Rail track charges in Great Britain—the issue of charging for capacity
-
Upload
chris-nash -
Category
Documents
-
view
213 -
download
0
Transcript of Rail track charges in Great Britain—the issue of charging for capacity
Rail track charges in Great Britain—the issue of charging for capacity
Chris Nash*, Simon Coulthard1, Bryan Matthews
University of Leeds, Institute for Transport Studies, 36-40 University Road, Leeds LS2 9JT, UK
Received 10 March 2003; revised 1 July 2003; accepted 1 December 2003
Available online 10 March 2004
Abstract
Separation of infrastructure from operations in rail transport raises the issue of what should be the structure and level of charges for
infrastructure use. This paper outlines the solution adopted in Britain, and how it has developed. It concludes that the principle defect in the
current system is the lack of any charge to reflect scarce capacity. A way of measuring the capacity requirements of different types of train
and of identifying their opportunity cost is put forward, but it is recognised that reflecting this in the charges would be complex.
q 2004 Elsevier Ltd. All rights reserved.
Keywords: Rail; Charges; Capacity
1. Introduction
When the government chose to privatise British Rail using
a structure that separated infrastructure from operations, the
result was a need to develop a method of charging for the use of
rail infrastructure. Given that this charging regime would be
one of the key incentives influencing the service level
decisions of train operators, it is obviously of crucial
importance to the privatised railway regime. Economic
principles suggest that train operators will only have the
correct incentives regarding speed and frequency of service
and type of equipment to use, if the change in the charge levied
as a result of a service level change reflects the marginal social
cost of that change. In the case of rail infrastructure that
marginal social cost will generally reflect wear and tear on the
system (leading to changes in maintenance and renewal costs),
any increased operating costs such as signalling, any external
costs of accidents and environmental effects, and costs of
increasing capacity utilisation, including increased delays to
other operators and scarcity costs (the inability of other
operators to get the slots they want).
The aim of this paper is to explain the arguments behind
the development of rail infrastructure charges in Britain to
date, to present a critique of the system as it now stands
and to offer some suggestions for further improvement. It is
argued that the key failure of the current system is its failure
to charge adequately for scarce capacity and a major part of
the paper will be devoted to proposals to overcome this
deficiency. Section 2 of this paper presents the history from
the original set of charges to the first periodic review.
Section 3 presents a critique of the outcome and discusses
ways to overcome its deficiencies, Section 4 presents
proposals regarding the development of appropriate
capacity charges and Section 5 illustrates these proposals
with a case study. Our conclusions are presented in Section 6.
2. The development of rail track charges in Britain
The original approach to rail access charges in Great
Britain was determined by the government prior to
privatisation and set out in the document Department of
Transport (1993). What this paper proposed was that freight
and open access operators should pay a negotiated charge, at
least covering their avoidable costs and making as large a
contribution as possible to fixed and common costs.
Franchised operators should pay a variable charge equal
to the cost implications of running additional trains, and a
fixed charge equal to their other avoidable costs plus a share
of fixed costs not covered by freight and open access
operators or other sources of revenue.
The aim of this structure was to reconcile the fact that the
majority of infrastructure costs were found to be common
0967-070X/$ - see front matter q 2004 Elsevier Ltd. All rights reserved.
doi:10.1016/j.tranpol.2003.12.003
Transport Policy 11 (2004) 315–327
www.elsevier.com/locate/tranpol
1 Simon Coulthard works in the rail industry; he was a part-time Masters
student at the Institute between 1999 and 2001.
* Corresponding author. Tel.: þ44-113-343-5325; fax: þ44-113-343-
5334.
E-mail address: [email protected] (C. Nash).
between operators, and—at least in the short to medium
term—fixed (para 3.2) with a belief that efficiency of the
infrastructure provider would be promoted if all its costs had
to be covered from revenue from train operators. Para 1.3
illustrates this logic:
Where subsidy of the operation of railways is appropriate
on social grounds, it is more efficiently directed at
particular services and paid to the operator rather than to
the provider of the infrastructure.
However, this could not be done simply by raising
charges above marginal cost without major distortions to the
efficiency of use of the infrastructure (para 3.3).
If Railtrack were to charge all operators a proportion of
common and fixed costs through a standard tariff, it
would drive off the railways traffic which was in a
position to pay for its avoidable costs….
The recommended solution was therefore that:
The long term health of the railway industry will be best
secured if Railtrack pursues a policy of market pricing,
subject to the avoidance of unfair discrimination between
competing operators in the same market. All operators
should therefore pay the avoidable costs which can be
attributed directly to them, and should contribute to
common costs differentially, reflecting their ability to pay.
It became the duty of the Rail Regulator to review all
aspects of access agreements, including infrastructure
charges, and he first consulted on this in Office of the Rail
Regulator (1994a).
By this time it was clear that the proposed structure of
charges for franchised passenger operators was one in which
the short run implications of changes in service levels for
charges would be very small. On average, only 8% of the
total charge they paid would be variable in the short run, and
most of this was simply paying for electricity. Thirty seven
percent of the charge would be to cover the long term
incremental cost of meeting the operators’ need for
capacity, but the level of this would not vary, at least
during the 5 year review period. Around half of the total
charge would be an arbitrary allocation based on some
measure of output. Forty three percent of the total would be
an allocation of common costs (of which about half, arising
at below the zone level were allocated on the basis of
planned vehicle miles and half arising at national or zonal
levels were allocated on the basis of budgeted revenue). The
remaining 12% would be station and depot access charges,
which again were shared between operators using them
based on an arbitrary allocation formulae.
