Activity ID Activity Name Original Duration Start Finish CONTRACT 2 : ORBITAL HIGHWAY: Structural Works 335 01-Apr-15 02-May-16 CONSTRUCTION 335 01-Apr-15 02-May-16 JUNCTION 4 & SOUTH OF DUKHAN ROAD - REMAINING WORKS (NOT PART OF M7) 335 01-Apr-15 02-May-16 JUNCTION 4-(Sta. 57+300 to Sta. 59+500- 2000 M) 335 01-Apr-15 02-May-16 Q-RAIL GREEN LINE TUNNEL 335 01-Apr-15 02-May-16 SITE INSTRUCTION 28 01-Apr-15 03-May-15 A1040 Receipt of SI 0 01-Apr-15* A1050 Shop Drawing Preparion and Approval 28 01-Apr-15 03-May-15 PHASE 1 220 01-Apr-15 19-Dec-15 SITE CLEANRANCE 5 01-Apr-15 06-Apr-15 M8J4S-QR-SC-100 Site Clearance 5 01-Apr-15 06-Apr-15 EXCAVATION FOR TUNNEL 124 01-Apr-15 26-Aug-15 M8J4S-QR-EW-100 General Excavation 10 01-Apr-15 12-Apr-15 M8J4S-QR-EW-110 Excvation for Foundation and Formation Preparation for Main Tunnel 5 13-Apr-15 18-Apr-15 M8J4S-QR-EW-120 Excvation for Foundation and Formation Preparation for U-Section 5 19-Apr-15 23-Apr-15 M8J4S-QR-TD-130 Installation of Traffic Diversion for Phase 1 14 07-Apr-15 22-Apr-15 M8J4S-QR-TD-140 Earthworks and Road Works for Phase 2 Traffic Diversion 90 23-Apr-15 09-Aug-15 M8J4S-QR-TD-150 Installation of Traffic Diversion for Phase 1 7 19-Aug-15 26-Aug-15 UTILITY CORRIDOR (PANEL 2 AND 3 OF MAIN TUNNEL FOR UTILITY CORRIDOR) 75 23-Apr-15 22-Jul-15 FOUNDATION 30 23-Apr-15 27-May-15 PANEL 2 21 23-Apr-15 17-May-15 M8J4S-QR-T1FP2-100 Laying of Blinding 1 23-Apr-15 23-Apr-15 M8J4S-QR-T1FP2-110 Waterproofing 1 25-Apr-15 25-Apr-15 M8J4S-QR-T1FP2-120 Reinfocement Fixing 9 26-Apr-15 05-May-15 M8J4S-QR-T1FP2-130 Formworks 2 05-May-15 06-May-15 M8J4S-QR-T1FP2-140 Concreting 1 07-May-15 07-May-15 M8J4S-QR-T1FP2-150 Deshuttering 1 09-May-15 09-May-15 M8J4S-QR-T1FP2-160 Curing 7 10-May-15 17-May-15 PANEL 3 21 04-May-15 27-May-15 M8J4S-QR-T1FP3-100 Laying of Blinding 1 04-May-15 04-May-15 M8J4S-QR-T1FP3-110 Waterproofing 1 05-May-15 05-May-15 M8J4S-QR-T1FP3-120 Reinfocement Fixing 9 06-May-15 16-May-15 M8J4S-QR-T1FP3-130 Formworks 2 16-May-15 17-May-15 M8J4S-QR-T1FP3-140 Concreting 1 18-May-15 18-May-15 M8J4S-QR-T1FP3-150 Deshuttering 1 19-May-15 19-May-15 M8J4S-QR-T1FP3-160 Curing 7 20-May-15 27-May-15 ELEVEVATION (SIDE WALL) 23 20-May-15 15-Jun-15 PANEL 2 19 20-May-15 10-Jun-15 M8J4S-QR-T1EP2-220 Reinfocement Fixing for W1(East Wall) 2 20-May-15 21-May-15 M8J4S-QR-T1EP2-230 Formworks for W1(East Wall) 2 21-May-15 23-May-15 M8J4S-QR-T1EP2-240 Concreting for W1(East Wall) 1 24-May-15 24-May-15 M8J4S-QR-T1EP2-250 Deshuttering for W1(East Wall) 1 25-May-15 25-May-15 M8J4S-QR-T1EP2-260 Curing for W1(East Wall) 7 26-May-15 02-Jun-15 M8J4S-QR-T1EP2-270 Waterproofing for foudation and Wall for W1(East Wall) 5 03-Jun-15 08-Jun-15 M8J4S-QR-T1EP2-280 Reinfocement Fixing for W2 (West Wall) 2 23-May-15 24-May-15 Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun 2015 2016 PROJECT: DESIGN & CONSTRUCT NEW ORBITAL HIGHWAY & TRUCK ROUTE (P023) - CONTRACT 2: ORBITAL HIGHWAY SALWA ROAD TO NORTH RELIEF ROAD INTERNAL TARGET PROGRAMME OF WORKS GREEN LINE TUNNEL PROGRAMME Remaining Level of Effort Actual Level of Effort Actual Work Remaining Work Critical Remaining ... Milestone Page 1 of 19 TASK filter: Q-RAIL GREEN LINE. © Oracle Corporation

description

Qa rail Program

Transcript of Q rail

Activity ID Activity Name OriginalDuration

Start Finish

CONTRACT 2 : ORBITAL HIGHCONTRACT 2 : ORBITAL HIGHWAY: Structural Works 335 01-Apr-15 02-May-16

CONSTRUCTIONCONSTRUCTION 335 01-Apr-15 02-May-16

JUNCTION 4 & SOUTH OF DUKHJUNCTION 4 & SOUTH OF DUKHAN ROAD - REMAINING WORKS (NOT PART OF M7) 335 01-Apr-15 02-May-16

JUNCTION 4-(Sta. 57+300 to Sta. JUNCTION 4-(Sta. 57+300 to Sta. 59+500- 2000 M) 335 01-Apr-15 02-May-16

Q-RAIL GREEN LINE TUNNELQ-RAIL GREEN LINE TUNNEL 335 01-Apr-15 02-May-16

SITE INSTRUCTIONSITE INSTRUCTION 28 01-Apr-15 03-May-15

A1040 Receipt of SI 0 01-Apr-15*

A1050 Shop Drawing Preparion and Approval 28 01-Apr-15 03-May-15

PHASE 1PHASE 1 220 01-Apr-15 19-Dec-15

SITE CLEANRANCESITE CLEANRANCE 5 01-Apr-15 06-Apr-15

M8J4S-QR-SC-100 Site Clearance 5 01-Apr-15 06-Apr-15

EXCAVATION FOR TUNNELEXCAVATION FOR TUNNEL 124 01-Apr-15 26-Aug-15

M8J4S-QR-EW-100 General Excavation 10 01-Apr-15 12-Apr-15

M8J4S-QR-EW-110 Excvation for Foundation and Formation Preparation for Main Tunnel 5 13-Apr-15 18-Apr-15

M8J4S-QR-EW-120 Excvation for Foundation and Formation Preparation for U-Section 5 19-Apr-15 23-Apr-15

M8J4S-QR-TD-130 Installation of Traffic Diversion for Phase 1 14 07-Apr-15 22-Apr-15

M8J4S-QR-TD-140 Earthworks and Road Works for Phase 2 Traffic Diversion 90 23-Apr-15 09-Aug-15

M8J4S-QR-TD-150 Installation of Traffic Diversion for Phase 1 7 19-Aug-15 26-Aug-15

UTILITY CORRIDOR (PANEL 2UTILITY CORRIDOR (PANEL 2 AND 3 OF MAIN TUNNEL FOR UTILITY CORRIDOR) 75 23-Apr-15 22-Jul-15

FOUNDATIONFOUNDATION 30 23-Apr-15 27-May-15

PANEL 2PANEL 2 21 23-Apr-15 17-May-15

M8J4S-QR-T1FP2-100 Laying of Blinding 1 23-Apr-15 23-Apr-15

M8J4S-QR-T1FP2-110 Waterproofing 1 25-Apr-15 25-Apr-15

M8J4S-QR-T1FP2-120 Reinfocement Fixing 9 26-Apr-15 05-May-15

M8J4S-QR-T1FP2-130 Formworks 2 05-May-15 06-May-15

M8J4S-QR-T1FP2-140 Concreting 1 07-May-15 07-May-15

M8J4S-QR-T1FP2-150 Deshuttering 1 09-May-15 09-May-15

M8J4S-QR-T1FP2-160 Curing 7 10-May-15 17-May-15

PANEL 3PANEL 3 21 04-May-15 27-May-15

M8J4S-QR-T1FP3-100 Laying of Blinding 1 04-May-15 04-May-15

M8J4S-QR-T1FP3-110 Waterproofing 1 05-May-15 05-May-15

M8J4S-QR-T1FP3-120 Reinfocement Fixing 9 06-May-15 16-May-15

M8J4S-QR-T1FP3-130 Formworks 2 16-May-15 17-May-15

M8J4S-QR-T1FP3-140 Concreting 1 18-May-15 18-May-15

M8J4S-QR-T1FP3-150 Deshuttering 1 19-May-15 19-May-15

M8J4S-QR-T1FP3-160 Curing 7 20-May-15 27-May-15

ELEVEVATION (SIDE WALL)ELEVEVATION (SIDE WALL) 23 20-May-15 15-Jun-15

PANEL 2PANEL 2 19 20-May-15 10-Jun-15

M8J4S-QR-T1EP2-220 Reinfocement Fixing for W1(East Wall) 2 20-May-15 21-May-15

M8J4S-QR-T1EP2-230 Formworks for W1(East Wall) 2 21-May-15 23-May-15

M8J4S-QR-T1EP2-240 Concreting for W1(East Wall) 1 24-May-15 24-May-15

M8J4S-QR-T1EP2-250 Deshuttering for W1(East Wall) 1 25-May-15 25-May-15

M8J4S-QR-T1EP2-260 Curing for W1(East Wall) 7 26-May-15 02-Jun-15

M8J4S-QR-T1EP2-270 Waterproofing for foudation and Wall for W1(East Wall) 5 03-Jun-15 08-Jun-15

M8J4S-QR-T1EP2-280 Reinfocement Fixing for W2 (West Wall) 2 23-May-15 24-May-15

Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun2015 2016

PROJECT: DESIGN & CONSTRUCT NEW ORBITAL HIGHWAY & TRUCK ROUTE (P023) -CONTRACT 2: ORBITAL HIGHWAY SALWA ROAD TO NORTH RELIEF ROADINTERNAL TARGET PROGRAMME OF WORKS

GREEN LINE TUNNEL PROGRAMME

Remaining Level of EffortActual Level of Effort

Actual WorkRemaining Work

Critical Remaining ...Milestone

Page 1 of 19 TASK filter: Q-RAIL GREEN LINE.© Oracle Corporation

Activity ID Activity Name OriginalDuration

Start Finish

M8J4S-QR-T1EP2-290 Formworks for W2 (West Wall) 2 24-May-15 25-May-15

M8J4S-QR-T1EP2-300 Concreting for W2 (West Wall) 1 26-May-15 26-May-15

M8J4S-QR-T1EP2-310 Deshuttering for W2 (West Wall) 1 27-May-15 27-May-15

M8J4S-QR-T1EP2-320 Curing for W2 (West Wall) 7 28-May-15 04-Jun-15

M8J4S-QR-T1EP2-330 Waterproofing for foudation and Wall for W2 (West Wall) 5 06-Jun-15 10-Jun-15

PANEL 3PANEL 3 19 25-May-15 15-Jun-15

M8J4S-QR-T1EP3-220 Reinfocement Fixing for W1(East Wall) 2 25-May-15 26-May-15

M8J4S-QR-T1EP3-230 Formworks for W1(East Wall) 2 26-May-15 27-May-15

M8J4S-QR-T1EP3-240 Concreting for W1(East Wall) 1 28-May-15 28-May-15

M8J4S-QR-T1EP3-250 Deshuttering for W1(East Wall) 1 30-May-15 30-May-15

M8J4S-QR-T1EP3-260 Curing for W1(East Wall) 7 31-May-15 07-Jun-15

M8J4S-QR-T1EP3-270 Waterproofing for foudation and Wall for W1(East Wall) 5 08-Jun-15 13-Jun-15

M8J4S-QR-T1EP3-280 Reinfocement Fixing for W2 (West Wall) 2 27-May-15 28-May-15

M8J4S-QR-T1EP3-290 Formworks for W2 (West Wall) 2 28-May-15 30-May-15

M8J4S-QR-T1EP3-300 Concreting for W2 (West Wall) 1 31-May-15 31-May-15

M8J4S-QR-T1EP3-310 Deshuttering for W2 (West Wall) 1 01-Jun-15 01-Jun-15

M8J4S-QR-T1EP3-320 Curing for W2 (West Wall) 7 02-Jun-15 09-Jun-15

M8J4S-QR-T1EP3-330 Waterproofing for foudation and Wall for W2 (West Wall) 5 10-Jun-15 15-Jun-15

ELEVEVATION (CROSS WALLELEVEVATION (CROSS WALL) 29 02-Jun-15 05-Jul-15

M8J4S-QR-T1EP3-340 Reinforcement Fixing 18 02-Jun-15 22-Jun-15

M8J4S-QR-T1EP3-350 Formworks Fixing 18 04-Jun-15 24-Jun-15

M8J4S-QR-T1EP3-360 Concrete Works 18 07-Jun-15 27-Jun-15

M8J4S-QR-T1EP3-370 Curing 7 28-Jun-15 05-Jul-15

TOP SLABTOP SLAB 19 28-Jun-15 22-Jul-15

PANEL 2PANEL 2 15 02-Jul-15 22-Jul-15

M8J4S-QR-T1DWP2-170 Erection of Scaffolding for Deck Slab 1 02-Jul-15 02-Jul-15

M8J4S-QR-T1DWP2-180 Formworks for Deck Slab 3 04-Jul-15 06-Jul-15

M8J4S-QR-T1DWP2-190 Steel FIxing 6 04-Jul-15 09-Jul-15

M8J4S-QR-T1DWP2-200 Concreting 1 11-Jul-15 11-Jul-15

M8J4S-QR-T1DWP2-210 Removal of Scaffolding and Deshuttering 1 14-Jul-15 14-Jul-15

