Government of Nunavut
November 2017
Qikiqtani Correctional Healing Centre Project Information
PRESENTATION OBJECTIVES
• Overview of the Project Design Process and Design
• Operational Program
• Next Steps
• Questions
• Drawings and Discussion
FUNDING AND OPERATIONS
ACTIVITY RESULTS
Approved Funding
• $57 Million – Government of Canada
• $19 Million – Government of Nunavut • $76 Million – Total Funding
Operations
• The operational budget for QCHC is still being
reviewed.
ACTIVITY TIMELINE
Design Contract Awarded January 2017
Design Consultations Spring, Summer and Fall 2017
Conceptual Design and Revisions Spring, Summer and Fall 2017
Construction (Site Preparation) Summer 2017
Final Specifications and Drawings February 2017
Phase 1 Construction (Piling) Spring 2018
Phase 1 & 2 Tender and Contract Award Spring 2018
Construction Start for Phase 1 (New Facility) Summer 2018
Phase 1 Opening (All inmate and staff in new facility) Summer 2020
Phase 2 Construction Start (Renovations to BCC) Summer 2020
Phase 2 Opening Fall 2021
PROJECT SCHEDULE
ACTIVITY AGENCY
Development Permit Process City of Iqaluit
Final review of drawings for construction and planning Government of Nunavut
Preparing documents for Tenders Government of Nunavut
Project Phasing – Ensuring that operations in the existing facility continue during construction
Government of Nunavut/Department of Justice
Facility maintenance and operations planning Government of Nunavut
KEY ACTIVITIES
• The Department of Justice recognizes the significant expertise that the Elders bring to this project.
• Created the Tassiugarjuaqmi Mamisarviksamik Qanurtutrtiit committee to inform the design consultants and the Department of Justice on how to make this facility a success.
• The Department of Justice has provided regular updates to Nunavut Tunngavik Incorporated (NTI).
• Recently, the current stage of design was presented to Justice staff. • In June 2017, the Department of Justice presented to the City of Iqaluit Development Committee. • In June 2017, the Department of Justice hosted an Elders Conference at the Rankin Inlet Healing
Facility to help inform the project.
CONSULTATION SO FAR
Rankin Inlet Healing Facility Elders Conference June 12-14, 2017
• Support cultural concept of healing • Design for the next 20 years – The total bed space including Makigiarvik will be
approximate 160. • The new facility will have a significant increase in programming space to allow
inmates to address their needs in a safe and secure environment. • The look of the new Qikiqtani Correctional Healing Center will be given special
attention due to the facility’s location near the new airport • Create a facility that the community can be proud of and embrace.
DESIGN OBJECTIVES INFORMATION ONLY
These drawings are provided for information purposes only and are not to be relied on or used for any
tendering process
• Programming that will benefit the community such as the Town Crew program
• Safer Community as the new facility is being designed using current standards.
• Better layout to facilitate the healing process and minimize disruption.
• Employment opportunity for people in the community during construction and operation (Inuit employment)
BENEFITS TO THE COMMUNITY
BUILDING CONSTRUCTION • Total Construction Building Area: 5700 m2 • New Addition
• 4000 m2 of non-combustible construction • Foundation: Adfreeze Steel Pipe Piles in Clusters with airspace to u/s of Soffit • Structural System: Steel Post and Beam with Cast-in-place Concrete Bracing Elements • Floor Systems: Concrete Topping on Composite Metal Deck • Wall Systems: Concrete Masonry Units for Secure areas and Steel Stud for Non-Secure
areas (typical) • Roof System: Mineral Wool Insulation and SBS Membrane Roofing • Exterior Wall Systems: Metal Cladding • Heating: Hydronic based on Diesel Oil
• Existing Building Renovation • Full demolition to structure, new construction is non-combustible • Foundation: Adfreeze Steel Pipe Piles in Clusters with airspace to u/s of Soffit • Structural System: Steel Post and Beam Existing • Floor Systems: Concrete Topping on Existing • Wall Systems: Steel Stud (typical) • Roof Systems and Exterior Wall Systems as per new addition
SITE PLAN INFORMATION ONLY These drawings are provided for
information purposes only and are not to be relied on or used for any
tendering process
BUILDING DESIGN INFORMATION ONLY These drawings are provided for
information purposes only and are not to be relied on or used for any
tendering process
BUILDING DESIGN INFORMATION ONLY These drawings are provided for
information purposes only and are not to be relied on or used for any
tendering process
BUILDING DESIGN INFORMATION ONLY These drawings are provided for
information purposes only and are not to be relied on or used for any
tendering process
FLOOR PLAN INFORMATION ONLY These drawings are provided for
information purposes only and are not to be relied on or used for any
tendering process
FLOOR PLAN INFORMATION ONLY These drawings are provided for
information purposes only and are not to be relied on or used for any
tendering process
DISCUSSIONS ABOUT PROGRAMS
NEXT STEPS
ACTIVITY AGENCY
Development Permit Application with the City of Iqaluit
Tendering the Work and Selecting the Contractor Government of Nunavut
Logistics and planning • Draft Traffic and Dust Management Plans • Preparing a Draft Construction Schedule • Moving equipment and materials for 2018 sealift season • Phase 1 Construction begins – expected 2018
Contractor
Please send comments or questions to: Don Galloway Procurement Officer (867) 975-6846 [email protected]