questions.xls
-
Upload
dhaval-mer -
Category
Documents
-
view
219 -
download
0
Transcript of questions.xls
![Page 1: questions.xls](https://reader031.fdocuments.in/reader031/viewer/2022021220/577cd8d41a28ab9e78a21840/html5/thumbnails/1.jpg)
7/29/2019 questions.xls
http://slidepdf.com/reader/full/questionsxls 1/11
Sr.
No.Question Text Option 1 (A) Option 2 (B)
1 Electricity Act 2003 replacesElectricity Act
1910
Eletricity Act
1948
2 For generating Thermal electricity, clearance from CentralElectricity Authority
is required is not required
3 Open Access refers to
wheeling
electricity using
existing
transmission
Generation of
Electricity
4 Implementaiton of the Act
Legalizes the
State Electricity
Board (SEB)
Eliminates SEB
5Transfer of SEB personnel can be contested under
Industrial Dispute ActTrue FALSE
6Judgment of the appellate tribunal can be appealed against
in
Sessions Court High Court
7Under offences and penalty clause, consumer is
categorized as
above/below
10KW
LT/HT
Consumer
8 Captive generation refers to generation of electricity For Own use For Govt. Use
9 Cross subsidy is that part of electricity cost realized fromHigh End
Consumer Government
10 Grid Operator refers toNational
Operator
Regional
Operator
11
Which section of the Electricity Act, 2003 empowers the
RLDCs to give directions to licensees, Generating
companies, generating stations, sub-station and any other
person connected with the operation of power system for
ensuring stability of grid operations.
Section 16 Section 29
12
Who can issue directions to RLDCs or SLDCs for mainting
smooth and stable transmission and supply of Electricity to
any Region or State.
Setion 37 Section 30
13Name the forum for redressal of the consumers grievance
within the area of distribution licensee.Section 39 Section 45
14The terms and condition for determination of tariff by the
apporopriate commission is specified under
Section 52 of
Electricity Act,
2003
Section 62 of
Electricity Act,
2003
15The constitution of the Central Commission is enshrined
under which Section of Electricity Act, 2003Section Section 46
16
Which section of the Electricity Act, 2003 provides for the
functions of the Central Commission Section 49 Section 58
17Function of the State Commission is provided in which
section of the Electricity Act, 2003Section 43 Section 56
18
Appeal form the order of the State Commission or the
Central Commission can be preferred before which
authority?
Disctrict court Appellete
Tribunal
19The limitation for filing Appeal beofre the Appellate
Tribunal is30 DAYS 60 DAYS
![Page 2: questions.xls](https://reader031.fdocuments.in/reader031/viewer/2022021220/577cd8d41a28ab9e78a21840/html5/thumbnails/2.jpg)
7/29/2019 questions.xls
http://slidepdf.com/reader/full/questionsxls 2/11
20Revision against the order of the appropriate commission
can be filed within how many days of the date of order 90 days 60 days
21
Under which provisions of the Act or the Regulation can
review peition be filed against the order of the Central
Commission?
Section 110 of
Ecltricity Act,
2003
Section 130 of
the CERC of
Conduct
Business
Regulations,
1999
22
Which setion of the Electricity Act, 2003 empowers the
Central Commssion to make Regulation for carrying out
the provision of the Electricity Act?
108 110
23 What do you understand by UI?Unscheduled
Institute
Unscheduled
Intercange
24 What is meant by Grid Code?
Grid cade means
a code specified
by the cnetal
government
under Section 79(1) of the
Eletricity Act,
2003
Grid means a
Regulation that
lays down the
Rules guidelines
and standards to
be followed byvarious persons
and particiants in
the power
system
25 Open Access means
Non-
discreminatry
provision for the
use of
transmission
lines by any
licensee or consumer or a
person engaged
in Generation in
accordance with
the Regulations
Non-
discremninatry
provision for use
of distribution
system or
associated
facilities by any
licensee or
consumer or a
person engaged
in genration in
accordance with
the regulation
26
Name the section that enables or transmission licensee to
engage in other business with prior intimation to the
appropriate commssion:
Section 29 Section 31
27 Which entity is designated as CTU? Power Grid NTPC
28Which part of the Electricity Act, 2003 deals with the
offenses and penalities under the Act? Part XIV Part X
29
Which Section of Electiricty Act , 2003 provides for the
punishment for non-compliance of directions by the
appropriate commssion?
