 30.00 594.00 19.80 2.48 222.80 80.00 12.00 314.80 4842.48 3.15 48.42 10.33

5 1½" 4578.00 45.78 91.56 457.80 5173.14 258.66 5431.80 9.00 30.00 594.00 19.80 3.00 228.00 84.00 14.00 326.00 5757.80 3.26 57.58 10.69

6 2" 6105.00 61.05 122.10 610.50 6898.65 344.93 7243.58 8.00 28.00 594.00 21.21 4.00 252.14 94.00 16.00 362.14 7605.73 3.62 76.06 11.88

7 2½" 7936.00 79.36 158.72 793.60 8967.68 448.38 9416.06 8.00 28.00 594.00 21.21 5.00 262.14 100.00 18.00 380.14 9796.21 3.80 97.96 12.47

8 3" 10072.00 100.72 201.44 1007.20 11381.36 569.07 11950.43 7.00 25.00 594.00 23.76 6.00 297.60 120.00 24.00 441.60 12392.03 4.42 123.92 14.48

9 4" 14344.00 143.44 286.88 1434.40 16208.72 810.44 17019.16 7.00 23.00 594.00 25.83 8.00 338.26 120.00 28.00 486.26 17505.42 4.86 175.05 15.95

10 5" 19838.00 198.38 396.76 1983.80 22416.94 2241.69 24658.63 6.00 20.00 594.00 29.70 10.00 397.00 140.00 32.00 569.00 25227.63 5.69 252.28 18.66

11 6" 23653.00 236.53 473.06 2365.30 26727.89 2672.79 29400.68 6.00 20.00 594.00 29.70 12.00 417.00 140.00 36.00 593.00 29993.68 5.93 299.94 19.45

Plumber 1 No. 170.00 170.00

Cooly 2 Nos. 140.00 280.00

Page 79: Rate analsis Chapter No. 23 (Tube Wells)

79

Total 450.00

Contractor's Profit & Overheads 20.00 Percent 90.00 Sundries 10.00 Percent 54.00

Total 540.00 Total 594.00

Page 80: Rate analsis Chapter No. 23 (Tube Wells)

80

22 Providing, laying, cutting, jointing, testing and disinfecting GI pipeline in trenches, with socket joint, using GI pipes of BSS 1387 - 1967

complete in all respects, with specials and valves.

(iii) Heavy QualityLength of pipe 18' (5.4 M). Rate for 100'

Material Labour Rate Rate per MetreS. Dia of Rate per Adust- Wastage Special Total Contra- Total No of Prog- Daily Cost Total Total Carr- Testing Labour Compo- Labour Composite Labour

No. pipe in 100' for orum 2% 10% ctor's Joints ress Charges per jointing 13 + 14 iage site for for Per ft for per ft

Inche light 1% 3 + 4 + Profit in line Joint material x 10 15 + 16 100'

quality 5 + 6 20.00 + 17 9 + 18 18 / 100 19 / 100

Perfect

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22

1 ½" 1862.00 18.62 37.24 186.20 2104.06 105.20 2209.26 10.00 40.00 594.00 14.85 1.00 158.50 80.00 - 238.50 2447.76 2.39 24.48 7.83

2 ¾" 2335.00 23.35 46.70 233.50 2638.55 131.93 2770.48 10.00 35.00 594.00 16.97 1.52 184.91 80.00 - 264.91 3035.39 2.65 30.35 8.69

3 1" 3511.00 35.11 70.22 351.10 3967.43 198.37 4165.80 9.00 30.00 594.00 19.80 2.00 218.00 80.00 12.00 310.00 4475.80 3.10 44.76 10.17

4 1¼" 4503.00 45.03 90.06 450.30 5088.39 254.42 5342.81 9.00 30.00 594.00 19.80 2.48 222.80 80.00 12.00 314.80 5657.61 3.15 56.58 10.33

5 1½" 5342.00 53.42 106.84 534.20 6036.46 301.82 6338.28 9.00 30.00 594.00 19.80 3.00 228.00 84.00 14.00 326.00 6664.28 3.26 66.64 10.69

6 2" 7173.00 71.73 143.46 717.30 8105.49 405.27 8510.76 8.00 28.00 594.00 21.21 4.00 252.14 94.00 16.00 362.14 8872.91 3.62 88.73 11.88

7 2½" 9307.00 93.07 186.14 930.70 10516.91 525.85 11042.76 8.00 28.00 594.00 21.21 5.00 262.14 100.00 18.00 380.14 11422.90 3.80 114.23 12.47

8 3" 11751.00 117.51 235.02 1175.10 13278.63 663.93 13942.56 7.00 25.00 594.00 23.76 6.00 297.60 120.00 24.00 441.60 14384.16 4.42 143.84 14.48

9 4" 16939.00 169.39 338.78 1693.90 19141.07 957.05 20098.12 7.00 23.00 594.00 25.83 8.00 338.26 120.00 28.00 486.26 20584.38 4.86 205.84 15.95

10 5" 22127.00 221.27 442.54 2212.70 25003.51 2500.35 27503.86 6.00 20.00 594.00 29.70 10.00 397.00 140.00 32.00 569.00 28072.86 5.69 280.73 18.66

11 6" 25943.00 259.43 518.86 2594.30 29315.59 2931.56 32247.15 6.00 20.00 594.00 29.70 12.00 417.00 140.00 36.00 593.00 32840.15 5.93 328.40 19.45

Plumber 1 No. 170.00 170.00

Cooly 2 Nos. 140.00 280.00

Page 81: Rate analsis Chapter No. 23 (Tube Wells)

81

Total 450.00

Contractor's Profit & Overheads 20.00 Percent 90.00 Sundries 10.00 Percent 54.00

Total 540.00 Total 594.00

Page 82: Rate analsis Chapter No. 23 (Tube Wells)

82

Rate per MetreComposite

23

61.12

82.87

112.99

143.90

175.07

212.70

295.21

341.83

498.01

Page 83: Rate analsis Chapter No. 23 (Tube Wells)

83

Page 84: Rate analsis Chapter No. 23 (Tube Wells)

84

Rate per MetreComposite

23

70.79

89.48

128.98

158.83

188.86

249.47

321.32

406.46

574.18

827.47

983.79

Page 85: Rate analsis Chapter No. 23 (Tube Wells)

85

Page 86: Rate analsis Chapter No. 23 (Tube Wells)

86

Rate per MetreComposite

23

80.29

99.56

146.81

185.57

218.59

291.03

374.67

471.80

675.17

920.79

1077.16

Page 87: Rate analsis Chapter No. 23 (Tube Wells)

87

Page 88: Rate analsis Chapter No. 23 (Tube Wells)

88

23 Providing laying, cutting, jointing, testing & disinfecting AC pipeline of BSS with "B" Class working pressure pipe in

trenches with cement joint & rubbering complete in all respect.

Material Labour for 100' Rate per 100 Ft Rate per Ft Rate per MetreS. Dia Cost of Wast- Total Contra- Total Carriage Grand Lowering Cutting Cleaning Testing Plugging Labour Compo- Labour Composite Labour Composite

No. of pipe with age ctor's for 100' Per ft Total into end end of and wooden site for for per

pipe coment 2% (3 + 4) Profit AC pipe length for 100 Ft trenches pipe disinf- plug Per ft ft

joint & 20.00 (5 + 6) (4 chain) & laying ecting 10 + 16

rubber Percent

ring

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21

1 3" 44.93 0.90 45.83 2.29 48.12 1.90 0.02 4813.90 297.00 18.15 16.10 46.44 5.32 383.01 5196.91 3.83 51.97 12.56 170.46

2 4" 65.82 1.32 67.14 3.36 70.49 2.45 0.02 7051.77 305.91 25.92 17.61 50.03 7.10 406.57 7458.34 4.07 74.58 13.34 244.63

3 6" 99.28 1.99 101.27 5.06 106.33 3.75 0.04 10636.64 417.58 45.38 19.56 59.39 13.32 555.23 11191.87 5.55 111.92 18.21 367.09

4 8" 164.33 3.29 167.62 8.38 176.00 6.35 0.06 17606.09 578.56 72.60 26.15 68.61 19.43 765.35 18371.44 7.65 183.71 25.10 602.58

5 10" 257.79 5.16 262.95 13.15 276.09 8.50 0.09 27617.81 765.67 80.17 29.78 81.87 36.20 993.69 28611.50 9.94 286.11 32.59 938.46

6 12" 355.21 7.10 362.31 18.12 380.43 11.00 0.11 38053.99 993.76 90.75 39.23 91.79 50.81 1266.33 39320.32 12.66 393.20 41.54 1289.71

7 14" 481.85 9.64 491.49 24.57 516.06 14.58 0.15 51620.71 1137.51 96.30 43.11 105.55 81.67 1464.14 53084.85 14.64 530.85 48.02 1741.18

8 16" 604.36 12.09 616.45 30.82 647.27 18.15 0.18 64745.10 1281.26 103.72 45.51 119.30 104.08 1653.87 66398.97 16.54 663.99 54.25 2177.89

9 18" 749.16 14.98 764.14 38.21 802.35 23.35 0.23 80258.38 1517.67 121.00 48.30 131.01 134.20 1952.18 82210.56 19.52 822.11 64.03 2696.51

10 20" 911.60 18.23 929.83 46.49 976.32 24.75 0.25 97657.11 1770.71 145.20 59.56 154.34 165.80 2295.61 99952.71 22.96 999.53 75.30 3278.45

11 24" 1288.59 25.77 1314.36 65.72 1380.08 27.45 0.27 138035.44 2067.12 145.20 70.45 183.21 282.31 2748.29 140783.72 27.48 1407.84 90.14 4617.71

Page 89: Rate analsis Chapter No. 23 (Tube Wells)

89

24 Providing laying, cutting, jointing, testing & disinfecting AC pipeline of BSS with "C" Class working pressure pipe in

trenches with cement joint & rubbering complete in all respect.