Where new access rights were required, the price for
these would be negotiated at a level in between avoidable
cost and the value of the path to the operator on the basis that
Railtrack would be entitled to a greater share of the revenue
the more it was bearing risk.
The Regulator did not propose any major changes to
structure, but did comment that different operators would
vary in the quality of the paths they required and in their
peakedness, and suggested the possibility of the variable
element of the charge varying according to these factors.
Thus, the fact that the structure of charges implemented
gave no incentives for the efficient use of limited peak
capacity was recognised very early on.
The Regulator’s conclusions on the structure of track
access charges were published in Office of the Rail
Regulator (1994b). Whilst the Regulator argued that it
would be desirable for a greater proportion of access
charges to be variable with use, he did not consider it
appropriate to change the structure of charges in the short
term. Instead, he introduced procedures for the renegotia-
tion of access rights and charges, in the hope that this would
give Railtrack an incentive to ‘buy back’ scarce capacity
where it could put it to better use.
The first periodic review of track access charges started
with the publication of a consultation document in
December 1997 (Office of the Rail Regulator, 1997). The
Regulator considered that charges should incentivise Rail-
track, train operators and funders to maximise the efficient
use and development of the network whilst avoiding undue
discrimination between operators, appropriately rewarding
Railtrack for changes in the level of output and meeting the
government’s overall transport objectives.
Arguably, existing charges were meeting none of these
objectives. Negotiations for freight and open access operators
were complex and time consuming, whilst negotiations on
variation of access rights for franchisees were simply not
working. Moreover, the ability of Railtrack to negotiate
charges according to the ability of a TOC to pay, led to extreme
secrecy about demand on the part of TOCs to the detriment of
service and investment planning. More crucially, the charging
structure for franchisees gave no incentive for economy in the
use of scarce capacity and no adequate mechanism for the
replacement of existing low value services by higher value
ones. Operators were not adequately charged even for wear
and tear, and not charged at all for congestion and opportunity
cost of slots. The problem was particularly acute since there
had been a rapid growth in both rail traffic and train service
levels. Partly this was simply recovering from the recession
but even after this recovery was complete over the period
1997/8 to 2002/3 there was a 14% increase in passenger
kilometres and a similar increase in passenger train kilometres
(Strategic Rail Authority, 2003b). There was also continued
growth in freight traffic (11% increase in freight tonne km
between these years). This led to much greater congestion and
requirements for investment in new capacity than had been
anticipated, and it was the policy of the new government that
this should continue.
During the review, Railtrack provided evidence of
substantially higher wear and tear costs than allowed for
C. Nash et al. / Transport Policy 11 (2004) 315–327316
in the existing charges, and also quantified congestion costs
in fine detail by track section and time period. (Gibson et al.,
2002). It should be noted that the direct delays caused by an
additional train, for instance due to locomotive failure, were
already charged for through the performance regime; what
was charged for here was the additional delays to
subsequent trains simply due to the train in question
taking up capacity and thus reducing the ability of the
system to recover from delays caused by other factors.
Consideration was given to improving the incentive of
Railtrack to expand the network by also incorporating the
capital costs of expansion into the variable element of the
access charge on the basis of a calculation of long run marginal
cost; however, it was found that this varied enormously with
the location, size and nature of the additional capacity required,
and no feasible way of including this in the tariff was found.
Instead, attention concentrated on quantifying the congestion
cost of adding additional trains to the network. Arguably this
was sensible, given the long time periods and indivisibilities
involved in many plans to upgrade capacity. The cost of
additional delays has been estimated by means of modelling
(Gibson et al., 2002). The approach taken by Railtrack was to
use historical data on delays and capacity utilisation to specify a
function that could replicate the observed delays. This involved
identifying appropriate measures of delay and of capacity
utilisation, identifying appropriate functional forms and then
testing the strength of the relationship between incremental
delay and capacity utilisation. The result was a proposed tariff
broken down into several thousand-track sections and by time
of day. However, the Regulator both simplified the structure
and halved the level of charges before incorporating this
elementofcosts into the tariff. It seems that he was concerned at
the degree to which levying the full congestion charge might
reduce demand (and it must be said that the proposed charge
was based on existing, rather than equilibrium, levels of
congestion. On the other hand, given the expected underlying
growth in demand, it may reasonably be expected that
congestion will get worse rather than better, and there is
certainly no good reason to suppose that it would halve). He
may also have considered that the value attached to delays in
the calculation was too high.
The recommendations of the Regulator at the end of the
process were (Office of the Rail Regulator, 2000, 2001):
† an increase in the variable part of the track charges to
reflect the full wear and tear cost and 50% of the
quantified congestion cost.
† a move to a published tariff for all operators, with
franchised operators continuing to pay on a two part
tariff, but freight and open access operators paying only
the variable element of the tariff. However, open access
continued to be heavily restricted, and the Regulator,
subsequently, suggested that where open access entry on
a hitherto protected flow was permitted, the entrant might
be required to compensate the franchisee for loss of
profits.
† an incentive payment to Railtrack based on increases in
traffic in order to encourage expansion of the network.
Because this was not funded through the variable part of
the track access charge, there was no corresponding
disincentive to train operators to expand, as there would
have been had train operators paid this directly.
In the event not all of the costs falling on Railtrack as a
result of these decisions were added to the fixed element of
franchisees’ charges; the Strategic Rail Authority agreed to
pay for the removal of the contribution to joint and common
costs from freight operators, and a part of the general increase
in Railtrack’s costs through direct payment to Railtrack. This
avoided a situation whereby franchisees’ fixed payments
would have increased, but under the terms of the franchise
agreements SRA would have had to compensate them for
these increases anyway. By entering into a direct financial
relationship with Railtrack, arguably SRA would have more
control on how the money was spent.