M8J4S-QR-T1DWP2-220 Curing 7 12-Jul-15 22-Jul-15

PANEL 3PANEL 3 15 28-Jun-15 14-Jul-15

M8J4S-QR-T1DWP3-170 Erection of Scaffolding for Deck Slab 1 28-Jun-15 28-Jun-15

M8J4S-QR-T1DWP3-180 Formworks for Deck Slab 3 29-Jun-15 01-Jul-15

M8J4S-QR-T1DWP3-190 Steel FIxing 6 29-Jun-15 05-Jul-15

M8J4S-QR-T1DWP3-200 Concreting 1 06-Jul-15 06-Jul-15

M8J4S-QR-T1DWP3-210 Removal of Scaffolding and Deshuttering 1 09-Jul-15 09-Jul-15

M8J4S-QR-T1DWP3-220 Curing 7 07-Jul-15 14-Jul-15

U SHAPED TUNNEL PART ON U SHAPED TUNNEL PART ON DUKHAN TO ORBITAL HIGHWAY RAMP 63 14-May-15 29-Jul-15

FOUNDATIONFOUNDATION 29 14-May-15 16-Jun-15

PANEL 1PANEL 1 20 14-May-15 06-Jun-15

M8J4S-QR-U1FP1-100 Laying of Blinding 1 14-May-15 14-May-15

M8J4S-QR-U1FP1-110 Waterproofing 1 16-May-15 16-May-15

M8J4S-QR-U1FP1-120 Reinfocement Fixing 8 17-May-15 25-May-15

M8J4S-QR-U1FP1-130 Formworks 2 25-May-15 26-May-15

Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun2015 2016

PROJECT: DESIGN & CONSTRUCT NEW ORBITAL HIGHWAY & TRUCK ROUTE (P023) -CONTRACT 2: ORBITAL HIGHWAY SALWA ROAD TO NORTH RELIEF ROADINTERNAL TARGET PROGRAMME OF WORKS

GREEN LINE TUNNEL PROGRAMME

Remaining Level of EffortActual Level of Effort

Actual WorkRemaining Work

Critical Remaining ...Milestone

Page 2 of 19 TASK filter: Q-RAIL GREEN LINE.© Oracle Corporation

Activity ID Activity Name OriginalDuration

Start Finish

M8J4S-QR-U1FP1-140 Concreting 1 27-May-15 27-May-15

M8J4S-QR-U1FP1-150 Deshuttering 1 28-May-15 28-May-15

M8J4S-QR-U1FP1-160 Curing 7 30-May-15 06-Jun-15

PANEL 2PANEL 2 20 25-May-15 16-Jun-15

M8J4S-QR-U1FP2-100 Laying of Blinding 1 25-May-15 25-May-15

M8J4S-QR-U1FP2-110 Waterproofing 1 26-May-15 26-May-15

M8J4S-QR-U1FP2-120 Reinfocement Fixing 8 27-May-15 04-Jun-15

M8J4S-QR-U1FP2-130 Formworks 2 04-Jun-15 06-Jun-15

M8J4S-QR-U1FP2-140 Concreting 1 07-Jun-15 07-Jun-15

M8J4S-QR-U1FP2-150 Deshuttering 1 08-Jun-15 08-Jun-15

M8J4S-QR-U1FP2-160 Curing 7 09-Jun-15 16-Jun-15

WALL CASTINGWALL CASTING 31 09-Jun-15 14-Jul-15

PANEL 1PANEL 1 23 09-Jun-15 05-Jul-15

M8J4S-QR-U1EP1-100 Reinfocement Fixing for W1(East Wall) 4 09-Jun-15 13-Jun-15

M8J4S-QR-U1EP1-110 Formworks for W1(East Wall) 2 13-Jun-15 14-Jun-15

M8J4S-QR-U1EP1-120 Concreting for W1(East Wall) 1 15-Jun-15 15-Jun-15

M8J4S-QR-U1EP1-130 Deshuttering for W1(East Wall) 1 16-Jun-15 16-Jun-15

M8J4S-QR-U1EP1-140 Curing for W1(East Wall) 7 17-Jun-15 24-Jun-15

M8J4S-QR-U1EP1-150 Waterproofing for foudation and Wall for W1(East Wall) 5 25-Jun-15 30-Jun-15

M8J4S-QR-U1EP1-160 Reinfocement Fixing for W2 (West Wall) 4 14-Jun-15 17-Jun-15

M8J4S-QR-U1EP1-170 Formworks for W2 (West Wall) 2 17-Jun-15 18-Jun-15

M8J4S-QR-U1EP1-180 Concreting for W2 (West Wall) 1 20-Jun-15 20-Jun-15

M8J4S-QR-U1EP1-190 Deshuttering for W2 (West Wall) 1 21-Jun-15 21-Jun-15

M8J4S-QR-U1EP1-200 Curing for W2 (West Wall) 7 22-Jun-15 29-Jun-15

M8J4S-QR-U1EP1-210 Waterproofing for foudation and Wall for W2 (West Wall) 5 30-Jun-15 05-Jul-15

PANEL 2PANEL 2 23 18-Jun-15 14-Jul-15

M8J4S-QR-U1EP2-120 Reinfocement Fixing for W1(East Wall) 4 18-Jun-15 22-Jun-15

M8J4S-QR-U1EP2-130 Formworks for W1(East Wall) 2 22-Jun-15 23-Jun-15

M8J4S-QR-U1EP2-140 Concreting for W1(East Wall) 1 24-Jun-15 24-Jun-15

M8J4S-QR-U1EP2-150 Deshuttering for W1(East Wall) 1 25-Jun-15 25-Jun-15

M8J4S-QR-U1EP2-160 Curing for W1(East Wall) 7 27-Jun-15 04-Jul-15

M8J4S-QR-U1EP2-170 Waterproofing for foudation and Wall for W1(East Wall) 5 05-Jul-15 09-Jul-15

M8J4S-QR-U1EP2-180 Reinfocement Fixing for W2 (West Wall) 4 23-Jun-15 27-Jun-15

M8J4S-QR-U1EP2-190 Formworks for W2 (West Wall) 2 27-Jun-15 28-Jun-15

M8J4S-QR-U1EP2-200 Concreting for W2 (West Wall) 1 29-Jun-15 29-Jun-15

M8J4S-QR-U1EP2-210 Deshuttering for W2 (West Wall) 1 30-Jun-15 30-Jun-15

M8J4S-QR-U1EP2-220 Curing for W2 (West Wall) 7 01-Jul-15 08-Jul-15

M8J4S-QR-U1EP2-230 Waterproofing for foudation and Wall for W2 (West Wall) 5 09-Jul-15 14-Jul-15

BACKFILLING BEHIND WALLBACKFILLING BEHIND WALL 10 15-Jul-15 29-Jul-15

M8J4S-QR-U1EW-100 Bacfilling behind the Wall 1 5 15-Jul-15 23-Jul-15

M8J4S-QR-U1EW-110 Bacfilling behind the Wall 2 5 25-Jul-15 29-Jul-15

RECTANGLE SHAPE TUNNEL RECTANGLE SHAPE TUNNEL PART ON DUKHAN TO ORBITAL HIGHWAY RAMP 116 09-Jun-15 27-Oct-15

FOUNDATIONFOUNDATION 48 09-Jun-15 06-Aug-15

MAIN TUNNEL (PANEL 2 ANDMAIN TUNNEL (PANEL 2 AND 3 IS FOR UTILITY CORRIDOR) 48 09-Jun-15 06-Aug-15

PANEL 1PANEL 1 21 09-Jun-15 02-Jul-15

Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun2015 2016

PROJECT: DESIGN & CONSTRUCT NEW ORBITAL HIGHWAY & TRUCK ROUTE (P023) -CONTRACT 2: ORBITAL HIGHWAY SALWA ROAD TO NORTH RELIEF ROADINTERNAL TARGET PROGRAMME OF WORKS

GREEN LINE TUNNEL PROGRAMME

Remaining Level of EffortActual Level of Effort

Actual WorkRemaining Work

Critical Remaining ...Milestone

Page 3 of 19 TASK filter: Q-RAIL GREEN LINE.© Oracle Corporation

Activity ID Activity Name OriginalDuration

Start Finish

M8J4S-QR-T1FP1-100 Laying of Blinding 1 09-Jun-15 09-Jun-15

M8J4S-QR-T1FP1-110 Waterproofing 1 10-Jun-15 10-Jun-15

M8J4S-QR-T1FP1-120 Reinfocement Fixing 9 11-Jun-15 21-Jun-15

M8J4S-QR-T1FP1-130 Formworks 2 21-Jun-15 22-Jun-15

M8J4S-QR-T1FP1-140 Concreting 1 23-Jun-15 23-Jun-15

M8J4S-QR-T1FP1-150 Deshuttering 1 24-Jun-15 24-Jun-15

M8J4S-QR-T1FP1-160 Curing 7 25-Jun-15 02-Jul-15

PANEL 4PANEL 4 21 20-Jun-15 13-Jul-15

M8J4S-QR-T1FP4-100 Laying of Blinding 1 20-Jun-15 20-Jun-15

M8J4S-QR-T1FP4-110 Waterproofing 1 21-Jun-15 21-Jun-15

M8J4S-QR-T1FP4-120 Reinfocement Fixing 9 22-Jun-15 01-Jul-15

M8J4S-QR-T1FP4-130 Formworks 2 01-Jul-15 02-Jul-15

M8J4S-QR-T1FP4-140 Concreting 1 04-Jul-15 04-Jul-15

M8J4S-QR-T1FP4-150 Deshuttering 1 05-Jul-15 05-Jul-15

M8J4S-QR-T1FP4-160 Curing 7 06-Jul-15 13-Jul-15

PANEL 5PANEL 5 21 30-Jun-15 27-Jul-15

M8J4S-QR-T1FP5-100 Laying of Blinding 1 30-Jun-15 30-Jun-15

M8J4S-QR-T1FP5-110 Waterproofing 1 01-Jul-15 01-Jul-15

M8J4S-QR-T1FP5-120 Reinfocement Fixing 9 02-Jul-15 12-Jul-15

M8J4S-QR-T1FP5-130 Formworks 2 12-Jul-15 13-Jul-15

M8J4S-QR-T1FP5-140 Concreting 1 14-Jul-15 14-Jul-15

M8J4S-QR-T1FP5-150 Deshuttering 1 15-Jul-15 15-Jul-15

M8J4S-QR-T1FP5-160 Curing 7 16-Jul-15 27-Jul-15

PANEL 6PANEL 6 21 11-Jul-15 06-Aug-15

M8J4S-QR-T1FP6-100 Laying of Blinding 1 11-Jul-15 11-Jul-15

M8J4S-QR-T1FP6-110 Waterproofing 1 12-Jul-15 12-Jul-15

M8J4S-QR-T1FP6-120 Reinfocement Fixing 9 13-Jul-15 26-Jul-15

M8J4S-QR-T1FP6-130 Formworks 2 26-Jul-15 27-Jul-15

M8J4S-QR-T1FP6-140 Concreting 1 28-Jul-15 28-Jul-15

M8J4S-QR-T1FP6-150 Deshuttering 1 29-Jul-15 29-Jul-15

M8J4S-QR-T1FP6-160 Curing 7 30-Jul-15 06-Aug-15

WALLWALL 81 25-Jun-15 03-Oct-15

PANEL 1PANEL 1 27 25-Jun-15 29-Jul-15

M8J4S-QR-T1EP1-100 Reinfocement Fixing for W1(East Wall) 6 25-Jun-15 01-Jul-15

M8J4S-QR-T1EP1-110 Formworks for W1(East Wall) 5 28-Jun-15 02-Jul-15

M8J4S-QR-T1EP1-120 Concreting for W1(East Wall) 1 04-Jul-15 04-Jul-15

M8J4S-QR-T1EP1-130 Deshuttering for W1(East Wall) 1 05-Jul-15 05-Jul-15

M8J4S-QR-T1EP1-140 Curing for W1(East Wall) 7 06-Jul-15 13-Jul-15

M8J4S-QR-T1EP1-150 Waterproofing for foudation and Wall for W1(East Wall) 5 14-Jul-15 22-Jul-15

M8J4S-QR-T1EP1-160 Reinfocement Fixing for W2 (West Wall) 6 02-Jul-15 08-Jul-15

M8J4S-QR-T1EP1-170 Formworks for W2 (West Wall) 5 05-Jul-15 09-Jul-15

M8J4S-QR-T1EP1-180 Concreting for W2 (West Wall) 1 11-Jul-15 11-Jul-15

M8J4S-QR-T1EP1-190 Deshuttering for W2 (West Wall) 1 12-Jul-15 12-Jul-15

M8J4S-QR-T1EP1-200 Curing for W2 (West Wall) 7 13-Jul-15 23-Jul-15

M8J4S-QR-T1EP1-210 Waterproofing for foudation and Wall for W2 (West Wall) 5 25-Jul-15 29-Jul-15

Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun2015 2016

PROJECT: DESIGN & CONSTRUCT NEW ORBITAL HIGHWAY & TRUCK ROUTE (P023) -CONTRACT 2: ORBITAL HIGHWAY SALWA ROAD TO NORTH RELIEF ROADINTERNAL TARGET PROGRAMME OF WORKS