Material Labour for 100' Rate per 100 Ft Rate per Ft Rate per Metre

S. Dia Cost of Wast- Total Contra- Total Carriage Grand Lowering Cutting Cleaning Testing Plugging Labour Compo- Labour Composite Labour Composite

No. of pipe with age ctor's for 100' Per ft Total into end end of and wooden site for for per

pipe coment 2% (3 + 4) Profit AC pipe length for 100 Ft trenches pipe disinf- plug Per ft ft

joint & 20.00 (5 + 6) (4 chain) & laying ecting 10 + 16

rubber Percent

ring 20

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21

1 3" 44.93 0.90 45.83 2.29 48.12 1.90 0.02 4813.90 297.00 18.15 16.10 46.44 5.32 383.01 5196.91 3.83 51.97 12.56 170.46

2 4" 69.12 1.38 70.50 3.53 74.03 2.45 0.02 7405.20 305.91 25.92 17.61 50.03 7.10 406.57 7811.77 4.07 78.12 13.34 256.23

3 6" 141.58 2.83 144.41 7.22 151.63 3.75 0.04 15166.97 417.58 45.38 19.56 59.39 13.32 555.23 15722.20 5.55 157.22 18.21 515.69

4 8" 208.85 4.18 213.03 10.65 223.68 6.35 0.06 22374.19 578.56 72.60 26.15 68.61 19.43 765.35 23139.53 7.65 231.40 25.10 758.98

5 10" 337.43 6.75 344.18 17.21 361.39 8.50 0.09 36147.25 765.67 80.17 29.78 81.87 36.20 993.69 37140.94 9.94 371.41 32.59 1218.22

6 12" 474.86 9.50 484.36 24.22 508.58 11.00 0.11 50868.50 993.76 90.75 39.23 91.79 50.81 1266.33 52134.84 12.66 521.35 41.54 1710.02

7 14" 657.88 13.16 671.04 33.55 704.59 14.58 0.15 70473.52 1137.51 96.30 43.11 105.55 81.67 1464.14 71937.67 14.64 719.38 48.02 2359.56

8 16" 895.40 17.91 913.31 45.67 958.97 18.15 0.18 95915.49 1281.26 103.72 45.51 119.30 104.08 1653.87 97569.36 16.54 975.69 54.25 3200.27

9 18" 1111.93 22.24 1134.17 56.71 1190.88 23.35 0.23 119111.06 1517.67 121.00 48.30 131.01 134.20 1952.18 121063.23 19.52 1210.63 64.03 3970.87

10 20" 1352.60 27.05 1379.65 68.98 1448.63 24.75 0.25 144888.21 1770.71 145.20 59.56 154.34 165.80 2295.61 147183.81 22.96 1471.84 75.30 4827.63

11 24" 1936.43 38.73 1975.16 197.52 2172.67 27.45 0.27 217294.90 2067.12 181.50 70.45 183.21 282.31 2784.59 220079.49 27.85 2200.79 91.33 7218.61

Page 90: Rate analsis Chapter No. 23 (Tube Wells)

90

25 Providing laying, cutting, jointing, testing & disinfecting AC pipeline of BSS with "D" Class working pressure pipe in

trenches with commet joint & rubbering complete in all respect.

Material Labour for 100' Rate per 100 Ft Rate per Ft Rate per Metre

S. Dia Cost of Wast- Total Contra- Total Carriage Grand Lowering Cutting Cleaning Testing Plugging Labour Compo- Labour Composite Labour Composite

No. of pipe with age ctor's for 100' Per ft Total into end end of and wooden site for for per

pipe coment 2% (3 + 4) Profit AC pipe length for 100 Ft trenches pipe disinf- plug Per ft ft

joint & 20.00 (5 + 6) (4 chain) & laying ecting 10 + 16

rubber Percent

ring

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21

1 3" 44.92 0.90 45.82 2.29 48.11 1.90 0.02 4812.83 297.00 18.15 16.10 46.44 5.32 383.01 5195.84 3.83 51.96 12.56 170.42

2 4" 89.18 1.78 90.96 4.55 95.51 2.45 0.02 9553.63 305.91 25.92 17.61 50.03 7.10 406.57 9960.19 4.07 99.60 13.34 326.69

3 6" 177.71 3.55 181.26 9.06 190.33 3.75 0.04 19036.49 417.58 45.38 19.56 59.39 13.32 555.23 19591.72 5.55 195.92 18.21 642.61

4 8" 304.66 6.09 310.75 15.54 326.29 6.35 0.06 32635.44 578.56 72.60 26.15 68.61 19.43 765.35 33400.78 7.65 334.01 25.10 1095.55

5 10" 509.08 10.18 519.26 25.96 545.22 8.50 0.09 54530.97 765.67 80.17 29.78 81.87 36.20 993.69 55524.65 9.94 555.25 32.59 1821.21

6 12" 733.79 14.68 748.47 37.42 785.89 11.00 0.11 78599.91 993.76 90.75 39.23 91.79 50.81 1266.33 79866.24 12.66 798.66 41.54 2619.61

7 14" 938.45 18.77 957.22 47.86 1005.08 14.58 0.15 100522.57 1137.51 96.30 43.11 105.55 81.67 1464.14 101986.72 14.64 1019.87 48.02 3345.16

8 16" 1317.78 26.36 1344.14 67.21 1411.34 18.15 0.18 141152.39 1281.26 103.72 45.51 119.30 104.08 1653.87 142806.26 16.54 1428.06 54.25 4684.05

9 18" 1645.91 32.92 1678.83 83.94 1762.77 23.35 0.23 176300.31 1517.67 121.00 48.30 131.01 134.20 1952.18 178252.49 19.52 1782.52 64.03 5846.68

10 20" 2090.69 41.81 2132.50 106.63 2239.13 24.75 0.25 223937.64 1770.71 145.20 59.56 154.34 165.80 2295.61 226233.25 22.96 2262.33 75.30 7420.45

Page 91: Rate analsis Chapter No. 23 (Tube Wells)

91

Composite

Page 92: Rate analsis Chapter No. 23 (Tube Wells)

92

Composite

Page 93: Rate analsis Chapter No. 23 (Tube Wells)

93

Composite

Page 94: Rate analsis Chapter No. 23 (Tube Wells)

94

Cleaning pipe placing rubber in position pressing with assembling machine, of AC pipe.

S. I/D No of Labour Amount Hire Total

# of joining charges Charges

Pipe per day per day of Machine

1 2 3 4 5 61 3" 36.00 435.60 12.10 4.00 16.10 Cleaning pipe placing rubber in position pressing with assembling 2 4" 32.00 435.60 13.61 4.00 17.61 machine, and jointing.

3 6" 28.00 435.60 15.56 4.00 19.56 LABOUR 4 8" 24.00 435.60 18.15 8.00 26.15 Plumber 1 No 170.00 170.005 10" 20.00 435.60 21.78 8.00 29.78 Skilled Cooly 1 No 160.00 160.006 12" 16.00 435.60 27.23 12.00 39.23 Total 330.007 14" 14.00 435.60 31.11 12.00 43.11 Sundries 10.00 Percent 33.008 16" 13.00 435.60 33.51 12.00 45.519 18" 12.00 435.60 36.30 12.00 48.30 Total 363.0010 20" 10.00 435.60 43.56 16.00 59.56 Contractor's Profit & Overheads 20.00 Percent 72.60

11 24" 8.00 435.60 54.45 16.00 70.45 435.60

Page 95: Rate analsis Chapter No. 23 (Tube Wells)

95

23 - Lowering into trenches, stringing and laying to correct alignment AC pipe "Class B" etc.

S. Size No. of Labour for Amount

No. of Days Charges

pipe for 100' per day

1 2 3 4 5

1 3" 0.500 594.00 297.00 Lowering into trenches stringing and laying to correct alignment.

