Quality Built In into ProjectsProject Quality Gates
May 2011
© 2011 SAP AG. All rights reserved. 2
Topics
Project Quality Gate Value Proposition
Project Quality Gate Process and Tools
Project Quality Gate Value Proposition
© 2011 SAP AG. All rights reserved. 4
SAP places Quality Built-In at the center of projects that we deliver for our Customers.Quality oversight and early visibility of potential problems have a profound impact on reducing project risk and drive Customer Value.
Project Quality Gate Process supports this: The Project Quality Gate process is a formal way of specifying and recording the transition
between critical stages in the project lifecycle.
Each Project Quality Gate verifies that acceptance is meet for the deliverables required and actions to be completed for the associated critical stage.
The Project Quality Gate Plan is defined in the Project Management Plan
© 2011 SAP AG. All rights reserved. 5
Project Quality Gate Value Proposition
Click icon to add picture
Objectives: Assure quality at the milestones of the project
Assure that all key deliverables and actions have been completed in compliance with best practices
Avoid customer dissatisfaction
Enable project managers to continuously communicate and build quality into the project
Benefits: Enhance project quality
Minimize project risk exposure
Manage expectations and monitor customer satisfaction
Improve transparency of the project
Reduce cycle time: get it done right the first time
Project Quality Gate Process and Tools
© 2011 SAP AG. All rights reserved. 7
Project Quality Gate Concept
Project Quality Gate means: Formal assessment of the quality and integrity of the project deliverables
Formal checklists are used throughout the life of a project
Formal sign-off and acceptance occurs at each gate
Measure customer satisfaction throughout the project
Information is assured to be communicated to the correct stakeholders during the project
Purpose and ImpactThe intention of Q-Gates is to ensure that when we reach significant milestones in the project we check the Quality of the delivery: Are we on track?
Are all deliverables complete?
Are they fit for purpose?
Do the Partner/Customer agree?
Is risk managed?
Can we start the next phase without delay
© 2011 SAP AG. All rights reserved. 8
Project Quality Gates are defined in the Project Management Plan and are set at critical stages in the project lifecycle.
Four quality gates are mandatory: Project Preparation Phase
Blueprint Phase
Realization Phase
Final Preparation
Other 3 gates are optional as agreed with the customer.
Four (of seven) Q-Gates are mandated for SAP Projects
21 3 4
1
2
3
4
© 2011 SAP AG. All rights reserved. 9
Result
Follow-Up
Scope
Delivery events
Review efforts
ROLES
Project Quality GatesExecuted at end of each Project Phase , it is a formal way of specifying
and recording the transition between critical stages in the project lifecycle
Evaluate quality of each deliverable in the phase based on questionnaire and actual deliverable
Formal approval of the Quality Gate Focus on Project Management + limited coverage of Functional/Technical
topics
Prior to the end of each stage in the project lifecycle, before moving into the next phase
Preparation – 0,5 Hours Assessment Meeting– 2-4 Hours
Pass/No Pass Status (based on Approval from QA Manager and Delivery Manager)
QA manager dispatch all follow-up activities and ensure that they have been executed
QA Manager (Role) Mandatory - Moderator
QA Subject Matter Expert Optional (On demand) - Questioner
Project Manager Mandatory - Presenter
SME (Project team) Optional (On demand) - Supporter
Delivery Manager Mandatory - Approver
Other Optional Participants Optional
Project Q-Gates Process
© 2011 SAP AG. All rights reserved. 10
Project Quality Gate Process
Approach Preparation call to establish pre-requisites
Quality Gate Meeting duration half day to full day, owner is Project Manager
Project Manager presents overall project status and Team Leads the status of each key deliverable
Project Manager and Customer Project Manager review deliverable quality and verify completeness and accuracy
Sign off Quality Gate scorecard Action items for follow-up are established.
All address specific project matters for second opinion & follow-up
Key Deliverables The key deliverables assessed at each project quality gate are
listed in the Project Quality Gate Scorecard.
© 2011 SAP AG. All rights reserved. 11
Project Quality Gate Review Meeting
Prior to meeting: Project Manager prepares Quality Gate scorecard by indicating the project phase deliverables according to project WBS and assures deliverables will be available for review
Project Manager is owner of the meeting and presents the status of the project phase.