3. The existing structure—a critique
The modifications brought about by the first periodic
review brought the structure of rail track charges in Britain
much closer to the theoretical ideal. Wear and tear was more
appropriately charged for, with the charges varying in fine
detail according to the characteristics of the vehicle although
still not representing variation by track type. A capacity charge
was introduced based on the congestion cost caused by an
additional train, and although the Regulator simplified Rail-
track’s original proposal, it was intended that this should still
vary in fairly fine detail according to where and when the train
operated. In practice, it is understood that the capacity charge
only varies by train type, and not by time and place, because of
problems with the billing software. This is disappointing, but
we do not believe it reflects a fundamental problem with
moving to a more finely differentiated charging system.
We commented in the introduction that infrastructure
charges should also meet the external accident and
environmental costs of additional services. Given the low
accident risks, and the fact that railway companies are
responsible for their own insurance, it seems unlikely that
the external accident cost is very large. Environmental costs
have been quantified in a recent study (Sansom et al., 2001)
and are shown in Tables 1 and 2. Although, these are much
smaller for rail than road, it is clear that they are typically
significant relative to the marginal infrastructure usage costs
and should therefore be included.
One of the most difficult issues to deal with in rail
infrastructure charging is that of scarce capacity. Ideally
charges would give train operators appropriate incentives to
expand services only where the value of the service is at
least as high as the costs it causes, and where capacity is
scarce to ensure that it is used to provide the services of
greatest value. This issue has become of great importance
C. Nash et al. / Transport Policy 11 (2004) 315–327 317
given the growth of traffic and the high costs of expansion
and the consequent need to make the most effective use
possible of what capacity is available (Bowker, 2002).
We explained above how a capacity charge based on the
cost of congestion was introduced. But congestion is only the
appropriate capacity cost where the train in question
constitutes an additional train to what would otherwise have
been run; where the train in question runs instead of some other
train the appropriate capacity cost is the opportunity cost of
trains forced off the system by lack of capacity. Where
capacity constraints bite, use of a particular slot by one train
operator leads to inability of others to obtain their desired slots.
Where there is a choice between operating an additional train
and forcing another one off the system, obviously the course of
action with the lower social cost should be taken, so it will be
the lower of these two values that should be adopted.
Charging for scarce capacity would require estimation of
the opportunity cost of a slot. The most attractive solution to
this problem in theory is to ‘auction’ scarce slots. There are
many practical difficulties, however, including the compli-
cated ways in which slots can be put together to produce a
variety of types of service, and the fact that the value of
a particular slot for a particular use depends on how other
slots are being used (in terms of the operation of
complementary or competing trains). It is also the case
that the willingness to pay for the slot by the train operating
company will only reflect its social value to them if
appropriate subsidy regimes are in place to reflect the user
and non-user benefits of the service as discussed below. In
practice, it is therefore usually accepted that any degree of
price rationing of scarce slots will have to be on the basis of
administered prices rather than bid prices, although some
countries, including Britain, allow for a degree of
‘secondary trading’ in which slots change hands between
operators at enhanced prices (strictly, this must take place
through Railtrack, so it is not secondary trading in the sense
forbidden by EC Directive 2001/14). Nilsson (2002)
provides a more detailed consideration of auctioning.
A second possibility is to simply impose a price and see
what happens to demand, and then iterate until demand
equals capacity. The risk is, however, that serious distor-
tions may occur whilst the price is adjusting, and that
strategic game playing may occur to force the price down by
withholding demand, where competition is not strong.
A third approach, recommended by NERA (1998), is to
identify sections of infrastructure where capacity is con-
strained and to charge the long run average incremental cost of
expanding capacity. However, as explained above this is a
very difficult concept to measure (the cost of expanding
capacity varies enormously according to the exact proposal
considered, and it is not easy to relate this to the number of
paths created, since they depend on the precise number and
order of trains run). It may be argued, however, that more
appropriate incentives are given to infrastructure managers if
they are allowed to charge the costs of investment they actually
undertake, rather than for the scarcity resulting from a lack of
investment, at least, if they are commercially oriented. For
short run marginal cost pricing encourages them to restrict
capacity in order to keep price high; whereas a system
where a capacity charge reflected actual expenditure on
expanding capacity would overcome this problem. EC
Directive 2001/14 which governs rail infrastructure charges,
seeks to get round this by requiring infrastructure managers to
undertake studies to determine the cost of expanding capacity,
and to test whether this is justified on cost-benefit grounds,
where scarcity charges are levied.
Given the difficulties with all these approaches, it may be
thought that the best way of handling the issue is to permit
direct negotiation between operators and the infrastructure
manager over the price and allocation of slots, including
investment in new or upgraded capacity. However, British
experience of this approach is that it is complex, time
Table 2
Marginal cost and revenue analysis for passenger rail £/train km, low cost
estimates
Costs Category
Inter-city Regional London Passenger
sector
Marginal infrastructure
usage
1.116 0.149 0.406 0.424
Vehicle operating cost 11.79 5.04 6.68 7.07
Electricity 0.483 0.068 0.371 0.228
Congestion 0.15 0.09 0.28 0.18
Mohring effect 21.55 20.67 21.19 21.05
Air pollution 0.279 0.041 0.067 0.098
Noise 0.122 0.042 0.088 0.076
Climate change 0.067 0.031 0.037 0.040
VAT not paid 2.46 0.54 1.48 1.32
Total 14.92 5.33 8.22 8.38
Revenue 14.07 3.11 8.47 7.52
Difference cost-
revenue
0.85 2.22 -0.25 0.86
Note: Low cost estimates apply to environmental categories only.