2 4" 0.515 594.00 305.91 Daily Labour Charges

3 6" 0.703 594.00 417.58

4 8" 0.974 594.00 578.56 Plumber 1 No 170.00 170.00

5 10" 1.289 594.00 765.67 Unskilled Cooly 2 Nos 140.00 280.00

6 12" 1.673 594.00 993.76 Total 450.00

7 14" 1.915 594.00 1137.51 Sundries 10 Percent 45.00

8 16" 2.157 594.00 1281.26 Total 495.00

9 18" 2.555 594.00 1517.67 Contractor's Profit & Overheads 20 20.00 99.00

10 20" 2.981 594.00 1770.71 594.00

11 24" 3.480 594.00 2067.12

Page 96: Rate analsis Chapter No. 23 (Tube Wells)

96

Providing, laying, cutting, jointing testing & disinfecting A.C. pipe line of BSS with "B Class" workingpressure pipe in trenches with cement joint and rubber ring complete in all respect.

Detail for 1000' (Disinfecting and testing rates) Rate for 100'S. Dia Volume of Amount Disin- Amount Hire Total Contra- Total Labour Per Joint Composite Composite Composite Rate

# of Water in @ Rs fecting @ Rs. Charges ctor's Plugging Labour Total rate for rate for Rate per Rate per

pipe P. Gallon 12 agent 20 of testing 4 + 6 Profit 8 + 9 of pipe for testing ‰ ft % ft. Rft Metre

Per ‰ in Lbs Per apparatus + 7 20.00 and disin- 11 + 12 10 + 13

Gallons Lbs Percent fecting

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

1 3" 310.00 3.72 0.50 10.00 100.00 113.72 5.69 119.41 48.00 297.00 345.00 464.41 46.44 0.46 1.52

2 4" 720.00 8.64 1.20 24.00 100.00 132.64 6.63 139.27 64.00 297.00 361.00 500.27 50.03 0.50 1.64

3 6" 1820.00 21.84 2.00 40.00 100.00 161.84 8.09 169.93 127.00 297.00 424.00 593.93 59.39 0.59 1.95

4 8" 2180.00 26.16 3.65 73.00 100.00 199.16 9.96 209.12 180.00 297.00 477.00 686.12 68.61 0.69 2.25

5 10" 3410.00 40.92 5.70 114.00 100.00 254.92 12.75 267.67 254.00 297.00 551.00 818.67 81.87 0.82 2.69

6 12" 4910.00 58.92 8.00 160.00 100.00 318.92 15.95 334.87 286.00 297.00 583.00 917.87 91.79 0.92 3.01

7 14" 6810.00 81.72 11.15 223.00 100.00 404.72 20.24 424.96 333.50 297.00 630.50 1055.46 105.55 1.06 3.46

8 16" 8710.00 104.52 14.30 286.00 100.00 490.52 24.53 515.05 381.00 297.00 678.00 1193.05 119.30 1.19 3.91

9 18" 11000.00 132.00 18.50 370.00 100.00 602.00 30.10 632.10 381.00 297.00 678.00 1310.10 131.01 1.31 4.30

10 20" 13600.00 163.20 22.00 440.00 100.00 703.20 35.16 738.36 508.00 297.00 805.00 1543.36 154.34 1.54 5.06

11 24" 19600.00 235.20 32.15 643.00 100.00 978.20 48.91 1027.11 508.00 297.00 805.00 1832.11 183.21 1.83 6.01

Labour for Testing 2000 ft

Mechanic 1 No. 170.00 170.00 Sundires 10.00 45.00 594 297.00

Cooly 2 Nos 140.00 280.00 Total 495.002

Total 450.00 Contractor's Profit & Overheads 20.00 99.00

Total 594.00

Page 97: Rate analsis Chapter No. 23 (Tube Wells)

97

Providing and fixing temporary wooden plug.

Assume for 500'S. Size PLUG MATERIAL LABOUR FOR MAKING PLUG LABOUR FOR FIXING

# of Area of Length Rate Contents Amount Daily Daily Amount L.S. Sundries Total Contra- Total Grand Rate Rate

pipe Plug Sft per Cft in Cft Progress Rate 20 10 ctor's Total for 100' per Metre

5 x 6 in No. 9 / 8 Percent Profit 13 + 14 for 500'

20 7 + 10

Percent + 15

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18

1 3" 0.50 300.00 0.02 6.00 34.00 676.80 19.91 0.60 0.06 0.66 0.03 0.69 26.60 5.32 0.17

2 4" 0.50 300.00 0.04 12.00 30.00 676.80 22.56 0.80 0.08 0.88 0.04 0.92 35.48 7.10 0.23

3 6" 0.50 300.00 0.10 30.00 19.00 676.80 35.62 0.84 0.08 0.92 0.05 0.97 66.59 13.32 0.44

4 8" 0.50 300.00 0.17 51.00 15.00 676.80 45.12 0.88 0.09 0.97 0.05 1.02 97.14 19.43 0.64

5 10" 0.75 300.00 0.41 123.00 12.00 676.80 56.40 1.40 0.14 1.54 0.08 1.62 181.02 36.20 1.19

6 12" 0.75 300.00 0.59 177.00 9.00 676.80 75.20 1.60 0.16 1.76 0.09 1.85 254.05 50.81 1.67

7 14" 0.75 300.00 1.07 321.00 8.00 676.80 84.60 2.40 0.24 2.64 0.13 2.77 408.37 81.67 2.68

8 16" 1.00 300.00 1.40 420.00 7.00 676.80 96.69 3.20 0.32 3.52 0.18 3.70 520.38 104.08 3.41

9 18" 1.00 300.00 1.77 531.00 5.00 676.80 135.36 4.00 0.40 4.40 0.22 4.62 670.98 134.20 4.40

10 20" 1.00 300.00 2.18 654.00 4.00 676.80 169.20 5.00 0.50 5.50 0.28 5.78 828.98 165.80 5.44

11 24" 1.25 300.00 3.93 1179.00 3.00 676.80 225.60 6.00 0.60 6.60 0.33 6.93 1411.53 282.31 9.26

9x(3)2

4x144

9x(4)2

4x144

9x(6)2

4x144

9x(8)2

4x144

9x(10)2

4x144

9x(12)2

4x144

9x(14)2

4x144

9x(16)2

4x144

9x(18)2

4x144

9x(20)2

4x144

9x(20)2

4x144

Page 98: Rate analsis Chapter No. 23 (Tube Wells)

98

Lowering into trenches, stringing and laying to correct alignment AC pipe "Class D" etc.

S. Size No. of Labour for Amount

No. of Days Charges

pipe for 100' per day

1 2 3 4 51 3" 0.500 594.00 297.00 Lowering into trenches stringing and laying to correct alignment.2 4" 0.515 594.00 305.91 Daily Labour Charges 3 6" 0.703 594.00 417.584 8" 0.974 594.00 578.56 Plumber 1 No 170.00 170.005 10" 1.289 594.00 765.67 Unskilled Cooly 2 Nos 140.00 280.006 12" 1.673 594.00 993.76 Total 450.007 14" 1.920 594.00 1140.48 Sundries 10 Percent 45.008 16" 2.157 594.00 1281.26 Total 495.009 18" 2.555 594.00 1517.67 Contractor's Profit & Overheads 20 Percent 99.00

10 20" 2.981 594.00 1770.71 594.00

11 24" 3.480 594.00 2067.12

Page 99: Rate analsis Chapter No. 23 (Tube Wells)

99

Rate for 100'

19

Daily Charges

250.00 250.00

20.00 50.00

Total 300.00

300.00 300.00

170.00 170.00

Total 470.00

Sundries 20.00 94.00

Total 564.00

20.00 112.80

Total 676.80

Hard Wood 1 Cft

Contractor's Profit & Overheads

Carpenter 1 No.

Turner 1 No.

Contractor's Profit & Overheads

Page 100: Rate analsis Chapter No. 23 (Tube Wells)

100

26 Providing, laying cutting jointing testing and disinfecting PVC pipeline of BSS with Class "B" workingpressure pipe in pipes trenches complete in all respect.