Section 156 Section 142
30El;ectricity Act, 2003 was promulgated after repealing
which earlier enactment of Electricity Laws
Electtricity Act,
1910
Electricity Supply
Act, 1948
31What are the activities that are licensed under the new
Elecitiricty Act, 2003 ?Generation Ttransmission
![Page 3: questions.xls](https://reader031.fdocuments.in/reader031/viewer/2022021220/577cd8d41a28ab9e78a21840/html5/thumbnails/3.jpg)
7/29/2019 questions.xls
http://slidepdf.com/reader/full/questionsxls 3/11
32
Under which section of the Electriicty Act the Central
Government prepares the national electiricty policy and
tarif policy?
Section 8 Section 15
33Which Section of the Electricity Act, 2003 empowers the
appropriate commission to grant licencse?Section 14 Section 23
34 The Electricity Act, 2003 extends to which part of India? Whole of IndiaWhole of India
exceptJ&K
35Which was the first State in the Country to establish
Regulatory Commission Andhra Karnataka
36 CERC was established under the provisions of
Indian
Electricity Act
1910
Electricity
Supply Act 1948
37 ATE consists of Three
MembersFive Members
38 Generation Tariff is determined by CERC SERC
39 As per CERC , Subsistence & Validity of PPA to be looked
into by LDC while granting Open AccessTRUE False
40 Standards for Grid operation are specified by ATE SERC
41 IEGC Regulation -2010 Came Into Force On 1-Apr-10 3-Apr-10
42
An outage of a generating unit or a transmission element
due to a fault or other reasons which has not been
planned. This para talks in IEGC about:
“force majeure” “forced outage”
43 A central generating station or other generating station , in
which two or more states have shares ; is/are known as ISTS ISGS
44 Available transfer capability (atc), mathematically can be
written as ATC=TTC –TRM ATC =TTC+ TRM
45 UI stands for Unscheduled Exc Unscheduled Int
46 In IEGC regulation-2010 part-5 deals with Planning code General code
47 As per iegc “frequency band” in hz. Is 49.2 – 50.5 49.5 – 50.3
48 As per iegc, the operating voltage range for 400 kv system
is
MAX MIN440kv
360kv
MAX MIN
420kv 380kv
49
If system frequency falls to 49.7 hz and constituents draw
more than their scheduled drawal then they are violating
grid code clause no. 5.4.2 (d) 5.4.2 (x)
50
Grid code 5.4.2 (b) says “ the SLDC/ SEB/SEB/Distribution
licencee and bulk consumer shall ensure that requisite
load shedding is carried out in its control area so that
there is no overdrawl when frequency is ----------hz or
below. 49.2 HZ 49.5 HZ
51
When system frequency is below 49.7 hz but above 49.5
hz and constituents can overdraw up to __________ % of
schedule subject to grid conditions 0.1 0.12
52
No part of the grid shall be deliberately isolated from the
rest of the national / regional grid , except under an
emergency, and conditions in which such isolation would
prevent a total grid collapse and / or would enable early
restoration of power supply,……………. 6.8 ( a) 5.2 (b)
53Which clause of grid code allows the users, ctu, and stu for
isolation of the part of the grid ? 6.8 ( a) 5.2 (b)
![Page 4: questions.xls](https://reader031.fdocuments.in/reader031/viewer/2022021220/577cd8d41a28ab9e78a21840/html5/thumbnails/4.jpg)
7/29/2019 questions.xls
http://slidepdf.com/reader/full/questionsxls 4/11
54
if concerned SLDC/CTU/User is not intimating RLDC about
important element tripping manual or automatic then they
are violating grid code clause no 5.2(b) 6.2(d)
55
As per iegc clause no.5.2 (e), any prolonged outage of
power system elements of any user/ ctu/stu, which causing
or likely to cause danger to the grid or sub-optimal
operation of the grid shall regularly be monitored
by………….. NLDC RPC
56
If any user reduces generation of a unit of 210mw capacity
down to 90mw without any case of emergency or any act to
prevent imminent damage to costly equipment then that
user violates grid code clause no. ……. 6.2 (l) 5.2 (j )
57
No user / SEB shall cause a sudden variation in its load by
more than …………mw without prior intimation to and
consent of the RLDC 50 MW 100 MW
58
As per IEGC, all SEBs, distribution licensees, ctu stus and
sldcs shall ensure that the -------------and-----------schemes
are always functional. RLDC shall inform RPC secretariat
about instances when the desired load relief is not obtainedthrough relays in real time operation.