Source: Sansom et al. (2001).
Table 1
Marginal cost and revenue analysis for rail freight £/train km, low cost
estimates
Costs Category
Bulk Other Freight sector
Marginal infrastructure usage 1.79 0.88 1.19
Vehicle operating cost 8.60 9.70 9.28
Air pollution 0.166 0.166 0.166
Noise 0.170 0.170 0.170
Climate change 0.131 0.131 0.131
Total 10.86 11.05 10.94
Revenue 13.01 13.61 13.41
Difference cost-revenue 22.15 22.56 22.47
Note: Low cost estimates apply to environmental categories only.
Source: Sansom et al. (2001).
C. Nash et al. / Transport Policy 11 (2004) 315–327318
consuming and will not necessarily lead to an optimal
outcome given the number of parties involved and the scope
for free-riding.
An alternative is for the track charging authority (or the
Strategic Rail Authority on its behalf) to attempt to calculate
directly the costs involved. For instance, if a train has to be
run at a different time from that desired, it is possible to
use studies of the value people place on departure time shifts
to estimate the value to its customers of the cost involved.
Similarly, the costs of slower speeds may be estimated from
passengers’ values of time.
Given the current degree of excess demand for slots, it is
likely that the failure to charge for scarce capacity, together
with the under charging for congestion and the exclusion of
certain other elements of marginal social cost, is leading to a
situation where slots are substantially under priced,
compounding the problem of capacity shortage by leading
to incentives to train operating companies to run too many
trains, to have too strong a preference for frequent short
trains rather than less frequent long, and to seek particular
timings that are wasteful of capacity. The importance of
these issues is illustrated in the case study below.
One counter argument should be considered first,
however. That is the argument that the infrastructure of
other modes, including road and air, are also not charged for
in a way that adequately reflects marginal social cost, and in
particular congestion and scarcity costs. Indeed, the study
referred to above (Sansom et al., 2001) found substantial
undercharging for the road mode on average, and too little
differentiation in the current charges (primarily fuel tax)
between locations and times where congestion is a problem
and those where it is not. It might therefore, be argued that
to charge rail operators for these costs when road operators
do not have to pay them is counter productive.
This is, however, a very simplistic view of the
appropriate approach to such ‘second best’ conditions.
The extent to which particular services divert passenger or
freight traffic from congested or environmentally damaging
roads or airports will differ with the type of service and how
heavily it is loaded. The appropriate way of dealing with
such second best considerations is, therefore, to pay train
operating companies grants to reflect the benefits elsewhere
of diverting traffic from other modes. The Strategic
Rail Authority does indeed already pay grants to freight
customers designed to attract traffic to rail in such
circumstances, and it and the Passenger Transport Execu-
tives do of course also provide financial aid for passenger
services. However, the grants do not at present vary with or
reflect the benefits of the attraction of additional passengers
to rail, and more could be done to improve incentives here.
4. Capacity charges—a proposed approach
The basis of this theory is that operators should be
charged for the capacity they use in accordance with the
social opportunity cost of that capacity. In order to
implement this approach, it is necessary first to measure
the amount of capacity used by each train run, and then to
estimate its opportunity cost. Both stages of the process are
very complex.
The big problem with measuring rail capacity is that the
capacity of a given stretch of railway line depends not just
on its physical characteristics (number of tracks, signalling
system, line speed) but also on the characteristics of the
trains using it, and in particular whether they are travelling
at different speeds, and the order in which they run.
Capacity (though not necessary benefit) is maximised, if all
trains have the same average speed; generally the more
diverse the speeds the fewer the number of trains that can be
accommodated. Moreover, all these factors will vary for
individual segments of the route and the services operating
will vary by time of day, requiring calculations to be done in
fairly fine detail.
The following two figures provide an illustration of this
point; clearly showing that the capacity of the same route
section can be greatly influenced by the differing charac-
teristics of train slots. Fig. 1 shows an allocation of capacity
where all train slots have uniform characteristics (average
speed, stopping pattern, etc.). In these circumstances, it is
possible to plan trains to the minimum headway (5 min apart
on this route section). The result shows the maximum
number of slots per hour over the route to be 12. This would
be the same whatever the uniform characteristics.
Fig. 1. Theoretical capacity allocation between Huddersfield and Stalybridge assuming uniform train slots.
C. Nash et al. / Transport Policy 11 (2004) 315–327 319
Fig. 2 shows how the capacity available on the same
route section is greatly reduced when train slots of varying
characteristics are planned in a mixed pattern. The addition
of stopping passenger and freight train slots greatly reduces
capacity. In this scenario, the introduction of two stopping
passenger and one freight train has reduced the capacity of
the route by a half.
The result is that it is only possible to tell how much
capacity a particular service will consume in the light of the
other services operating on the route.
This suggests that a sensible way forward may be to
define, for each stretch of track, a prime user in terms of the
dominant type of train, and to consider one path for such a
train as a standard path. Other types of train will then be
considered in terms of the number of standard paths they
use. Whilst strictly, even this will depend on what types of
trains are running in the adjacent slots, it may be reasonable
to assume that—in the absence of knowledge to the
contrary–the adjacent slots will be occupied by trains
requiring standard paths.