Assume for 500' Rate for P. ftS. Dia MATERIAL LABOUR Rate per 100' Rate per Rft Rate per Metre

No. of Rate Wastage Total Contra- Total Weight Rate Amount Contra- Total Labour Total Labour Composite Labour Composite Labour Composite

pipe for 100' 2% ctor's in of ctor's as per for 100' for 100' rate rate rate rate

Profit (5 + 6) Kg Lubricant (8 x 9) Profit (10 + 11) detail (12 +13) (7 + 15)

20.00 in Kg 20.00

Percent Percent

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

1 3" 3659.00 73.18 3732.18 186.61 3918.79 0.303 200.00 60.60 3.03 63.63 102.45 166.08 ### 4084.89 1.66 40.85 5.45 133.98

2 4" 5488.00 109.76 5597.76 279.89 5877.65 0.339 200.00 67.80 3.39 71.19 131.45 202.64 ### 6080.30 2.03 60.80 6.65 199.43

3 5" 7622.00 152.44 7774.44 388.72 8163.16 0.464 200.00 92.80 4.64 97.44 153.65 251.09 ### 8414.26 2.51 84.14 8.24 275.99

4 6" 10976.00 219.52 11195.52 559.78 11755.30 0.544 200.00 108.80 5.44 114.24 20.00 134.24 ### 11889.55 1.34 118.90 4.40 389.98

5 8" 16159.00 323.18 16482.18 824.11 17306.29 0.789 200.00 157.80 7.89 165.69 224.85 390.54 ### 17696.84 3.91 176.97 12.81 580.46

6 10" 25305.00 506.10 25811.10 1290.56 27101.66 0.865 200.00 173.00 8.65 181.65 309.45 491.10 ### 27592.76 4.91 275.93 16.11 905.04

7 12" 35366.00 707.32 36073.32 1803.67 37876.99 1.037 200.00 207.40 10.37 217.77 385.70 603.47 ### 38480.44 6.03 384.80 19.79 1262.16

8 14" 42378.00 847.56 43225.56 2161.28 45386.84 1.179 200.00 235.80 11.79 247.59 502.05 749.64 ### 46136.49 7.50 461.36 24.59 1513.28

Page 101: Rate analsis Chapter No. 23 (Tube Wells)

101

Labour for laying, cutting, jointing, pipeline in trenches with PVC pipes of BSS with

"B" Class working pressure, complete in all respect.

Rate for 100 ftS. # Dia CarriageLAYING, FIXING, CUTTING, JOINTING Testing Total Rate

of for lead Time for Daily Amount & for 100'

pipe 4 chains 100' Expenses Disinfecting 6 + 7

1 2 3 4 5 6 7 8 9

1 2" 0.32 0.10 646.80 64.68 21.36 86.04 86.05 2 3" 0.37 1/8 646.80 80.85 21.58 102.43 ### Plumber 1 No 170.00 170.00

3 4" 0.58 1/6 646.80 107.80 23.67 131.47 ### S. Coolies 2 No 160.00 320.00

4 5" 0.79 1/5 646.80 129.36 24.28 153.64 ### Total 490.00

5 6" 1.09 1/5 646.80 129.36 35.97 165.33 20.00 Sundries 10.00 Percent 49.00

6 8" 4.60 2/7 646.80 184.80 40.06 224.86 ### Total 539.00

7 10" 2.95 2/5 646.80 258.72 50.73 309.45 ### Contractor's P 20.00 Percent 107.80

8 12" 4.15 1/2 646.80 323.40 62.31 385.71 ### Total 646.80

9 14" 5.40 2/3 646.80 431.20 70.83 502.03 ###

Page 102: Rate analsis Chapter No. 23 (Tube Wells)

102

Composite

Page 103: Rate analsis Chapter No. 23 (Tube Wells)

103

27 Providing, laying, cutting, jointing, testing & disinfecting pipeline in trenches with PVC pipes of BSS with "D"

Class working pressure, complete in all respect.

Unit of rate per ft.S. Dia Material Labour Rate per 100' Rate per Ft Rate per Metre

# of Rate for Wastage Total Contra- Total Lubri- Rate Amount Contra- Total Labour Total Labour Composite Labour Composite Labour Composite

pipe 100' 2% ctor's cant per Kgs ctor's as per

(3 + 4) Profit (5 + 6) Kgs (8 x 9) Profit (10+11) detail (12+13) (7 + 15)

20.00 20.00 24

Percent Percent

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

1 2" 2683.00 53.66 2736.66 136.83 2873.49 0.259 200.00 51.80 2.59 54.39 86.04 140.43 140.43 3013.92 1.40 30.14 4.61 98.86

2 3" 5640.00 112.80 5752.80 287.64 6040.44 0.303 200.00 60.60 3.03 63.63 102.43 166.06 166.06 6206.50 1.66 62.07 5.45 203.57

3 4" 9299.00 185.98 9484.98 474.25 9959.23 0.339 200.00 67.80 3.39 71.19 131.47 202.66 202.66 10161.89 2.03 101.62 6.65 333.31

4 5" 14024.00 280.48 14304.48 715.22 15019.70 0.464 200.00 92.80 4.64 97.44 153.64 251.08 251.08 15270.78 2.51 152.71 8.24 500.88

5 6" 20122.00 402.44 20524.44 1026.22 21550.66 0.544 200.00 108.80 5.44 114.24 165.33 279.57 279.57 21830.23 2.80 218.30 9.17 716.03

Page 104: Rate analsis Chapter No. 23 (Tube Wells)

104

20

Page 105: Rate analsis Chapter No. 23 (Tube Wells)

105

28 Providing and fixing cast iron special of BSS class "B" (such as bend, tee, cross collar, reducer, tail piece, flanged spigot,

cap, flanged socket, taper, angle branch, plug, etc.) for cast iron pipe line, complete.

a - C-I specials with spigot and socket joint.

Labour Casting material (Supply of specials i/c moulding, painting,

carriage to site of work.

S. Dia Average Labour Material Total Total Total Rate Rate Contractor's Total Rate Rate per Kg

No. of Waight for for Labour for weight Cost per Kg per Cwt Profit per Kg Labour Composite

pipe in 2 Joints 2 Joints 2 Joints of special 20.00 13 + 14

Lbs 4 + 5 Percent

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15

1 3" 46.00 107.32 138.62 245.94 ###

4" 61.00 137.77 176.63 314.40 ###

5" 88.00 170.86 213.59 384.45 ###

6" 111.00 201.77 265.83 467.60 1412.39 10.17 1394.00 139.40 1533.40 30.19 10.17 40.36

2 8" 182.00 216.69 364.46 581.15 ###

10" 273.00 356.29 504.13 860.42 ###

12" 392.00 422.96 583.26 1006.22 2447.79 6.17 1394.00 139.40 1533.40 30.19 6.17 36.36

3 15" 540.00 542.08 768.55 1310.63 ###

18" 746.00 706.96 1061.98 1768.94 3079.57 5.28 1394.00 139.40 1533.40 30.19 5.28 35.46

306 Lbs or

138.84 Kg

847 Lbs or

396.55 Kg

1286 Lbs or 583.48

Kg

Page 106: Rate analsis Chapter No. 23 (Tube Wells)

106

28 - Providing and fixing cast iron special of BSS class "B" (such as bend, tee, cross collar, reducer, tail piece, flanged spigot,

cap, flanged socket, taper, angle branch, plug, etc.) for cast iron pipe line, complete.

b - CI flanged special with flanged and flanged joints.

Labour Material Rate

S. Dia Average Labour rate for 2 Labour rate per Lbs Supply of special (cost of material, Rate per Kg

No. of Weight joints. weight. with moulding, painting, and carriage to Labour Composite

pipe in Labour Material Total Total Total Rate site of work. rate per rate per

Lbs/Kg weight Amount per Kg Rate Contractor's Total Rate Kg Kg

(4 + 5) 20 P/ Cwt Profit per Kg

20.00

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15

1 3" 32.00 34.07 67.58 101.65 ###

4" 48.00 37.95 74.34 112.29 ###

5" 83.00 41.67 154.74 196.41 ###

6" 93.00 46.88 159.53 206.41 616.76 5.31 1650.00 330.00 1980.00 38.98 5.31 44.29

2 8" 161.00 46.88 192.19 239.07 ###

10" 250.00 62.50 295.60 358.10 ###

12" 376.00 74.98 325.38 400.36 813.17 2.28 1650.00 330.00 1980.00 38.98 2.28 41.25

3 15" 453.00 124.96 410.71 535.67 ###

18" 646.00 187.47 437.54 625.01 1160.68 2.33 1650.00 330.00 1980.00 38.98 2.33 41.31

256 Lbs or

116.15 Kg

787 Lbs or

357.08 Kg

1099 Lbs or 498.00

Kg

Page 107: Rate analsis Chapter No. 23 (Tube Wells)

107

28 Providing and fixing cast iron special of BSS class "B" (such as bend, tee, cross collar, reducer, tail piece, flanged spigot,

cap, flanged socket, taper, angle branch, plug, etc.) for cast iron pipe line, complete.

c - CI specials with tyton joints.

Weight Labour Material Rate

S. Dia Average Labour rate for 2 Labour rate per Lbs Supply of special (cost of material, Rate Rate per Kg

No. of Weight joints. weight. with moulding, painting, and per Labour Composite

pipe in Labour Material Total Total Total Rate carriage to site of work. Kg rate per rate per

Lbs weight of cost per Rate Contr- Total Kg Kg

specials Kg per Cwt actor's

Profit

20.00

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15

1 3" 42.00 89.06 ###

4" 60.00 117.71 ###

5" 84.00 143.26 ###

6" 109.00 169.59 519.62 3.52 1510.00 302.00 1812.00 35.67 3.52 39.19

2 8" 175.00 228.45 ###

10" 265.00 283.85 ###

12" 374.00 347.28 859.58 3.52 1510.00 302.00 1812.00 35.67 3.52 39.19

3 15" 654.00 670.63 ###

18" 898.00 804.25 1474.88 3.52 1510.00 302.00 1812.00 35.67 3.52 39.19

324.76 Lbs or 147.62

Kg

537.24 Lbs or 244.20

Kg

921.80 Lbs or 419.00

Kg

Page 108: Rate analsis Chapter No. 23 (Tube Wells)

108

29 Providing and fixing C.I. special of BSS Class "B" (such as bend, tee, cross, collar, reducer, tail piece, flanged socket, flanged

spigot, cap, taper, angle branch plug etc.) for AC pipe line with comet joint and rubber ring complete.

