RAP of River Mindhola INDEX Sr. No. Particulates Page No. A EXECUTING SUMMARY 1 River Action Plan of River Mindhola 1 Background 4 2 Municipal Sewage Generation and Treatment 4 3 Status of Industrial effluent and treatment facilities 5 4 Drain out-falling in River Mindhola 6 5 Status of Water Quality 7 6 Plan for restoration of Water Quality 8 7A Solid Waste Generation & Treatment 8 7B Bio Medical Waste 9 7C Industrial Waste 9 8 Ground Water extraction details 9 8A Details of bore well samples- River Mindhola 10 9 Environmental Flow (E-Flow) 12 10 Plantation/Vegetation cover along the River stretch/River 12 11 Biodiversity Park 12 12 Details of good Irrigation Practices 12 13 Details on Flood plain management zone 13 14 Public Health Study in the vicinity of polluted river stretch 13 15 Time Targeted Management Plan 13 ANNEXURE Annexure-I List of other Responsible Organization (s) for implementation of River action plans 14 Annexure-I (a) Responsible Organization (s) for implementation of action plans of STPs & CETPs 15 Annexure:- II Proposed Mechanism for execution of action plans 16 Annexure-A Map of Mindhola River 17 Annexure-B Data received from Health dept. (Health Impact Study & Mitigation Measures) 18

Transcript of RAP of River Mindhola INDEX Sr. No. Particulates Page No ... · RAP of River Mindhola INDEX Sr. No....

RAP of River Mindhola

INDEX

Sr. No. Particulates Page No. A EXECUTING SUMMARY 1

River Action Plan of River Mindhola 1 Background 4

2 Municipal Sewage Generation and Treatment 4 3 Status of Industrial effluent and treatment facilities 5

4 Drain out-falling in River Mindhola 6 5 Status of Water Quality 7

6 Plan for restoration of Water Quality 8

7A Solid Waste Generation & Treatment 8 7B Bio Medical Waste 9

7C Industrial Waste 9 8 Ground Water extraction details 9

8A Details of bore well samples- River Mindhola 10 9 Environmental Flow (E-Flow) 12

10 Plantation/Vegetation cover along the River stretch/River

12

11 Biodiversity Park 12

12 Details of good Irrigation Practices 12 13 Details on Flood plain management zone 13

14 Public Health Study in the vicinity of polluted river stretch

13

15 Time Targeted Management Plan 13

ANNEXURE

Annexure-I List of other Responsible Organization (s) for implementation of River action plans

14

Annexure-I (a) Responsible Organization (s) for implementation of action plans of STPs & CETPs

15

Annexure:- II Proposed Mechanism for execution of action plans 16

Annexure-A Map of Mindhola River 17

Annexure-B Data received from Health dept. (Health Impact Study & Mitigation Measures)

18

TABLE Table: 1 Status of Domestic Pollution in Mindhola 5

Table: 2 Industries- Water shed of River Mindhola 6 Table: 3 Particulars of Drains Falling into River Mindhola 6

Table: 4 Status of water quality in Major Drains 7

Table: 5 Quantity of effluent in sub tributary drains meting to major drains

7

Table: 6 Status of Water Quality of Mindhola 7

Page | 1

EXECUTING SUMMARY ON PROPOSED ACTION PLANS OF MINDHOLA FOR REJUVENATION OF POLLUTED RIVER STRETCH (PRS) Of MINDHOLA

S. No.

DESCRIPTION OF ITEM Details

1. Name of the identified polluted river and its tributaries

: River:- MINDHOLA PRS:- Along Sachin

Tributaries of PRS:- -- pl. Refer tablel-5

2. Is river is perineal and total length of the polluted river

: Non- Perennial river Length:- 10 KM

3. No of drains contributing to pollution and names of major drains

: Total No of drains:- 01 Name of Drains (Location):

i) Kapletha village drain

4. Whether ‘River Rejuvenation Committee (RRC) constituted by the State Govt./UT Administration and If so, Date of constitution of ‘RRC’

: Yes, The “River Rejuvenation Committee (RRC)” has been constituted on 29th November, 2018 by Forest and Environment Department, Govt. of Gujarat for the execution of River Action Plan (RAP) of the Gujarat.