GREEN LINE TUNNEL PROGRAMME

Remaining Level of EffortActual Level of Effort

Actual WorkRemaining Work

Critical Remaining ...Milestone

Page 4 of 19 TASK filter: Q-RAIL GREEN LINE.© Oracle Corporation

Activity ID Activity Name OriginalDuration

Start Finish

PANEL 2PANEL 2 27 09-Jul-15 12-Aug-15

M8J4S-QR-T1EP2-100 Reinfocement Fixing for W1(East Wall) 6 09-Jul-15 15-Jul-15

M8J4S-QR-T1EP2-110 Formworks for W1(East Wall) 5 12-Jul-15 16-Jul-15

M8J4S-QR-T1EP2-120 Concreting for W1(East Wall) 1 21-Jul-15 21-Jul-15

M8J4S-QR-T1EP2-130 Deshuttering for W1(East Wall) 1 22-Jul-15 22-Jul-15

M8J4S-QR-T1EP2-140 Curing for W1(East Wall) 7 23-Jul-15 30-Jul-15

M8J4S-QR-T1EP2-150 Waterproofing for foudation and Wall for W1(East Wall) 5 01-Aug-15 05-Aug-15

M8J4S-QR-T1EP2-160 Reinfocement Fixing for W2 (West Wall) 6 16-Jul-15 26-Jul-15

M8J4S-QR-T1EP2-170 Formworks for W2 (West Wall) 5 22-Jul-15 27-Jul-15

M8J4S-QR-T1EP2-180 Concreting for W2 (West Wall) 1 28-Jul-15 28-Jul-15

M8J4S-QR-T1EP2-190 Deshuttering for W2 (West Wall) 1 29-Jul-15 29-Jul-15

M8J4S-QR-T1EP2-200 Curing for W2 (West Wall) 7 30-Jul-15 06-Aug-15

M8J4S-QR-T1EP2-210 Waterproofing for foudation and Wall for W2 (West Wall) 5 08-Aug-15 12-Aug-15

PANEL 3PANEL 3 27 27-Jul-15 26-Aug-15

M8J4S-QR-T1EP3-100 Reinfocement Fixing for W1(East Wall) 6 27-Jul-15 02-Aug-15

M8J4S-QR-T1EP3-110 Formworks for W1(East Wall) 5 29-Jul-15 03-Aug-15

M8J4S-QR-T1EP3-120 Concreting for W1(East Wall) 1 04-Aug-15 04-Aug-15

M8J4S-QR-T1EP3-130 Deshuttering for W1(East Wall) 1 05-Aug-15 05-Aug-15

M8J4S-QR-T1EP3-140 Curing for W1(East Wall) 7 06-Aug-15 13-Aug-15

M8J4S-QR-T1EP3-150 Waterproofing for foudation and Wall for W1(East Wall) 5 15-Aug-15 19-Aug-15

M8J4S-QR-T1EP3-160 Reinfocement Fixing for W2 (West Wall) 6 03-Aug-15 09-Aug-15

M8J4S-QR-T1EP3-170 Formworks for W2 (West Wall) 5 05-Aug-15 10-Aug-15

M8J4S-QR-T1EP3-180 Concreting for W2 (West Wall) 1 11-Aug-15 11-Aug-15

M8J4S-QR-T1EP3-190 Deshuttering for W2 (West Wall) 1 12-Aug-15 12-Aug-15

M8J4S-QR-T1EP3-200 Curing for W2 (West Wall) 7 13-Aug-15 20-Aug-15

M8J4S-QR-T1EP3-210 Waterproofing for foudation and Wall for W2 (West Wall) 5 22-Aug-15 26-Aug-15

PANEL 4PANEL 4 27 03-Aug-15 02-Sep-15

M8J4S-QR-T1EP4-100 Reinfocement Fixing for W1(East Wall) 6 03-Aug-15 09-Aug-15

M8J4S-QR-T1EP4-110 Formworks for W1(East Wall) 5 05-Aug-15 10-Aug-15

M8J4S-QR-T1EP4-120 Concreting for W1(East Wall) 1 11-Aug-15 11-Aug-15

M8J4S-QR-T1EP4-130 Deshuttering for W1(East Wall) 1 12-Aug-15 12-Aug-15

M8J4S-QR-T1EP4-140 Curing for W1(East Wall) 7 13-Aug-15 20-Aug-15

M8J4S-QR-T1EP4-150 Waterproofing for foudation and Wall for W1(East Wall) 5 22-Aug-15 26-Aug-15

M8J4S-QR-T1EP4-160 Reinfocement Fixing for W2 (West Wall) 6 10-Aug-15 16-Aug-15

M8J4S-QR-T1EP4-170 Formworks for W2 (West Wall) 5 12-Aug-15 17-Aug-15

M8J4S-QR-T1EP4-180 Concreting for W2 (West Wall) 1 18-Aug-15 18-Aug-15

M8J4S-QR-T1EP4-190 Deshuttering for W2 (West Wall) 1 19-Aug-15 19-Aug-15

M8J4S-QR-T1EP4-200 Curing for W2 (West Wall) 7 20-Aug-15 27-Aug-15

M8J4S-QR-T1EP4-210 Waterproofing for foudation and Wall for W2 (West Wall) 5 29-Aug-15 02-Sep-15

PANEL 5PANEL 5 27 17-Aug-15 16-Sep-15

M8J4S-QR-T1EP5-100 Reinfocement Fixing for W1(East Wall) 6 17-Aug-15 23-Aug-15

M8J4S-QR-T1EP5-110 Formworks for W1(East Wall) 5 19-Aug-15 24-Aug-15

M8J4S-QR-T1EP5-120 Concreting for W1(East Wall) 1 25-Aug-15 25-Aug-15

M8J4S-QR-T1EP5-130 Deshuttering for W1(East Wall) 1 26-Aug-15 26-Aug-15

M8J4S-QR-T1EP5-140 Curing for W1(East Wall) 7 27-Aug-15 03-Sep-15

Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun2015 2016

PROJECT: DESIGN & CONSTRUCT NEW ORBITAL HIGHWAY & TRUCK ROUTE (P023) -CONTRACT 2: ORBITAL HIGHWAY SALWA ROAD TO NORTH RELIEF ROADINTERNAL TARGET PROGRAMME OF WORKS

GREEN LINE TUNNEL PROGRAMME

Remaining Level of EffortActual Level of Effort

Actual WorkRemaining Work

Critical Remaining ...Milestone

Page 5 of 19 TASK filter: Q-RAIL GREEN LINE.© Oracle Corporation

Activity ID Activity Name OriginalDuration

Start Finish

M8J4S-QR-T1EP5-150 Waterproofing for foudation and Wall for W1(East Wall) 5 05-Sep-15 09-Sep-15

M8J4S-QR-T1EP5-160 Reinfocement Fixing for W2 (West Wall) 6 24-Aug-15 30-Aug-15

M8J4S-QR-T1EP5-170 Formworks for W2 (West Wall) 5 26-Aug-15 31-Aug-15

M8J4S-QR-T1EP5-180 Concreting for W2 (West Wall) 1 01-Sep-15 01-Sep-15

M8J4S-QR-T1EP5-190 Deshuttering for W2 (West Wall) 1 02-Sep-15 02-Sep-15

M8J4S-QR-T1EP5-200 Curing for W2 (West Wall) 7 03-Sep-15 10-Sep-15

M8J4S-QR-T1EP5-210 Waterproofing for foudation and Wall for W2 (West Wall) 5 12-Sep-15 16-Sep-15

PANEL 6PANEL 6 27 31-Aug-15 03-Oct-15

M8J4S-QR-T1EP6-100 Reinfocement Fixing for W1(East Wall) 6 31-Aug-15 06-Sep-15

M8J4S-QR-T1EP6-110 Formworks for W1(East Wall) 5 02-Sep-15 07-Sep-15

M8J4S-QR-T1EP6-120 Concreting for W1(East Wall) 1 08-Sep-15 08-Sep-15

M8J4S-QR-T1EP6-130 Deshuttering for W1(East Wall) 1 09-Sep-15 09-Sep-15

M8J4S-QR-T1EP6-140 Curing for W1(East Wall) 7 10-Sep-15 17-Sep-15

M8J4S-QR-T1EP6-150 Waterproofing for foudation and Wall for W1(East Wall) 5 19-Sep-15 26-Sep-15

M8J4S-QR-T1EP6-160 Reinfocement Fixing for W2 (West Wall) 6 07-Sep-15 13-Sep-15

M8J4S-QR-T1EP6-170 Formworks for W2 (West Wall) 5 09-Sep-15 14-Sep-15

M8J4S-QR-T1EP6-180 Concreting for W2 (West Wall) 1 15-Sep-15 15-Sep-15

M8J4S-QR-T1EP6-190 Deshuttering for W2 (West Wall) 1 16-Sep-15 16-Sep-15

M8J4S-QR-T1EP6-200 Curing for W2 (West Wall) 7 17-Sep-15 27-Sep-15

M8J4S-QR-T1EP6-210 Waterproofing for foudation and Wall for W2 (West Wall) 5 28-Sep-15 03-Oct-15

TOP SLABTOP SLAB 80 25-Jul-15 27-Oct-15

PANEL 1PANEL 1 20 25-Jul-15 16-Aug-15

M8J4S-QR-T1DWP1-100 Erection of Scaffolding for Deck Slab 3 25-Jul-15 27-Jul-15

M8J4S-QR-T1DWP1-110 Formworks for Deck Slab 3 28-Jul-15 30-Jul-15

M8J4S-QR-T1DWP1-120 Steel FIxing 6 28-Jul-15 03-Aug-15

M8J4S-QR-T1DWP1-130 Concreting 1 04-Aug-15 04-Aug-15

M8J4S-QR-T1DWP1-140 Removal of Scaffolding and Deshuttering 1 08-Aug-15 08-Aug-15

M8J4S-QR-T1DWP1-150 Curing 7 05-Aug-15 12-Aug-15

M8J4S-QR-T1DWP1-160 Waterprofing 3 13-Aug-15 16-Aug-15

PANEL 2PANEL 2 18 09-Aug-15 29-Aug-15

M8J4S-QR-T1DWP2-100 Erection of Scaffolding for Deck Slab 1 09-Aug-15 09-Aug-15

M8J4S-QR-T1DWP2-110 Formworks for Deck Slab 3 10-Aug-15 12-Aug-15

M8J4S-QR-T1DWP2-120 Steel FIxing 6 10-Aug-15 16-Aug-15

M8J4S-QR-T1DWP2-130 Concreting 1 17-Aug-15 17-Aug-15

M8J4S-QR-T1DWP2-140 Removal of Scaffolding and Deshuttering 1 20-Aug-15 20-Aug-15

M8J4S-QR-T1DWP2-150 Curing 7 18-Aug-15 25-Aug-15

M8J4S-QR-T1DWP2-160 Waterprofing 3 26-Aug-15 29-Aug-15

PANEL 3PANEL 3 18 22-Aug-15 10-Sep-15

M8J4S-QR-T1DWP3-100 Erection of Scaffolding for Deck Slab 1 22-Aug-15 22-Aug-15

M8J4S-QR-T1DWP3-110 Formworks for Deck Slab 3 23-Aug-15 25-Aug-15

M8J4S-QR-T1DWP3-120 Steel FIxing 6 23-Aug-15 29-Aug-15

M8J4S-QR-T1DWP3-130 Concreting 1 30-Aug-15 30-Aug-15

M8J4S-QR-T1DWP3-140 Removal of Scaffolding and Deshuttering 1 02-Sep-15 02-Sep-15

M8J4S-QR-T1DWP3-150 Curing 7 31-Aug-15 07-Sep-15

M8J4S-QR-T1DWP3-160 Waterprofing 3 08-Sep-15 10-Sep-15

Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun2015 2016

PROJECT: DESIGN & CONSTRUCT NEW ORBITAL HIGHWAY & TRUCK ROUTE (P023) -CONTRACT 2: ORBITAL HIGHWAY SALWA ROAD TO NORTH RELIEF ROADINTERNAL TARGET PROGRAMME OF WORKS

GREEN LINE TUNNEL PROGRAMME

Remaining Level of EffortActual Level of Effort

Actual WorkRemaining Work

Critical Remaining ...Milestone

Page 6 of 19 TASK filter: Q-RAIL GREEN LINE.© Oracle Corporation

Activity ID Activity Name OriginalDuration

Start Finish

PANEL 4PANEL 4 18 03-Sep-15 26-Sep-15

M8J4S-QR-T1DWP4-100 Erection of Scaffolding for Deck Slab 1 03-Sep-15 03-Sep-15

M8J4S-QR-T1DWP4-110 Formworks for Deck Slab 3 05-Sep-15 07-Sep-15

M8J4S-QR-T1DWP4-120 Steel FIxing 6 05-Sep-15 10-Sep-15

M8J4S-QR-T1DWP4-130 Concreting 1 12-Sep-15 12-Sep-15

M8J4S-QR-T1DWP4-140 Removal of Scaffolding and Deshuttering 1 15-Sep-15 15-Sep-15

M8J4S-QR-T1DWP4-150 Curing 7 13-Sep-15 20-Sep-15

M8J4S-QR-T1DWP4-160 Waterprofing 3 21-Sep-15 26-Sep-15

PANEL 5PANEL 5 18 16-Sep-15 08-Oct-15

M8J4S-QR-T1DWP5-100 Erection of Scaffolding for Deck Slab 1 16-Sep-15 16-Sep-15

M8J4S-QR-T1DWP5-110 Formworks for Deck Slab 3 17-Sep-15 20-Sep-15

M8J4S-QR-T1DWP5-120 Steel FIxing 6 17-Sep-15 26-Sep-15

M8J4S-QR-T1DWP5-130 Concreting 1 27-Sep-15 27-Sep-15

M8J4S-QR-T1DWP5-140 Removal of Scaffolding and Deshuttering 1 30-Sep-15 30-Sep-15