Over flux andover load
Under frequencyand df/dt
59
“NLDC / RLDC are authorized to defer the planned outage”
under which grid code clause, should they can exercise
this power? 5.7.4 (g) 5.9.2 (a)
60
The power system utilities are made to operate closer to
their design capabilities and security margins due to
Constraints in
Economic,
environmental
and regulatory
aspects.
Co plexity in the
operation of
huge power
system network
61
The developing countries are facing the challenges duringsystem operation and control due to
Large gap
between the
generation anddemand
Small gap
between the
generation anddemand
62
Which of the following statement is true regarding the
power system secure state?
Only Voltage is
within the
acceptable limits
Only Voltage &
frequency are
within the
acceptable limits
63
A power system is said to be in Alert State when,
Frequency
,Voltage,
equipment
loadings are
within acceptable
limits, n-1 , n-2
outage
acceptable, all
loads met
Frequency
,Voltage,
equipment
loadings are
within acceptable
limits, n-1, n-2
outage not
acceptable, all
loads met
![Page 5: questions.xls](https://reader031.fdocuments.in/reader031/viewer/2022021220/577cd8d41a28ab9e78a21840/html5/thumbnails/5.jpg)
7/29/2019 questions.xls
http://slidepdf.com/reader/full/questionsxls 5/11
64
What does STOR stand for?
Storage
Technology
Operation
Region
Short Term
Operating
Reserve
65
The major functions of a load dispatch center are:
Monitoring &
Assessing only Controlling only
66
The grid operation is a fundamentally important function for Utilities only
Transmission
companies only
67The system if insecure, under disturbed condition will bring
the normal operating state of a power system to Alert Restorative
68
Worldwide, the system operators & network companies will
need to invest in ______ required to manage the
complexity Share markets Control systems
69
What does a balancing service platform represent?
Demand side
working group
Holding
balancing
services open
day
70Flexible Reserve Product: ____________ volumes of reserve shall be made available during core hours 8am to
6pm on working days Lesser Greater
71
A consolidated reserve product shall offer ____________
operation of the transmission system needs. Flexibility
Good Service
characteristics
72The grid operators are continuing to work on developing
___________ processes so that they have better reflectingvarying wind forecasting into reserve requirements.
Dynamicreserve for wind
Static reservefor wind
73Series compensators are devices which _______the
apparent impedance of a circuit thus ___________ the
transfer capability where it is limited by system stability.
Reduce,
increasing
Increase,
decreasing
74
__________ has conducted wide range of research
initiatives in the system operation such as advanced alarm
management, report on human centered situational
awareness etc CPRI EPRI
75 The real time security monitoring functions does not
include,
Network
topology
processing
Observability
Analysis
76 The operator request load flow, load forecasting,
contingency analysis and fault study are functions of
Security
Monitoring
system
Security
assessment
![Page 6: questions.xls](https://reader031.fdocuments.in/reader031/viewer/2022021220/577cd8d41a28ab9e78a21840/html5/thumbnails/6.jpg)
7/29/2019 questions.xls
http://slidepdf.com/reader/full/questionsxls 6/11
Option 3 (C) Option 4 (D)
Electricity
Regulation Act
1998
All the above
- -
Utilization of
electricityNone of the above
Strengthens the
SEB
None of
the above
- -
Supreme CourtNone of
the abovePrivate/Public
Consumer
None of
the above
For Public UseFor Rural
Use
Public Generation Company3 14- license
State Operator All the
above 26 nldc
Section 79none of
the above
28 rldc 29 - NON
Section 25None of
the above32 SLDC
Section 42 Section 4140
Section 42 of
Electricity Act,
2003
None of
the above41 - other business
Section 60 Section 7662 -TCT
Section 64 Section 7963 -competitve bidding
Section 86 Section 83142
High CourtSupremie
Court178 - regualtions
90 DAYS 45 DAYS
![Page 7: questions.xls](https://reader031.fdocuments.in/reader031/viewer/2022021220/577cd8d41a28ab9e78a21840/html5/thumbnails/7.jpg)
7/29/2019 questions.xls
http://slidepdf.com/reader/full/questionsxls 7/11
45 days 30 days
Section 108 of
the Ecltricity Act.