5. Major Towns on the banks of the river with population

: Name of Town/Area/villages

Population

Town Sachin 129585

a. Total water consumption and sewage generation in MLD

: Total Water consumption:- 2 MLD Total Sewage generation:- 1.6 MLD

b. Total no. of existing STPs and the total capacities in MLD

: No. of existing STPs: - No STPs

c. Gaps in sewage treatment in MLD and no. of towns not having STPs

: Total Gaps in sewage treatment: - 1.6 MLD. No. of Towns/Villages not having STPs:- as per below:-

Name of Area/Towns/

Villages

Remarks

Sachin Town Proposed STP- 2MLD + 2 MLD cap.

d. Total MSW generation in TPA : MSW:- 3650 TPA (10 TPD)

e. Existing treatment and disposal facilities and total capacity

: Authorized Agencies/end users/recyclers

6. Major industrial estates located with total no. of industries

: No effluent discharge by industry into this stretch

a. Total water consumption and total industrial effluent generation in MLD

:

b. No. of industries having captive :

Page | 2

ETPs and their treatment capacity in MLD

c. No of CETP’s and their treatment capacity

: No CETPs

d. Gaps in treatment of industrial effluent

: No effluent discharge by industry into this

stretch

e. Total HW generation in TPA in the catchment area

: NA

f. Existing HW Treatment and Disposal Facilities and total capacity with life span

:

7. Action plan includes mainly covering aspect such as (Proposal for utilisation of sewage, ground water recharging or rain water harvesting, measures for regulating ground water use, protection and management of flood plain zone, maintaining minimum E-flows and water shed management, plantation on both sides of the river, setting up of bio-diversity parks etc., as per Hon’ble NGT Orders dated 20.09.2018 and 19.12.2018)

: No, details are not available with the Board hence letters to concern authority/organizations have been issued as under for the necessary actions. Please also refer Annexure:- I

Concern

Authority/

Organizations

For the activities

/issues

Central Ground Water Authority/Gujarat Water Resource Development Corporation Ltd.

Ground water related

issues & for

implementation of the

schemes related to

recharging of Ground

water

Irrigation department

E-flow, regulation of

activities in flood plain

zone & Flood plain

management , Good

Irrigation Practices etc.

Forest offices of the Gujarat

Plantation /Vegetation

cover along the River

stretch/River, setting

up of Biodiversity Park

etc.

Sachin Notified Area

Proper

disposal/Treatment of

Sewage

Page | 3

8. Min. and Max. required time period for implementation of action plans

up to 2020 (Approximate)

9. Total estimated budget in crores

towards implementation of

proposed action plans with break-

up ( e.g. No. of STPs, capacity, total

cost; No of CETPs, total capacity,

Cost towards interception and

diversion of sewage/effluent to

STPs/CETPs etc.,)

: STPs Details:-

Proposed STP MLD

Time Limit

Estimated Budget in Cr.

Responsible Agency

Sachin- 2 +2 MLD

24 months (2020)

20 cr. Sachin Notified Area

CETPs Details:- No effluent discharge by industry into this

stretch

10. Responsible Organisation (s) for implementation of proposed action plans (Please enclose details as annexure )

: Annexure:- I & I (a)

11. Proposed Mechanism for execution of action plans

: Annexure:-II

12. Expected deliverables w r to achieving Goals (Please enclose as annexure )

: As above

Page | 4

River Action Plan of River Mindhola

AlongSachin

Priority V

1. Background

Location of river stretch with geographical detail like Latitude & Longitude etc.

Stretch identified: River Mindhola flowing along Sachin having 10 KM stretch

and is non-perennial river.