M8J4S-QR-T1DWP5-150 Curing 7 28-Sep-15 05-Oct-15

M8J4S-QR-T1DWP5-160 Waterprofing 3 06-Oct-15 08-Oct-15

PANEL 6PANEL 6 23 01-Oct-15 27-Oct-15

M8J4S-QR-T1DWP6-100 Erection of Scaffolding for Deck Slab 1 01-Oct-15 01-Oct-15

M8J4S-QR-T1DWP6-110 Formworks for Deck Slab 3 03-Oct-15 05-Oct-15

M8J4S-QR-T1DWP6-120 Steel FIxing 6 08-Oct-15 14-Oct-15

M8J4S-QR-T1DWP6-130 Concreting 1 15-Oct-15 15-Oct-15

M8J4S-QR-T1DWP6-140 Removal of Scaffolding and Deshuttering 1 19-Oct-15 19-Oct-15

M8J4S-QR-T1DWP6-150 Curing 7 17-Oct-15 24-Oct-15

M8J4S-QR-T1DWP6-160 Waterprofing 3 25-Oct-15 27-Oct-15

RECTANGLE SHAPE TUNNEL RECTANGLE SHAPE TUNNEL PART ON ORBITAL TO DUKHAN HIGHWAY RAMP 200 25-Apr-15 19-Dec-15

SITE CLEARANCE & EXCAVATSITE CLEARANCE & EXCAVATION 42 25-Apr-15 11-Jun-15

M8J4S-QRT2SC-100 Site Clearance 5 25-Apr-15 29-Apr-15

M8J4S-QRT2SC-110 General Excavation 28 25-Apr-15 26-May-15

M8J4S-QRT2SC-120 Excvation for Foundation and Formation Preparation for Main Tunnel 14 27-May-15 11-Jun-15

FOUNDATIONFOUNDATION 56 05-Aug-15 11-Oct-15

PANEL 1PANEL 1 29 05-Aug-15 07-Sep-15

M8J4S-QR-T2FP1-100 Laying of Blinding 1 05-Aug-15 05-Aug-15

M8J4S-QR-T2FP1-110 Waterproofing 1 06-Aug-15 06-Aug-15

M8J4S-QR-T2FP1-120 Reinfocement Fixing 9 17-Aug-15 26-Aug-15

M8J4S-QR-T2FP1-130 Formworks 2 26-Aug-15 27-Aug-15

M8J4S-QR-T2FP1-140 Concreting 1 29-Aug-15 29-Aug-15

M8J4S-QR-T2FP1-150 Deshuttering 1 30-Aug-15 30-Aug-15

M8J4S-QR-T2FP1-160 Curing 7 31-Aug-15 07-Sep-15

PANEL 2PANEL 2 29 16-Aug-15 17-Sep-15

M8J4S-QR-T2FP2-100 Laying of Blinding 1 16-Aug-15 16-Aug-15

M8J4S-QR-T2FP2-110 Waterproofing 1 17-Aug-15 17-Aug-15

M8J4S-QR-T2FP2-120 Reinfocement Fixing 9 27-Aug-15 06-Sep-15

M8J4S-QR-T2FP2-130 Formworks 2 06-Sep-15 07-Sep-15

M8J4S-QR-T2FP2-140 Concreting 1 08-Sep-15 08-Sep-15

M8J4S-QR-T2FP2-150 Deshuttering 1 09-Sep-15 09-Sep-15

Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun2015 2016

PROJECT: DESIGN & CONSTRUCT NEW ORBITAL HIGHWAY & TRUCK ROUTE (P023) -CONTRACT 2: ORBITAL HIGHWAY SALWA ROAD TO NORTH RELIEF ROADINTERNAL TARGET PROGRAMME OF WORKS

GREEN LINE TUNNEL PROGRAMME

Remaining Level of EffortActual Level of Effort

Actual WorkRemaining Work

Critical Remaining ...Milestone

Page 7 of 19 TASK filter: Q-RAIL GREEN LINE.© Oracle Corporation

Activity ID Activity Name OriginalDuration

Start Finish

M8J4S-QR-T2FP2-160 Curing 7 10-Sep-15 17-Sep-15

PANEL 3PANEL 3 29 26-Aug-15 30-Sep-15

M8J4S-QR-T2FP3-100 Laying of Blinding 1 26-Aug-15 26-Aug-15

M8J4S-QR-T2FP3-110 Waterproofing 1 27-Aug-15 27-Aug-15

M8J4S-QR-T2FP3-120 Reinfocement Fixing 9 07-Sep-15 16-Sep-15

M8J4S-QR-T2FP3-130 Formworks 2 16-Sep-15 17-Sep-15

M8J4S-QR-T2FP3-140 Concreting 1 19-Sep-15 19-Sep-15

M8J4S-QR-T2FP3-150 Deshuttering 1 20-Sep-15 20-Sep-15

M8J4S-QR-T2FP3-160 Curing 7 21-Sep-15 30-Sep-15

PANEL 4PANEL 4 29 06-Sep-15 11-Oct-15

M8J4S-QR-T2FP4-100 Laying of Blinding 1 06-Sep-15 06-Sep-15

M8J4S-QR-T2FP4-110 Waterproofing 1 07-Sep-15 07-Sep-15

M8J4S-QR-T2FP4-120 Reinfocement Fixing 9 17-Sep-15 29-Sep-15

M8J4S-QR-T2FP4-130 Formworks 2 29-Sep-15 30-Sep-15

M8J4S-QR-T2FP4-140 Concreting 1 01-Oct-15 01-Oct-15

M8J4S-QR-T2FP4-150 Deshuttering 1 03-Oct-15 03-Oct-15

M8J4S-QR-T2FP4-160 Curing 7 04-Oct-15 11-Oct-15

WALLWALL 57 14-Sep-15 21-Nov-15

PANEL 1PANEL 1 27 14-Sep-15 17-Oct-15

M8J4S-QR-T2EP1-100 Reinfocement Fixing for W1(East Wall) 6 14-Sep-15 20-Sep-15

M8J4S-QR-T2EP1-110 Formworks for W1(East Wall) 5 17-Sep-15 22-Sep-15

M8J4S-QR-T2EP1-120 Concreting for W1(East Wall) 1 26-Sep-15 26-Sep-15

M8J4S-QR-T2EP1-130 Deshuttering for W1(East Wall) 1 27-Sep-15 27-Sep-15

M8J4S-QR-T2EP1-140 Curing for W1(East Wall) 7 28-Sep-15 05-Oct-15

M8J4S-QR-T2EP1-150 Waterproofing for foudation and Wall for W1(East Wall) 5 06-Oct-15 11-Oct-15

M8J4S-QR-T2EP1-160 Reinfocement Fixing for W2 (West Wall) 6 21-Sep-15 29-Sep-15

M8J4S-QR-T2EP1-170 Formworks for W2 (West Wall) 5 26-Sep-15 30-Sep-15

M8J4S-QR-T2EP1-180 Concreting for W2 (West Wall) 1 01-Oct-15 01-Oct-15

M8J4S-QR-T2EP1-190 Deshuttering for W2 (West Wall) 1 03-Oct-15 03-Oct-15

M8J4S-QR-T2EP1-200 Curing for W2 (West Wall) 7 04-Oct-15 11-Oct-15

M8J4S-QR-T2EP1-210 Waterproofing for foudation and Wall for W2 (West Wall) 5 12-Oct-15 17-Oct-15

PANEL 2PANEL 2 27 30-Sep-15 31-Oct-15

M8J4S-QR-T2EP2-100 Reinfocement Fixing for W1(East Wall) 6 30-Sep-15 06-Oct-15

M8J4S-QR-T2EP2-110 Formworks for W1(East Wall) 5 03-Oct-15 07-Oct-15

M8J4S-QR-T2EP2-120 Concreting for W1(East Wall) 1 08-Oct-15 08-Oct-15

M8J4S-QR-T2EP2-130 Deshuttering for W1(East Wall) 1 10-Oct-15 10-Oct-15

M8J4S-QR-T2EP2-140 Curing for W1(East Wall) 7 11-Oct-15 18-Oct-15

M8J4S-QR-T2EP2-150 Waterproofing for foudation and Wall for W1(East Wall) 5 19-Oct-15 24-Oct-15

M8J4S-QR-T2EP2-160 Reinfocement Fixing for W2 (West Wall) 6 07-Oct-15 13-Oct-15

M8J4S-QR-T2EP2-170 Formworks for W2 (West Wall) 5 10-Oct-15 14-Oct-15

M8J4S-QR-T2EP2-180 Concreting for W2 (West Wall) 1 15-Oct-15 15-Oct-15

M8J4S-QR-T2EP2-190 Deshuttering for W2 (West Wall) 1 17-Oct-15 17-Oct-15

M8J4S-QR-T2EP2-200 Curing for W2 (West Wall) 7 18-Oct-15 25-Oct-15

M8J4S-QR-T2EP2-210 Waterproofing for foudation and Wall for W2 (West Wall) 5 26-Oct-15 31-Oct-15

PANEL 3PANEL 3 27 14-Oct-15 14-Nov-15

Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun2015 2016

PROJECT: DESIGN & CONSTRUCT NEW ORBITAL HIGHWAY & TRUCK ROUTE (P023) -CONTRACT 2: ORBITAL HIGHWAY SALWA ROAD TO NORTH RELIEF ROADINTERNAL TARGET PROGRAMME OF WORKS

GREEN LINE TUNNEL PROGRAMME

Remaining Level of EffortActual Level of Effort

Actual WorkRemaining Work

Critical Remaining ...Milestone

Page 8 of 19 TASK filter: Q-RAIL GREEN LINE.© Oracle Corporation

Activity ID Activity Name OriginalDuration

Start Finish

M8J4S-QR-T2EP3-100 Reinfocement Fixing for W1(East Wall) 6 14-Oct-15 20-Oct-15

M8J4S-QR-T2EP3-110 Formworks for W1(East Wall) 5 17-Oct-15 21-Oct-15

M8J4S-QR-T2EP3-120 Concreting for W1(East Wall) 1 22-Oct-15 22-Oct-15

M8J4S-QR-T2EP3-130 Deshuttering for W1(East Wall) 1 24-Oct-15 24-Oct-15

M8J4S-QR-T2EP3-140 Curing for W1(East Wall) 7 25-Oct-15 01-Nov-15

M8J4S-QR-T2EP3-150 Waterproofing for foudation and Wall for W1(East Wall) 5 02-Nov-15 07-Nov-15

M8J4S-QR-T2EP3-160 Reinfocement Fixing for W2 (West Wall) 6 21-Oct-15 27-Oct-15

M8J4S-QR-T2EP3-170 Formworks for W2 (West Wall) 5 24-Oct-15 28-Oct-15

M8J4S-QR-T2EP3-180 Concreting for W2 (West Wall) 1 29-Oct-15 29-Oct-15

M8J4S-QR-T2EP3-190 Deshuttering for W2 (West Wall) 1 31-Oct-15 31-Oct-15

M8J4S-QR-T2EP3-200 Curing for W2 (West Wall) 7 01-Nov-15 08-Nov-15

M8J4S-QR-T2EP3-210 Waterproofing for foudation and Wall for W2 (West Wall) 5 09-Nov-15 14-Nov-15

PANEL 4PANEL 4 27 21-Oct-15 21-Nov-15

M8J4S-QR-T2EP4-100 Reinfocement Fixing for W1(East Wall) 6 21-Oct-15 27-Oct-15

M8J4S-QR-T2EP4-110 Formworks for W1(East Wall) 5 24-Oct-15 28-Oct-15

M8J4S-QR-T2EP4-120 Concreting for W1(East Wall) 1 29-Oct-15 29-Oct-15

M8J4S-QR-T2EP4-130 Deshuttering for W1(East Wall) 1 31-Oct-15 31-Oct-15

M8J4S-QR-T2EP4-140 Curing for W1(East Wall) 7 01-Nov-15 08-Nov-15

M8J4S-QR-T2EP4-150 Waterproofing for foudation and Wall for W1(East Wall) 5 09-Nov-15 14-Nov-15

M8J4S-QR-T2EP4-160 Reinfocement Fixing for W2 (West Wall) 6 28-Oct-15 03-Nov-15

M8J4S-QR-T2EP4-170 Formworks for W2 (West Wall) 5 31-Oct-15 04-Nov-15

M8J4S-QR-T2EP4-180 Concreting for W2 (West Wall) 1 05-Nov-15 05-Nov-15

M8J4S-QR-T2EP4-190 Deshuttering for W2 (West Wall) 1 07-Nov-15 07-Nov-15

M8J4S-QR-T2EP4-200 Curing for W2 (West Wall) 7 08-Nov-15 15-Nov-15

M8J4S-QR-T2EP4-210 Waterproofing for foudation and Wall for W2 (West Wall) 5 16-Nov-15 21-Nov-15

TOP SLABTOP SLAB 52 20-Oct-15 19-Dec-15

PANEL 1PANEL 1 19 20-Oct-15 10-Nov-15

M8J4S-QR-T2DWP1-100 Erection of Scaffolding for Deck Slab 2 20-Oct-15 21-Oct-15

M8J4S-QR-T2DWP1-110 Formworks for Deck Slab 3 22-Oct-15 25-Oct-15

M8J4S-QR-T2DWP1-120 Steel FIxing 6 22-Oct-15 28-Oct-15

M8J4S-QR-T2DWP1-130 Concreting 1 29-Oct-15 29-Oct-15

M8J4S-QR-T2DWP1-140 Removal of Scaffolding and Deshuttering 1 02-Nov-15 02-Nov-15

