Quantity Take Off

download Quantity Take Off

of 14

description

Some way of quantity take off

Transcript of Quantity Take Off

  • QUANTITY TAKE-OFF

    Quantity take off problems are relatively easy to figure out. You just need to know a little bit about geometry and use a little bit of engineering common sense. I will show you a couple tricks of the trade that will make life a little easier and then some example problems for you to practice to gain experience and confidence. The most likely questions that you will see during the exam are quantity take off for; 1. Soil (excavation, hauling, compacting), 2. Formwork for concrete, 3. Masonry work, and 4. Steel (structural beams, steel in concrete).

    Trick of the Trade #1: To find the length of Excavation Be careful to fully understand what the given dimension are measuring. The below is the example of a footing plan. If the dimension are given for the centerline or the outer perimeter your calculation is different.

    42ft

    17ft

    24ft

    63ft

    41ft

    20ft

    If the dimension are the centerline the calculation are easy. The Length of Trench equals = 42+17+20+24+63+41 = 207 ft

    However if the dimension are the outside perimeter use Horizontal In-In and Vertical Out-Out Method. Which just means measure the walls in the Horizontal distance on the inside and in the vertical distance on the outside. The Length of Trench equals = 38+17+20+24+59+41= 199 ft

    2ft

    42ft

    17ft

    24ft

    63ft

    41ft

    20ft

    2ft

    38ft

    20ft

    59ft

  • QUANTITY TAKE-OFF EARTHWORK PROBLEM

    Question #1: 42ft

    17ft

    24ft

    63ft

    41ft

    20ft

    3ft

    A contractor is excavating the above trench. He is supposed to dig the trench 5 ft deep x 3 ft wide. The soil was tested to have an approximate swell factor of 15% and a shrinkage factor of 12%. The contractor is placing a 8 water pipe in the trench and then backfilling with the soil that was removed. The above dimensions are on centerline. Does the contractor have enough soil to backfill the trench, or will he/she have to need more? If he needs more soil, how much does he/she need to bring in. Answer in LCY.

    Ans.

    a. It fits

    b. 14.5 LCY

    c. 12.34 LCY

    d. 7.25 LCY

  • Step 1: Find length of trench Trench = 42ft+17ft+20ft+24ft+63ft+41ft = 207 ft

    Step 2: Find the Volume of the soil in the trench 5ft x 3ft x 207ft = 3105 ft3

    Step 3: Find the Volume after compaction (3105 ft3)(1-.12) = (3105 ft3)(.88) = 2732.4 ft3

    Step 4: Find the Volume of the soil needed Volume of Trench Volume of Pipe

    3105 ft3 - (d2/4)(207ft) = ((8/12)2/4)(207ft) 3105 ft3 - 72.25 ft3 = 3032.75 ft3

    Step 5: Find out if you need more soil Volume of compacted soil need Volume of compacted soil available 3032.75 ft3 - 2732.4 ft3 = 300.35 ft3 So the KTR needs to bring in more soil

    Step 6: How much soil does the contractor need to bring in Volume of compacted soil = (1-Shrinkage factor) x BCF

    300.35/.88 = 341 BCF, LCF = BCF x 1.15 = 392/27 = 14.5 LCY

    QUANTITY TAKE-OFF SOLUTION 1

  • MASONARY QUANTITY TAKE-OFF

    There are tables available for estimating the number of bricks required, but for the PE Exam it is relatively easy to just reason out most answers.

    For figuring out the number of bricks required in a wall there is a Five step process.

    Trick of the Trade #2: Estimating number of bricks

    Step 1: Calculate the net surface area of the wall. (ft2 or m2) - Gross surface Area openings surface area - Do not double count area of corners

    Step 2: Calculate the surface area of one brick as positioned(including the mortar joint.

    - Standard brick size is 8x2.25x3.75 - plus half the joint thickness on each side

    Step 3: Divide Net wall area by surface area of the brick.

    Step 4: Multiply the number by the number of rows of brinks required.