Latitude : 21o3’17.53” N

Longitude: 72o52’47.31” E

Towns mentioned: Sachin

Background of pollution causes into river stretch

River Mindhola flows passing from villages in BardoliTaluka and merges into Arabian Sea via

Sachin. The domestic discharge is done in River Mindhola. The downstream of the river

Mindhola witnesses domestic discharge via creeks. There is no industrial discharge from GIDC

or notified area in this stretch. This stretch along Sachin is basically the downstream part which

is not contaminating the sweet water.

2. Municipal Sewage Generation and Treatment

Name of towns/villages/area which are discharging their domestic sewage into river

stretch

Total domestic water consumption:-2 MLD

Town identified by CPCB is Sachin which are discharging their domestic sewage into this river

stretch are Kanakpur – Kansad, Pardi, Sachin GIDC, etc.

Page | 5

Quantity of domestic sewage discharged into river stretch

Quantity of domestic sewage discharged into this stretch is approximately 1.6 MLD.

Source: https://www.suratmunicipal.gov.in/TheCity/City/Stml2

Action taken to reduce pollution in river stretch

STP can be made by local authority. As per NGT application no. 50/2015(WZ) (M.A. No.

192/2015) GIDC Sachin notified area will provide STP and they have appointed M/s. M-W2E Eco

Ventures Pvt. Ltd. for technical assistance for this work. They are also intimated via written

letter regarding providing action plan for sewage treatment via letter no: ગપુ્રનિબોર્ડ/પ્રા.ક.

સરુત/કેમ્પ-સરુત/NGT/૨૩૬૩તા. ૧૬/૦૧/૨૦૧૯.

Table 1: Status of Domestic Pollution in River Mindhola

District

name/

area

Total domestic water consumption

Total

Sewage

Generati-

on in

MLD

Total

Capacity

of Sewage

Treatment

Plant in

MLD

Total gap

between

generation

&

treatment

capacity

in MLD

Achieve

norms

or not

if not

give

detail

plan to

achiev-

e it

Action to

be taken

to cover

gap

(model

plan STP-

with

capacity)

Time line

for

proposed

model

plan

(STP)

Population

Dist:

Surat

Town

Sachin

2 MLD 1.6 STP not

provided

1.6 -- 2 MLD +

2 MLD

at

different

location

in

Notified

area

Budget:

@ 20

crore

Year 2020 Population

of Sachin

129585

Total 2 MLD 1.6 MLD -- 1.6 MLD -- -- -- --

3. Status of Industrial effluent and treatment facilities

Total industrial water consumption:-No industrial waste water discharge so N A.

Total no. of industries: - N A

Major industrial estates located with total no. of industries: -N A

No. of industries having captive ETPs and their treatment capacity in MLD: - N A

Nos. of CETPs & Treatment capacity of CETPs: - N A

Page | 6

Type/category of industries discharging effluent into river stretch

No effluent discharge by industry into this stretch

Quantity of industrial effluentdischarged into river stretch

No effluent discharge by industry into this stretch

Table 2: Industries- water shed of River Mindhola

Sr.No. Category of

industries/Name of

CETP/Common

Pipeline

Location

/Area

(District)

Quantity Quality of

discharge

effluent

(Whether

achieve Outlet

norms or not

if not give

detail plan to

achieve it)

Proposed

model

plan

( CETP

with

Capacity)

Time

limit

Remarks

Not applicable

Analysis report format for CETP

Parameters pH COD

Mg/L

BOD

Mg/L

Not applicable

4. Drain out –Falling in river Mindhola

Table 3: Particulars of drains falling into River Mindhola.

Sr.No. Location Name of

Inletting

River/Drain

Discharged Length

(Km)

Width

(mtr)

Depth

(mtr)

Gradient of

the river

(cm/km) Max Min

1 Sachin

Notified

area

Kapletha

village drain

meeting

River

Mindhola

1.6

MLD

0.5 MLD

3 km 3 0.5 -

Note:- Entire Baleshwar Khadi is meeting to River Mindhola at village Samrod as major drain.

Polluted River action plan of Baleshwar Khadi is prepared and submitted separately.