Labour Material

S. Dia Average Labour rate for 2 Labour rate per Supply of special (cost of material, Rate per Kg

# of Weight joints. Kg. with moulding, painting, and carriage to Labour Composite

pipe in Labour Material Total Total Total Rate site of work. rate per rate per

Lbs weight Amount per Kg Rate P. Contractor's Total Rate Kg Kg

Cwt Profit per Lbs

20.00

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15

1 3" 46.00 18.02 203.10 221.12 ###4" 61.00 19.43 303.85 323.28 ###

6" 97.00 21.19 439.30 460.49 1004.89 10.86 1510.00 302.00 1812.00 35.67 10.86 46.53

2 8" 175.00 30.55 642.54 673.09 ###10" 250.00 33.86 819.60 853.46 ###12" 370.00 38.86 1004.25 1043.11

16" 549.00 51.60 1871.26 1922.86 ###

18" 693.00 54.13 2265.26 2319.39 6811.91 7.35 1510.00 302.00 1812.00 35.67 7.35 43.02

3 20" 937.00 67.72 2839.09 2906.81 ###

24" 1317.00 86.80 4120.37 4207.17 7113.98 6.96 1510.00 302.00 1812.00 35.67 6.96 42.63

204 Lbs or 92.56

Kgs

2037 Lbs or 927.23

Kgs

2254 Lbs or 1022 Kgs

Page 109: Rate analsis Chapter No. 23 (Tube Wells)

109

30 - Providing and fixing sluice valve of BSS quality and weight Class "B" for cast iron pipe

line, and asbestos cement pipe line (including cost of jointing material).

Each

Material Labour RateS. Dia of Cost of Contractor's Total No of Daily Total Labour Composite

No. sluice sluice Profit day Labour

valve valve 20 (3 + 4) (5 + 9)

Percent

1 2 3 4 5 6 7 8 9 10

1 3" 1,675.00 83.75 1758.75 0.340 565.95 192.42 ### 1951.15 Labour 3" to 8"

2 4" 2,350.00 117.50 2467.50 0.370 565.95 209.40 ### 2676.90 Plumber 1 No 170.00 170.00

3 5" 2,750.00 137.50 2887.50 0.666 565.95 376.92 ### 3264.40 Skilled Coolies 2 No 160.00 320.00

4 6" 3,400.00 170.00 3570.00 0.710 565.95 401.82 ### 3971.85 Total 490.00

5 8" 5,610.00 280.50 5890.50 0.829 565.95 469.17 ### 6359.65 Sundries 10.00 Percent 49.00

6 10" 7,500.00 375.00 7875.00 0.889 889.35 790.63 ### 8665.65 Total 539.00

7 12" 9,500.00 475.00 9975.00 0.999 889.35 888.46 ### 10863.45 Contractor's Profit & 20.00 Percent 26.95

8 15" 18,000.00 900.00 18900.00 1.325 889.35 ### ### 20078.40 Total 565.95

9 18" 24,000.00 1200.00 25200.00 1.525 889.35 ### ### 26556.25 Labour 10" to 18"

Plumber 1 No 170.00 170.00

Skilled Coolies 2 No 160.00 320.00

Unskilled Coolies 2 No 140.00 280.00

Total 770.00

Sundries 10.00 Percent 77.00

Total 847.00

Contractor's Profit & 20.00 Percent 42.35

Total 889.35

Page 110: Rate analsis Chapter No. 23 (Tube Wells)

110

20

Page 111: Rate analsis Chapter No. 23 (Tube Wells)

111

31 Providing and fixing sluice valve of BSS quality & weight for AC pipeline with

commet joint & rubber ring complete i/c cost of jointing material.

S. Dia Material Labour for 2 joints Rate

No. of Cost of Contractor's Total Labour Material Total Labour Composite

sluice sluice Profit 6 + 7 rate rate

valve 20.00 (3 + 4) 5 + 8

Percent

1 2 3 4 5 6 7 8 9 10

1 3" 900.00 45.00 945.00 46.01 230.80 276.81 276.80 1221.81

2 4" 1,100.00 55.00 1155.00 49.64 345.20 394.84 394.85 1549.84

3 6" 2,000.00 100.00 2100.00 54.68 499.20 553.88 553.90 2653.88

4 8" 3,000.00 150.00 3150.00 76.48 730.16 806.64 806.65 3956.64

5 10" 3,500.00 175.00 3675.00 109.29 931.36 1040.65 ### 4715.65

6 12" 7,500.00 375.00 7875.00 146.67 1141.20 1287.87 ### 9162.87

7 16" 16,000.00 800.00 16800.00 166.62 2126.24 2292.86 ### 19092.86

8 18" 20,000.00 1000.00 21000.00 175.85 2574.16 2750.01 ### 23750.01

Page 112: Rate analsis Chapter No. 23 (Tube Wells)

112

20

Page 113: Rate analsis Chapter No. 23 (Tube Wells)

113

31a Providing and fixing sluice valve of BSS quality and weight for A.C. pipe line with cement jointand rubber ring complete including cost of jointing material.

LabourSr. Size No. of Charge Amount Daily ChargeNo. Day per day

1 3" 12.30 565.95 46.01

2 4" 11.40 565.95 49.64

3 6" 10.35 565.95 54.68

4 8" 7.40 565.95 76.48

5 10" 9.30 1016.40 109.29

6 12" 6.93 1016.40 146.67

7 16" 6.10 1016.40 166.62

8 18" 5.78 1016.40 175.85

Labour 3' to 8'

Plumber 1 No. 170.00 170.00Skilled Cooly 2 Nos. 160.00 320.00

Total 490.00Sundries 10.00 Percent 49.00Total 539.00Contractor's Pro 20.00 Percent 26.95

565.9510' to 18"Plumber 1 No. 170.00 170.00Skilled Cooly 2 Nos. 160.00 320.00Coolies 2 Nos. 140.00 280.00

Total 770.00Sundries 10.00 Percent 77.00Total 847.00Contractor's Pro 20.00 Percent 169.40

1016.40

Page 114: Rate analsis Chapter No. 23 (Tube Wells)

114

32 Providing and fixing fire hydrant BSS quality and weight of 2½" dia including cost ofjointing material.

Material Fixing (Labour) RateSr. Dia of Cost of Contractor's Total Labour CompositeNo. Pipe Hydrant Profit Labour Material Total

20.00

1 2½" 1,400.00 280.00 1,680.00 5.32 39.60 44.92 44.90 1,724.92

33 Providing and fixing Air Valve 3" (75mm) internal dia of BSS quality and weight completewith jointing material.

Material Fixing (Labour) RateSr. Dia of Cost of Contractor's Total Labour CompositeNo. Pipe Air Valve Profit Labour Material Total

20.00

a Single 3,500.00 700.00 4,200.00 10.64 79.20 89.84 89.85 4,289.84

b Double 4,000.00 800.00 4,800.00 10.64 79.20 89.84 89.85 4,889.84

20

Page 115: Rate analsis Chapter No. 23 (Tube Wells)

115

34 Providing and fitting CI flanges on pipes, including turning, threading, facing and fitting etc.

complete in all respects.

Per Flange Rates

S. Dia Labour Material Per Flange Per Kgs

# of No of Daily End Cutting Total Weight cost per cwt Total Labour Compo- Labour Compo-

pipe end Charges thread end per end of site site

thread flange (10 + 11)

P. day (5 + 6) in Lbs

1 2 3 4 5 6 7 8 9 10 11 12 13 14

a 3" 15.00 495.10 33.01 14.04 47.05 8.40 1270.00 102.49 47.05 149.54 12.34 39.24 Labour

4" 14.00 495.10 35.36 18.76 54.12 12.60 1270.00 120.85 54.12 174.97 9.47 30.61 Turner 1 No ### 170.00

5" 12.00 495.10 41.26 28.12 69.38 17.00 1270.00 192.77 69.38 262.15 8.99 33.99 Unskilled Coolies 1 No ### 140.00

6" 11.00 495.10 45.01 37.48 82.49 21.00 1270.00 238.13 82.49 320.62 8.66 33.65 Total 310.00

Average 8.88 33.87 Sundries 10.00 Percen 31.00

b 8" 9.00 495.10 55.01 56.24 111.25 35.70 1270.00 404.81 111.25 516.06 6.87 31.86 Total 341.00

10" 7.00 495.10 70.73 75.00 145.73 52.50 1270.00 595.31 145.73 741.04 6.12 31.11 Contractor's Prof 10.00 Percen 34.10