M8J4S-QR-T2DWP1-150 Curing 7 31-Oct-15 07-Nov-15

M8J4S-QR-T2DWP1-160 Waterprofing 3 08-Nov-15 10-Nov-15

PANEL 2PANEL 2 18 03-Nov-15 23-Nov-15

M8J4S-QR-T2DWP2-100 Erection of Scaffolding for Deck Slab 1 03-Nov-15 03-Nov-15

M8J4S-QR-T2DWP2-110 Formworks for Deck Slab 3 04-Nov-15 07-Nov-15

M8J4S-QR-T2DWP2-120 Steel FIxing 6 04-Nov-15 10-Nov-15

M8J4S-QR-T2DWP2-130 Concreting 1 11-Nov-15 11-Nov-15

M8J4S-QR-T2DWP2-140 Removal of Scaffolding and Deshuttering 1 15-Nov-15 15-Nov-15

M8J4S-QR-T2DWP2-150 Curing 7 12-Nov-15 19-Nov-15

M8J4S-QR-T2DWP2-160 Waterprofing 3 21-Nov-15 23-Nov-15

PANEL 3PANEL 3 18 16-Nov-15 06-Dec-15

M8J4S-QR-T2DWP3-100 Erection of Scaffolding for Deck Slab 1 16-Nov-15 16-Nov-15

M8J4S-QR-T2DWP3-110 Formworks for Deck Slab 3 17-Nov-15 19-Nov-15

Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun2015 2016

PROJECT: DESIGN & CONSTRUCT NEW ORBITAL HIGHWAY & TRUCK ROUTE (P023) -CONTRACT 2: ORBITAL HIGHWAY SALWA ROAD TO NORTH RELIEF ROADINTERNAL TARGET PROGRAMME OF WORKS

GREEN LINE TUNNEL PROGRAMME

Remaining Level of EffortActual Level of Effort

Actual WorkRemaining Work

Critical Remaining ...Milestone

Page 9 of 19 TASK filter: Q-RAIL GREEN LINE.© Oracle Corporation

Activity ID Activity Name OriginalDuration

Start Finish

M8J4S-QR-T2DWP3-120 Steel FIxing 6 17-Nov-15 23-Nov-15

M8J4S-QR-T2DWP3-130 Concreting 1 24-Nov-15 24-Nov-15

M8J4S-QR-T2DWP3-140 Removal of Scaffolding and Deshuttering 1 28-Nov-15 28-Nov-15

M8J4S-QR-T2DWP3-150 Curing 7 25-Nov-15 02-Dec-15

M8J4S-QR-T2DWP3-160 Waterprofing 3 03-Dec-15 06-Dec-15

PANEL 4PANEL 4 18 29-Nov-15 19-Dec-15

M8J4S-QR-T2DWP4-100 Erection of Scaffolding for Deck Slab 1 29-Nov-15 29-Nov-15

M8J4S-QR-T2DWP4-110 Formworks for Deck Slab 3 30-Nov-15 02-Dec-15

M8J4S-QR-T2DWP4-120 Steel FIxing 6 30-Nov-15 06-Dec-15

M8J4S-QR-T2DWP4-130 Concreting 1 07-Dec-15 07-Dec-15

M8J4S-QR-T2DWP4-140 Removal of Scaffolding and Deshuttering 1 10-Dec-15 10-Dec-15

M8J4S-QR-T2DWP4-150 Curing 7 08-Dec-15 15-Dec-15

M8J4S-QR-T2DWP4-160 Waterprofing 3 16-Dec-15 19-Dec-15

PHASE 2PHASE 2 310 30-Apr-15 02-May-16

RECTANGLE SHAPE TUNNEL RECTANGLE SHAPE TUNNEL PART ON ORBITAL TO DUKHAN HIGHWAY RAMP 310 30-Apr-15 02-May-16

SITE CLEARANCESITE CLEARANCE 61 30-Apr-15 09-Jul-15

M8J4S-QRT2SC-130 Site Clearance 5 30-Apr-15 05-May-15

M8J4S-QRT2SC-140 General Excavation 28 06-May-15 07-Jun-15

M8J4S-QRT2SC-150 Excvation for Foundation and Formation Preparation for Main Tunnel 28 08-Jun-15 09-Jul-15

FOUNDATIONFOUNDATION 85 25-Jul-15 02-Nov-15

PANEL 5PANEL 5 21 25-Jul-15 17-Aug-15

M8J4S-QR-T2FP5-100 Laying of Blinding 1 25-Jul-15 25-Jul-15

M8J4S-QR-T2FP5-110 Waterproofing 1 26-Jul-15 26-Jul-15

M8J4S-QR-T2FP5-120 Reinfocement Fixing 9 27-Jul-15 05-Aug-15

M8J4S-QR-T2FP5-130 Formworks 2 05-Aug-15 06-Aug-15

M8J4S-QR-T2FP5-140 Concreting 1 08-Aug-15 08-Aug-15

M8J4S-QR-T2FP5-150 Deshuttering 1 09-Aug-15 09-Aug-15

M8J4S-QR-T2FP5-160 Curing 7 10-Aug-15 17-Aug-15

PANEL 6PANEL 6 21 04-Aug-15 27-Aug-15

M8J4S-QR-T2FP6-100 Laying of Blinding 1 04-Aug-15 04-Aug-15

M8J4S-QR-T2FP6-110 Waterproofing 1 05-Aug-15 05-Aug-15

M8J4S-QR-T2FP6-120 Reinfocement Fixing 9 06-Aug-15 16-Aug-15

M8J4S-QR-T2FP6-130 Formworks 2 16-Aug-15 17-Aug-15

M8J4S-QR-T2FP6-140 Concreting 1 18-Aug-15 18-Aug-15

M8J4S-QR-T2FP6-150 Deshuttering 1 19-Aug-15 19-Aug-15

M8J4S-QR-T2FP6-160 Curing 7 20-Aug-15 27-Aug-15

PANEL 7PANEL 7 21 05-Aug-15 29-Aug-15

M8J4S-QR-T2FP7-100 Laying of Blinding 1 05-Aug-15 05-Aug-15

M8J4S-QR-T2FP7-110 Waterproofing 1 06-Aug-15 06-Aug-15

M8J4S-QR-T2FP7-120 Reinfocement Fixing 9 08-Aug-15 17-Aug-15

M8J4S-QR-T2FP7-130 Formworks 2 17-Aug-15 18-Aug-15

M8J4S-QR-T2FP7-140 Concreting 1 19-Aug-15 19-Aug-15

M8J4S-QR-T2FP7-150 Deshuttering 1 20-Aug-15 20-Aug-15

M8J4S-QR-T2FP7-160 Curing 7 22-Aug-15 29-Aug-15

PANEL 8PANEL 8 21 16-Aug-15 08-Sep-15

Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun2015 2016

PROJECT: DESIGN & CONSTRUCT NEW ORBITAL HIGHWAY & TRUCK ROUTE (P023) -CONTRACT 2: ORBITAL HIGHWAY SALWA ROAD TO NORTH RELIEF ROADINTERNAL TARGET PROGRAMME OF WORKS

GREEN LINE TUNNEL PROGRAMME

Remaining Level of EffortActual Level of Effort

Actual WorkRemaining Work

Critical Remaining ...Milestone

Page 10 of 19 TASK filter: Q-RAIL GREEN LINE.© Oracle Corporation

Activity ID Activity Name OriginalDuration

Start Finish

M8J4S-QR-T2FP8-100 Laying of Blinding 1 16-Aug-15 16-Aug-15

M8J4S-QR-T2FP8-110 Waterproofing 1 17-Aug-15 17-Aug-15

M8J4S-QR-T2FP8-120 Reinfocement Fixing 9 18-Aug-15 27-Aug-15

M8J4S-QR-T2FP8-130 Formworks 2 27-Aug-15 29-Aug-15

M8J4S-QR-T2FP8-140 Concreting 1 30-Aug-15 30-Aug-15

M8J4S-QR-T2FP8-150 Deshuttering 1 31-Aug-15 31-Aug-15

M8J4S-QR-T2FP8-160 Curing 7 01-Sep-15 08-Sep-15

PANEL 9PANEL 9 21 26-Aug-15 19-Sep-15

M8J4S-QR-T2FP9-100 Laying of Blinding 1 26-Aug-15 26-Aug-15

M8J4S-QR-T2FP9-110 Waterproofing 1 27-Aug-15 27-Aug-15

M8J4S-QR-T2FP9-120 Reinfocement Fixing 9 29-Aug-15 07-Sep-15

M8J4S-QR-T2FP9-130 Formworks 2 07-Sep-15 08-Sep-15

M8J4S-QR-T2FP9-140 Concreting 1 09-Sep-15 09-Sep-15

M8J4S-QR-T2FP9-150 Deshuttering 1 10-Sep-15 10-Sep-15

M8J4S-QR-T2FP9-160 Curing 7 12-Sep-15 19-Sep-15

PANEL 10PANEL 10 21 06-Sep-15 01-Oct-15

M8J4S-QR-T2FP10-100 Laying of Blinding 1 06-Sep-15 06-Sep-15

M8J4S-QR-T2FP10-110 Waterproofing 1 07-Sep-15 07-Sep-15

M8J4S-QR-T2FP10-120 Reinfocement Fixing 9 08-Sep-15 17-Sep-15

M8J4S-QR-T2FP10-130 Formworks 2 17-Sep-15 19-Sep-15

M8J4S-QR-T2FP10-140 Concreting 1 20-Sep-15 20-Sep-15

M8J4S-QR-T2FP10-150 Deshuttering 1 21-Sep-15 21-Sep-15

M8J4S-QR-T2FP10-160 Curing 7 22-Sep-15 01-Oct-15

PANEL 11PANEL 11 21 16-Sep-15 12-Oct-15

M8J4S-QR-T2FP11-100 Laying of Blinding 1 16-Sep-15 16-Sep-15

M8J4S-QR-T2FP11-110 Waterproofing 1 17-Sep-15 17-Sep-15

M8J4S-QR-T2FP11-120 Reinfocement Fixing 9 19-Sep-15 30-Sep-15

M8J4S-QR-T2FP11-130 Formworks 2 30-Sep-15 01-Oct-15

M8J4S-QR-T2FP11-140 Concreting 1 03-Oct-15 03-Oct-15

M8J4S-QR-T2FP11-150 Deshuttering 1 04-Oct-15 04-Oct-15

M8J4S-QR-T2FP11-160 Curing 7 05-Oct-15 12-Oct-15

PANEL 12PANEL 12 21 29-Sep-15 22-Oct-15

M8J4S-QR-T2FP12-100 Laying of Blinding 1 29-Sep-15 29-Sep-15

M8J4S-QR-T2FP12-110 Waterproofing 1 30-Sep-15 30-Sep-15

M8J4S-QR-T2FP12-120 Reinfocement Fixing 9 01-Oct-15 11-Oct-15

M8J4S-QR-T2FP12-130 Formworks 2 11-Oct-15 12-Oct-15

M8J4S-QR-T2FP12-140 Concreting 1 13-Oct-15 13-Oct-15

M8J4S-QR-T2FP12-150 Deshuttering 1 14-Oct-15 14-Oct-15

M8J4S-QR-T2FP12-160 Curing 7 15-Oct-15 22-Oct-15

PANEL 13PANEL 13 21 10-Oct-15 02-Nov-15

M8J4S-QR-T2FP13-100 Laying of Blinding 1 10-Oct-15 10-Oct-15

M8J4S-QR-T2FP13-110 Waterproofing 1 11-Oct-15 11-Oct-15

M8J4S-QR-T2FP13-120 Reinfocement Fixing 9 12-Oct-15 21-Oct-15

M8J4S-QR-T2FP13-130 Formworks 2 21-Oct-15 22-Oct-15

M8J4S-QR-T2FP13-140 Concreting 1 24-Oct-15 24-Oct-15

Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun2015 2016

PROJECT: DESIGN & CONSTRUCT NEW ORBITAL HIGHWAY & TRUCK ROUTE (P023) -CONTRACT 2: ORBITAL HIGHWAY SALWA ROAD TO NORTH RELIEF ROADINTERNAL TARGET PROGRAMME OF WORKS

GREEN LINE TUNNEL PROGRAMME

Remaining Level of EffortActual Level of Effort

Actual WorkRemaining Work

Critical Remaining ...Milestone

Page 11 of 19 TASK filter: Q-RAIL GREEN LINE.© Oracle Corporation

Activity ID Activity Name OriginalDuration

Start Finish

M8J4S-QR-T2FP13-150 Deshuttering 1 25-Oct-15 25-Oct-15

M8J4S-QR-T2FP13-160 Curing 7 26-Oct-15 02-Nov-15

WALLWALL 117 04-Nov-15 20-Mar-16

PANEL 5PANEL 5 27 04-Nov-15 05-Dec-15

M8J4S-QR-T2EP5-100 Reinfocement Fixing for W1(East Wall) 6 04-Nov-15 10-Nov-15

M8J4S-QR-T2EP5-110 Formworks for W1(East Wall) 5 07-Nov-15 11-Nov-15

M8J4S-QR-T2EP5-120 Concreting for W1(East Wall) 1 12-Nov-15 12-Nov-15

M8J4S-QR-T2EP5-130 Deshuttering for W1(East Wall) 1 14-Nov-15 14-Nov-15

M8J4S-QR-T2EP5-140 Curing for W1(East Wall) 7 15-Nov-15 22-Nov-15

M8J4S-QR-T2EP5-150 Waterproofing for foudation and Wall for W1(East Wall) 5 23-Nov-15 28-Nov-15