Page | 7

Table 4: Status of Water quality in Major Drains

Location Major Drain BOD(mg/L) COD( mg/L)

River Mindholaat S.H.Surat-

NavsariRoad,Sachin

Kapletha village

drain meeting

River Mindhola

2.51 60.2

Table 5: Quantity of effluent in sub tributary drains meeting to major drains

Sr.

No

District Name of

the Drain

Place where

drains join

with river

Quantity of

effluent (MLD)

Remarks

No sub-tributary drains meeting to major drains.

5. Status of Water Quality

Location of water quality measuring station under NWMP

River Mindhola at S.H. Surat-Navsari Road,Sachin

Table 6: Status of Water Quality of River Mindhola

Year Location DO (mg/l) pH BOD (mg/l) COD (mg/l) Fecal

Coliform

(MPN/100)

Total

Coliform

(MPN/100)

Min

.

Max

.

Min

.

Max

.

Min

.

Max

.

Min

.

Max

.

Min. Max

.

Min. Max

.

2016 River Mindholaat

S.H. Surat-Navsari

Road

1.2 6 7.1

3

8.11 1 6 12 236 23 348 23 130

2017 River

MindholaatS.H.Sur

at-Navsari Road

3.6 6.5 7.0

8

8.19 1.2 3.1 4 45 94 426 278 542

2018 River

MindholaatS.H.Sur

at-NavsariRoad

4.6 6.9 7.1

3

7.88 1.2 9 42 89 3 120 17 348

Page | 8

6. Plan for Restoration of Water Quality

STP can be made by local authority. As per NGT application no. 50/2015(WZ) (M.A. No.

192/2015) GIDC Sachin notified area will provide STP and they have appointed M/s. M-W2E Eco

Ventures Pvt. Ltd. for technical assistance for this work. They are also intimated via written

letter regarding providing action plan for sewage treatment via letter no: ગપુ્રનિબોર્ડ/પ્રા.ક.

સરુત/કેમ્પ-સરુત/NGT/૨૩૬૩તા. ૧૬/૦૧/૨૦૧૯.

Steps Taken

STP can be made by local authority. As per NGT application no. 50/2015(WZ) (M.A. No.

192/2015) GIDC Sachin notified area will provide STP and they have appointed M/s. M-W2E Eco

Ventures Pvt. Ltd. for technical assistance for this work. Reply is received from Sachin Notified

Area Authority with reference to the letter sent.

Directions issued for planning and execution of facilities by municipal authorities to

develop infrastructure for sewage treatment

Directions issued for setting up online monitoring system in the industrial units for

enforcement of prescribed standards

7A. Solid Waste generation & Treatment

This data is relevant to local authority

Type of

waste/

Characteristic

of waste

Generated

quantity/

day

Collection/

Storage

facility with

capacity

Disposal/Treatment

facility with

capacity along with

location

Total Gap

with

generation

&existing

treatment

facilities if

any

Proposed

action

plan/facility

to cover

gap

Time

limit

Remarks

Solid waste, 10

-

-

Authorized

Agencies/end

users/recyclers

10

DPR is

under

processes

Year

2020

Total 10 10

Note: - Letter has been issued to Panchayat, Rural Housing & Rural Development Department by GPCB, Head

office-Gandhinagar (Letter No.:- GPCB/HO/Ankl/P-3-101 (3)/493163-2 dated 31/01/2019)

Page | 9

7B:- Bio-medical waste (BMW):-

Total no. of healthcare units in this stretch: 30

Disposal facilities i.e. Common Biomedical Waste Treatment Facility operational in Surat in this

stretch:

1) Globe Bio-Care

7C. Industrial Waste:-

All Industrial Units have consent with the authorization under Haz. Waste Management Rules,

amended time to time & they all are member of TSDF/CHWIF/registered recycler under Rule-

9/Co-processing and disposed their Industrial waste as per consent conditions. Please refer

Annexure:-I.

8. Ground Water extraction details

The details are not available with the Board hence letter to Central Ground Water Authority has been

issued by GPCB, Head office-Gandhinagar for the submission of the details.(Letter No.:-

GPCB/HO/Ankl/P-3-101 (3)/493160-2 dated 31/01/2019).