12" 5.00 495.10 99.02 90.00 189.02 74.55 1270.00 845.34 189.02 1034.36 5.59 30.58 Total 375.10

Average 5.70 30.69 L.S. 120.00

c 15" 3.00 495.10 165.03 102.28 267.31 110.00 1270.00 1247.32 267.31 1514.63 5.36 30.35 Total 495.10

18" 2.00 495.10 247.55 112.52 360.07 153.00 1270.00 1734.91 360.07 2094.98 5.19 30.18

Average 4.73 29.72 ###

Mechanic & Electrical charges

Page 116: Rate analsis Chapter No. 23 (Tube Wells)

116

20

Page 117: Rate analsis Chapter No. 23 (Tube Wells)

117

35 Cutting C.I. Pipe and welding spigot or socket, flanged or tyton end after finishing ends of pipes.

Sr. No. Dia of Cutting Circumference Welding Charges Cutting G.Total Say Rate per Rate per Pipe Inch. End of Pipe in Rate per Total 2 Ends and inch bore cm bore

Inch. Inch. (4 + 5) Finishing (Double Col. 3)

1 2 3 4 5 6 7 8 9 10 11

1 3" (75mm) 14.04 9.42 4.80 45.22 28.08 73.30 73.30 24.43

2 4" (100mm) 18.76 12.57 4.80 60.34 37.52 97.86 97.85 24.46

3 5" (125mm) 28.12 15.71 4.80 75.41 56.24 131.65 131.65 26.33

4 6" (150mm) 37.48 18.85 4.80 90.48 74.96 165.44 165.45 27.58

Average 25.71 10.15

5 8" (20mm) 56.24 25.13 4.80 120.62 112.48 233.10 233.10 29.14

6 10" (250mm) 75.00 31.42 4.80 150.82 150.00 300.82 300.80 30.08

7 12" (300mm) 90.00 37.70 4.80 180.96 180.00 360.96 360.95 30.08

Average 29.77 11.70

8 15" (385mm) 102.28 47.12 4.80 226.18 204.56 430.74 430.75 28.72

9 18" (450mm) 112.52 56.55 4.80 271.44 225.04 496.48 496.50 27.58

Average 28.15 11.70

Page 118: Rate analsis Chapter No. 23 (Tube Wells)

118

20

Page 119: Rate analsis Chapter No. 23 (Tube Wells)

119

36 Providing, laying, cutting, jointing, testing and disinfecting G.I. Pipe Line in trenches, with flanged joints, using G.I. pipe of BSS 1387-1967 Heavy Quality complete in all

respects, including specials and valves:-

i) G.I. FLANGED JOINTS

Sr. Dia of Cost Speical Advot Wastage Total Contractor Total No. of Daily Daily Total Material Per Ft. Length of Pipe Total

No. Pipe Inch 100' 10% 1% 2% (3 + 4 + Profit Joints Progress Charges Size No. Rate Amount Wt. Amount (13 +

heavy + 5 + 6) 10% (7 + 8) (15 x 16) Lbs. Rs. 17 +

quality 24.00 19)

per Lbs.

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

a 1½" (40mm) 542 54.20 5.42 10.84 612.46 61.25 673.71 8 20 495.00 198.00 3/8 3.00 4 12.00 0.35 8.40 218.40

b 2" (50mm) 7,176 717.60 71.76 143.52 8108.88 810.89 8919.77 8 20 495.00 198.00 3/8 3.00 4 12.00 0.35 8.40 218.40

c 2½" (63mm) 9,310 931.00 93.10 186.20 10520.30 1052.03 11572.33 8 20 495.00 198.00 5/8 3.00 6 18.00 0.50 12.00 228.00

d 3" (75mm) 11,754 1175.40 117.54 235.08 13282.02 1328.20 14610.22 6 15 495.00 198.00 5/8 4.00 6 24.00 0.50 12.00 234.00

e 4" (100mm) 16,943 1694.30 169.43 338.86 19145.59 1914.56 21060.15 6 12 495.00 247.50 5/8 4.00 6 24.00 0.60 14.40 285.90

f 6" (125mm) 23,243 2324.30 232.43 464.86 26264.59 2626.46 28891.05 6 10 495.00 297.00 5/8 4.00 6 24.00 0.60 14.40 335.40

g 8" (150mm) 27,443 2744.30 274.43 548.86 31010.59 3101.06 34111.65 6 10 495.00 297.00 5/8 4.00 6 24.00 0.60 14.40 335.40

DAILY PROGRESS

Mechanic 1 No. 17 170.00 170.00

Cooly 2 No. 7 140.00 280.00

Total 450.00

Sundries 10.00 Percent 45.00

Total 495.00

36 Providing, laying, cutting, jointing, testing and disinfecting G.I. Pipe Line in trenches, with flanged joints, using G.I. pipe of BSS complete in all 1387-1967 Medium Quality

respects, including specials and valves:-

ii) G.I. FLANGED JOINTS 20

Sr. Dia of Cost of Speical Advot Wastage Total Contr- Total No. of Daily Daily Labour Bolts and Nuts Rubber Insertion Total

No. Pipe Flanged 20.00 1% 2% actor's Joints Progress Charges for Size No. Rate Amount Wt. Amount (13 + 17

Inch. Pipe Profit 100' Lbs. Rs. + 19)

Page 120: Rate analsis Chapter No. 23 (Tube Wells)

120

20.00 24

per Lbs.

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

a 1½" (40mm) 5,350 1070.00 107.00 214.00 6741.00 1348.20 8089.20 8 20 495.00 198.00 3/8 3.00 4.00 12.00 0.35 8.40 218.40

b 2" (50mm) 6,640 1328.00 132.80 265.60 8366.40 1673.28 10039.68 8 20 495.00 198.00 3/8 3.00 4.00 12.00 0.35 8.40 218.40

c 2½" (63mm) 9,224 1844.80 184.48 368.96 11622.24 2324.45 13946.69 8 20 495.00 198.00 5/8 3.00 6.00 18.00 0.50 12.00 228.00

d 3" (75mm) 10,640 2128.00 212.80 425.60 13406.40 2681.28 16087.68 6 15 495.00 198.00 5/8 4.00 6.00 24.00 0.50 12.00 234.00

e 4" (100mm) 16,740 3348.00 334.80 669.60 21092.40 4218.48 25310.88 6 12 495.00 247.50 5/8 4.00 6.00 24.00 0.60 14.40 285.90

f 6" (125mm) 22,138 4427.60 442.76 885.52 27893.88 5578.78 33472.66 6 10 495.00 297.00 5/8 4.00 6.00 24.00 0.60 14.40 335.40

g 8" (150mm) 25,950 5190.00 519.00 1038.00 32697.00 6539.40 39236.40 6 10 495.00 297.00 5/8 4.00 6.00 24.00 0.60 14.40 335.40

DAILY PROGRESS

Mechanic 1 No. 17 170.00 170.00

Cooly 2 No. 7 140.00 280.00

Total 450.00

Sundries 10.00 Percent 45.00

Total 495.00

Page 121: Rate analsis Chapter No. 23 (Tube Wells)

121

Contrator Total Carriage Testing Grand Rate Per 100 Ft Rate Per Foot Rate Per Metre

Profit & Total Labour Composte Labour Composite Labour Composite

10% (20 + Disfi- (22 + 23 (9 + 26)

21) necting + 24)

21 22 23 24 25 26 27 28 29 30 31

21.84 240.24 100.00 25.20 387.28 387.30 1061.01 3.87 10.61 12.70 34.80

21.84 240.24 100.00 25.60 387.68 387.70 9307.47 3.88 93.07 12.72 305.28

22.80 250.80 120.00 26.00 419.60 419.60 11991.93 4.20 119.92 13.76 393.34

23.40 257.40 120.00 26.40 427.20 427.20 15037.42 4.27 150.37 14.01 493.23

28.59 314.49 120.00 28.10 491.18 491.20 21551.35 4.91 215.51 16.11 706.88

33.54 368.94 120.00 29.50 551.98 552.00 29443.05 5.52 294.43 18.11 965.73

33.54 368.94 120.00 31.00 553.48 553.50 34665.15 5.54 346.65 18.15 1137.02

Contr- Total Carriage Testing Grand Rate Per 100 Ft. Rate Per Ft. Rate Per Metre.

ator's (20 + 21) and Total Labour Compo- Labour Compo- Labour Composite

Profit disin- (22 + 23 site site

Page 122: Rate analsis Chapter No. 23 (Tube Wells)

122

10% fection + 24) (26 + 9)

