    INTRODUCTION OFPROJECT QUALITY MANAGEMENT

    in Oil and Gas Industry

    Public Lecture

    Institut Sains Dan Teknologi Nasional

    Jakarta

    22 June 2013

    Ina Khanifah Hakim ST.MT

  • 7/28/2019 Quality Intro

    2/20

    References

    1. PMBOK Guide - 4th Edition

    2. ISO 21500

    3. ISO 9001 : 2008 Quality ManagementRequirements.

    4. API Q1, 8th edition Specification for Quality Programfor the Petroleum, Petrochemical, and Natural GasIndustry.

    5. ISO 10006 : 2003 Guideline for Quality Management

    in Projects6. ISO 10005 : 2005 Quality Management System

    Guideline For Quality Plans

  • 7/28/2019 Quality Intro

    3/20

    Quality is.

    Fit For Purpose

    Meeting Customer Requirements

    Zero Defect Etc

  • 7/28/2019 Quality Intro

    4/20

    Why Quality important to ..

    OWNER

    a. Requirements are met

    b. Defect free products

    c. On-Time deliveriesd. Reliable service

    CONTRACOR

    a. Reduced cost

    b. Improved productivity

    c. Fewer problems

    d. Avoids product liability

    claims

  • 7/28/2019 Quality Intro

    5/20

    Consequences of Lack of Quality ..

    OWNER

    a. Requirements are not

    met

    b. Schedule delayc. Project cost increased

    CONSTACTORa. Increased cost due to

    inefficient performance

    b. Reputation Suffer

    c. Product liability claims

  • 7/28/2019 Quality Intro

    6/20

    Quality Life Cycle

    Strategic Initiatives

    Work Planning

    for Prevention

    Implement,

    Plan &

    Perform

    Measure

    Effect iveness

    COQ (Project)

    +

    KP I

    (Functional

    Process)

    +

    Audits

    +

    Performance

    AppraisalsEvaluate

    Strengths

    Weaknesses &

    Risks

    Determine

    Action

    Awareness Training - People

    Change Process - ProcessLessons Learned - Project

    New Materials/Equipment -

    Resources

    Revise

    Prevention

    Planning

    IMS

    Continuous

    Improvement

  • 7/28/2019 Quality Intro

    7/20

    Commitment of Management

    Quality is effective only when it is the intention

    of Corporate Policy and Procedures

    MEASURE OF

    EFFECTIVENESS

    POLICY IMS (INFRASTRUCTURE)

    ACCOUNTABILITY QUALITY

    AWARENESS

    TRAINING

    EXECUTIVE MANAGEMENT

    COMMITMENT BY EXAMPLECOMMUNICATION

    Effectiveness is a measure of the outcome of the cause

  • 7/28/2019 Quality Intro

    8/20

  • 7/28/2019 Quality Intro

    9/20

    Plan Quality

    Input

    1. Scope baseline

    2. Stakeholder register

    3. Cost performance baseline

    4. Schedule baseline

    5. Risk Register

    6. Enterprise environmentalfactor

    7. Organizational process assets

    Tool and Techniques

    1. Cost-benefit analysis2. Cost of quality

    3. Control chart

    4. Benchmarking

    5. Design of experiments

    6. Statistical sampling

    7. Flow charting8. Proprietary qualitymanagement

    9. Additional quality planningtools

    Output1. Quality management plan

    2. Quality metric

    3. Quality checklists

    4. Process improvements plan

    5. Project document updates

  • 7/28/2019 Quality Intro

    10/20

    Project Quality Plan

    1. Scope of the Plan2. Measurable Quality Objectives

    3. Management Responsibilities

    4. Documentation Management (including records)

    5. Resources

    6. Specific Requirements (project)

    7. Communication8. Design development, validation and verification

    9. Procurement

    10. Fabrication / Construction (Production)

    11. Identification and Traceability

    12. Storage and Handling

    13. Non Conforming Product14. Monitoring and Measurements

    15. Inspection And Testing Equipment

    16. Audit

  • 7/28/2019 Quality Intro

    11/20

    Project Quality Organization (typical)

    Project QualityManager (PQM)

    QA EngineerQC Supervisor /

    Site QC

    DisciplineInspectors

    Certification

    Secretary

  • 7/28/2019 Quality Intro

    12/20

    Quality Metric

    How the Quality metric measurement drive the

    improvement ?