The details received from Central Ground Water Board, West Central Region are as under

District Taluka

Net Annual Ground Water

Availability (mcm)

Total Ground Water Draft

(mcm)

Gap between

availability and Draft

(mcm)

Stage of Ground Water

Development (%)*

Category

Surat CHORASI 171.63 70.16 101.47 40.88 *Safe (≤ 70) Surat PALSANA 122.74 60.99 61.76 49.69

Note:-The ground water resources assessment is carried out on Taluka wise(Administrative Units) The State Govt. has taken up various Recharge/Water Conservation Schemes like Sujalam Sufalam Yojana, Jal Sanchay Abhiyan etc for augmentation of ground water resources.

NOTE: Analysis results of borewells are attached as Annexure A

Page | 10

8A. Details of borewell samples- River Mindhola 41672 - WATER PROJECT NWQM BOREWELL ATSACHIN GIDC (SIEL), HALF YEARLY / S

Samp ID & Dt %NA ABHC ALK ARS BOD BOR CAD CAL CHL CND COD COL COP DDT DOX FCO FDS FLU HCH IRO

244578-08/10/2018 42.42 0.00 150 NA 0.9 0.05 NA 264.53 1570 9017.6 11 5 BDL 0.00 2.1 13 NA 0.4 0.0 NA

230988-04/04/2018 ND 140 BDL 2.2 0.08 BDL 104.2 1489 8571 11 5 BDL ND 4.5 2 NA 0.69

In process BDL

Avg. 42.4200 0.0000 145.0000 BDL 1.55 0.065 BDL 184.365 1529.5 8794.3 11.00 5.00 BDL 0.0000 3.3000 7.5000 NA 0.5450 0.0000 BDL

Samp ID & Dt LEA LIN MAG MER NH3 NIC NTR pH PHO POT SOD SS SUP T.H TCH TCO TDS TKN TMP TUR ZIN

244578-08/10/2018 BDL ND 182.4 NA 0.56 NA 0.118 7.42 0.033 5 480.11 32 580 1410 0.074 83 5636 3.08 32 8 0.029

230988-04/04/2018 BDL ND 68 BDL 0.56 0.012 0.108 7.64 0.02 2.72 212.2 12 330 540 BDL 8 5546 3.92 32 0.7 BDL

Avg. BDL ND 125.2 NA 0.56 0.012 0.113 7.53 0.0265 3.86 346.155 22 455 975 0.0740 45.5 5591 3.50 32.0 4.35 0.029