    Step 5: Add an amount for waste ( A factor of 2-10% is usually added)

    .5in

    .5in

  • MASONARY QUANTITY TAKE-OFF

    If you need to figure out the quantity of mortar required.

    Trick of the Trade #3: Quantity of mortar

    Step 1: Calculate out the volume of mortar of one brick. (ft3 or m3) - Volume per brick = (t)(w)(L+H+t)

    -t = mortar thickness -w = brick width/depth - L = brick length - H = brick height

    Step 2: Multiply the mortar required/ brick by the total number of bricks.

    Step 3: If more than one row the volume of mortar needed to fill the gap between rows need to be added. This is volume is the joint thickness times the net area of the wall.

    Step 4: Add an amount for waste ( A factor of 25% is usually added)

  • QUANTITY TAKE OFF MASONRY

    PRACTICE PROBLEM #2 Find the quantity of standard size bricks(8inx3.75inx2.25in) you should have delivered to your project if the following conditions are given: -Wall is 8 ft high, 14 ft wide - two opening, one 48in x 72in, one 32in x 48in - Mortar joints are .5in thick - 2 rows are required - Allow for 3% brick waste

    a. 1275 b. 953 c. 477 d. 982

  • QUANTITY TAKE OFF MASONRY SOLUTION#2

    Step 1: Calculate the net surface area of the wall. (ft2 or m2) - Gross surface Area openings surface area : (8ft x 14ft) (48in x 72in) (32in x 48 in) = 77.33 ft2 144 144

    Step 2: Calculate the surface area of one brick as positioned(including the mortar joint. - the thickness of mortar = .5in - so each side of the brick carries .25in, two side so add .5in to dimension of the brick Surface area of one brick = (8in +.5)(2.25+.5) = .1623 ft2 144

    -Step 3: Divide Net wall area by surface area of the brick. 77.33 ft2 = 476.5 = number of bricks .1623 ft2

    Step 4: Multiply the number by the number of rows of brinks required. (476.5)(2 rows) = 952.9 bricks

    Step 5: Add an amount for waste ( A factor of 2-10% is usually added) (952.9 bricks)(1.03) = 982 bricks

  • QUANTITY TAKE OFF MASONRY

    PRACTICE PROBLEM #2A Estimate the quantity of mortar required in problem #1. The joint thickness between rows is in thick. Assume 25% waste.

    a. 20.5 ft3 b. 18.3 ft3 c. 14.6 ft3 d. 11.4 ft3

    Step 1: Calculate out the volume of mortar of one brick. (ft3 or m3) - Volume per brick = (t)(w)(L+H+t) - Volume per brick = (.5)(3.75)(8.0+2.25+.5) = .01166 ft3

    Step 2: Multiply the mortar required/ brick by the total number of bricks. - Volume of mortar = (.01166 ft3/brick) x (982 bricks) = 11.4 ft3

    Step 3: Volume between rows = (.5/12)(77.33) = 3.2 ft3

    Step 4: Mortar Req. = 1.25(11.4+3.2) = 18.3 ft3

    SOLUTION #2A

  • QUANTITY TAKE OFF BOARD FEET

    Board Feet is a measurement of lumber volume. A board foot is equal to 144 cubic inches of wood. Actually its easy to calculate using the following formula:

    (Thickness(in) x Width(in) x Length(in)/144 = Board Feet Or # piece of lumber (P) x (Thickness(in) x width(in))/12 x Length = Board Feet

    Note: Lumber is specified by its rough size. This is why a 1 x 4 board is actually thick and a 2 x 4 board is actually 1-1/2 thick.

    When you are figuring up board feet, keep in mind a waste factor. If you purchase good clear material add about 15% for waste, if you elect to use lower grade material you will have to allow for defects and more wasted material add about 30%.

    Ex. What is the board feet for one 2x4 that is 10 feet long?

    Solution: 1 x (2inx4in)/12 x 10ft = 5 2/3 board feet

  • QUANTITY TAKE-OFF REBAR

    As everyone knows rebar is added to concrete in order to provide tensile strength since concrete is very weak in tension.