M8J4S-QR-T2EP5-160 Reinfocement Fixing for W2 (West Wall) 6 11-Nov-15 17-Nov-15

M8J4S-QR-T2EP5-170 Formworks for W2 (West Wall) 5 14-Nov-15 18-Nov-15

M8J4S-QR-T2EP5-180 Concreting for W2 (West Wall) 1 19-Nov-15 19-Nov-15

M8J4S-QR-T2EP5-190 Deshuttering for W2 (West Wall) 1 21-Nov-15 21-Nov-15

M8J4S-QR-T2EP5-200 Curing for W2 (West Wall) 7 22-Nov-15 29-Nov-15

M8J4S-QR-T2EP5-210 Waterproofing for foudation and Wall for W2 (West Wall) 5 30-Nov-15 05-Dec-15

PANEL 6PANEL 6 27 18-Nov-15 19-Dec-15

M8J4S-QR-T2EP6-100 Reinfocement Fixing for W1(East Wall) 6 18-Nov-15 24-Nov-15

M8J4S-QR-T2EP6-110 Formworks for W1(East Wall) 5 21-Nov-15 25-Nov-15

M8J4S-QR-T2EP6-120 Concreting for W1(East Wall) 1 26-Nov-15 26-Nov-15

M8J4S-QR-T2EP6-130 Deshuttering for W1(East Wall) 1 28-Nov-15 28-Nov-15

M8J4S-QR-T2EP6-140 Curing for W1(East Wall) 7 29-Nov-15 06-Dec-15

M8J4S-QR-T2EP6-150 Waterproofing for foudation and Wall for W1(East Wall) 5 07-Dec-15 12-Dec-15

M8J4S-QR-T2EP6-160 Reinfocement Fixing for W2 (West Wall) 6 25-Nov-15 01-Dec-15

M8J4S-QR-T2EP6-170 Formworks for W2 (West Wall) 5 28-Nov-15 02-Dec-15

M8J4S-QR-T2EP6-180 Concreting for W2 (West Wall) 1 03-Dec-15 03-Dec-15

M8J4S-QR-T2EP6-190 Deshuttering for W2 (West Wall) 1 05-Dec-15 05-Dec-15

M8J4S-QR-T2EP6-200 Curing for W2 (West Wall) 7 06-Dec-15 13-Dec-15

M8J4S-QR-T2EP6-210 Waterproofing for foudation and Wall for W2 (West Wall) 5 14-Dec-15 19-Dec-15

PANEL 7PANEL 7 27 02-Dec-15 02-Jan-16

M8J4S-QR-T2EP7-100 Reinfocement Fixing for W1(East Wall) 6 02-Dec-15 08-Dec-15

M8J4S-QR-T2EP7-110 Formworks for W1(East Wall) 5 05-Dec-15 09-Dec-15

M8J4S-QR-T2EP7-120 Concreting for W1(East Wall) 1 10-Dec-15 10-Dec-15

M8J4S-QR-T2EP7-130 Deshuttering for W1(East Wall) 1 12-Dec-15 12-Dec-15

M8J4S-QR-T2EP7-140 Curing for W1(East Wall) 7 13-Dec-15 20-Dec-15

M8J4S-QR-T2EP7-150 Waterproofing for foudation and Wall for W1(East Wall) 5 21-Dec-15 26-Dec-15

M8J4S-QR-T2EP7-160 Reinfocement Fixing for W2 (West Wall) 6 09-Dec-15 15-Dec-15

M8J4S-QR-T2EP7-170 Formworks for W2 (West Wall) 5 12-Dec-15 16-Dec-15

M8J4S-QR-T2EP7-180 Concreting for W2 (West Wall) 1 17-Dec-15 17-Dec-15

M8J4S-QR-T2EP7-190 Deshuttering for W2 (West Wall) 1 19-Dec-15 19-Dec-15

M8J4S-QR-T2EP7-200 Curing for W2 (West Wall) 7 20-Dec-15 27-Dec-15

M8J4S-QR-T2EP7-210 Waterproofing for foudation and Wall for W2 (West Wall) 5 28-Dec-15 02-Jan-16

PANEL 8PANEL 8 27 16-Dec-15 16-Jan-16

M8J4S-QR-T2EP8-100 Reinfocement Fixing for W1(East Wall) 6 16-Dec-15 22-Dec-15

M8J4S-QR-T2EP8-110 Formworks for W1(East Wall) 5 19-Dec-15 23-Dec-15

Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun2015 2016

PROJECT: DESIGN & CONSTRUCT NEW ORBITAL HIGHWAY & TRUCK ROUTE (P023) -CONTRACT 2: ORBITAL HIGHWAY SALWA ROAD TO NORTH RELIEF ROADINTERNAL TARGET PROGRAMME OF WORKS

GREEN LINE TUNNEL PROGRAMME

Remaining Level of EffortActual Level of Effort

Actual WorkRemaining Work

Critical Remaining ...Milestone

Page 12 of 19 TASK filter: Q-RAIL GREEN LINE.© Oracle Corporation

Activity ID Activity Name OriginalDuration

Start Finish

M8J4S-QR-T2EP8-120 Concreting for W1(East Wall) 1 24-Dec-15 24-Dec-15

M8J4S-QR-T2EP8-130 Deshuttering for W1(East Wall) 1 26-Dec-15 26-Dec-15

M8J4S-QR-T2EP8-140 Curing for W1(East Wall) 7 27-Dec-15 03-Jan-16

M8J4S-QR-T2EP8-150 Waterproofing for foudation and Wall for W1(East Wall) 5 04-Jan-16 09-Jan-16

M8J4S-QR-T2EP8-160 Reinfocement Fixing for W2 (West Wall) 6 23-Dec-15 29-Dec-15

M8J4S-QR-T2EP8-170 Formworks for W2 (West Wall) 5 26-Dec-15 30-Dec-15

M8J4S-QR-T2EP8-180 Concreting for W2 (West Wall) 1 31-Dec-15 31-Dec-15

M8J4S-QR-T2EP8-190 Deshuttering for W2 (West Wall) 1 02-Jan-16 02-Jan-16

M8J4S-QR-T2EP8-200 Curing for W2 (West Wall) 7 03-Jan-16 10-Jan-16

M8J4S-QR-T2EP8-210 Waterproofing for foudation and Wall for W2 (West Wall) 5 11-Jan-16 16-Jan-16

PANEL 9PANEL 9 27 30-Dec-15 30-Jan-16

M8J4S-QR-T2EP9-100 Reinfocement Fixing for W1(East Wall) 6 30-Dec-15 05-Jan-16

M8J4S-QR-T2EP9-110 Formworks for W1(East Wall) 5 02-Jan-16 06-Jan-16

M8J4S-QR-T2EP9-120 Concreting for W1(East Wall) 1 07-Jan-16 07-Jan-16

M8J4S-QR-T2EP9-130 Deshuttering for W1(East Wall) 1 09-Jan-16 09-Jan-16

M8J4S-QR-T2EP9-140 Curing for W1(East Wall) 7 10-Jan-16 17-Jan-16

M8J4S-QR-T2EP9-150 Waterproofing for foudation and Wall for W1(East Wall) 5 18-Jan-16 23-Jan-16

M8J4S-QR-T2EP9-160 Reinfocement Fixing for W2 (West Wall) 6 06-Jan-16 12-Jan-16

M8J4S-QR-T2EP9-170 Formworks for W2 (West Wall) 5 09-Jan-16 13-Jan-16

M8J4S-QR-T2EP9-180 Concreting for W2 (West Wall) 1 14-Jan-16 14-Jan-16

M8J4S-QR-T2EP9-190 Deshuttering for W2 (West Wall) 1 16-Jan-16 16-Jan-16

M8J4S-QR-T2EP9-200 Curing for W2 (West Wall) 7 17-Jan-16 24-Jan-16

M8J4S-QR-T2EP9-210 Waterproofing for foudation and Wall for W2 (West Wall) 5 25-Jan-16 30-Jan-16

PANEL 10PANEL 10 27 06-Jan-16 06-Feb-16

M8J4S-QR-T2EP10-100 Reinfocement Fixing for W1(East Wall) 6 06-Jan-16 12-Jan-16

M8J4S-QR-T2EP10-110 Formworks for W1(East Wall) 5 09-Jan-16 13-Jan-16

M8J4S-QR-T2EP10-120 Concreting for W1(East Wall) 1 14-Jan-16 14-Jan-16

M8J4S-QR-T2EP10-130 Deshuttering for W1(East Wall) 1 16-Jan-16 16-Jan-16

M8J4S-QR-T2EP10-140 Curing for W1(East Wall) 7 17-Jan-16 24-Jan-16

M8J4S-QR-T2EP10-150 Waterproofing for foudation and Wall for W1(East Wall) 5 25-Jan-16 30-Jan-16

M8J4S-QR-T2EP10-160 Reinfocement Fixing for W2 (West Wall) 6 13-Jan-16 19-Jan-16

M8J4S-QR-T2EP10-170 Formworks for W2 (West Wall) 5 16-Jan-16 20-Jan-16

M8J4S-QR-T2EP10-180 Concreting for W2 (West Wall) 1 21-Jan-16 21-Jan-16

M8J4S-QR-T2EP10-190 Deshuttering for W2 (West Wall) 1 23-Jan-16 23-Jan-16

M8J4S-QR-T2EP10-200 Curing for W2 (West Wall) 7 24-Jan-16 31-Jan-16

M8J4S-QR-T2EP10-210 Waterproofing for foudation and Wall for W2 (West Wall) 5 01-Feb-16 06-Feb-16

PANEL 11PANEL 11 27 20-Jan-16 21-Feb-16

M8J4S-QR-T2EP11-100 Reinfocement Fixing for W1(East Wall) 6 20-Jan-16 26-Jan-16

M8J4S-QR-T2EP11-110 Formworks for W1(East Wall) 5 23-Jan-16 27-Jan-16

M8J4S-QR-T2EP11-120 Concreting for W1(East Wall) 1 28-Jan-16 28-Jan-16

M8J4S-QR-T2EP11-130 Deshuttering for W1(East Wall) 1 30-Jan-16 30-Jan-16

M8J4S-QR-T2EP11-140 Curing for W1(East Wall) 7 31-Jan-16 07-Feb-16

M8J4S-QR-T2EP11-150 Waterproofing for foudation and Wall for W1(East Wall) 5 08-Feb-16 14-Feb-16

M8J4S-QR-T2EP11-160 Reinfocement Fixing for W2 (West Wall) 6 27-Jan-16 02-Feb-16

M8J4S-QR-T2EP11-170 Formworks for W2 (West Wall) 5 30-Jan-16 03-Feb-16

Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun2015 2016

PROJECT: DESIGN & CONSTRUCT NEW ORBITAL HIGHWAY & TRUCK ROUTE (P023) -CONTRACT 2: ORBITAL HIGHWAY SALWA ROAD TO NORTH RELIEF ROADINTERNAL TARGET PROGRAMME OF WORKS

GREEN LINE TUNNEL PROGRAMME

Remaining Level of EffortActual Level of Effort

Actual WorkRemaining Work

Critical Remaining ...Milestone

Page 13 of 19 TASK filter: Q-RAIL GREEN LINE.© Oracle Corporation

Activity ID Activity Name OriginalDuration

Start Finish

M8J4S-QR-T2EP11-180 Concreting for W2 (West Wall) 1 04-Feb-16 04-Feb-16

M8J4S-QR-T2EP11-190 Deshuttering for W2 (West Wall) 1 06-Feb-16 06-Feb-16

M8J4S-QR-T2EP11-200 Curing for W2 (West Wall) 7 07-Feb-16 15-Feb-16

M8J4S-QR-T2EP11-210 Waterproofing for foudation and Wall for W2 (West Wall) 5 16-Feb-16 21-Feb-16

PANEL 12PANEL 12 27 03-Feb-16 06-Mar-16

M8J4S-QR-T2EP12-100 Reinfocement Fixing for W1(East Wall) 6 03-Feb-16 10-Feb-16

M8J4S-QR-T2EP12-110 Formworks for W1(East Wall) 5 06-Feb-16 11-Feb-16

M8J4S-QR-T2EP12-120 Concreting for W1(East Wall) 1 13-Feb-16 13-Feb-16

M8J4S-QR-T2EP12-130 Deshuttering for W1(East Wall) 1 14-Feb-16 14-Feb-16

M8J4S-QR-T2EP12-140 Curing for W1(East Wall) 7 15-Feb-16 22-Feb-16

M8J4S-QR-T2EP12-150 Waterproofing for foudation and Wall for W1(East Wall) 5 23-Feb-16 28-Feb-16

M8J4S-QR-T2EP12-160 Reinfocement Fixing for W2 (West Wall) 6 11-Feb-16 17-Feb-16

M8J4S-QR-T2EP12-170 Formworks for W2 (West Wall) 5 14-Feb-16 18-Feb-16

M8J4S-QR-T2EP12-180 Concreting for W2 (West Wall) 1 20-Feb-16 20-Feb-16

M8J4S-QR-T2EP12-190 Deshuttering for W2 (West Wall) 1 21-Feb-16 21-Feb-16

M8J4S-QR-T2EP12-200 Curing for W2 (West Wall) 7 22-Feb-16 29-Feb-16

M8J4S-QR-T2EP12-210 Waterproofing for foudation and Wall for W2 (West Wall) 5 01-Mar-16 06-Mar-16

PANEL 13PANEL 13 27 18-Feb-16 20-Mar-16

M8J4S-QR-T2EP13-100 Reinfocement Fixing for W1(East Wall) 6 18-Feb-16 24-Feb-16

M8J4S-QR-T2EP13-110 Formworks for W1(East Wall) 5 21-Feb-16 25-Feb-16

M8J4S-QR-T2EP13-120 Concreting for W1(East Wall) 1 27-Feb-16 27-Feb-16

M8J4S-QR-T2EP13-130 Deshuttering for W1(East Wall) 1 28-Feb-16 28-Feb-16

M8J4S-QR-T2EP13-140 Curing for W1(East Wall) 7 29-Feb-16 07-Mar-16

M8J4S-QR-T2EP13-150 Waterproofing for foudation and Wall for W1(East Wall) 5 08-Mar-16 13-Mar-16