As explained above, there are two reasons why a train
may require more than one standard path. The first is that it
operates at a different speed to other trains on the route in
question. The second is the precise times at which the trains
operate. The calculation of these two elements will be
illustrated in Section 5.
The second issue is the calculation of the opportunity
cost of a slot. This is also difficult. Indeed, it can only be
known precisely when the exact timetable has been
developed and the identity of the marginal train excluded
is known (Quinet, 2003). However, by that stage all
decisions as to the allocation of capacity for the current
period have been taken, and therefore, the capacity charge
cannot help to achieve an efficient allocation for that period.
What is needed, therefore, is a simpler approach that still
gives reasonable signals to train operating companies on
which they can base their longer term planning.
Where there is no shortage of capacity, and it is not
expected to be a problem within the planning period then of
course, the most efficient approach demands a capacity charge,
over and above any congestion charge, of zero. Thus, we are
only talking here of capacity constrained sections.
When considering services other than those of the prime
user of the route, it will often be sensible to measure
opportunity cost in terms of the value of an additional standard
path to the prime user. The prime user is usually a passenger
operator, and existing passenger demand forecasting models
(such as the industry standard model MOIRA or the more
detailed simulation model PRAISE) may be used to forecast
the impact on demand and revenue of the allocation of the
additional slot. In addition, it is necessary to forecast user
benefits not captured as revenue, and non-user benefits—in
particular the proportion of traffic diverted from road and the
saving in external cost that entails.
If the best alternative use of the slot is not an additional path
to the prime user this will of course understate the value of the
slot. If the identity of the best alternative use may be found then
the same procedure may be followed to find a more accurate
estimate of the opportunity cost of the slot. Note that if the
alternative use requires more than one standard slot, then the
value of the alternative train must be scaled down propor-
tionately to find the value of a standard slot. It should also be
noted that the opportunity cost might be not that the user in
question is forced off the system completely but that they get a
slower or otherwise less desirable slot.
For the prime user itself, the opportunity cost of the slot
is of course always going to be in terms of additional trains
of another type. Thus, it will always be necessary to
estimate the value of competing uses of the route in question
to implement this approach to capacity pricing.
5. Applying the proposed capacity charge in practice:
assessing the theory on the North Transpennine
Rail Route
To illustrate how the theory of scarcity charges might
work in practice analysis was conducted on the main North
Transpennine rail route between Leeds and Manchester
(Fig. 3) and was based on the Summer 2001 Timetable
Fig. 2. Theoretical capacity allocation between Huddersfield and Stalybridge assuming successive non-uniform train slots.
C. Nash et al. / Transport Policy 11 (2004) 315–327320
(with a later, updated examination of the Summer 2002
Timetable). This route has seen a dramatic rise in patronage
since the late 1980s; accompanied by modernisation of
rolling stock, improved frequencies and a change of main
station in Manchester. There have also been exogenous
factors that have influenced the growth on the route,
including: increased economic prosperity of Leeds and
Manchester, and growing congestion on the M62 (the main
Fig. 3. The North Transpennine Route.
C. Nash et al. / Transport Policy 11 (2004) 315–327 321
competitor for transpennine travel). In addition, the rail
industry has been considering how to upgrade the route and the
services over it. The Strategic Rail Authority has been
sufficiently convinced by the growth of the passenger service
crossing the Pennines that it has commenced a process to
refranchise ‘Transpennine Express’ as a separate train operator
with a distinctive quality of service. It is primarily a two-track
route with occasional passing loops. We do not consider the
problem of assessing capacity charges for single track routes,
where the interaction between trains may be much more
complex (although, in Britain at least the pattern of services is
typically simpler and the capacity problems less severe).
For our assessment ,the route was divided into three
sections, each route section being assigned a category
according to the ‘prime user’ characteristics of the rail traffic
over the route:
Huddersfield–Stalybridge: high speed express route.
Piccadilly–Guide Bridge: slow speed suburban route.
Huddersfield–Leeds: high speed express route.
The Guide Bridge–Stalybridge section is ignored as being
a relatively low speed section with no capacity problems.
On the basis of these categories a benchmark can be set
for the maximum slots per hour over each route section; and
the minimum time consumed per slot for each route section.
(Fig. 1 provides an illustration of this process).
The benchmark for the three route sections is as follows:
Huddersfield–Stalybridge: 12 standard paths per hour
(mean headway 5 min).
Piccadilly–Guide Bridge: 15 standard paths per hour
(mean headway 4 min).
Huddersfield–Leeds: 12 standard paths per hour
(mean headway 5 min).
The issues examined can be summarised as follows:
† How allocation of capacity to non-standard trains con-
sumes more than 100% of the capacity of a standard slot.
† An examination of the impact on capacity allocation of
the aspiration to operate a regular, clockface pattern of
four transpennine expresses per hour.
† An analysis of the impact of increasing the number of
train slots allocated to freight services.
5.1. The impact of allocating capacity
to non-standard trains
To illustrate the impact of allocating scarce capacity to
non-standard trains an assessment was made of the peak
hour on each of the three route sections. The capacity
utilised on each route section was assessed using the
‘capacity utilisation’ measure devised by Gibson et al.
(2002). Essentially, this squeezes the trains together,
preserving their ordering, to find the minimum time period
in which that set of trains could be run if the precise times at
which they run did not matter.
5.2. Huddersfield–Stalybridge
The actual capacity allocated during the peak hour (Fig. 4)
on this route results in seven paths being allocated in a
period of 65 min, with an average headway of 9.3 min,
compared to the benchmark of 5 min.
