Quantifying the capital requirement: 19% RE by...
Transcript of Quantifying the capital requirement: 19% RE by...
Sh
utt
ers
tock
Presentation at IDC Offices
Quantifying the capital requirement: 19% RE by 2030
Megan Sager, Consulting for
Sustainable Solutions
29 August 2014
WWF RE Vision 2030
Overview
WWF Renewable
Energy Vision 2030Articulating the Capital Requirement
29 August 2014 - 2
• Government plans for investment in renewable energy are not
ambitious by international standards
• Renewable energy is the right choice for SA: it is affordable,
promotes energy security and a sustainable future
• Achieving a meaningful renewable energy share will require creative
problem solving: public/private capital and the grid
Overview
WWF Renewable
Energy Vision 2030Articulating the Capital Requirement
29 August 2014 - 3
• Government plans for investment in renewable energy are not
ambitious by international standards
• Renewable energy is the right choice for SA: it is affordable,
promotes energy security and a sustainable future
• Achieving a meaningful renewable energy share will require creative
problem solving: public/private capital and the grid
The IRP2010-2030 Update allows for a
9% share of renewable energy by 2030
69%
12%
5%
9% 4%
Coal NuclearGas RenewablesHydro & other
29 August 2014 - 4
By 2030, 9% of SA’s energy requirement will be
supplied by 17 GW renewable energy (RE)
capacity. More than two thirds electricity will still
come from coal, including 2.5 GW new capacity.
Coal emissions alone will exceed the DEA’s PPD
GHG emissions implicit electricity sector target,
despite remaining within the DOE’s IRP target.
In the low economic growth scenario, RE falls to
a share of just 6% SA’s electricity.
SA electricity mix, 2030
(IRP Update Base Case scenario)
Source: Own calculations based on DOE (2013)
WWF Renewable
Energy Vision 2030Articulating the Capital Requirement
+15%Information
descriptor
Can appear
below
the numbers
Renewable energy generation share and share growth
in emerging markets, 2013
29 August 2014 - 5
This is not ambitious by
international standards
Brazil and Chile have
already met or exceeded
South Africa’s targeted RE
share for 2030.
China and Turkey will
reach 9% within the next 3
years if current RE share
growth rates continue.
Source: BP (2014); own calculations.
11%9%
5% 4% 4%
19%
25%
9%
37%
28%
0%
5%
10%
15%
20%
25%
30%
35%
40%
Brazil Chile India China Turkey
Share of electricity generation by renewables, 2013
Annualised growth in share of renewable electricity generation, 2010-2013 (CAGR)
WWF Renewable
Energy Vision 2030Articulating the Capital Requirement
The WWF calls for a 19% share
of renewable energy by 2030
29 August 2014 - 6
No further investment in coal or nuclear is
supported. When possible, old coal-fired
power stations should be decommissioned to
lower emissions. Gas is acceptable as a bridge
fuel: high ramp rates, lower emissions.
Should low economic growth materialise, the
proposed RE share falls to 9%.
High RE penetration rate: 20%+. Global studies
show a 20% wind share and 7.5-10% solar PV
peak supply share are already feasible (Citi).
26% Germany’s electricity comes from RE.
Source: Own calculations
WWF Renewable
Energy Vision 2030Articulating the Capital Requirement
SA electricity mix, 2030
(WWF high growth scenario)
66%4%
6%
19%
5%
Coal Nuclear Gas Renewables Hydro & other
This will cost SA 1-2% GDP p.a.
but with likely multiplier effects
29 August 2014 - 7
High
economic
growth (5.4%
p.a.) scenario
Low economic
growth (2.9%
p.a.) scenario
Capacity (MW) Generation (TWh) Fiscal cost : 2015-2030 (Rand)
Add 2 200 MW p.a.
Total: 35 000 MW
• Solar*: 19 000 MW
• Wind: 16 000 MW
Annual: 78TWh+ Annual: R78 billion
Total: R1.1 trillion
Add up to 2 200 MW
p.a. (min 1 100 MW)
Total: 17 500 MW
• Solar*: 9 000 MW
• Wind: 8 000 MW
Annual: 39TWh+ Annual: R40-R78 billion p.a.