M8J4S-QR-T2EP13-160 Reinfocement Fixing for W2 (West Wall) 6 25-Feb-16 02-Mar-16

M8J4S-QR-T2EP13-170 Formworks for W2 (West Wall) 5 28-Feb-16 03-Mar-16

M8J4S-QR-T2EP13-180 Concreting for W2 (West Wall) 1 05-Mar-16 05-Mar-16

M8J4S-QR-T2EP13-190 Deshuttering for W2 (West Wall) 1 06-Mar-16 06-Mar-16

M8J4S-QR-T2EP13-200 Curing for W2 (West Wall) 7 07-Mar-16 14-Mar-16

M8J4S-QR-T2EP13-210 Waterproofing for foudation and Wall for W2 (West Wall) 5 15-Mar-16 20-Mar-16

TOP SLABTOP SLAB 122 12-Dec-15 02-May-16

PANEL 5PANEL 5 19 12-Dec-15 02-Jan-16

M8J4S-QR-T2DWP5-100 Erection of Scaffolding for Deck Slab 2 12-Dec-15 13-Dec-15

M8J4S-QR-T2DWP5-110 Formworks for Deck Slab 3 14-Dec-15 16-Dec-15

M8J4S-QR-T2DWP5-120 Steel FIxing 6 14-Dec-15 20-Dec-15

M8J4S-QR-T2DWP5-130 Concreting 1 21-Dec-15 21-Dec-15

M8J4S-QR-T2DWP5-140 Removal of Scaffolding and Deshuttering 1 24-Dec-15 24-Dec-15

M8J4S-QR-T2DWP5-150 Curing 7 22-Dec-15 29-Dec-15

M8J4S-QR-T2DWP5-160 Waterprofing 3 30-Dec-15 02-Jan-16

PANEL 6PANEL 6 23 26-Dec-15 20-Jan-16

M8J4S-QR-T2DWP6-100 Erection of Scaffolding for Deck Slab 1 26-Dec-15 26-Dec-15

M8J4S-QR-T2DWP6-110 Formworks for Deck Slab 3 27-Dec-15 29-Dec-15

M8J4S-QR-T2DWP6-120 Steel FIxing 6 02-Jan-16 07-Jan-16

M8J4S-QR-T2DWP6-130 Concreting 1 09-Jan-16 09-Jan-16

M8J4S-QR-T2DWP6-140 Removal of Scaffolding and Deshuttering 1 12-Jan-16 12-Jan-16

Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun2015 2016

PROJECT: DESIGN & CONSTRUCT NEW ORBITAL HIGHWAY & TRUCK ROUTE (P023) -CONTRACT 2: ORBITAL HIGHWAY SALWA ROAD TO NORTH RELIEF ROADINTERNAL TARGET PROGRAMME OF WORKS

GREEN LINE TUNNEL PROGRAMME

Remaining Level of EffortActual Level of Effort

Actual WorkRemaining Work

Critical Remaining ...Milestone

Page 14 of 19 TASK filter: Q-RAIL GREEN LINE.© Oracle Corporation

Activity ID Activity Name OriginalDuration

Start Finish

M8J4S-QR-T2DWP6-150 Curing 7 10-Jan-16 17-Jan-16

M8J4S-QR-T2DWP6-160 Waterprofing 3 18-Jan-16 20-Jan-16

PANEL 7PANEL 7 18 13-Jan-16 02-Feb-16

M8J4S-QR-T2DWP7-100 Erection of Scaffolding for Deck Slab 1 13-Jan-16 13-Jan-16

M8J4S-QR-T2DWP7-110 Formworks for Deck Slab 3 14-Jan-16 17-Jan-16

M8J4S-QR-T2DWP7-120 Steel FIxing 6 14-Jan-16 20-Jan-16

M8J4S-QR-T2DWP7-130 Concreting 1 21-Jan-16 21-Jan-16

M8J4S-QR-T2DWP7-140 Removal of Scaffolding and Deshuttering 1 25-Jan-16 25-Jan-16

M8J4S-QR-T2DWP7-150 Curing 7 23-Jan-16 30-Jan-16

M8J4S-QR-T2DWP7-160 Waterprofing 3 31-Jan-16 02-Feb-16

PANEL 8PANEL 8 18 26-Jan-16 16-Feb-16

M8J4S-QR-T2DWP8-100 Erection of Scaffolding for Deck Slab 1 26-Jan-16 26-Jan-16

M8J4S-QR-T2DWP8-110 Formworks for Deck Slab 3 27-Jan-16 30-Jan-16

M8J4S-QR-T2DWP8-120 Steel FIxing 6 27-Jan-16 02-Feb-16

M8J4S-QR-T2DWP8-130 Concreting 1 03-Feb-16 03-Feb-16

M8J4S-QR-T2DWP8-140 Removal of Scaffolding and Deshuttering 1 07-Feb-16 07-Feb-16

M8J4S-QR-T2DWP8-150 Curing 7 04-Feb-16 13-Feb-16

M8J4S-QR-T2DWP8-160 Waterprofing 3 14-Feb-16 16-Feb-16

PANEL 9PANEL 9 18 08-Feb-16 29-Feb-16

M8J4S-QR-T2DWP9-100 Erection of Scaffolding for Deck Slab 1 08-Feb-16 08-Feb-16

M8J4S-QR-T2DWP9-110 Formworks for Deck Slab 3 10-Feb-16 13-Feb-16

M8J4S-QR-T2DWP9-120 Steel FIxing 6 10-Feb-16 16-Feb-16

M8J4S-QR-T2DWP9-130 Concreting 1 17-Feb-16 17-Feb-16

M8J4S-QR-T2DWP9-140 Removal of Scaffolding and Deshuttering 1 21-Feb-16 21-Feb-16

M8J4S-QR-T2DWP9-150 Curing 7 18-Feb-16 25-Feb-16

M8J4S-QR-T2DWP9-160 Waterprofing 3 27-Feb-16 29-Feb-16

PANEL 10PANEL 10 18 22-Feb-16 13-Mar-16

M8J4S-QR-T2DWP10-10 Erection of Scaffolding for Deck Slab 1 22-Feb-16 22-Feb-16

M8J4S-QR-T2DWP10-11 Formworks for Deck Slab 3 23-Feb-16 25-Feb-16

M8J4S-QR-T2DWP10-12 Steel FIxing 6 23-Feb-16 29-Feb-16

M8J4S-QR-T2DWP10-13 Concreting 1 01-Mar-16 01-Mar-16

M8J4S-QR-T2DWP10-14 Removal of Scaffolding and Deshuttering 1 05-Mar-16 05-Mar-16

M8J4S-QR-T2DWP10-15 Curing 7 02-Mar-16 09-Mar-16

M8J4S-QR-T2DWP10-16 Waterprofing 3 10-Mar-16 13-Mar-16

PANEL 11PANEL 11 18 06-Mar-16 26-Mar-16

M8J4S-QR-T2DWP11-10 Erection of Scaffolding for Deck Slab 1 06-Mar-16 06-Mar-16

M8J4S-QR-T2DWP11-11 Formworks for Deck Slab 3 07-Mar-16 09-Mar-16

M8J4S-QR-T2DWP11-12 Steel FIxing 6 07-Mar-16 13-Mar-16

M8J4S-QR-T2DWP11-13 Concreting 1 14-Mar-16 14-Mar-16

M8J4S-QR-T2DWP11-14 Removal of Scaffolding and Deshuttering 1 17-Mar-16 17-Mar-16

M8J4S-QR-T2DWP11-15 Curing 7 15-Mar-16 22-Mar-16

M8J4S-QR-T2DWP11-16 Waterprofing 3 23-Mar-16 26-Mar-16

PANEL 12PANEL 12 23 19-Mar-16 13-Apr-16

M8J4S-QR-T2DWP12-10 Erection of Scaffolding for Deck Slab 1 19-Mar-16 19-Mar-16

M8J4S-QR-T2DWP12-11 Formworks for Deck Slab 3 20-Mar-16 22-Mar-16

Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun2015 2016

PROJECT: DESIGN & CONSTRUCT NEW ORBITAL HIGHWAY & TRUCK ROUTE (P023) -CONTRACT 2: ORBITAL HIGHWAY SALWA ROAD TO NORTH RELIEF ROADINTERNAL TARGET PROGRAMME OF WORKS

GREEN LINE TUNNEL PROGRAMME

Remaining Level of EffortActual Level of Effort

Actual WorkRemaining Work

Critical Remaining ...Milestone

Page 15 of 19 TASK filter: Q-RAIL GREEN LINE.© Oracle Corporation

Activity ID Activity Name OriginalDuration

Start Finish

M8J4S-QR-T2DWP12-12 Steel FIxing 6 26-Mar-16 31-Mar-16

M8J4S-QR-T2DWP12-13 Concreting 1 02-Apr-16 02-Apr-16

M8J4S-QR-T2DWP12-14 Removal of Scaffolding and Deshuttering 1 05-Apr-16 05-Apr-16

M8J4S-QR-T2DWP12-15 Curing 7 03-Apr-16 10-Apr-16

M8J4S-QR-T2DWP12-16 Waterprofing 3 11-Apr-16 13-Apr-16

PANEL 13PANEL 13 23 06-Apr-16 02-May-16

M8J4S-QR-T2DWP13-10 Erection of Scaffolding for Deck Slab 1 06-Apr-16 06-Apr-16

M8J4S-QR-T2DWP13-11 Formworks for Deck Slab 3 07-Apr-16 10-Apr-16

M8J4S-QR-T2DWP13-12 Steel FIxing 6 13-Apr-16 19-Apr-16

M8J4S-QR-T2DWP13-13 Concreting 1 20-Apr-16 20-Apr-16

M8J4S-QR-T2DWP13-14 Removal of Scaffolding and Deshuttering 1 24-Apr-16 24-Apr-16

M8J4S-QR-T2DWP13-15 Curing 7 21-Apr-16 28-Apr-16

M8J4S-QR-T2DWP13-16 Waterprofing 3 30-Apr-16 02-May-16

U SHAPED TUNNEL BETWEENU SHAPED TUNNEL BETWEEN TUNNEL AND DUKHAN TO ORBITAL HIGHWAY RAMP 86 19-Oct-15 26-Jan-16

FOUNDATIONFOUNDATION 69 19-Oct-15 06-Jan-16

PANEL 1PANEL 1 21 19-Oct-15 11-Nov-15

M8J4S-QR-U2FP1-100 Laying of Blinding 1 19-Oct-15 19-Oct-15

M8J4S-QR-U2FP1-110 Waterproofing 1 20-Oct-15 20-Oct-15

M8J4S-QR-U2FP1-120 Reinfocement Fixing 8 22-Oct-15 31-Oct-15

M8J4S-QR-U2FP1-130 Formworks 2 31-Oct-15 01-Nov-15

M8J4S-QR-U2FP1-140 Concreting 1 02-Nov-15 02-Nov-15

M8J4S-QR-U2FP1-150 Deshuttering 1 03-Nov-15 03-Nov-15

M8J4S-QR-U2FP1-160 Curing 7 04-Nov-15 11-Nov-15

PANEL 2PANEL 2 21 28-Oct-15 21-Nov-15

M8J4S-QR-U2FP2-100 Laying of Blinding 1 28-Oct-15 28-Oct-15

M8J4S-QR-U2FP2-110 Waterproofing 1 29-Oct-15 29-Oct-15

M8J4S-QR-U2FP2-120 Reinfocement Fixing 8 01-Nov-15 09-Nov-15

M8J4S-QR-U2FP2-130 Formworks 2 09-Nov-15 10-Nov-15

M8J4S-QR-U2FP2-140 Concreting 1 11-Nov-15 11-Nov-15

M8J4S-QR-U2FP2-150 Deshuttering 1 12-Nov-15 12-Nov-15

M8J4S-QR-U2FP2-160 Curing 7 14-Nov-15 21-Nov-15

PANEL 3PANEL 3 21 07-Nov-15 30-Nov-15

M8J4S-QR-U2FP3-100 Laying of Blinding 1 07-Nov-15 07-Nov-15

M8J4S-QR-U2FP3-110 Waterproofing 1 08-Nov-15 08-Nov-15

M8J4S-QR-U2FP3-120 Reinfocement Fixing 8 10-Nov-15 18-Nov-15

M8J4S-QR-U2FP3-130 Formworks 2 18-Nov-15 19-Nov-15

M8J4S-QR-U2FP3-140 Concreting 1 21-Nov-15 21-Nov-15

M8J4S-QR-U2FP3-150 Deshuttering 1 22-Nov-15 22-Nov-15

M8J4S-QR-U2FP3-160 Curing 7 23-Nov-15 30-Nov-15

PANEL 4PANEL 4 21 16-Nov-15 09-Dec-15

M8J4S-QR-U2FP4-100 Laying of Blinding 1 16-Nov-15 16-Nov-15

M8J4S-QR-U2FP4-110 Waterproofing 1 17-Nov-15 17-Nov-15

M8J4S-QR-U2FP4-120 Reinfocement Fixing 8 19-Nov-15 28-Nov-15

M8J4S-QR-U2FP4-130 Formworks 2 28-Nov-15 29-Nov-15

M8J4S-QR-U2FP4-140 Concreting 1 30-Nov-15 30-Nov-15

Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun2015 2016

PROJECT: DESIGN & CONSTRUCT NEW ORBITAL HIGHWAY & TRUCK ROUTE (P023) -CONTRACT 2: ORBITAL HIGHWAY SALWA ROAD TO NORTH RELIEF ROADINTERNAL TARGET PROGRAMME OF WORKS