    1. Measure the efficiency and effectiveness of a

    work process.2. Use to track improving or deteriorating TRENDS.

    3. Use to identify where a problem lies.

    4. Use to set improvement TARGETS and GOALS.

  • 7/28/2019 Quality Intro

    13/20

    Quality Metric measurement

    KPI 4 (a) - Shop Drawing Zero Defect - Structural

    (M 10)Data Source: Robin D' Cruz

    0.04

    0.19

    0.060.14 0.12 0.07 0.05 0.04

    0

    1000

    2000

    3000

    4000

    5000

    6000

    Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

    0.0

    0.2

    0.4

    0.6

    0.8

    1.0

    1.2

    1.4

    1.6

    1.8

    2.0

    Sum DeliverablesSum Errors

    Avg. % ErrorsTarget

    Formula: No. of Drawing Errors =Avg % Error No. of Draw ings Checked

    CY 05 Target 0.25%

  • 7/28/2019 Quality Intro

    14/20

    Perform Quality Assurance

    Input

    1. Project Management Plan

    2. Quality Metrics3. Work performanceinformation

    4. Quality Control measurements

    Tool and Techniques

    1. Plan quality and performquality control tools andtechniques

    2. Quality audit

    3. Process analysis

    Output1. Organization process assetsupdates

    2. Change requests

    3. Project management planupdates

    4. Project documents updates

  • 7/28/2019 Quality Intro

    15/20

    Quality Audit

    Audit within the Project may be used for severalpurposes, such as :

    - To monitor the implementation and effectivenessof quality plans;

    - To monitor and verify conformity with specifiedrequirements;

    - For surveillance of suppliers to the organization;

    - To provide independent objectives assessment,when required, to meet the needs of customersor other interested parties.

  • 7/28/2019 Quality Intro

    16/20

    Perform Quality Control

    Input

    1. Project management plan

    2. Quality metrics

    3. Work performancemeasurement

    4. Approved change requests

    5. Approved change request

    6. Deliverables

    7. Organizational process assets

    Tool and Techniques

    1. Cause and effect diagram

    2. Control charts

    3. Flowcharting

    4. Histogram

    5. Pareto chart

    6. Run chart

    7. Scatter diagram

    8. Statistical sampling

    9. Inspections

    10. Approved change requestreview

    Output

    1. Quality control measurements

    2. Validated changes

    3. Validated deliverables

    4. Organizational process assetsupdates

    5. Change requests

    6. Project Management Planupdates

    7. Project document updates

  • 7/28/2019 Quality Intro

    17/20

    Inspection

    An Inspection is the examination of a workproduct to determine whether it confirms to

    documented standard. The result of an

    inspection generally include measurements and

    may be conducted at all level

  • 7/28/2019 Quality Intro

    18/20

    The figure represents the percentage error in the Welds

    performed. The graph represents the data for Structural Linear

    UT welds performed and the repairs done. The measurement

    is categorized as 'Product Quality'. The data collected reflects

    an increase in the weld repairs for the last three months but exhibits an

    overall improvement in the process.

    AREAS FOR IMPROVEMENT

    1. Chevron cracking in December in Pipe Mill and avoidance

    of Chevron Cracking

    2. Implement preventive action

    SHARE BEST PRACTICE ACTION PLAN

    1. Welder training program and coaching

    2. Welder audit on regular basis

    3. Improve WPS

    4. Modify PCM to ID welder individual repair rates

    5. Train Supervisors to be coaches

    6. Stage development of training & Qualification protocol of

    Fillet, Plate and Pipe

    7. PCM for welder performance

    8. Source young talent to train

    9. Recognition for good performance

    10. Fitters to be measured

    11. Empower welder to reject fit ups

    12. Welding council to improve equipment quality

    13. Stress on quality control topics during toolbox talks

    14. First line inspection CWI for all leadermen15. Foreman to record manhours for repair

    16. Maintain 40 hrs Training Course

    17. Tool box Meeting to address Technical and Method

    Statement prior to work commencement

    18. Consider coaching of welder by Supervisors based on

    criticality of work

    KPI 1(b)-Weld Repairs by Discipline

    Structural Linear - UT (M 2)