Treating the actual train paths using the Gibson method
(i.e. squeezing them together to the minimum headway
apart) produces the results shown in Fig. 5
The seven slots can now be squeezed into 50 min, with
an average headway of 7.1 min. In other words, it would
be possible to provide a further two standard paths per
hour, if there were complete flexibility over the precise
times of these slots. However, the presence of the non-
standard slots is still reducing capacity from 12 trains per
hour to 8.45.
Another way of looking at this question is to consider the
opportunity cost of introducing a single non-standard path
into an otherwise uniform pattern of standard paths such as
is shown in Fig. 1. For the Huddersfield to Stalybridge route,
the introduction of a single stopping train among a uniform
pattern of express services creates an opportunity cost of
three standard paths. Inserting a single freight service in
the same manner creates an opportunity cost of four
standard paths.
Fig. 4. Actual path allocation in busiest hour between Huddersfield and Stalybridge in Summer 2001 Timetable (Source: Railtrack Working Timetable).
C. Nash et al. / Transport Policy 11 (2004) 315–327322
On the Manchester Piccadilly to Guide Bridge route the
issue of scarcity was not considered because the capacity
(even in the busiest hour) was clearly not fully utilised.
The opportunity cost of introducing a single non-
standard path into a uniform pattern of standard paths on
this route is two standard paths (stopping services). This
applies where the non-standard path is either an express or a
freight service.
Between Huddersfield and Leeds, the allotted slot
departure time pattern was responsible for an opportunity
cost of three prime user slots. The allocation of capacity to
non-standard slots was also responsible for an opportunity
cost of three prime user slots in the sample hour.
The opportunity cost of introducing a single non-
standard path (stopping service) into a uniform pattern of
standard paths on this route is three standard paths (express
services).
5.3. The impact of regularising train slot patterns
When we conducted our assessment of the Summer 2001
timetable there existed an aspiration to provide a regular,
even interval, clockface pattern of four transpennine express
services per hour between Leeds and Manchester. With the
introduction of the Summer 2002 timetable, four transpen-
nine express services were introduced (although not at even
intervals). The pattern of four express trains per hour
provides an interesting example of allocating capacity at the
expense of other services.
Fig. 6 shows how capacity has been allocated between
Huddersfield and Stalybridge in the busiest 2 h period of the
Summer 2002 timetable. Careful planning has ensured that
the introduction of the four express services has not
compromised the ability to operate an hourly stopping
service (and an additional peak hour local service from
Greenfield). The service pattern has also accommodated a
freight service, albeit with a long layover in the passing loop
at Marsden. The compromise is the inability to provide an
even interval express service. The planned interval between
express services is 11, 16 12; 13, 19 1
2; 10, 17 1
2; and 13 min.
The ideal would be a regular interval of 15 min. This is
explored further in Fig. 7.
Fig. 7 clearly shows the opportunity cost of planning a
15 min interval express service. All non-standard paths have
been lost, with the exception of the additional peak hour
service from Greenfield. Within this rigid train pattern, there
Fig. 5. Capacity utilisation method applied to the busiest hour between Huddersfield and Stalybridge.
Fig. 6. Actual allocation of track capacity between Huddersfield and Stalybridge in busiest two hour period (Source: Summer 2002 Working Timetable).
C. Nash et al. / Transport Policy 11 (2004) 315–327 323
is no way of accommodating a transpennine freight service
without substantial investment in additional running lines, at
least between Huddersfield and Diggle. There is potential to
include a transpennine stopping service, but only by
requiring an additional 11 min layover at Marsden.
5.4. Providing greater access for freight services
The Government’s Ten Year Plan for transport includes a
target of increasing freight tonne-kilometres by rail by 80%.
Key to delivering this target will be the ability for major
routes such as the north transpennine to accommodate
increased freight train usage. To illustrate the potential
impact of increasing freight train access, we modelled a
scenario where the local stopping service was substituted by
freight services. The results are shown in Fig. 8.
Our analysis suggests that it is possible to substitute the
existing stopping passenger service with a freight train.
However, the freight service is required to wait in the
passing loop at Marsden for two successive express services
to pass. The four express services per hour have been
retained but the interval between them has to be further
compromised to intervals of 5 12; 24 1
2; 5 and 25 min.
The opportunity cost of expanding the allocation of capacity
to freight services is the loss of the stopping passenger
service and loss of anything close to a 15 min interval
express passenger service.
To minimise delay to freight services, it would be
preferable to operate these trains without the layover at
Marsden. The impact of inserting two direct freight services
into the regular pattern of standard (express) paths is to
consume all but three potential standard paths within each
hour. The opportunity cost of such an option is not only the
loss of the stopping service but also one of the remaining
express slots. The interval between the remaining express
services would now be 27, 5, and 28 min.
6. Estimating the opportunity cost of slots
The prime user of the Huddersfield–Stalybridge route
section is the inter-urban express passenger service. It may
be reasonable to assume that an additional service of any
other type would require a reduction of the number of slots
allocated to this service. Therefore, we need to know
what is the opportunity cost of a slot for this type of service.
Fig. 7. Allocation of capacity required to deliver transpennine express services at 15 min intervals, showing paths ‘lost’ from allocation in Figure 6.
Fig. 8. Theoretical re-allocation of track capacity to additional freight services between Huddersfield and Stalybridge.
C. Nash et al. / Transport Policy 11 (2004) 315–327324
This can be estimated as the sum of:
† the additional amount of traffic attracted to rail by the
presence of this train multiplied by the price it pays.
† the consumers surplus to rail users as a result of the
additional quality and capacity provided by the train.
† the savings of external costs to road users and the
public at large from the train attracting passengers
from road.