21 22 23 24 25 26 27 28 29 30 31

21.84 240.24 100.00 34.14 396.22 396.20 8485.40 3.96 84.85 13.00 278.32

21.84 240.24 100.00 34.68 396.76 396.75 10436.43 3.97 104.36 13.01 342.31

22.80 250.80 120.00 34.71 428.31 428.30 14374.99 4.28 143.75 14.05 471.50

23.40 257.40 120.00 34.94 435.74 435.75 16523.43 4.36 165.23 14.29 541.97

28.59 314.49 120.00 37.47 500.55 500.55 25811.43 5.01 258.11 16.42 846.61

33.54 368.94 120.00 39.64 562.12 562.10 34034.76 5.62 340.35 18.44 1116.34

33.54 368.94 120.00 41.66 564.14 564.15 39800.55 5.64 398.01 18.50 1305.46

Page 123: Rate analsis Chapter No. 23 (Tube Wells)

123

37 Providing and Installing PVC Bends of BSS.

(i) Class "B" Working Pressure

Sr. Size MATERIAL LABOUR JOINTING Grand RATE

No. Rate Contractor's Total SOLVENT Daily Daily Amount Total Labour Composite

Each Profit (3 + 4) Quantity Rate Total Contractor Total progress Charges (10 + 13) (5 + 15)

20 Profit

Percent Kgs. Per Kg. 20.00 (8 + 9) (Joints)

1 2 3 4 5 6 7.00 8 9 10 11 12 13 14 15 16

1 3" (75mm) 305.00 61.00 366.00 1/27 748.00 27.70 5.54 33.24 50.00 394.43 15.78 49.02 49.00 415.00

2 4" (100mm) 577.40 115.48 692.88 1/20 748.00 37.40 7.48 44.88 50.00 394.43 15.78 60.66 60.65 753.53

3 5" (125mm) 724.00 144.80 868.80 1/16 748.00 46.75 9.35 56.10 40.00 394.43 19.72 75.82 75.80 944.60

4 6" (150mm) 996.00 199.20 1195.20 1/15 748.00 49.87 9.97 59.84 40.00 394.43 19.72 79.56 79.55 1274.75

(ii) CLASS "D" WORKING PRESSURE

1 1¼" (32mm) 68.00 6.80 74.80 1/64 748.00 11.69 1.17 12.86 60.00 394.43 13.15 26.00 26.00 100.80

2 1½" (40mm) 86.00 8.60 94.60 1/50 748.00 14.96 1.50 16.46 60.00 394.43 13.15 29.60 29.60 124.20

3 2" (50mm) 127.00 12.70 139.70 1/40 748.00 18.70 1.87 20.57 60.00 394.43 13.15 33.72 33.70 173.40

4 3" (75mm) 305.00 30.50 335.50 1/27 748.00 27.70 2.77 30.47 50.00 394.43 15.78 46.25 46.25 381.75

5 4" (100mm) 577.49 57.75 635.24 1/20 748.00 37.40 3.74 41.14 50.00 394.43 15.78 56.92 56.90 692.14

6 5" (125mm) 724.00 72.40 796.40 1/16 748.00 46.75 4.68 51.43 40.00 394.43 19.72 71.15 71.15 867.55

7 6" (150mm) 996.00 99.60 1095.60 1/15 748.00 49.87 4.99 54.85 40.00 394.43 19.72 74.57 74.60 1170.20

DAILY PROGRESS

Plumber 1 N 170.00 Per day 170.00 Sundries 10.00 Percent 29.88 Total 394.43Cooly 0.9 140.00 Per day 128.80 Total 328.68 Say 394.43Total 298.80 Contractor Profit 20.00 Percent 65.74

Page 124: Rate analsis Chapter No. 23 (Tube Wells)

124

38 Providing and Installing PVC Tee of BSS.20

(i) Class "B" Working Pressure

Sr. Size MATERIAL LABOUR JOINTING Grand RATENo. Rate Contractor's Total SOLVENT Daily Daily Amount Total Labour Composite

Each Profit (3 + 4) Quantity Rate TotalContractor's Total progress Charges (10 + 13) (5 + 15) 20.00 Kgs. Per Kg. 20.00 (8 + 9) (Joints)

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 161 3" (75mm) 361 72.20 433.2 1/18 748.00 41.56 8.31 49.87 50.00 394.43 23.67 73.53 73.55 506.752 4" (100mm) 725 145.00 870.0 1/13 748.00 57.54 11.51 69.05 50.00 394.43 23.67 92.71 92.70 962.703 5" (125mm) 1,100 220.00 1320.0 1/11 748.00 68.00 13.60 81.60 40.00 394.43 29.58 111.18 111.20 1431.204 6" (150mm) 1,450 290.00 1740.0 1/10 748.00 74.80 14.96 89.76 40.00 394.43 29.58 119.34 119.35 1859.35

(ii) CLASS "D" WORKING PRESSURE

1 1¼" (32mm) 96 19.20 115.2 1/40 748.00 18.70 3.74 22.44 60.00 394.43 19.72 42.16 42.15 157.352 1½" (40mm) 118 23.60 141.6 1/33 748.00 22.67 4.53 27.20 60.00 394.43 19.72 46.92 46.90 188.503 2" (50mm) 157 31.40 188.4 1/27 748.00 27.70 5.54 33.24 60.00 394.43 19.72 52.97 52.95 241.354 3" (75mm) 361 72.20 433.2 1/18 748.00 41.56 8.31 49.87 50.00 394.43 23.67 73.53 73.55 506.755 4" (100mm) 725 145.00 870.0 1/13 748.00 57.54 11.51 69.05 50.00 394.43 23.67 92.71 92.70 962.706 5" (125mm) 1,100 220.00 1320.0 1/11 748.00 68.00 13.60 81.60 40.00 394.43 29.58 111.18 111.20 1431.207 6" (150mm) 1,450 290.00 1740.0 1/10 748.00 74.80 14.96 89.76 40.00 394.43 29.58 119.34 119.35 1859.35

DAILY PROGRESS

Plumber 1 N 170.00 Per day 170.00 Sundries 10.00 Percent 29.88 Total 394.43Cooly 0.9 140.00 Per day 128.80 Total 328.68 Say 394.43Total 298.80 Contractor Profit 20.00 Percent 65.74

Page 125: Rate analsis Chapter No. 23 (Tube Wells)

125

39 Providing and Installation of PVC Sockets B.S.S

(i) Class "B" Working Pressure

Sr. Size MATERIAL LABOUR JOINTING Grand RATENo. Rate Contr- Total SOLVENT No. of Daily Amount Total Labour Composite

Each actor's (3 + 4) Quantity Rate Total Contra- Total Joints Charges (10 + 13) (5 + 15) 10.00 Kgs. Per Kg. ctor's (8 + 9)

10.00 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 161 3" (75mm) 27.00 2.70 29.70 1/27 748.00 27.70 2.77 30.47 50.00 394.43 7.89 38.36 38.35 68.052 4" (100mm) 52.00 5.20 57.20 1/20 748.00 37.40 3.74 41.14 50.00 394.43 7.89 49.03 49.05 106.253 5" (125mm) 108.00 10.80 118.80 1/16 748.00 46.75 4.68 51.43 40.00 394.43 9.86 61.29 61.30 180.104 6" (150mm) 164.00 16.40 180.40 1/15 748.00 49.87 4.99 54.85 40.00 394.43 9.86 64.71 64.70 245.105 8" (200mm) 267.00 26.70 293.70 1/10 748.00 74.80 7.48 82.28 30.00 394.43 13.15 95.43 95.45 389.156 10" (250mm) 315.50 31.55 347.05 1/8 748.00 93.50 9.35 102.85 30.00 394.43 13.15 116.00 116.00 463.057 12" (300mm) 364.00 36.40 400.40 1/7 748.00 106.86 10.69 117.54 25.00 394.43 15.78 133.32 133.30 533.708 14" (350mm) 435.00 43.50 478.50 1/6 748.00 124.67 12.47 137.13 25.00 394.43 15.78 152.91 152.90 631.40

(ii) CLASS "D" WORKING PRESSURE

1 1¼" (32mm) 8.30 0.83 9.13 1/64 748.00 11.69 1.17 12.86 60.00 394.43 6.57 19.43 19.45 28.582 1½" (40mm) 12.00 1.20 13.20 1/50 748.00 14.96 1.50 16.46 60.00 394.43 6.57 23.03 23.05 36.253 2" (50mm) 17.00 1.70 18.70 1/40 748.00 18.70 1.87 20.57 60.00 394.43 6.57 27.14 27.15 45.854 3" (75mm) 44.00 4.40 48.40 1/27 748.00 27.70 2.77 30.47 50.00 394.43 7.89 38.36 38.35 86.755 4" (100mm) 66.00 6.60 72.60 1/20 748.00 37.40 3.74 41.14 50.00 394.43 7.89 49.03 49.05 121.656 5" (125mm) 157.00 15.70 172.70 1/16 748.00 46.75 4.68 51.43 40.00 394.43 9.86 61.29 61.30 234.007 6" (150mm) 255.00 25.50 280.50 1/15 748.00 49.87 4.99 54.85 40.00 394.43 9.86 64.71 64.70 345.20

DAILY PROGRESS

Plumber 1 N 170.00 Per day 170.00 Sundries 10.00 Percent 29.88 Total 394.43Cooly 0.9 140.00 Per day 128.80 Total 328.68 Say 394.43Total 298.80 Contractor Profit 20.00 Percent 65.74

