R. Garaguso, M. MorgantiC. Sollima
INFN-University of Pisa
KM3NeT WP7 Meeting, Pylos (Greece), 16-18 January 2007:
WP7 Summary: Development
of QA-RA
in KM3NeT
WP7: RISK ASSESSMENT AND QUALITY ASSURANCE
Pylos (Greece), 16-18 April 2007
KM3NeT : Colaboration meeting 2
Contents
Roadmap Membership and activities performed Results Future activities
Pylos (Greece), 16-18 April 2007
KM3NeT : Colaboration meeting 3
Deep study of the Project to identify the processes involved RA Questionnaire Functional AnalysisFunctional Analysis of the processes Division of the Project in Units, Sub-Units, Components and ElementsFMEA/FMECA standards and methodology study and analysis (process & project)Implement FMEA/FMECA Compensating provisions & remarks in RA deviations according to KM3NeT specifications
RA road map
Deep study of the Project to identify the needed standards and normative for each process Collection and selection of several suitable normative and standards (ISO CD-ROM)Link between the different normative and standards and its applicationsQA Questionnaire Implement QADevelopment of a preliminary QA manual according to KM3NeT specificationsspecifications
QA road map
WP7: QA & RA Program
DIAGRAM
Pylos (Greece), 16-18 April 2007
KM3NeT : Colaboration meeting 5
Membership
INFN (Stefano Cecchini)
NCSRD (Ioannis A. Papazoglou )
CEA-Saclay (Frédéric Louis )
IN2P3 (Laurence Caillat)
Pylos (Greece), 16-18 April 2007
KM3NeT : Colaboration meeting 6
WPs cross-link
INTERFACE: INTERFACE: it is proposed to have one QA/RA responsible for each WP and per country. He refers directly to the WP7
Steering Committee:Steering Committee:
- Representative of the partners of the WP7: C. Sollima, S. Cecchini, I.A.Papazoglou, Frédéric Louis, L. Caillat
WP7 Meetings: WP7 Meetings: twice per year
Pylos (Greece), 16-18 April 2007
KM3NeT : Colaboration meeting 7
WP 7 activities: Starting Point
1.) Deep study of the overall Project to identify the WPs’ links
2.) RA & QA activities are carried out in the framework of the KM3NeT Project:
to increase the knowledge about the submarine technologies and neutrinos detection (lesson learned from ANTARES, NEMO & NESTOR Projects)
(meetings were done in Paris, Marseille, Aberdeen and Italy) to prove the reliability of the RA & QA methodology
(from the PCC meeting of October 2006, application to the on going project)
to identify the weakest points
Pylos (Greece), 16-18 April 2007
KM3NeT : Colaboration meeting 8
WP 7 activities performed: QA
Analysis of the ANTARES project- QA should start with the design study to be ready for the
production
Analysis of the NEMO project- Application of the QA and RA methodology developed to:
• Define and diffuseDefine and diffuse the “Quality Culture” overall the WPs• Obtained a common standardisation by an integrated strategy
among the different WPs.
Pylos (Greece), 16-18 April 2007
KM3NeT : Colaboration meeting 9
WP 7 results
Development of the QA applications for KM3NET QA index QA questionare Plan activities form (preliminary) Test form (preliminary)
Development of the RA methodology for KM3NET Plan of the activities (RA CDR) Example of FEMCA (methodology) to the Optical
module (Antares/NEMO-1)
Pylos (Greece), 16-18 April 2007
KM3NeT : Colaboration meeting 10
Quality manual
Documented procedures
Work instructions
Forms Quality plans Specifications
External documents
Records
WP 7 QA activities: How to reach the goals
Pylos (Greece), 16-18 April 2007
KM3NeT : Colaboration meeting 11
WP 7 QA activities: How to reach the goals
IDENTIFICATION /TRACEABILITY
Id. No Specification
No
Test
No
Procedure
No
Instruction
No
Registration
No
Form Risk index Bar Code (?)
Pylos (Greece), 16-18 April 2007
KM3NeT : Colaboration meeting 12
1. Macro Area
2. Process Analysis
3. Functional Analysis
4. Quality Control
5. Tools
WP 7 QA activities: How to reach the goals
Pylos (Greece), 16-18 April 2007
KM3NeT : Colaboration meeting 13
Macro Area – example (to be discussed)
Infrastuctures Electronics Software Logistic (Suppliers)
WP 7 QA activities: How to reach the goals
Pylos (Greece), 16-18 April 2007
KM3NeT : Colaboration meeting 14
Processes Analysis (1 of 2)
Requirements
Unit, Subunit, Element, Item (USEI)
Specifications Designs
Prototype
Preproduction
Production
Production
Test (Including System)
IntegrationIN
OUT Storage
WP 7 QA activities: How to reach the goals
Pylos (Greece), 16-18 April 2007
KM3NeT : Colaboration meeting 15
Processes Analysis (2 of 2)
Packaging
Unit, Subunit, Element, Item (USEI)
Transport
Recovery
Suppliers
Shore Operations
Off Shore Operations Deployment
Interfaces
WP 7 QA activities: How to reach the goals
Pylos (Greece), 16-18 April 2007
KM3NeT : Colaboration meeting 16
Functional AnalysisExample
4. Software5. Logistic Layout
Structural
Data Acquisition
Power Supply1. Optical Module
Instrumentation
Boa
Anchor
Structural Interface2. Structural Layout
Electronics
Power Supply
Data Acquisition
Control3. Connections
Structural (Interface and Cable)
WP 7 QA activities: How to reach the goals
Pylos (Greece), 16-18 April 2007
KM3NeT : Colaboration meeting 17
Quality Control Suppliers
Production
Acceptance
Integration
Test
Storage
Packaging
Delivering
WP 7 QA activities: How to reach the goals
Design Logistic Software
Pylos (Greece), 16-18 April 2007
KM3NeT : Colaboration meeting 18
Tools Proposed Flow Diagrams
Block Diagrams
Audit
Software
Process
Logistic
Questionnaires
(Database, etc.)