41675-WATER PROJECT NWQM BOREWELL AT NR COMMON HAZ WASTE DSPO.SITE (GEPIL), HALF YEARLY/S Samp ID &

Dt %NA ABHC ALK ARS BOD BOR CAD CAL CHL CND COD COL COP DDT DOX FCO FDS FLU HCH IRO

244567-08/10/2018 46.91 0.00 170 NA 0.9 0.04 NA 72.14 90 508.2 12 5 BDL 0.00 2.9 9 NA 0.38 0.0 NA

230987-04/04/2018 0.0 240 BDL 2.2 0.062 BDL 112.2 672 4555 11 5 BDL ND 4.5 2 NA 0.96 0.0 BDL

Avg. 46.91 0 205 BDL 1.550 0.051 BDL 92.170 381 2531.6 11.5 5 BDL 0.000 3.7 5.5 NA 0.67 0 BDL

Samp ID & Dt LEA LIN MAG MER NH3 NIC NTR pH PHO POT SOD SS SUP T.H TCH TCO TDS TKN TMP TUR ZIN

244567-08/10/2018 BDL 0.00 41.34 NA 0.84 NA 0.128 8.05 0.017 1.89 143.26 6 32 350 0.04 64 308 3.36 32 3 BDL

230987-04/04/2018 BDL ND 58.3 BDL 0.56 BDL 0.156 7.51 0.01 1.43 226.2 8 230 520 BDL 8 2718 4.48 32 1.3 BDL

Avg. BDL 0 49.820 NA 0.7 BDL 0.142 7.78 0.014 1.66 184.73 7 131 435 0.04 36 1513 3.920 32.000 2.150 BDL

Page | 11

31052 - WATER PROJECT NWQM OPEN WELL AT GABHENI OPP: PANCHYAT OFFICE, HALF YEARLY / S

Samp ID & Dt %NA ABHC ALK ARS BOD BOR CAD CAL CHL CND COD COL COP DDT DOX FCO FDS FLU HCH IRO

244570-08/10/2018 42.81 0.00 140 NA 0.8 0.03 NA 36.07 160 835.2 10 5 BDL 0.0 6.1 3 NA 0.14 0 NA

230985-04/04/2018 0.00 150 BDL 1.4 0.084 BDL 96.1 302 2178 9 5 BDL ND 4.9 120 NA 0.43 BDL BDL

Avg. 42.810 0.000 145.000 BDL 1.100 0.057 BDL 66.085 231 1506.6 9.5 5 BDL 0 5.5 61.5 NA 0.285 0.000 BDL

Samp ID & Dt LEA LIN MAG MER NH3 NIC NTR pH PHO POT SOD SS SUP T.H TCH TCO TDS TKN TMP TUR ZIN

244570-08/10/2018 BDL 0.00 29.18 NA 0.56 NA 0.088 8.2 0.013 2.12 73.26 8 65 210 0.042 0.04 522 2.8 32 3 BDL

230985-04/04/2018 BDL ND 46.2 BDL 0.28 BDL 0.098 7.25 0.02 3.8 143.2 12 89 430 BDL 348 1292 2.8 32 1.1 BDL

Avg. BDL 0 37.69 NA 0.420 BDL 0.093 7.725 0.017 2.96 108.23 10 77 320 0.042 174.021 907 2.8 32 2.05 BDL

ABHC α- B.H.C(Benzene

Hexa Chloride) CHL Chloride FCO Fecal coliform MAG Magnesium PHO Phosphate TCO Total Coliform

ALK Alkalinity CND Conductivitiy FDS Fixed Dissolved Solids MER Mercury POT Potassium TDS Total Dissolved Solids

ARS Arsenic COD

Chemical Oxygen Demand FLU Fluoride NH3

Ammonical Nitrogen SOD Sodium TKN Total Kjeldahl Nitrogen

BOD

Bio chemical oxygen Dimand COL Colour HCH

Hexa Valent Chromium NIC Nickel SS

Suspended Solids TMP Temperature

BOR Boron COP Copper IRO Iron NIT Nitrite SUP Sulphate TUR Turbidity

CAD Cadmium DDT

Dichloro Diphenyl trichloro Ethane LEA Lead NTR Nitrate TH Total Hardness ZIN Zinc

CAL Calcium DOX Dissolved Oxygen LIN Lindane pH pH TCH

Total Chromium %Na %Sodium

Page | 12

9. Environmental Flow (E-Flow)

Stretch Existing E-flow Proposed plan to

achieve min. E-

flow

Time Limit Remarks

This data is related to Irrigation Department. Letter is written to irrigation department by Regional

Office (via letter no: ગ.ુપ્ર.નિ.બોર્ડ/પ્રા.ક.સરુત/ટી-૩૩૬/૨૪૧૩dated 31/01/2019) & by Head office-

Gandhinagar (Letter No.:- GPCB/HO/Ankl/P-3-101 (3)/493164 dated 31/01/2019)

10. Plantation/Vegetation covers along River Stretch/River

This data is related to Forest Department. Letter is written to forest department by Regional Office

(via letter no: ગ.ુપ્ર.નિ.બોર્ડ/પ્રા.ક.સરુત/ટી-૩૩૬/૨૪૧૪dated 31/01/2019) & by Head office-Gandhinagar

(Letter No.:- GPCB/HO/Ankl/P-3-101 (3)/493160 dated 31/01/2019) for the submission of the details.

