This Quarterly Update on Mul modal Transporta on Projects details the informa on for bicycle and pedestrian projects within Leon County that are currently under design, under construc on, or that have been completed within the calendar year. Projects are organized by their implemen ng agency. There are currently five agencies funding and construc ng trans-porta on improvements in Leon County, including the City of Tallahassee, Leon County, Blueprint2000, Capital Region Transporta on Planning Agency, and the Florida Departmentof Transporta on.
For more informa on on the Quarterly Update or any of the projects contained within this report, please contact the Tallahassee-Leon County Planning Department at (850) 891-6400.
I N T R O D U C T I O N
Quarter 3 | July - September 20152016 Tallahassee-Leon County Multimodal Project Summary
Roadway Segment Project TypeRoad Side
(If Applicable)Improvement Program
Anticipated Start
DateNotes
FAMU Way Extension - Segment 2 Pinellas Street to Gamble Road Bike/Ped Improvements Both Capital Improvements 2017
FAMU Way Extension - Segment 3 Gamble Road to Lake Bradford Road Bike/Ped Improvements Both Capital Improvements 2018
Lorene Street Madison to St. Augustine Sidewalk Both Capital Improvements 2016 Project includes Boosters segment. Construction by college.
Mitchell Avenue Ann Dr to Betton Road Sidewalk WestCapital Improvements -
Prioritized Sidewalks2017
Palmetto Street MLK to Adams Street Sidewalk NorthCapital Improvements -
Prioritized Sidewalks2016
Weems Road Improvement Phase II CSX to Mahan Drive Multi-use path East Capital Improvements 2018
Weems Road Extension Mahan Drive to Automotive Way Multi-use path West/South Capital Improvements 2018
Yaeger Street East of South Meridian Street Sidewalk North Capital Improvements 2017
Putnam Drive South Monroe Street to Country Club Drive Sidewalk TBDCapital Improvements -
Prioritized Sidewalks2017
Polk Drive South Monroe Street to Orange Avenue Sidewalk TBDCapital Improvements -
Prioritized Sidewalks2017
Paul Russell Road Monday Street to Apalachee Parkway Sidewalk WestCapital Improvements -
Prioritized SidewalksTBD
Railroad Avenue FAMU Way to Gaines Street Sidewalk & Bike Lanes West Capital Improvements TBD
Oakland Avenue South Monroe Street to Meridian Street Sidewalk North/SouthCapital Improvements -
Prioritized Sidewalks2017
Shamrock Drive Shannon Lakes to Tralee Sidewalk North/EastCapital Improvements -
Prioritized Sidewalks2017
Some segments under design while others already under
construction.
Roadway Segment Project TypeRoad Side
(If Applicable)Improvement Program
Anticipated
Completion DateNotes
Downtown - University Protected Bike
Lanes
S. Adams between Madison Street and W
Van Buren StreetProtected Bike Lanes Both Capital Improvements 2016 Phase 2 is awaiting completion of utility upgrades
Shamrock Drive Shannon Lakes to Tralee Sidewalk North/EastCapital Improvements -
Prioritized Sidewalks2017
Some segments under design while others already under
construction.
Seventh Avenue West Monroe Street to Duval Street Sidewalk North Capital Improvements 2017
Sixth Avenue East Thomasville to Mitchell Sidewalk Varies Capital Improvements 2017
Flipper Street Campbell Street to Okaloosa Street Sidewalk West Capital Improvements/
Safe Routes to Schools2017
Lafayette Paseo Indianhead Dr./Service Road Sidewalk South Capital Improvements 2017 Design/ROW Complete
Quarterly Update on Multimodal Projects | City of Tallahassee | Q 3 & 4 (June - December) 2016
STATUS: Under Design as of December 31, 2016
STATUS: Under Construction as of December 31, 2016
Roadway Segment Project TypeRoad Side
(If Applicable)Improvement Program Completed Date Notes
Downtown - University Protected Bike
Lanes
St. Augustine and Pensacola Street
between S. Macomb Street and S. Adams
Street
Protected Bike LanesN westbound - S
EastboundCapital Improvements 2016 Phase 1 from Macomb to University Drive Complete.
North Ridge Road Sidewalks Creek to Toucan Sidewalk WestStarmetro -
Nova 20102016 Construction complete
FAMU Way Extension - Segment 1 Martin Luther King Jr Blvd to Pinellas Street Bike/Ped Improvements Both Capital Improvements 2016
Gaines Street North Bicycle Boulevard Woodward to Gay Street Bicycle Boulevard N/A Capital Improvements 2016 Const. by Developer - The Railyard at Collegetown LLC
Gaines Street South Bicycle Boulevard Stone Valley Way Alignment Bicycle Boulevard N/A Capital Improvements 2016Const by Developer - North American Properties along ‘Block C’
development
Lonnbladh Road Improvements - Phase II Capital Circle NE to Greer Sidewalk Both Capital Improvements 2016
STATUS: Completed as of December 31, 2016
Quarter 3 | July - September 20152016 Tallahassee-Leon County Multimodal Project Summary
Roadway Segment Project TypeRoad Side
(If Applicable)
Improvement
Program
Anticipated Start
DateNotes
Chaires Cross Road Green Oak Dr. to Capitola Road Sidewalk West/South Capital Projects N/A
The sidewalk has been completed from Green Oak Drive to the
eastern entrance of the Chaires Elementary School. The
remaining section from the School entrance to CSX Railroad is
under design.