Project Manager or Team leads (deliverable owners) present deliveries according to the scorecard
Project Manager and Customer Project Manager evaluate content and quality of each deliverable
Project Manager records result of the review in the scorecard and the deadlines and action owners for open points/tasks. Acceptance Level 1: Accepted Acceptance Level 2: Conditionally accepted. Quality improvement to the deliverable is needed. A comment
describes the next steps depending on the estimated impact to the project. Acceptance Level 3: Not available or not accepted. Fulfillment is needed. A comment describes the next steps,
depending on the estimated impact to the project.
Project Manager captures customer satisfaction ratings to success measures identified in the Project Management Plan and records actions for improvement.
Project Manager and the Customer Project Manager summarize the minutes and action items (area at the bottom of the scorecard) and release decision taken for the Quality Gate
After Quality Gate Review: Verify that follow-up actions have been taken place, provide scorecard to Phase Acceptance and Closure
© 2011 SAP AG. All rights reserved. 12
Quality Gate Review Meeting – Agenda template
Topic Responsible
2 -3 hours 2 Assessment
Presentation of status of project Project
Manager
Review of status of stage deliverables Team
Leads
Maintenance of scorecard
Project Manager
Identification of action items and satisfaction Project Manager
15 Min 1 Kick-off Project Manager
30 Min3 Other Project Matters Discussion all
30 Min 4 Sign-off scorecard, summary of action item Meeting close
Estimated Time
Project Manager Customer Project Manager
Customer Project Manager ratings
Yogesh to provide updated version
© 2011 SAP AG. All rights reserved. 13
Project Quality Gate – Scorecard
Excel format, stores all Quality Gates during the lifecycle of the project. Each Quality Gate has its own scorecard as sub-sheet
Review mandatory key deliverables in checklist to properly reflect the specific project WBS
The scorecard provides a default list, based on the ASAP WBS.
All key deliverables are documented in the ASAP Roadmap with templates
Other required project specific deliverables can be added on demand.
Verify that each deliverable has achieved the acceptance criteria Assign under column “Acceptance” the level of acceptance on the 1-3 numerical scale
Assign under the column “Impact to Project” the level of impact on the 1-3 numerical scale
Use the “Comments/Actions” field to record the reasons of any conditional acceptance and the action plan to produce an acceptable deliverable
Capture customer satisfaction ratings to success measures identified in the Project Management Plan and record actions for improvement
The Project Q-Gate assessment will be concluded by specifying the minutes of the assessment down the list of deliverables including the sign-off/release of the Q-Gate
© 2011 SAP AG. All rights reserved. 14
Evaluating individual deliverables
Project Manager & Quality/Delivery Manager(s) assess quality of deliverables in the scorecard: content review is focus of the Quality Gate
How to evaluate the deliverable?
Deliverable is physically available and in the right format/using the agreed template Example: Final version of Business Blueprint is shown on screen
Deliverable has followed the appropriate sign-off procedure Example: Business Blueprint has been physically signed off by Customer and Project Manager or e-
mail is shown where Customer and PM approved the document
Deliverable is actively used for the purpose it’s meant for Example: Business Blueprint will be used to accept the configured solution at the acceptance test
Deliverable content is realistic and assessed against any specific acceptance criteria Example: Take a snapshot on a specific page and review level of detail.
Judgment on required action is also related to the question: What risks does this incomplete deliverable bring to the project’s success? This is indicated by Impact indicator Low, Medium, High
Example: A final Blueprint which is not signed-off may bring a high risk to the project, and as such will be recorded as 3-Red for Impact and requires immediate action.
© 2011 SAP AG. All rights reserved. 15
Meeting Minutes: Quality Gate Released?
Indicates that this quality gate is passed.
There might be some action items in place in order to complete or improve certain deliverables.
Indicates that this quality gate is not passed.
There are serious action items in place and the Project Management insist to organize a second assessment to re-evaluate the actioned deliverables.
No brings a serious message that the overall quality of (some of) the key-deliverables is insufficient and causes a serious risk to the success of the project.
