Ralf Bruyninckx Case 1 Fire Water Network
-
Upload
baba-johneh -
Category
Documents
-
view
20 -
download
1
description
Transcript of Ralf Bruyninckx Case 1 Fire Water Network
Cdt 3/25/2011
Title goes here 1
Fire Safety Engineering
Module 6Case Study 1 : Fire Water Network
EVALUATION OF FIREWATER SUPPLY AND DISTRIBUTION SYSTEM, PETROCHEMICAL PLANT
Cdt 3/25/2011
Title goes here 2
Objective
Assess the impact of aAssess the impact of a new LLDPE plant
on the firewater network and firewater pumping capacity
of the existing site
Scope of Work New LLDPE plantNew storage sphere of iso-pentaneStorage area of containers of iso-pentaneFire safety at the jetty
Cdt 3/25/2011
Title goes here 3
Methodology
• Hazard ID • Definition of credible fire scenarios• Heat radiation calc.• Theoretical required firewater demand• Translate theoretical firewater demand into
application rates of fire fighting systemsapplication rates of fire fighting systems • Hydraulic analysis• Recommendations
Methodology - fire scenarios
Pool fires Gas jet fires
Vapor cloud explosion
Cdt 3/25/2011
Title goes here 4
Methodology – Heat rad. calc.
Methodology – Exposure prot.
• basic fire fighting strategy t t i t d t t→ protect equipment and structures
→ prevent domino effect
• maximum heat flux that equipment can receive without damage
→ threshold damage limit: 12.5 kW/m²
Cdt 3/25/2011
Title goes here 5
Methodology – Theo. Firew. D.
68
101214161820
w [l
/(min
m²)]
NFPA prescription
NFPA (from explanatory material)
IP - Theoretical 75% loss
DEP - not too windy
DEP - very windy
024
0 20 40 60 80 100 120 140 160 180 200q [kW/m²]
Methodology – Theo. Firew. D.
4
6
8
10
12
w [l
/(min
m²)] + 114 m³/h if flame
impingement of jet fire
0
2
0 10 20 30 40 50 60 70 80 90 100 110 120q [kW/m²]
Cdt 3/25/2011
Title goes here 6
Methodology – Pract. Firew. D.Translation of Theo Firew Dinto Pract. Fire Fight. Syst.
Methodology - Hydraulic
Piping network
RAW FIREWATER RAW FIREWATER PUMPSPUMPS
SEA FIREWATER SEA FIREWATER PUMPSPUMPS
Cdt 3/25/2011
Title goes here 7
Methodology – Pump Curve •
Methodology - Hydraulic analysis
Principle of assessment of the firewater network and pumping capacity
1600
200
400
600
800
1000
1200
1400
Pres
sure
at N
ode
[kPa
]
Node pressure in function of node demand
Required pressure 950 kPa
950 kPa
C=100
Main assumptions:
0
200
0 200 400 600 800 1000 1200 1400
Flow demand [m³/h]
1. C = 100
2. pumps curves
3. required pressure = 9.5 bar
Cdt 3/25/2011
Title goes here 8
Methodology - Hydraulic
Scenarios:• Normal operation• Normal operation,
raw firewater fire pumps and sea firewater fire pumps available
• Raw firewater not available, only sea firewater fire pumps available
• Shut down of the sea firewater intake,only raw firewater fire pumps available
Bl k d• Black day, no raw firewater fire pumps no sea firewater fire pumps available,only a mobile fire pump.
Methodology - Summary
• What is governing scenario for firewater d d?demand?
• What is the quantity of firewater strictly needed?• How can it practically be applied on site?• What quantity of firewater will really
be applied?• Can the firewater piping network & pumping
capacity cope with the demand?
Cdt 3/25/2011
Title goes here 9
scope of work • New LLDPE plant• New storage sphere of iso-pentane• Storage area of containers of iso-pentane• Fire safety at the jetty for an increased handling of ethylene by ships.