Old St. Augustine Road Old St. Augustine & Blairstone Road
IntersectionIntersection Improvement to add turn lane TBD Capital Projects TBD
Sidewalks will be added. Plans currently at 60%. Currently
working on Utility Coordination
Tharpe Street Capital Circle NW to Ocala Road Bicycle and Pedestrian Improvements Both Capital Projects N/A Construction is unfunded
Roadway Segment Project TypeRoad Side
(If Applicable)
Improvement
Program
Anticipated
Completion DateNotes
Bannerman Road Thomasville Road to Meridian RoadWidening and Bicycle and Pedestrian
ImprovementsBoth Capital Projects N/A
The first section (800 - 900 feet west of Quail Commons) has
been completed. Remainder of Bannerman improvements will
be funded by new sale tax which goes into effect 2020.
Roadway Segment Project TypeRoad Side
(If Applicable)
Improvement
ProgramCompletion Date Notes
Old Bainbridge Road Pullen Road Intersection Roundabout with Pedestrian Improvements N/A Capital Projects 2016Sidewalk has been built along Pullen from intersection to 300'
west.
Timberlane Road Deer Lane to Meridian Road Sidewalk South 2016 Completed
Lakeview Drive ImprovementsFrom S. Lake Bradford Road to 3567
Lakeview Drive
Drainage Improvements and Roadway
Reconstruction N/A Capital Improvements 2016 Completed
North Monroe StreetFrom Tallahassee Mall Entrance on North
Monroe Street to south of Lakeshore DriveTurn Lane/Through Lane Addition East Capital Projects 2016
The sidewalk on the east side of the Monroe Street within the
project boundary were reconstructed and improved.
Quarterly Update on Multimodal Projects | Leon County | Q 3 & 4 (June - December) 2016
STATUS: Under Design as of December 31, 2016
STATUS: Under Construction as of December 31, 2016
STATUS: Completed as of December 31, 2016
Quarter 3 | July - September 20152016 Tallahassee-Leon County Multimodal Project Summary
Roadway Segment Project TypeRoad Side
(If Applicable)
Improvement
Program
Anticipated Start
DateNotes
Magnolia Drive Multi-Use TrailPhase 3 Circle Dr. to Apalachee Parkway
Multi Use Trail West Blueprint 2017 Concept Development is underway
Magnolia Drive Multi-Use TrailPhase 4 S. Meridian St. to S. Monroe St.
Multi Use Trail TBD Blueprint 2017 Concept Development is underway
Magnolia Drive Multi-Use TrailPhase 6 S. Monroe St. to S. Adams St.
Multi Use Trail N&S Blueprint 2017 Concept has been approved, Permitting underway
Capital Circle NWSW - W1Crawfordville Rd. to Orange Ave
Roadway N/A FDOT TBD Construction Plans in development
Capital Circle NWSW - W1Springhill Rd. to Orange Ave
Joint Use Stormwater Facilities N/A Blueprint TBD Design and permitting estimated to be completed by Q3, 2017
Capital Cascades Trail - Segment 3DCleveland St. to Central Drainage Ditch
Multi Use Trail N/A Blueprint TBD Construction Letting Scheduled Spring 2017
Roadway Segment Project TypeRoad Side
(If Applicable)
Improvement
Program
Anticipated
Completion DateNotes
N2 - Capital Circle Northwest/Southwest North of Orange Avenue to US 90Highway Widening including Bike/Ped
Improvements and Wetland MitigationBoth Blueprint 2017
Notice to Proceed November 21, 2012 - 977 Days Original
Construction Schedule.
Roadway Segment Project TypeRoad Side
(If Applicable)
Improvement
ProgramCompletion Date Notes
Capital Cascades Trail - Segment 3BMartin Luther King Jr. Boulevard to South
Adams Street
Stormwater Pond/Conveyance and
Bike/Ped ImprovementsBoth Blueprint 2015 Grand Opening Held 10-15-15
Capital Circle NWSW - W1 Crawfordville Rd. to Orange Ave PD&E N/A Blueprint 2016 PD&E Accepted by FHWA January 2016
Capital Cascades Connector Bridge South Adams Street to Gadsden Street Pedestrian Bridge and Multi-Use Trail N/A Blueprint 2016 Grand Opening 16
Capital Cascades Trail - Segment 3CClevelend Street to Martin Luther King Jr.