Less the train operating and infrastructure cost savings
from failing to run this train.
In this particular case, there is no problem with the
capacity of the service to handle the number of passengers
since, it would be possible to run fewer longer trains with
the same capacity (with some complexity, in that the
additional capacity may only be needed over the Manche-
ster–Leeds section, and it might be difficult to achieve this
without joining and splitting trains at these stations). Thus,
the relevant revenue and other benefits relate simply to the
effect of higher frequency services.
It has not been possible to obtain data to make specific
calculations for this section of route. However, some
suggestions may be derived from other studies. These are
Regional services and the figures in Table 1 suggest that on
average there is a shortfall of £2.22 per train kilometre in
comparing revenue with marginal social cost for regional
services. This is with the typical load for these services
being of the order of 40 passengers. The standard rail
demand forecasting methods in use in great Britain would
suggest that, for this type of service, a change in frequency
from 4 to 3 per hour would be the equivalent to an addition
to journey time of some 4 min; the typical current journey
time might be of the order of 60 min including the frequency
penalty. Given evidence that the journey time elasticity is of
the order of 0.9, the conclusion is that this reduction in
services might lose around 5% of the total traffic. Assuming
the train in question, being 1 train out of 4, carried 25% of
the total of the service, then the lost traffic would be as high
as 40 only if the total number of passengers per train were as
high as 200, certainly well above that to be found on these
services. A more reasonable assumption would be 100
passengers per train, giving a revenue loss of half that in
Table 2 and a shortfall relative to costs of £3.77.
As against this, we must consider the loss of consumers
surplus, which for 400 passengers per hour losing 4 min
might total some £272, or £4.53 per train kilometre
(assuming a value of time of 17p per minute for the sort
of mix of traffic found on these services and a route length of
60 km). Strictly, we should deduct from this the Mohring
effect since we are calculating the effect of changing
frequency directly, so the additional benefit is £3.86.
We also need to consider the external costs imposed by
any passengers diverting to road. There is evidence that for
inter urban train services about 60% of the passengers would
otherwise use car (Vicario, 1999). Thus, this service
improvement may be diverting some 12 passengers per
hour from car, or with an occupancy rate of 1.5 relieving the
roads of eight cars per hour. Assuming that the roads
concerned are 50% outer conurbation motorway and 50%
rural motorway, and that 50% of the traffic is in the peak,
Sansom et al. (2001) suggests a benefit of 18p per car km, or
£1.44 per train km. This leads to a net benefit of around £1.5
per train km. Given that to achieve these benefits a train has
to operate right through from Leeds to Manchester, a train
which deprives the service of such a slot even for part of the
route should be charged for the full route, i.e. 60 £ 1.5 or
around £90 per slot.
It should be noted that this is a day long average. During
the peak, it is likely that the benefits will be much greater
than this and in the off-peak lower. Stopping passenger
services may have higher benefits per train kilometre, at
least in the peak, if they relieve congested urban roads to a
greater extent. On the other hand, they often operate with
much lower loads of passengers per train, particularly in the
contra-peak direction, although, their need for a slot may
still be strong in order to get into position for a second peak
run. It should be noted that the value of a slot as a
positioning movement is something we have not considered
in this paper but it may be an important factor.
Given that this route is one where a major conflict
appears to exist between plans for passenger services and
the desire to expand freight services, it may be interesting to
do some similar exploratory estimates for the net benefit of
an additional freight service. Table 2 suggests that non-bulk
freight services are already earning revenue some £2.50 in
excess of marginal social cost. Assuming an average load of
900 tonnes that would otherwise use road and require 45
articulated goods vehicles, and on the same assumptions
about the roads from which this is drawn but assuming it is
in the off-peak, there is a benefit of 23.5p per vehicle km
from relieving the roads of this traffic. In other words, per
train km there is a benefit of £10.58 to add to the £2.5 above.
So the total benefit of the freight service is £13 per train km.
If it is travelling the same 60 km as the passenger service
this gives a value per slot of £780, but of course, it may be
going considerably further than that. There is little doubt in
this case, therefore, that space should be freed up to fully
meet demand for freight services even though they require
more than one standard slot per train run. On the other hand,
it is more likely that freight services may be retimed or
rerouted, as opposed to the traffic being totally lost, in which
case the relevant net benefit may be much lower than that
quoted above. Moreover, there is less certainty that a slot
allocated to freight traffic will actually be used given short
term fluctuations in traffic.
If it is the case that the marginal benefit of allocating
additional paths to freight is substantially greater than that
of additional paths to the prime user, then of course charging
the prime user the value of one of its own paths will not be
sufficient to encourage transferring marginal paths to the
alternative use. This situation would not arise if the timetable
C. Nash et al. / Transport Policy 11 (2004) 315–327 325
had already been optimised, for then the marginal value of a
slot should be the same to any operator. But given the
indivisibility involved this is only a limited response even if
one has a lot of faith in the allocation body. An alternative
might be a return to the pre-privatisation approach whereby
a prime user bore all the costs of the infrastructure on a
particular route except those paths paid for by other
operators. For then, again provided that other operators
are subsidised to the extent of the net social benefits of their
services, the prime user would bear a marginal cost of using
a slot equal to the opportunity cost to the next best use.
It must be stressed again that the above calculations are
exploratory; since they do not utilise actual data for the route
in question, they must not be taken to imply particular policy
conclusions regarding that route. These simple examples
show that the data exists to estimate opportunity costs, but that
the information requirements are severe. The data in question
is not usually available to the infrastructure manager, though
in Britain it is available to the Strategic Rail Authority.