11LDPE2 LDPE2 ––New LLDPENew LLDPE
ir Dirk Smeets15 mei 2009
Pressure Temperature Leak Frequency Fire typeBarg °C (mm) (Per year)
LLDPE-1Ethylene Pipe supply Gaseous
800 10 (to
LDPE2) 2.11E-3Jet
LLDPE-2Ethylene Pipe supply Gaseous
800 35 (to
LDPE2) 5.34E-4Jet
Ethylene Pipe supply Gaseous 0 35 (to Jet
Scenario n°
Product Location State
LLDPE – LDPE2 – Scenario selection
LLDPE-2Ethylene Pipe supply Gaseous
800 35 (to
LLDPE) 5.34E-4Jet
LLDPE-3Ethylene C2109 Gaseous
33100 35 (to
LDPE2) 5.2E-5Jet
LLDPE-5Ethylene C2109 Gaseous
33100 100 (to
LDPE2) 9.7E-6Jet
LLDPE-6 Butene C1008 Gaseous 4.6 48.4 100 9.7E-6 Jet
LLDPE-7 Butene C1007 Liquid 4.8 50.2 35 5.2E-5 Jet
LLDPE-8 Butene C1007 Liquid 4.8 50.2 100 9.7E-6 Jet
LLDPE-9 Butene C1004 Liquid 30 43 35 5.2E-5 Jet
LLDPE-10 Butene C1004 Liquid 30 43 100 9.7E-6 Jet
LLDPE-11 Butene C1004 Liquid 30 43 rupture 9.7E-6 Pool
LLDPE-12 N-pentane C1421 Liquid 2.46 55 35 5.2E-5 Jet
LLDPE-13 N-pentane C1421 Liquid 2.46 55 100 9.7E-6 Jet
LLDPE-14 N-pentane C1419 Liquid 30 43 35 5.2E-5 Jet
LLDPE 15 N pentane C1419 Liquid 30 43 100 9 7E 6 JetLLDPE-15 N-pentane C1419 Liquid 30 43 100 9.7E-6 Jet
LDPE2-1 Ethylene (E8101) Gaseous 80 0 35 5.34 E-4 Jet
LDPE2-2 Ethylene V8101 Gaseous 66 40 35 5.20 E-5 Jet
LDPE2-3 Ethylene V8101 Gaseous 66 40 100 9.70 E-6 Jet
LDPE2-4 Ethylene K8103 Gaseous 280 35 35 7.60 E-4 Jet
LDPE2-5Ethylene Final
processGaseous
900250 20
-Jet
LDPE2-6 Propane V8407 Liquid 17 50 Pool
LDPE2-7 Xylene P-8404 Liquid 200 40 35 - Jet
LDPE2-8 Xylene P-8404 Liquid 200 40 100 - JetLDPE2-9 Xylene V8409 Liquid 0.1 40 - Pool
Cdt 3/25/2011
Title goes here 10
• 4 selected scenarios:LLDPE l fi
LLDPE – LDPE2 – Scenario selection
– LLDPE - pool fire – LLDPE - jet fire – LDPE2 - pool fire – LDPE2 - jet fire
LLDPE – LDPE2 – Scenario selection
• Jet fire with Dleak = 100 mm – Huge size– Short expected fire duration (few sec.)
• Most water demanding firesMost water demanding fireswith Dleak = 35 mm
Cdt 3/25/2011
Title goes here 11
LLDPE – LDPE2 – 4 scenarios for WD
Scenario LLDPE-11b
Pool fire
Liquid butene
C1004C1004
30barg – 43°C
LLDPE – LDPE2 – 4 scenarios for WD
Scenario LLDPE-14
Jet fire
Liquid N-pentane
C 1419C-1419
30barg – 43°C
Cdt 3/25/2011
Title goes here 12
LLDPE – LDPE2 – 4 scenarios for WD
Scenario LDPE2-6
Pool fire
Liquid propane
V-8407
17barg – 50°C
LLDPE – LDPE2 – 4 scenarios for WD
Scenario LDPE2-6
Jet
Liquid Xylene
P-8404
200barg – 40°C
Cdt 3/25/2011
Title goes here 13
LLDPE – LDPE2 – 4 scenarios for WDGround area Mean heat flux Exposed area Water density TOT water TOT water
Unit m² kw/m² % l/min/m² l/min m³/hBlending 325 < 12,5 0 0 0 0Purging/pelleting 1820 engulfed by flame 10 10,2 1856 111
60 15 4 1092 6640 15 2,67 728 4420 40 2 1456 87
Scenario LLDPE-14
Jet fire
Liquid N-pentane
C 1419
20 40 2 1456 87Reaction 1290 engulfed by flame 30 10,2 3947 237
60 10 4 516 3140 20 2,67 688 4120 40 2 1032 62
T2 60 < 12,5 0 0 0 0Pit 80 < 12,5 0 0 0 0Purification 660 20 10 2 132 8Vent recovery 650 60 5 4 130 8
40 15 2,67 260 1620 50 2 650 39