Boulevard
Stormwater Pond/Conveyance and
Bike/Ped ImprovementsNorth & South Blueprint 2016 Project complete other than permit closeout and as-builts
Quarterly Update on Multimodal Projects | Blueprint2000 | Q 3 & 4 (June - December) 2016
STATUS: Under Design as of December 31, 2016
STATUS: Under Construction as of December 31, 2016
Completed as of December 31, 2016
Quarter 3 | July - September 20152016 Tallahassee-Leon County Multimodal Project Summary
Roadway Segment Project TypeRoad Side
(If Applicable)
Improvement
Program
Anticipated Start
DateNotes
Capital City to the Sea Trails Leon County segment Environmental/Planning Study N/A N/A 2014 PD&E underway, led by Apalachicola National Forest
Roadway Segment Project TypeRoad Side
(If Applicable)
Improvement
Program
Anticipated Start
DateNotes
Apalachee Parkway Monroe Street to east of railroad underpassSidewalk construction associated with
roadway resurfacingBoth RMP 2016
Sidewalk construction from the State Capitol at Monroe Street
intersection eastward to join existing sidewalks on service roads
east of railroad underpass
Woodville Highway Gaile Avenue to Leon County Line Transportation Master Plan N/A RMP N/A
Woodville Highway Paul Russell Road to Capital Circle Design for road widening with sidewalks Both RMP 2014
Roadway Segment Project TypeRoad Side
(If Applicable)
Improvement
Program
Anticipated
Completion DateNotes
Sixth Avenue (East) Monroe Street to Gadsden Street Design/Construction for Bike/Ped
ImprovementsBoth RMP 2017 Construction funded; City of Tallahassee to construct
North Monroe Street Tharpe Street to Seventh Avenue Medians/ Pedestrian Improvements N/A RMP 2017Design complete; construction funded in FY 2017 and
scheduled to begin in late 2016.
Quarterly Update on Multimodal Projects | Capital Region Transportation Planning Agency | Q 3 & 4 (June - December) 2016
STATUS: Under Design as of December 31, 2016
STATUS: Planning Study, PD&E, Pre-Engineering as of December 31, 2016
STATUS: Under Construction as of December 31, 2016
Quarter 3 | July - September 20152016 Tallahassee-Leon County Multimodal Project Summary
Roadway Segment Project TypeRoad Side
(If Applicable)
Improvement
Program
Anticipated Start
DateNotes
Orange Avenue Capital Circle SE to Lake Bradford Road Sidewalks TBD Capital Projects 2017 Pre-Construction Underway
SR 10 (US 90)SR 10 (US 90) east of CR 59 to Jefferson
County Line5' Paved Shoulders Both Capital Projects 2017 Pre-Construction Underway
Orange Avenue Lake Bradford to Monroe Street Resurfacing BothResurfacing -
Maintenance2017 Includes sidewalks and pedestrian crossing upgrades
North Monroe Street John Knox Road to Thomasville Road Addition of thru lane East Capital Projects 2018Includes replacement of existing sidewalk (and new sidewalk
where not previously constructed)
Appalachee Parkway Magnolia Drive Intersection Addition of Crosswalk East Intersection 2018
Roadway Segment Project TypeRoad Side
(If Applicable)
Improvement
Program
Anticipated
Completion DateNotes
Magnolia Drive South Meridian to Pontiac Drive Sidewalk North Capital Projects 2017 Wth Leon County
E Lafayette Street service road CSX RR Tunnel to Seminole Drive Bike Path/Trail South N/A 2017 Under constuction
6th AvenueMonroe Street to Gadsden Street & South
to Beard StreetSidewalks Both Capital Projects 2017 Under construction
7th Avenue Colonial Drive to Gadsen Street Sidewalks North Capital Projects 2017Pre-Construction Underway
North Monroe Street Seventh Avenue to Tharpe StreetRight of Way Acquisition for Pedestrian
Improvements and Raised MediansN/A Capital Projects 2017
Apalachee Parkway Monroe Street to Frontage Roads Sidewalks and Safety Improvements BothResurfacing -
Maintenance2017
Roadway Segment Project TypeRoad Side
(If Applicable)
Improvement
ProgramCompletion Date Notes
Orchard Pond Greenway Road Old Bainbridge Road to Meridian Road New Road Construction N/AState Infrastructure
Bank/Tolls/Private 2016 Project will include bike lanes and a shared use path
Quarterly Update on Multimodal Projects | Florida Department of Transportation | Q 3 & 4 (June - December) 2016
STATUS: Under Design as of December 31, 2016
STATUS: Under Construction as of December 31, 2016
STATUS: Completed as of December 31, 2016