Total: R480 billion
Recent US infrastructure study shows 2x GDP multiplier effect for up to 10 years after investment
* Solar mix (PV and CSP) determined dynamically according to developments in pricing, storage and the need for dispatchable power
WWF Renewable
Energy Vision 2030Articulating the Capital Requirement
Overview
29 August 2014 - 8
WWF Renewable
Energy Vision 2030Articulating the Capital Requirement
• Government plans for investment in renewable energy are not
ambitious by international standards
• Renewable energy is the right choice for SA: it is affordable,
promotes energy security and promotes a sustainable future
• Achieving a meaningful renewable energy share will require
creative problem solving: public/private capital and the grid
+15%Information
descriptor
Can appear
below
the numbers
Price of electricity, 2013 (R/kWh)
29 August 2014 - 9
0 0,5 1 1,5 2
Coal
Nuclear
Solar PV
Wind
International Reference Prices, 2013 Rand Local Reference Prices, 2013 Rand
Citi Research: 2013 Rand IRP Update: Adjusted, 2013 Rand
Sources: DOE (2013); Citi Research (2013); Papapetrou (2014); Own analysis
In the IRP Update, coal
and nuclear are very
cheap internationally
speaking. PV expensive.
Nuclear is likely to cost
much more, while PV
averaged R0.88/kWh in
REIPPPP Round 3.
RE technologies compete favourably with
conventional technologies on price
WWF Renewable
Energy Vision 2030Articulating the Capital Requirement
+15%Information
descriptor
Can appear
below
the numbers
Best-in-class global utility-scale solar PV costs,
2010-2013 (USD/W)
29 August 2014 - 10
Source: BNEF (2014)
The dollar price of utility-
scale solar PV has halved
in the last 3 years.
Drivers:
• Shift to China
• Low commodity prices
• Weak global economy
In US PPAs are being
signed for $60/MWh.
The recent rapid drop in PV prices
is not an anomaly
1,85
0,72
0,3
0,11
0,5
0,26
0,41
0,31
0,18
0,15
0
0,5
1
1,5
2
2,5
3
3,5
2010 2013
Module Inverter Balance of Plant EPC services Other
WWF Renewable
Energy Vision 2030Articulating the Capital Requirement
+15%Information
descriptor
Can appear
below
the numbers
Projected tariff trajectory,
2014-2030 (2014 Rand)
29 August 2014 - 11
Source: Own analysis; Donnelly (2014)
Notes: CSP estimate refers to CSP with 3 hours storage
The average price of grid
electricity to Eskom was
R0.82/kWh in 2013. Wind
is already cheaper.
PV will be the cheapest
RE source by 2020. CSP
is an alternative to nuclear.
A weakening Rand may
increase the wind price.
Indeed market forces will support long term
grid parity for wind and PV
-
0,20
0,40
0,60
0,80
1,00
1,20
1,40
1,60
201
4
201
5
201
6
201
7
201
8
201
9
202
0
202
1
202
2
202
3
202
4
202
5
202
6
202
7
202
8
202
9
203
0SOLAR PV SOLAR CSP - 3HR
WIND AVE COST GRID ELECTRICITY, 2013
WWF Renewable
Energy Vision 2030Articulating the Capital Requirement
29 August 2014 - 12
Local factors may drive further price
advantage
Tariff (Levelised cost of electricity)
Capital cost Discount rate Capacity factorLearning rate
Price
Variable
Lever 1:
WACC
Lever 2:
Local-
isation
• 1% cut ~ 6% tariff
reduction
• Change in capital
structure OR
better terms (e.g.
CPI linked debt)
• Imported inflation drives project cost up and
exposes sector to forex risk
• Local manufacturing is a partial buffer
• Strong policy and regulatory environment
required to enable sector development
WWF Renewable
Energy Vision 2030Articulating the Capital Requirement
Overview
29 August 2014 - 13
WWF Renewable
Energy Vision 2030Articulating the Capital Requirement
• Government plans for investment in renewable energy are not
ambitious by international standards
• Renewable energy is the right choice for SA: it is affordable,
promotes energy security and a sustainable future
• Achieving a meaningful renewable energy share will require
creative problem solving: public/private capital and the grid
The first challenge to
consider is grid integration
Transmission and distribution infrastructure is
inadequate. The Cape* region will be worst affected: grid
stability limit = 15GW.
Extensive upgrades will be costly and these have longer
time horizons than RE plant construction… Uncertainty
about plant location hinders investment.