YES
NO
© 2011 SAP AG. All rights reserved. 16
No part of this publication may be reproduced or transmitted in any form or for any purpose without the express permission of SAP AG. The information contained herein may be changed without prior notice.
Some software products marketed by SAP AG and its distributors contain proprietary software components of other software vendors.
Microsoft, Windows, Excel, Outlook, and PowerPoint are registered trademarks of Microsoft Corporation.
IBM, DB2, DB2 Universal Database, System i, System i5, System p, System p5, System x, System z, System z10, System z9, z10, z9, iSeries, pSeries, xSeries, zSeries, eServer, z/VM, z/OS, i5/OS, S/390, OS/390, OS/400, AS/400, S/390 Parallel Enterprise Server, PowerVM, Power Architecture, POWER6+, POWER6, POWER5+, POWER5, POWER, OpenPower, PowerPC, BatchPipes, BladeCenter, System Storage, GPFS, HACMP, RETAIN, DB2 Connect, RACF, Redbooks, OS/2, Parallel Sysplex, MVS/ESA, AIX, Intelligent Miner, WebSphere, Netfinity, Tivoli and Informix are trademarks or registered trademarks of IBM Corporation.
Linux is the registered trademark of Linus Torvalds in the U.S. and other countries.
Adobe, the Adobe logo, Acrobat, PostScript, and Reader are either trademarks or registered trademarks of Adobe Systems Incorporated in the United States and/or other countries.
Oracle is a registered trademark of Oracle Corporation.
UNIX, X/Open, OSF/1, and Motif are registered trademarks of the Open Group.
Citrix, ICA, Program Neighborhood, MetaFrame, WinFrame, VideoFrame, and MultiWin are trademarks or registered trademarks of Citrix Systems, Inc.
HTML, XML, XHTML and W3C are trademarks or registered trademarks of W3C®, World Wide Web Consortium, Massachusetts Institute of Technology.
Java is a registered trademark of Sun Microsystems, Inc.
JavaScript is a registered trademark of Sun Microsystems, Inc., used under license for technology invented and implemented by Netscape.
SAP, R/3, SAP NetWeaver, Duet, PartnerEdge, ByDesign, SAP BusinessObjects Explorer, StreamWork, and other SAP products and services mentioned herein as well as their respective logos are trademarks or registered trademarks of SAP AG in Germany and other countries.
© 2011 SAP AG. All rights reserved
Business Objects and the Business Objects logo, BusinessObjects, Crystal Reports, Crystal Decisions, Web Intelligence, Xcelsius, and other Business Objects products and services mentioned herein as well as their respective logos are trademarks or registered trademarks of Business Objects Software Ltd. Business Objects is an SAP company.
Sybase and Adaptive Server, iAnywhere, Sybase 365, SQL Anywhere, and other Sybase products and services mentioned herein as well as their respective logos are trademarks or registered trademarks of Sybase, Inc. Sybase is an SAP company.
All other product and service names mentioned are the trademarks of their respective companies. Data contained in this document serves informational purposes only. National product specifications may vary.
The information in this document is proprietary to SAP. No part of this document may be reproduced, copied, or transmitted in any form or for any purpose without the express prior written permission of SAP AG.
This document is a preliminary version and not subject to your license agreement or any other agreement with SAP. This document contains only intended strategies, developments, and functionalities of the SAP® product and is not intended to be binding upon SAP to any particular course of business, product strategy, and/or development. Please note that this document is subject to change and may be changed by SAP at any time without notice.
SAP assumes no responsibility for errors or omissions in this document. SAP does not warrant the accuracy or completeness of the information, text, graphics, links, or other items contained within this material. This document is provided without a warranty of any kind, either express or implied, including but not limited to the implied warranties of merchantability, fitness for a particular purpose, or non-infringement.
SAP shall have no liability for damages of any kind including without limitation direct, special, indirect, or consequential damages that may result from the use of these materials. This limitation shall not apply in cases of intent or gross negligence.
The statutory liability for personal injury and defective products is not affected. SAP has no control over the information that you may access through the use of hot links contained in these materials and does not endorse your use of third-party Web pages nor provide any warranty whatsoever relating to third-party Web pages.