The details received from Social Forestry wing, Aranya Bhavan, Gandhinagar are as under

Stretch/river Existing

plantation/vegetation

cover details

Proposed plan to

cover remaining gap

along river/river

stretch

Time limit Remarks

Mindhola

(Along

sachin)

1250 trees

Presently there is no separate scheme for plantations

along river /river stretch

11. Biodiversity Park

This data is related to Forest Department. Letter is written to forest department by Regional Office

(via letter no: ગ.ુપ્ર.નિ.બોર્ડ/પ્રા.ક.સરુત/ટી-૩૩૬/૨૪૧૪dated 31/01/2019) & by Head office-Gandhinagar

(Letter No.:- GPCB/HO/Ankl/P-3-101 (3)/493160 dated 31/01/2019) for the submission of the details. The details received from Social Forestry wing, Aranya Bhavan, Gandhinagar are as under

District/Area

Name

Existing

Biodiversity

Park Name

Total area of

Biodiversity

park

Proposed

Biodiversity

park

Time limit Remarks

Nil

12. Details of good Irrigation Practices:

This data is related to Irrigation Department. Letter is written to irrigation department by Regional

Office (via letter no: ગ.ુપ્ર.નિ.બોર્ડ/પ્રા.ક.સરુત/ટી-૩૩૬/૨૪૧૩dated 31/01/2019) & by Head office-

Gandhinagar (Letter No.:- GPCB/HO/Ankl/P-3-101 (3)/493164 dated 31/01/2019)

Page | 13

13. Details on Flood plain management zone: This data is related to Irrigation Department. Letter is written to irrigation department by Regional

Office (via letter no: ગ.ુપ્ર.નિ.બોર્ડ/પ્રા.ક.સરુત/ટી-૩૩૬/૨૪૧૩dated 31/01/2019) & by Head office-

Gandhinagar (Letter No.:- GPCB/HO/Ankl/P-3-101 (3)/493164 dated 31/01/2019)

14. Public Health Study in the vicinity of polluted river stretch:- As details on Health Aspects are not available with the Board, it was decided to give the work to carry out Health impact study to NIOH, Ahmedabad. However as per the letter received from NIOH (letter No.:- DIR/108/GPCB-Proj/2019/9752 dated 07/02/2019) they are not able to carried out the study as per requirement, So letter has been issued to Health & Family welfare dept. to submit the action plan of Health Aspects includes Health impact study and mitigation measures to improve the health in the catchment of polluted river stretch. Data received from Health dept. is attached as Annexure-B

15. Time Targeted Management Plan STP can be made by local authority. As per NGT application no. 50/2015(WZ) (M.A. No. 192/2015) GIDC Sachin notified area will provide STP and they have appointed M/s. M-W2E Eco Ventures Pvt. Ltd. for technical assistance for this work. They are also intimated via written letter regarding providing action

plan for sewage treatment via letter no: ગપુ્રનિબોર્ડ/પ્રા.ક. સરુત/કેમ્પ-સરુત/NGT/૨૩૬૩તા. ૧૬/૦૧/૨૦૧૯.

Steps to be taken (Action plan) STP can be made by local authority. As per NGT application no. 50/2015(WZ) (M.A. No. 192/2015) GIDC Sachin notified area will provide STP and they have appointed M/s. M-W2E Eco Ventures Pvt. Ltd. for technical assistance for this work. Reply is received from Sachin Notified Area Authority with reference to the letter sent.

Timelines for implementation of model restoration plan for STPs at Sachin area (2+2 MLD)

Activity/Year Responsible Agency 2019 2020 Remarks

Reconnaissance

Survey

Sachin notified area

Sampling GPCB/CPCB Continuous

Process

Preparation of DPR Sachin notified area

Execution (Setting up

of model, facility)

Augmentation of

river flow if any and

restoration of water

quality

-- -- -- --

Note: - Letter has been issued to Panchayat, Rural Housing & Rural Development Department by GPCB, Head

office-Gandhinagar (Letter No.:- GPCB/HO/Ankl/P-3-101 (3)/493163-2 dated 31/01/2019)

Page | 14

Annexure:- I

List of other Responsible Organization (s) for implementation of River action plans

Responsible Organization

for the activities /issues Remarks

Central Ground Water Authority / Gujarat Water Resource Development Corporation Ltd.