Page 126: Rate analsis Chapter No. 23 (Tube Wells)

126

40 - Providing and installing PVC Tappered Core BSS

41 (i) Class "B" Working Pressure

Sr. Size MATERIAL LABOUR JOINTING Grand RATENo. Rate Contra- Total SOLVENT Daily Daily Amount Total Labour Composite

Each ctor's (3 + 4) Quantity Rate Total Contra- Total Progress Charges (10 + 13) (5 + 15) Profit Kgs. Per Kg. ctor's (8 + 9)

20.00 Profit 20.00

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 161 3" (75mm) 30.00 6.00 36.00 1/27 748.00 27.70 5.54 33.24 50.00 394.43 15.78 49.02 49.00 85.002 4" (100mm) 40.00 8.00 48.00 1/20 748.00 37.40 7.48 44.88 50.00 394.43 15.78 60.66 60.65 108.653 5" (125mm) 50.00 10.00 60.00 1/16 748.00 46.75 9.35 56.10 40.00 394.43 19.72 65.01 65.00 125.004 6" (150mm) 60.00 12.00 72.00 1/15 748.00 49.87 9.97 59.84 40.00 394.43 19.72 79.56 79.55 151.555 8" (200mm) 100.00 20.00 120.00 1/10 748.00 74.80 14.96 89.76 30.00 394.43 26.30 116.06 116.05 236.056 10" (250mm) 130.00 26.00 156.00 1/8 748.00 93.50 18.70 112.20 30.00 394.43 26.30 138.50 138.50 294.507 12" (300mm) 160.00 32.00 192.00 1/7 748.00 106.86 21.37 128.23 25.00 394.43 31.55 159.78 159.80 351.808 14" (350mm) 200.00 40.00 240.00 1/6 748.00 124.67 24.93 149.60 25.00 394.43 31.55 181.15 181.15 421.15

36 (ii) CLASS "D" WORKING PRESSURE

1 1¼" (32mm) 15.00 3.00 18.00 1/64 748.00 11.69 2.34 14.03 60.00 394.43 13.15 27.17 27.15 45.152 1½" (40mm) 20.00 4.00 24.00 1/50 748.00 14.96 2.99 17.95 60.00 394.43 13.15 31.10 31.10 55.103 2" (50mm) 25.00 5.00 30.00 1/40 748.00 18.70 3.74 22.44 60.00 394.43 13.15 35.59 35.60 65.60

DAILY PROGRESS

Plumber 1 N 170.00 Per day 170.00 Sundries 10.00 Percent 29.88 Total 394.43Cooly 0.9 140.00 Per day 128.80 Total 328.68 Say 394.43Total 298.80 Contractor Profit 20.00 Percent 65.74

Page 127: Rate analsis Chapter No. 23 (Tube Wells)

127

Sr. No. 41

Making Connection for new Water Supply lines with the running main, including excavation oftrench and refilling, complete, but excluding cost of pipe and specials, etc.

i) Upto 150mm (6") i/d

Detail Unit Rate (British System) per Connection

Qty RatePer Unit (Rs.) Amount (Rs.)

LabourCooly for excavating/ refilling thetrench 0.50 No 140.00 P. Day 70.00 Plumber for cutting, connectingpipe, etc. 2 cuts 0.25 No 170.00 P. Day 42.50

Total 112.50 Sundries 10.00 Percent 11.25 Total 123.75

Contractor's P 20.00 Percent 24.75 Total 148.50

Bailing out water from the trenchafter cutting running main, takingaverage quantity of water as 500Cft. (14 Cum) @ Rs. 272.25% Cft 277.20

(Item No. 35, Chap: Miscellaneous) 148.50

425.70

Rate Per Connection Say Rs. 425.70

20

Page 128: Rate analsis Chapter No. 23 (Tube Wells)

128

ii) Upto 200mm (8") i/d

Detail Unit Rate (British System) per Connection

Qty RatePer Unit (Rs.) Amount (Rs.)

Labour

Cooly for excavating/ refilling thetrench 0.50 No 140.00 P. Day 70.00 Plumber for cutting, connectingpipe, etc. 2 cuts 0.25 No 170.00 P. Day 42.50

Total 112.50 Sundries 10.00 Percent 11.25 Total 123.75

Contractor's PErr:540 Percent 12.38 Total 136.13

Bailing out water from the trenchafter cutting running main, takingaverage quantity of water as 700Cft. (19.60 Cum) @ Rs. 272.25% Cft 388.08 ( Item No. 35, Chap: 26 ) 136.13

524.20

Rate Per Connection Say Rs. 524.20

Page 129: Rate analsis Chapter No. 23 (Tube Wells)

129

iii) Upto 250mm (10") i/d

Detail Unit Rate (British System) per Connection

Qty RatePer Unit (Rs.) Amount (Rs.)

Labour

Cooly for excavating/ refilling thetrench 0.50 No 75.00 P. Day 37.50 Plumber for cutting pipe, etc.2 cuts 0.50 No 170.00 P. Day 85.00

Total 122.50 Sundries 10.00 Percent 12.25 Total 134.75

Contractor's Pr 20.00 Percent 26.95 Total 161.70

Bailing out water from the trenchafter cutting running main, takingaverage quantity of water as 1000Cft. (28 Cum) 554.40 554.40 ( Item No. 35, Chap: 26 ) 161.70

716.10

Labour Rate Per Connection Say Rs. 716.10

%o Cft.Rs.

Page 130: Rate analsis Chapter No. 23 (Tube Wells)

130

iv) Upto 300mm (12") i/d

Detail Unit Rate (British System) per Connection

Qty RatePer Unit (Rs.) Amount (Rs.)

Labour

Cooly for excavating/ refilling thetrench 0.50 No 75.00 P. Day 37.50 Plumber for cutting pipe, etc.2 cuts 0.50 No 170.00 P. Day 85.00

Total 122.50 Sundries 10.00 Percent 12.25 Total 134.75

Contractor's Pr 20.00 Percent 26.95 Total 161.70

Bailing out water from the trenchafter cutting running main, takingaverage quantity of water as 1500Cft. (48 Cum) 554.40 831.60 ( Item No. 35, Chap: 26 ) 161.70

993.30

Labour Rate Per Connection Say Rs. 993.30

%o Cft.Rs.

Page 131: Rate analsis Chapter No. 23 (Tube Wells)

131

v) Upto 400mm (16") i/d

Detail Unit Rate (British System) per Connection

Qty RatePer Unit (Rs.) Amount (Rs.)

Labour

Cooly for excavating/ refilling thetrench 0.50 No 75.00 P. Day 37.50 Plumber for cutting pipe, etc.2 cuts 0.75 No 170.00 P. Day 127.50

Total 165.00 Sundries 10.00 Percent 16.50 Total 181.50

Contractor's Pr 20.00 Percent 36.30 Total 217.80

Bailing out water from the trenchafter cutting running main, takingaverage quantity of water as 1825

Cft.(51.10 Cum 554.40 1,011.78 ( Item No. 35, Chap: 26 ) 217.80

1,229.58

Labour Rate Per Connection Say Rs. 1229.60

%o Cft.Rs.

Page 132: Rate analsis Chapter No. 23 (Tube Wells)

132

vi) Upto 500mm (20") i/d

Detail Unit Rate (British System) per Connection

Qty RatePer Unit (Rs.) Amount (Rs.)

Labour

Cooly for excavating/ refilling thetrench 0.50 No 75.00 P. Day 37.50 Plumber for cutting pipe, etc.2 cuts 0.75 No 170.00 P. Day 127.50

Total 165.00 Sundries 10.00 Percent 16.50 Total 181.50

Contractor's Pr 20.00 Percent 36.30 Total 217.80

Bailing out water from the trenchafter cutting running main, takingaverage quantity of water as 2500

Cft.(70 Cum) @ 554.40 1,386.00 ( Item No. 35, Chap: 26 ) 217.80

1,603.80

Labour Rate Per Connection Say Rs. 1603.80

%o Cft.Rs.

Page 133: Rate analsis Chapter No. 23 (Tube Wells)

133

vii) Upto 600mm (24") i/d

Detail Unit Rate (British System) per Connection

Qty RatePer Unit (Rs.) Amount (Rs.)

Labour

Cooly for excavating/ refilling thetrench 0.50 No 75.00 P. Day 37.50 Plumber for cutting pipe, etc.2 cuts 1.00 No 170.00 P. Day 170.00

Total 207.50 Sundries 10.00 Percent 20.75 Total 228.25

Contractor's Pr 20.00 Percent 45.65 Total 273.90

Bailing out water from the trenchafter cutting running main, takingaverage quantity of water as 3000

Cft. (85 Cum) @ 554.40 1,663.20 ( Item No. 35, Chap: 26 ) 273.90

1,937.10

Labour Rate Per Connection Say Rs. 1937.10

%o Cft.Rs.