    The following are tables for rebar, and wire fabric which are required to know for quantity take so you can know pounds of steel required.

  • QUANTITY TAKE-OFF REBAR

  • Trick of the Trade #3: When calculating the number of bars required find the total length Divided by the spacing of the bars and add 1.

    Example: You are building a 60 ft x 7.5ft concrete wall. The design is the diagram Below with 9 inch spacing of vertical rebar. Figure out the lbs of rebar required.

    profile view

    60 ft

    7.5 ft

    QUANTITY TAKE-OFF REBAR

    #3 rebar

    #4 rebar

    #4 rebar 9in spacing OC

    Step 1: Figure out the steel in the horizontal direction. - it is given that there are 4 #3 bars = .376 lbs/ft - it is given that the horizontal distance is 60 ft - American Concrete Institute recommends concrete cover for slabs, joints, walls NOT exposed to ground 3/4 in lbs of #3 rebar = (4)(60ft-((2)(3/4in)/12))(.376lbs/ft) = 90 lbs

    Step 2: Figure out the steel in the vertical direction. - it is given there are #4 = .668 lbs/ft - using the above trick of trade, ((60ft)(12in/ft)/9in) = 80 bars + 1 = 81 bars required - ACI recommends concrete cover for concrete exposed to the ground of 1.5 inchs, so you should estimate 1.5in off the ground and .75in on top of wall. - So the total length on one #4 rebar is 7.5ft-((1.5/12)-(.75/12)) = 7.31ft lbs of #4 rebar = 81(7.31ft)(.668lbs/ft) = 396 lbs

    Step 3: Find the total lbs of rebar - 90lbs+396lbs = 486 lbs

  • QUANTITY TAKE-OFF REBAR

    Question #3: Find the weight of the steel rebar in concrete filled drilled shaft which is 35 ft deep. The design calls for 8 vertical #10 rebars, and the ties every 5ft are #4 rebar. The diameter of the cylinder is 2 ft. Disregard any concrete cover offset for steel length.

    Answer #3: Step 1: Find pounds of steel in the vertical direction. - given 8 vertical bars = 8 - Total length of vertical bars = 35ft/bars x 8 bars = 280 ft - weight of #10 = 4.303 lbs/ft - total weight in the vertical direction = (4.303 lbs/ft )(280ft) = 1,205 lbs of #10 rebar

    Step 2: Find pounds of steel in the horizontal direction. - Find number of ties, using trick of trade #3, 35/5 +1 = 8 ties - Find length of ties = circumference of the circle = Pi(2ft) = 6.283 ft - Total length = (6.283 ft)(8) = 50.3 ft - Weight of #4 rebar = .668lbs/ft - Total Weight of #4 rebar = (.668lbs/ft)(50.3ft) = 33.6lbs

    Step 3: Find total weight of Rebar. - 1205lbs + 33.6lbs = 1238.6lbs

  • QUANTITY TAKE-OFF ROOFING

    Roof material quantity take-off are pretty easy trig problems, but I will go over it quick to make sure you get it, because most likely a question will be on the PE exam.

    Trick of the Trade #4: When thinking of roof problems you just need to worry about three things. 1.The angle of the roof, or the rise/run of the roof 2.The width of the house plus the overhang of the roof 3.Always remember to add in all sections of the roof and multiply by length of rafters and by the length of the house

    50 ft

    3 ft overhang

    1

    5

    Example: Find the Roofs area if the roof has a 1/5 rise over run angle with a 3ft overhang. The length of the house is 75ft. The width of the house is 50 ft.

    Step 1: Find the length of the roof - BC = 28ft - tan ABC = 1/5 = .20 - tan-1 .20 = 11.3o - AB cos 11.3 = BC - AB = BC/cos 11.3 = 28/cos 11.3 - AB = 28ft/.9806 = 28.55ft

    Step 2: Find the Area of the Roof - Area = 2 sides x (length of the rafter) x (length of the building) - Area = 2 x 28.55ft x 75ft

    - Area = 4,283ft2

    1

    25ft+3ft = 28ft

    x

    B C

    A