WP 7 QA activities: How to reach the goals
Functional tree Product tree
Pylos (Greece), 16-18 April 2007
KM3NeT : Colaboration meeting 19
Just to recall
QUALITY = Requirements definition
QUALITY ASSURANCE = To plan the actions to achieve the requirements defined
QUALITY CONTROL = Measurement of the results achieved with reference to the requirements defined
WP 7 QA activities: How to reach the goals
Pylos (Greece), 16-18 April 2007
KM3NeT : Colaboration meeting 20
WP7: RA Objectives & Road Map for KM3NeT
Road Map
Risk Analysis involves three major stages:
Collect project/processes data;
Assessment of the undesired consequences of a potential set of actions;
Assessment of the probability that these consequences may obtain.
Objectives
1) Define the mission of the neutrino telescope in quantifiable terms;
2) Assess specific scenarios (sequences of events) that can lead to the inability of the system to perform its mission;
3) Assess the probability of each and every scenario.
Pylos (Greece), 16-18 April 2007
KM3NeT : Colaboration meeting 21
WP7: Risk Analysis Actual ActivitiesFMECA ANALYSIS Qualitative Example (related to PCC Rome Meeting Request)
Analyzed Component : Optical Module
Hypothesis:
1. OM into its environmental conditions (working life);
2. Components cant’be repair (MTBF=MTTF=1/λ)
3. Criticality Analysis is only qualitative and based on MIL-STD 1629 A normative ;
4. Objects Information are based on the available licterature (there are not yet available risk data).
Goals:
Give remarks about possible test benchs development to simulate the Failure Causes put in evidence;
Focus on Risk parameters needed.
Pylos (Greece), 16-18 April 2007
KM3NeT : Colaboration meeting 22
WP7: Risk Analysis Actual ActivitiesFMECA ANALYSIS Steps
Explode the Objects under analysis in all its parts (through a filled Questionnaires)
Build up FMECA TABLE by using modified MIL-STD 1629 A worksheet
Put in evidence the relevant functions by logical flow diagram
Brainstorming on potential failure modes, causes and effects
Allocate severity level and probability of occurrence using MIL-STD-1629 A reference tables
Build Up “Criticality Matrix”
Give final remarks
Pylos (Greece), 16-18 April 2007
KM3NeT : Colaboration meeting 23
WP7: General RA Conclusion
1. Although Qualitative, Criticality Matrix focuses on :
Possible Criticality, using color ranking from Red (unacceptable condition) to Green (acceptable without revision)
Objects ordered by criticalities
2. Although Qualitative, Criticality Matrix gives a priority to the objects tests (related to the failure causes) based on the above ranking
Example of procedure after FMECA results:
Step 1) rank Criticality level by unacceptable to acceptable
Step 2) Calculate experimental MTBF from the worst to the better condition
Step 3) Verify availability and find solution to improve, if is necessary
Pylos (Greece), 16-18 April 2007
KM3NeT : Colaboration meeting 29
WP 7 results 1 of 2
The work performed outlines that for a correct application of the QA and RA, it is needed to develop in the design study:
Functional analysis Definition of the requirementes Definition of the technical specifications
It means interaction with the WPs
Pylos (Greece), 16-18 April 2007
KM3NeT : Colaboration meeting 30
WP 7 results 1 of 2
The QA/RA needs to define the reliability level to be reach. It is translated in:
Tests to be performed
Relation with the suppliers, which- Tests they should perform- Certificate they should release- Level of non conformity we consider acceptable
Definition of the preproduction and production specifications
Pylos (Greece), 16-18 April 2007
KM3NeT : Colaboration meeting 31
WP7: RISK ASSESSMENT AND QUALITY ASSURANCE
"Design Study for a Deep Sea Facility in the Mediterranean for Neutrino Astronomy and Associated Sciences”
WE HAVE A DREAM:
“Let us try”KM3NET WP7 Motto
Pylos (Greece), 16-18 April 2007
KM3NeT : Colaboration meeting 32
WP7: RISK ASSESSMENT AND QUALITY ASSURANCE
"Design Study for a Deep Sea Facility in the Mediterranean for Neutrino Astronomy and Associated Sciences”
THANK VERY MUCH FOR YOUR KIND ATTENTION
Pylos (Greece), 16-18 April 2007
KM3NeT : Colaboration meeting 33
Draft CDR contribution describing the standards and the quality evaluation method for all the Design Study procedures and initial results of the FMECA RA studies (16 month)
- Deep study of the Project (July 2006)- Collection of several normative and standards (June 2006)- Selection of the suitable normative and its application (ISO)
(May 2006)- QA & RA Questionnaire (May 2006)- Development of a preliminary QA manual (July 2006)- Preliminary Standard Data-Base model (June 2006)- FMEA/FMECA standards and methodology study (July 2006)
WP 7 future activities
Pylos (Greece), 16-18 April 2007
KM3NeT : Colaboration meeting 34
Work plan: WPs cross-link
Project Management Policy Statement
QA & RA InterfaceInterface QC (Development and Application) Procedures (General &/or Detailed) Data Base of the Work Documents
QA & RA Management QAP and RA Development Procedures (General) Audit Data Base of the Final Documents
WP1
WP7
WPi