2003
Section 103 of Condcut of
Business Regulation
178 184
Unscheduled
Interest
None of
the above
Both the aboveNone of
the above
Both the aboveNone of
the above
Section 41 Section 50
NHPCNone of
the above
Part V Part XV
Section 130 Section 80
The Electricity
Regulatory
Commssions
Act, 1998
All of
the above
Distribution B&C
![Page 8: questions.xls](https://reader031.fdocuments.in/reader031/viewer/2022021220/577cd8d41a28ab9e78a21840/html5/thumbnails/8.jpg)
7/29/2019 questions.xls
http://slidepdf.com/reader/full/questionsxls 8/11
Section 3 Section 14
Section 40 Section 12
Whole of India
except southern
Region
All of
the above
Orissa Haryana
ERC Act 1998Electricity
Act 2003
Four Members Six Members
Both CERC &
SERC ATE
- -
CERC CEA
3-May-10 1-Jun-10
“pre-planned
outage”
-
UMPP IPP/CPPS
ATC = TRM+AT-
Uniform Intercha Unscheduled Inter Exchange
Scheduling code Operating code
49.7 – 50.2 49.5 – 50.2
MAX MIN416kv
386kv
none of the above
5.4.2 (a)
5.4.2 (b)
49.7 HZ
49.8 HZ
0.08
0.15
5.2 (c)
5.2 (d)
5.2 (c)5.2 (d)
![Page 9: questions.xls](https://reader031.fdocuments.in/reader031/viewer/2022021220/577cd8d41a28ab9e78a21840/html5/thumbnails/9.jpg)
7/29/2019 questions.xls
http://slidepdf.com/reader/full/questionsxls 9/11
5.2(d)
4.2(b)
RLDC
CTU/STU
4.9 (d)
5.6.2(b)
75 MW
200 MW
Load shedding/islanding
Overcurrent and over voltage
5.2.3(c)
4.8(d)
Continuously
escalating fueo
costs and
depeleting
resources
All of the above.
Doesn’t dependupon the gap.
None of the above.
Voltage,
frequency are
within the
acceptable limits
but the system is
unstable for the
credible
contingency
conditions.
Voltage, frequency, equipment
loadings are within the
acceptable limits and system is
stable for the credible
contingency conditions.
Frequency
,Voltage,
equipment
loadings are not
within acceptable
limits, all loads
not met
None of the above
![Page 10: questions.xls](https://reader031.fdocuments.in/reader031/viewer/2022021220/577cd8d41a28ab9e78a21840/html5/thumbnails/10.jpg)
7/29/2019 questions.xls
http://slidepdf.com/reader/full/questionsxls 10/11
Short
Terminology for
Operator Region
Slow Temperature Operation
Region
Monitoring,
assessing &
controlling
None of the above
utilities,
transmission
companies &
ISOs/RTOs
ISOs only
EmergencyIn Extremis
Control &
information
systems
None of the above
Exhibiting at the
energy events
All of the above
Average
None of the above
Flexibility &
service
characteristics
necessary for
efficient,
economic &
secure
None of the above
Optimumreserve for wind
None of the above
Reduce,
decreasing
Increase, increasing
ESRI
None of the above
Contingency
Analysis
State Estimation with bad data
detection and elimination
Security Control
system
None of the above
![Page 11: questions.xls](https://reader031.fdocuments.in/reader031/viewer/2022021220/577cd8d41a28ab9e78a21840/html5/thumbnails/11.jpg)
7/29/2019 questions.xls
http://slidepdf.com/reader/full/questionsxls 11/11
s
OMPLIANCE
37- DIRECTION BY Govt