R 47 -09-12 Desalination GRP pipe sea water intake spool date 29 August 2012.docx

5
RAWEC QA/QC INSPECTION REPORT FROM PROCEDURE RW-RA01-QA-PR-001 PREPARED BY RAWEC INSPECTION PAGE 2 O F 2 PLANT NUMBER: ONE DATE INSPECTED: 02-09-12 ACTIVITY TITLE: INTERNAL INSPECTION REPORT NUMBER 47-08-12 PLANT LOCATION INSPECTORS NAME AND SIGNATURE Desalination Plant , Sea water intake GRP piping Inspected by : Approved by : Hatem Jafoura FROM PROCEDURE RW-RA01-QA- PR-001 PREPARED BY RAWEC INSPECTION REPORT 1.0 History : Last June 2011, repair of the internals of the flange connection ( job done by MHI during the T&I) 2.0 Findings: Desalination GRP pipe sea water intake spool . Drawing # DOGDB01BR005 Diameter : 44” length : 2m, operating pressure : 7 Kg/cm2 Two radial visible cracks on the middle of the spool .No water leak RECOMMENDATIONS(To be completed at the discretion of the Inspector) To drain the line, grind the externals around the cracks and apply fiber glass lamination (as reinforcement). To order a new pipe spool for the replacement of the damaged pipe structure. Copied to(Tick as required) PLANT MANAGER x TECHNICAL DIRECTOR x OPERATIONS MANAGER x MAINTENANCE MANAGER x TECH SERVICES LINE MANAGER x QA/QC FILE DRIVE H QA/QC OFFICE FILE D-2-4 X RAWEC form number: RW-RA01-QA-FO-026 REV 2

description

desalination

Transcript of R 47 -09-12 Desalination GRP pipe sea water intake spool date 29 August 2012.docx

Page 1: R 47 -09-12 Desalination GRP pipe sea water intake spool date 29 August 2012.docx

RAWEC QA/QC INSPECTION REPORT

FROM PROCEDURE RW-RA01-QA-PR-001 PREPARED BY RAWEC INSPECTION PAGE 2 OF 2PLANT NUMBER: ONE DATE INSPECTED: 02-09-12ACTIVITY TITLE: INTERNAL INSPECTION REPORT NUMBER 47-08-12

PLANT LOCATION INSPECTORS NAME AND SIGNATUREDesalination Plant , Sea water intake GRP piping Inspected by :

Approved by : Hatem JafouraFROM PROCEDURE RW-RA01-QA-PR-001 PREPARED BY RAWEC INSPECTION

REPORT1.0 History : Last June 2011, repair of the internals of the flange connection ( job done by MHI during the

T&I)

2.0 Findings:

Desalination GRP pipe sea water intake spool .Drawing # DOGDB01BR005Diameter : 44” length : 2m, operating pressure : 7 Kg/cm2

Two radial visible cracks on the middle of the spool .No water leak

RECOMMENDATIONS(To be completed at the discretion of the Inspector)

To drain the line, grind the externals around the cracks and apply fiber glass lamination (as reinforcement).To order a new pipe spool for the replacement of the damaged pipe structure.

Copied to(Tick as required)PLANT MANAGER x TECHNICAL DIRECTOR x OPERATIONS MANAGER xMAINTENANCE MANAGER x TECH SERVICES LINE MANAGER x QA/QC FILE DRIVE HQA/QC OFFICE FILE D-2-4 X

RAWEC form number: RW-RA01-QA-FO-026 REV 2

Page 2: R 47 -09-12 Desalination GRP pipe sea water intake spool date 29 August 2012.docx
Page 3: R 47 -09-12 Desalination GRP pipe sea water intake spool date 29 August 2012.docx
Page 4: R 47 -09-12 Desalination GRP pipe sea water intake spool date 29 August 2012.docx
Page 5: R 47 -09-12 Desalination GRP pipe sea water intake spool date 29 August 2012.docx