Ground water related issues & for execution of the plan for the same etc.

Letter issued to Central Ground Water Authority by GPCB, Head office-Gandhinagar for the submission of the details vide Letter No.:- GPCB/HO/Ankl/P-3-101 (3)/493160-2 dated 31/01/2019. Some data received in this regards from Central Ground Water Board, West Central Region, Gandhinagar, are incorporated in the Point 8 of Action Plan.

Irrigation department

E-flow, regulation of activities in flood plain zone & Flood plain management , Good Irrigation Practices etc.

Letter to Irrigation division has been issued by GPCB, Head office-Gandhinagar (Letter No.:- GPCB/HO/Ankl/P-3-101 (3)/493164 dated 31/01/2019) & by Regional Office, GPCB

(ગ.ુપ્ર.નિ.બોર્ડ/પ્રા.ક.સરુત/ટી-૩૩૬/૨૪૧૩dated 31/01/2019) for the

submission of the details.

Forest offices of the Gujarat

Plantation /Vegetation cover along the River stretch/River, Biodiversity Park etc.

Letter issued to concerned Forest office by regional Office vide Letter No.:-

ગ.ુપ્ર.નિ.બોર્ડ/પ્રા.ક.સરુત/ટી-૩૩૬/૨૪૧૪dated

31/01/2019& by GPCB, Head office-Gandhinagar (Letter No.:- GPCB/HO/Ankl/P-3-101 (3)/493160 dated 31/01/2019) Some data received in this regards from Social Forestry wing, Aranyabhavan, Gandhinagar are incorporated in the Point 10 & 11 of Action Plan.

Urban Development and Urban Housing Department

For discharge & disposal of Sewage/Solid waste in Environmentally sound manner such as efficient operation of existing STPs, up gradation of the existing STPs & provide new STPs, providing proper collection, disposal & treatment facilities for solid waste/garbage (MSW) etc.

Letter issued from ACS,F&ED, GoG to Urban Development and Urban Housing Department (UD&UHD), GoG dated 07/02/2019 for the necessary actions.

Page | 15

Annexure: - I (a) Responsible Organization (s) for implementation of action plans of STPs & CETPs

River STPs/Sewage CETPs/Effluent

Gap if any

As per Table:- 1

MLD

Proposed STP MLD

Time Limit

Estimated Fund

Responsible Organization

for Sewage/STP

Gap if any

As per Table:-

2 MLD

Proposed CETP MLD

Time Limit

Estimated Fund

Responsible Organization

for CETPs/Effluent

Mindhola 1.6 MLD

2 MLD + 2 MLD at different location

in Notified

area

2020 20 Crore Sachin notified

area

No effluent discharge by industry into this

stretch

Page | 16

Annexure: - II

Proposed Mechanism for execution of action plans

Monitoring Mechanism for the PRS water quality

Activities Frequency Time Line Organization

Sampling Monthly Preferably 1st week of the month GPCB

Analysis Monthly Preferably within 10 days of sampling

Review Quarterly --

Monitoring Mechanism for the Ground water quality within catchment area of PRS

Sampling Half yearly Preferably 1st week of that month

Analysis Half yearly Preferably within 10 days of sampling

Review In subsequent RRC meeting after analysis

--

Monitoring Mechanism for various discharges (STP O/L, CETP O/L etc.)

Frequency of monitoring of various Waste discharge/disposal including waste water, solid wastes, Bio-medical waste etc. will be followed as per CPCB guideline issued from time to time & action under the provision of the Act would be taken against defaulting units

Monitoring Mechanism for Model Restoration Plan

RRC meeting shall be held periodically to monitor environmental Infrastructure progress preferably once in 3 months.

Page | 17