However, these information requirements are just the same as
those needed to determine an optimal allocation of slots; if
that exercise is undertaken then the information needed for
optimal pricing will already exist. Indeed in Britain, the
Strategic Rail Authority is increasingly using just such an
approach to determine how best to use capacity in its Capacity
Utilisation Studies (Strategic Rail Authority, 2003).
7. Conclusions
The system of charging for track access in Great Britain
has been substantially improved as a result of the periodic
review. Firstly, the usage element of the charge has been
increased to reflect more accurately the wear and tear an
additional train causes. Secondly, a capacity charge has
been introduced to allow for the delays created by running
an additional train, although the level of this included in the
variable element of the tariff is only half that measured by
Railtrack and variation by location and time of day has not
been implemented. But there are other reasons to suppose
that the variable element of the charge is still far too low.
Firstly, environmental costs are excluded. Although, these
are far lower for rail than for road, relative to the size of the
variable element of the charge these are still significant. But
more crucially, the current charges do not allow for the
opportunity cost of scarce capacity.
A method has been outlined for identifying the relative
charge to be levied for different types of trains when capacity
is scarce, to allow for the fact that different types of trains
have different capacity requirements, and for identifying the
opportunity cost of scarce capacity. The method is complex,
but since these are the same calculations as are needed to
identify the optimal use of capacity, and SRA is increasingly
undertaking this exercise then the data should exist to
estimate the relevant opportunity cost of capacity.
Although, the calculations shown are only illustrative
they reveal some important points. Firstly, the overall
benefits per train kilometre, at least in British circum-
stances, seem to depend heavily on the consumer’s surplus
and external benefits, so that an auctioning system, which
did not find a way of feeding these into the bids, would be far
from optimal. Moreover, the point that is often made that,
where the trains competing for a particular slot belong to the
same company the costs in question are internalised, is again
only valid if those companies are being subsidised
according to the net social benefits they produce.
Would it be worth introducing such a charge? It would be
necessary to identify and make calculations for all capacity
constrained sections of track and translate this into charges
varying by time of day, in much the same way as is the case
with the current congestion charge. Even so, the charges
would be crude, and could not be used for detailed
assessment of slot allocation; as commented above, they
arise out of an optimal allocation of slots rather than
determining it (Quinet, 2003). Their role would be rather to
demonstrate the opportunity cost of slots to companies in
their longer term planning, and in that way influence them
before they reach the stage of detailed timetable planning.
But of course for that purpose, other anticipated changes in
circumstances, including infrastructure enhancement or
changes to the level of benefit produced by marginal
prime user train would need to be taken into account.
Perhaps, given the extent to which Britain has now
moved towards a centrally planned system in which the
Strategic Rail Authority determines the timetable to be
operated using cost-benefit analysis, the importance of
charging appropriately for the use of scarce capacity is now
reduced. But we consider that, in any country where it is
desired to give train operating companies appropriate
incentives for the long term development of their services,
capacity charges along the lines outlined in this paper will
be needed.
Acknowledgements
The authors are grateful to participants at the eighth
international conference on competition and ownership in
passenger transport (Thredbo 8), to Prof Ralph Turvey of
the London Business School, Dr J Preston as editor of this
journal and two unknown referees for very helpful
comments on an earlier version. All errors and opinions
are of course due to the authors alone.
References
Department of Transport, 1993. Department of Transport Gaining access to
the Railway network. The Government’s proposals..
Bowker, R., 2002. Britain’s Railway—Time for a New Radicalism. (The
Sir Robert Reid Railway Lecture 2002). The Institute of Logistics and
Transport, London.
Gibson, S., Cooper, G., Ball, B., 2002. Capacity charges on the UK rail
network. Journal of Transport Economics and Policy 36 (2), 341–354.
NERA, 1998. An Examination of Rail Infrastructure Charges. NERA,
London.
C. Nash et al. / Transport Policy 11 (2004) 315–327326
Nilsson, J.-E., 2002. Towards a welfare enhancing process to manage railway
infrastructure access. Transportation Research A 36 (5), 419–436.
Office of the Rail Regulator, 1994a. Framework for the Approval of
Railtrack’s Track Access Charges for Franchised Passenger Services. A
Consultation Document.
Office of the Rail Regulator, 1994b. Office of the Rail Regulator Railtrack’s
track access charges for franchised passenger services. Developing the
structure of charges. A Policy Statement.
Office of the Rail Regulator, 1997. The periodic review of Railtrack’s
access charges: a proposed framework and key issues.
Office of the Rail Regulator, 2000. Periodic Review of Railtrack’s Access
Charges: Final Conclusions. ORR, London.
Office of the Rail Regulator, 2001. Office of the Rail Regulator Review of
Freight Charging Policy: Provisional Conclusions. ORR, London.
Quinet, E., 2003. Short term adjustments in rail activity—the limited role of
infrastructure charges. Transport Policy 1, 73–80.
Sansom, T., et al., 2001. Surface Transport Costs and Charges, Institute for
Transport Studies, University of Leeds.
Strategic Rail Authority, 2003a. Strategic Rail Authority Capacity
Utilisation Policy: Network Utilisation Strategy. SRA, London.
Strategic Rail Authority, 2003b. National Rail Trends. Fourth quarter
2002–2003. SRA, London.
Vicario, A.J.B., 1999. Diversion Factors and Cross Elasticities, Unpublished
MA Dissertation, Institute for Transport Studies, University of Leeds.
C. Nash et al. / Transport Policy 11 (2004) 315–327 327