Solutions:
• Incentivise central procurement where capacity exists
• Perform ‘robustly required’ transmission system
upgrades (e.g. NC-GP line)
• Promote distributed generation near point of load
demand.
Information descriptor
Can appear below
the numbers
29 August 2014 - 14
WWF Renewable
Energy Vision 2030Articulating the Capital Requirement
Source: www.eskom.co.za
SA grid map, 2011
* This comprises the Western, Northern and Eastern Cape
Grid balancing is required to
ensure smooth power supply
RE has limited predictability and dispatchability:
challenging for system operator which needs to balance
the electricity system.
Solutions:
• Dispatchability issue solved with storage (energy
and thermal): substantial for CSP and emerging for
PV (1 MW battery already available)
• Intermittency countered with flexible power supply
such as gas turbines and pumped storage. Mid-
merit combined cycle gas turbines running off
natural gas are 1 option (e.g. Ankerlig conversion).
Information descriptor
Can appear below
the numbers
29 August 2014 - 15
Source: www.eskom.co.za
WWF Renewable
Energy Vision 2030Articulating the Capital Requirement
Ankerlig OCGT station, Atlantis
The second challenge is
Eskom as only offtaker
There is limited fiscal space to invest further in
utility scale RE. SA is close to the public debt ceiling of
60% GDP. Current obligations reach 56.9% GDP,
excluding REIPPPP guarantees.
Eskom already benefits from a R350bn guarantee (+-
10% GDP) for the new build programme. With a
revenue shortfall of R225bn, sustainability is questioned.
Solution:
Liberalise electricity market to enable private and
municipal utilities to connect to grid or go off-grid,
directly contracting with customers on micro grids.
Information descriptor
Can appear below
the numbers
29 August 2014 - 16
WWF Renewable
Energy Vision 2030Articulating the Capital Requirement
Information descriptor
Can appear below
the numbers
5 MW PV plant, India
Source: www.nrdc.org
The third challenge is policy
coordination and certainty
There is a perceived lack of strategic and planning
alignment between the various public sector entities:
DOE, DEA, DTI, DPE, NERSA and Eskom.
One example is multiplicity of emissions targets (DOE vs
DTI). More immediate issue: DTI’s desire for localisation
vs DOE’s lack of commitment to future RE procurement
(e.g. State of Nation address) and NERSA’s lack of
electricity sector reform.
Solution:
One coordinated policy position which enables RE
industry growth via commitment to RE procurement and
sector reform.
29 August 2014 - 17
Source: Wikipedia
WWF Renewable
Energy Vision 2030Articulating the Capital Requirement
Union Buildings
Finally, wider private investor
participation is required
Local bank balance sheets cannot carry
all of the project debt associated with the
WWF vision. Further, fully financed BEE
partners are said to be scarce.
Est. R400bn additional project debt will be
required to scale up the RE sector from
2015-2030. At R57bn, committed funds are
already 3-7% wholesale banking assets.
Solution:
Retirement funds (R3 trillion assets) can
assist in primary or secondary debt markets
for project and empowerment financing.
Information descriptor
Can appear below
the numbers
29 August 2014 - 18
Source: FirstRand (2013); Standard Bank (2014);
Nedbank (2014); ABSA (2014); Creamer 2013(b).
WWF Renewable
Energy Vision 2030Articulating the Capital Requirement
Commercial bank exposure to RE, 2013
0%
1%
2%
3%
4%
5%
6%
7%
8%
0
2
4
6
8
10
12
14
16
18
20
Nedbank Standard Bank RMB ABSA
Funds committed to RE, Rbn
Funds committed to RE as share of wholesale banking assets, %
Someone's sitting in the shade
today because someone planted a tree a long time ago
Warren Buffett, CEO Berkshire
Hathaway ($15bn RE investor)
29 August 2014 - 19
WWF Renewable
Energy Vision 2030Articulating the Capital Requirement
As financiers and stakeholders in the SA RE sector,
you are a vital part of the solution
Thank youMegan Sager
Director, Consulting for Sustainable Solutions (Pty) Ltd
[email protected] / 021 680 5390
www.panda.org
© 2010, WWF. All photographs used in this presentation are copyright protected and courtesy of the WWF-Canon Global Photo Network and the respective photographers.