    Process Owner: Roy Mathew

    0 . 4 1

    0.54

    0 . 4 60 . 4 3

    0 . 3 50 . 3 2 0 . 3 2

    0.530.51

    0 . 4 9

    0.52

    0 . 3 00 . 3 3

    0 . 4 0

    0 . 4 6

    0

    10000

    20000

    30000

    40000

    50000

    Jan Feb M ar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb M ar

    0.0

    0.2

    0.4

    0.6

    0.8

    1.0

    1.2

    Length Tested

    Repair Lengt h

    Avg . %

    Ind. Std

    Target

    Formula: Length Rejected =Avg. % Error

    Length Tested

    CY 2005CY 2004

    CY 05 T arget 0.3%

    CAUSE & EFFECT DIAGRAM

  • 7/28/2019 Quality Intro

    19/20

    DESIGN VERIFICATION& DESIGN REVIEW

    DEFICIENCY

    Management Commitment to Quality

    Quality not considered a Value and compromised

    Fab Supervision intimidation of QC Personnel

    Product liability Claim

    Loss of $ and Reputation

    OUTCOME

    PMT TEAMDEDICATED STAFF

    PROJECTCONTROLS

    DRIVESPROJECT

    PLANNING IMS SYSTEMPROCUREMENTMATERIALS MGT.

    FABRICATION

    CLIENT

    INFLUENCE

    CLIENT

    INFLUENCE

    CLIENT

    INFLUENCE

    PROJECT TIME LINE

    FUNCTIONAL INPUT CONTROLLED BY FUNCTIONAL STAFF

    FUNCTIONAL INPUT CONTROLLED BY FUNCTIONAL STAFF

    BIDSUBMISSION

    SCHEDULE

    HISTOGRAM

    CRITICAL PATH

    MILESTONE

    LEVIL 1 GUIDELINES

    LEVEL 2 PROCEDURES

    LEVEL 3 PLANS

    PROJECT AUDITS

    FREE ISSUE

    PROCUREMENT PLAN

    RFQ & TBE

    PRICE, DELIVERY

    VENDOR CAPABILITY

    SUB-CONTRACTOR CAPABILITY

    CONTRACT

    SOW & REQUIREMENT

    CRITERIA SPEC

    CHANGE ORDER/MGT.

    DESIGN

    TBE OF ENG. EQUIPMENT &ENG. BULK MATERIAL

    EFFECTIVE & TIMELYDELIVERABLES (ROS)

    MARINE

    ENVIRONMENT

    AGENT FACILITATION &SERVICES

    SITE LOGISTICS

    AWARD

    FEED

    PROGRESS MEASUREMENT

    WBS

    REPORTING EXPIDITING

    QC/NDT PRODUCT CONFORMITY

    PROJECT QA

    CORPORATE AUDITS

    QUALITY PLANNING

    ISO 9000

    MEASUREMENT

    REVIEW LESSONS LEARNED

    MILESTONES

    PROJECT QA

    DETAIL DESIGN

    MATERIAL CONTROL

    4 WEEK LOOK AHEAD

    HSE

    PRODUCTIVITY

    QC/NDT PRODUCT CONFORMITY

    HSE

    CARGO BARGE

    SUPPORT VESSEL

    LAYRATE / CYCLE TIME

    DOWNTIME

    LOGISTIC SCHEDULE

    QC/NDT PRODUCT CONFORMITY

    LOCAL WORKFORCE

    DESIGN PREMISE

    MGT. COMMITMENT

    BARGE SELECTION PREPARATION

    RISK ASSESSMENT

    DEPTH & TIDES & CURRENT

    CONSTRUCTION AID

    WELDING PROCEDURE

    WELDING PROCEDURE

    END

    PRODUCT

    CAUSE & EFFECT DIAGRAM

    PROJECT EXECUTION CORE PROCESS

  • 7/28/2019 Quality Intro

    20/20