Instrument Marshaling 140 30 25 2 70 4Electrical sub-station 500 < 12,5 0 0 0 0
C-1419
30barg – 43°CPipe rack 1 700 engulfed by flame 15 14,2 1491 89
60 5 4 140 840 15 2,67 280 1720 25 2 350 21
Pipe rack 2 300 < 12,5 0 0 0 0FLAME IMPIGMENT 1900 114
16719 l/min 1003 m³/hTotal theoretical firewater demand =
LLDPE–LDPE2 – Theo. Firewater demand
Scen
ario
n°
Prod
uct
Loca
tion
Stat
e
THEO
RET
ICA
L FI
REW
ATE
R
DEM
AN
D
P T Leak
Fire
type
Barg °C mm m³/h
LLDPE-11b Butene C1004 Liquid 30 43 - Pool 638 LLDPE-14 N-pentane C1419 Liquid 30 43 35 Jet 1003LDPE2-6 Propane V8407 Liquid 17 50 - Pool 587LDPE2-7 Xylene P-8404 Liquid 200 40 35 Jet 926
S P L S T F DP T L F
Cdt 3/25/2011
Title goes here 14
LLDPE–LDPE2 – Pract. Firewater demand
LLDPE-14: jet fireStrategy
Fixed/mobile monitors
Practical firewater demand:
Fixed/mobile monitors
→ Very flexibleFixed waterspray system for piperack
→ Not easilly accessible
• 1 section of the waterspray of the piperack 150 m³/h• 6 fixed monitors 6 x 150 = 900 m³/h• 2 mobile monitors 2 x 150 = 300 m³/h• TOTAL PRACTICAL FIREWATER DEMAND 1350 m³/h
LLDPE–LDPE2 – Hydraulic assessmentLDPE2 - LLDPE
1 raw water pump - 2 raw water pumps - 1 sea water pump - 2 sea water pumps
1400
1600
C=100
400
600
800
1000
1200
Pres
sure
at J
-043
[kPa
]
2 sea water pumps - No impairment1 sea water pump - No impairment1 sea water pump - Impairment X3 pipe P-0021 sea water pump - Impairment X4 pipe P-0082 raw water pumps - No impairment2 raw water pumps - Impairment X2 pipe P-019
950 kPa
0
200
400
0 200 400 600 800 1000 1200 1400 1600 1800 2000 2200 2400 2600 2800
Flow demand [m³/h]
2 raw water pumps - Impairment X2 pipe P-0192 raw water pumps - Impairment X1 pipe P-0211 raw water pump - No impairment1 raw water pump - Impairment X2 pipe P-0191 raw water pump - Impairment X1 pipe P-021Required pressure 950 kPaMaximum practical firewater demand Maximum theoretical firewater demand
Cdt 3/25/2011
Title goes here 15
Hydraulic – Friction loss coef.LDPE2 - LLDPE
2 raw water pumps
1400
1600
400
600
800
1000
1200
Pres
sure
at J
-043
[kPa
]
Required pressure 950 kPa
Maximum theoretical firewater demand
Maximum practical firewater demand
950 kPa
C = 80
C = 100
0
200
0 200 400 600 800 1000 1200 1400 1600 1800
Flow demand [m³/h]
C=100 - 2 raw water pumps - Impairment X1 pipe P-021
C=80 - 2 raw water pumps - Impairment X1 pipe P-021
Conclusions & Recommendations
FIRE WATER PUMPING CAPACITYLLDPE plant & sphere area
• 2 raw FW pumps are required• 1 (out of the two) sea FW pumps are sufficient to cope with the
demand
• Black day– 1 raw FW pump CANNOT cope with the demand– 1 or 2 tugboat(s) should be available on site
• The previous conclusions are only valid if:– The characteristic pump curves are realistic
→ Provide pump test facility→ Conduct pump performance test (actual flow/pressure curves)
Cdt 3/25/2011
Title goes here 16
Conclusions & Recommendations
• Raw firewater tank capacity– Firewater available for at least 7.4 h
• Firewater networkOK if C > 80– OK if C > 80
– Flow test to verify actual condition & C factor