GREEN LINE TUNNEL PROGRAMME

Remaining Level of EffortActual Level of Effort

Actual WorkRemaining Work

Critical Remaining ...Milestone

Page 16 of 19 TASK filter: Q-RAIL GREEN LINE.© Oracle Corporation

Activity ID Activity Name OriginalDuration

Start Finish

M8J4S-QR-U2FP4-150 Deshuttering 1 01-Dec-15 01-Dec-15

M8J4S-QR-U2FP4-160 Curing 7 02-Dec-15 09-Dec-15

PANEL 5PANEL 5 21 25-Nov-15 19-Dec-15

M8J4S-QR-U2FP5-100 Laying of Blinding 1 25-Nov-15 25-Nov-15

M8J4S-QR-U2FP5-110 Waterproofing 1 26-Nov-15 26-Nov-15

M8J4S-QR-U2FP5-120 Reinfocement Fixing 8 29-Nov-15 07-Dec-15

M8J4S-QR-U2FP5-130 Formworks 2 07-Dec-15 08-Dec-15

M8J4S-QR-U2FP5-140 Concreting 1 09-Dec-15 09-Dec-15

M8J4S-QR-U2FP5-150 Deshuttering 1 10-Dec-15 10-Dec-15

M8J4S-QR-U2FP5-160 Curing 7 12-Dec-15 19-Dec-15

PANEL 6PANEL 6 21 05-Dec-15 28-Dec-15

M8J4S-QR-U2FP6-100 Laying of Blinding 1 05-Dec-15 05-Dec-15

M8J4S-QR-U2FP6-110 Waterproofing 1 06-Dec-15 06-Dec-15

M8J4S-QR-U2FP6-120 Reinfocement Fixing 8 08-Dec-15 16-Dec-15

M8J4S-QR-U2FP6-130 Formworks 2 16-Dec-15 17-Dec-15

M8J4S-QR-U2FP6-140 Concreting 1 19-Dec-15 19-Dec-15

M8J4S-QR-U2FP6-150 Deshuttering 1 20-Dec-15 20-Dec-15

M8J4S-QR-U2FP6-160 Curing 7 21-Dec-15 28-Dec-15

PANEL 7PANEL 7 21 14-Dec-15 06-Jan-16

M8J4S-QR-U2FP7-100 Laying of Blinding 1 14-Dec-15 14-Dec-15

M8J4S-QR-U2FP7-110 Waterproofing 1 15-Dec-15 15-Dec-15

M8J4S-QR-U2FP7-120 Reinfocement Fixing 8 17-Dec-15 26-Dec-15

M8J4S-QR-U2FP7-130 Formworks 2 26-Dec-15 27-Dec-15

M8J4S-QR-U2FP7-140 Concreting 1 28-Dec-15 28-Dec-15

M8J4S-QR-U2FP7-150 Deshuttering 1 29-Dec-15 29-Dec-15

M8J4S-QR-U2FP7-160 Curing 7 30-Dec-15 06-Jan-16

WALL CASTINGWALL CASTING 71 05-Nov-15 26-Jan-16

PANEL 1PANEL 1 23 05-Nov-15 01-Dec-15

M8J4S-QR-U2EP1-100 Reinfocement Fixing for W1(East Wall) 4 05-Nov-15 09-Nov-15

M8J4S-QR-U2EP1-110 Formworks for W1(East Wall) 2 09-Nov-15 10-Nov-15

M8J4S-QR-U2EP1-120 Concreting for W1(East Wall) 1 11-Nov-15 11-Nov-15

M8J4S-QR-U2EP1-130 Deshuttering for W1(East Wall) 1 12-Nov-15 12-Nov-15

M8J4S-QR-U2EP1-140 Curing for W1(East Wall) 7 14-Nov-15 21-Nov-15

M8J4S-QR-U2EP1-150 Waterproofing for foudation and Wall for W1(East Wall) 5 22-Nov-15 26-Nov-15

M8J4S-QR-U2EP1-160 Reinfocement Fixing for W2 (West Wall) 4 10-Nov-15 14-Nov-15

M8J4S-QR-U2EP1-170 Formworks for W2 (West Wall) 2 14-Nov-15 15-Nov-15

M8J4S-QR-U2EP1-180 Concreting for W2 (West Wall) 1 16-Nov-15 16-Nov-15

M8J4S-QR-U2EP1-190 Deshuttering for W2 (West Wall) 1 17-Nov-15 17-Nov-15

M8J4S-QR-U2EP1-200 Curing for W2 (West Wall) 7 18-Nov-15 25-Nov-15

M8J4S-QR-U2EP1-210 Waterproofing for foudation and Wall for W2 (West Wall) 5 26-Nov-15 01-Dec-15

PANEL 2PANEL 2 23 15-Nov-15 10-Dec-15

M8J4S-QR-U2EP2-120 Reinfocement Fixing for W1(East Wall) 4 15-Nov-15 18-Nov-15

M8J4S-QR-U2EP2-130 Formworks for W1(East Wall) 2 18-Nov-15 19-Nov-15

M8J4S-QR-U2EP2-140 Concreting for W1(East Wall) 1 21-Nov-15 21-Nov-15

M8J4S-QR-U2EP2-150 Deshuttering for W1(East Wall) 1 22-Nov-15 22-Nov-15

Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun2015 2016

PROJECT: DESIGN & CONSTRUCT NEW ORBITAL HIGHWAY & TRUCK ROUTE (P023) -CONTRACT 2: ORBITAL HIGHWAY SALWA ROAD TO NORTH RELIEF ROADINTERNAL TARGET PROGRAMME OF WORKS

GREEN LINE TUNNEL PROGRAMME

Remaining Level of EffortActual Level of Effort

Actual WorkRemaining Work

Critical Remaining ...Milestone

Page 17 of 19 TASK filter: Q-RAIL GREEN LINE.© Oracle Corporation

Activity ID Activity Name OriginalDuration

Start Finish

M8J4S-QR-U2EP2-160 Curing for W1(East Wall) 7 23-Nov-15 30-Nov-15

M8J4S-QR-U2EP2-170 Waterproofing for foudation and Wall for W1(East Wall) 5 01-Dec-15 06-Dec-15

M8J4S-QR-U2EP2-180 Reinfocement Fixing for W2 (West Wall) 4 19-Nov-15 23-Nov-15

M8J4S-QR-U2EP2-190 Formworks for W2 (West Wall) 2 23-Nov-15 24-Nov-15

M8J4S-QR-U2EP2-200 Concreting for W2 (West Wall) 1 25-Nov-15 25-Nov-15

M8J4S-QR-U2EP2-210 Deshuttering for W2 (West Wall) 1 26-Nov-15 26-Nov-15

M8J4S-QR-U2EP2-220 Curing for W2 (West Wall) 7 28-Nov-15 05-Dec-15

M8J4S-QR-U2EP2-230 Waterproofing for foudation and Wall for W2 (West Wall) 5 06-Dec-15 10-Dec-15

PANEL 3PANEL 3 23 24-Nov-15 20-Dec-15

M8J4S-QR-U2EP3-120 Reinfocement Fixing for W1(East Wall) 4 24-Nov-15 28-Nov-15

M8J4S-QR-U2EP3-130 Formworks for W1(East Wall) 2 28-Nov-15 29-Nov-15

M8J4S-QR-U2EP3-140 Concreting for W1(East Wall) 1 30-Nov-15 30-Nov-15

M8J4S-QR-U2EP3-150 Deshuttering for W1(East Wall) 1 01-Dec-15 01-Dec-15

M8J4S-QR-U2EP3-160 Curing for W1(East Wall) 7 02-Dec-15 09-Dec-15

M8J4S-QR-U2EP3-170 Waterproofing for foudation and Wall for W1(East Wall) 5 10-Dec-15 15-Dec-15

M8J4S-QR-U2EP3-180 Reinfocement Fixing for W2 (West Wall) 4 29-Nov-15 02-Dec-15

M8J4S-QR-U2EP3-190 Formworks for W2 (West Wall) 2 02-Dec-15 03-Dec-15

M8J4S-QR-U2EP3-200 Concreting for W2 (West Wall) 1 05-Dec-15 05-Dec-15

M8J4S-QR-U2EP3-210 Deshuttering for W2 (West Wall) 1 06-Dec-15 06-Dec-15

M8J4S-QR-U2EP3-220 Curing for W2 (West Wall) 7 07-Dec-15 14-Dec-15

M8J4S-QR-U2EP3-230 Waterproofing for foudation and Wall for W2 (West Wall) 5 15-Dec-15 20-Dec-15

PANEL 4PANEL 4 23 03-Dec-15 29-Dec-15

M8J4S-QR-U2EP4-120 Reinfocement Fixing for W1(East Wall) 4 03-Dec-15 07-Dec-15

M8J4S-QR-U2EP4-130 Formworks for W1(East Wall) 2 07-Dec-15 08-Dec-15

M8J4S-QR-U2EP4-140 Concreting for W1(East Wall) 1 09-Dec-15 09-Dec-15

M8J4S-QR-U2EP4-150 Deshuttering for W1(East Wall) 1 10-Dec-15 10-Dec-15

M8J4S-QR-U2EP4-160 Curing for W1(East Wall) 7 12-Dec-15 19-Dec-15

M8J4S-QR-U2EP4-170 Waterproofing for foudation and Wall for W1(East Wall) 5 20-Dec-15 24-Dec-15

M8J4S-QR-U2EP4-180 Reinfocement Fixing for W2 (West Wall) 4 08-Dec-15 12-Dec-15

M8J4S-QR-U2EP4-190 Formworks for W2 (West Wall) 2 12-Dec-15 13-Dec-15

M8J4S-QR-U2EP4-200 Concreting for W2 (West Wall) 1 14-Dec-15 14-Dec-15

M8J4S-QR-U2EP4-210 Deshuttering for W2 (West Wall) 1 15-Dec-15 15-Dec-15

M8J4S-QR-U2EP4-220 Curing for W2 (West Wall) 7 16-Dec-15 23-Dec-15

M8J4S-QR-U2EP4-230 Waterproofing for foudation and Wall for W2 (West Wall) 5 24-Dec-15 29-Dec-15

PANEL 5PANEL 5 23 13-Dec-15 07-Jan-16

M8J4S-QR-U2EP5-120 Reinfocement Fixing for W1(East Wall) 4 13-Dec-15 16-Dec-15

M8J4S-QR-U2EP5-130 Formworks for W1(East Wall) 2 16-Dec-15 17-Dec-15

M8J4S-QR-U2EP5-140 Concreting for W1(East Wall) 1 19-Dec-15 19-Dec-15

M8J4S-QR-U2EP5-150 Deshuttering for W1(East Wall) 1 20-Dec-15 20-Dec-15

M8J4S-QR-U2EP5-160 Curing for W1(East Wall) 7 21-Dec-15 28-Dec-15

M8J4S-QR-U2EP5-170 Waterproofing for foudation and Wall for W1(East Wall) 5 29-Dec-15 03-Jan-16

M8J4S-QR-U2EP5-180 Reinfocement Fixing for W2 (West Wall) 4 17-Dec-15 21-Dec-15

M8J4S-QR-U2EP5-190 Formworks for W2 (West Wall) 2 21-Dec-15 22-Dec-15

M8J4S-QR-U2EP5-200 Concreting for W2 (West Wall) 1 23-Dec-15 23-Dec-15

M8J4S-QR-U2EP5-210 Deshuttering for W2 (West Wall) 1 24-Dec-15 24-Dec-15

Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun2015 2016

PROJECT: DESIGN & CONSTRUCT NEW ORBITAL HIGHWAY & TRUCK ROUTE (P023) -CONTRACT 2: ORBITAL HIGHWAY SALWA ROAD TO NORTH RELIEF ROADINTERNAL TARGET PROGRAMME OF WORKS

GREEN LINE TUNNEL PROGRAMME

Remaining Level of EffortActual Level of Effort

Actual WorkRemaining Work

Critical Remaining ...Milestone

Page 18 of 19 TASK filter: Q-RAIL GREEN LINE.© Oracle Corporation

Activity ID Activity Name OriginalDuration

Start Finish

M8J4S-QR-U2EP5-220 Curing for W2 (West Wall) 7 26-Dec-15 02-Jan-16

M8J4S-QR-U2EP5-230 Waterproofing for foudation and Wall for W2 (West Wall) 5 03-Jan-16 07-Jan-16

PANEL 6PANEL 6 23 22-Dec-15 17-Jan-16

M8J4S-QR-U2EP6-120 Reinfocement Fixing for W1(East Wall) 4 22-Dec-15 26-Dec-15

M8J4S-QR-U2EP6-130 Formworks for W1(East Wall) 2 26-Dec-15 27-Dec-15

M8J4S-QR-U2EP6-140 Concreting for W1(East Wall) 1 28-Dec-15 28-Dec-15

M8J4S-QR-U2EP6-150 Deshuttering for W1(East Wall) 1 29-Dec-15 29-Dec-15

M8J4S-QR-U2EP6-160 Curing for W1(East Wall) 7 30-Dec-15 06-Jan-16

M8J4S-QR-U2EP6-170 Waterproofing for foudation and Wall for W1(East Wall) 5 07-Jan-16 12-Jan-16

M8J4S-QR-U2EP6-180 Reinfocement Fixing for W2 (West Wall) 4 27-Dec-15 30-Dec-15

M8J4S-QR-U2EP6-190 Formworks for W2 (West Wall) 2 30-Dec-15 31-Dec-15

M8J4S-QR-U2EP6-200 Concreting for W2 (West Wall) 1 02-Jan-16 02-Jan-16

M8J4S-QR-U2EP6-210 Deshuttering for W2 (West Wall) 1 03-Jan-16 03-Jan-16

M8J4S-QR-U2EP6-220 Curing for W2 (West Wall) 7 04-Jan-16 11-Jan-16

M8J4S-QR-U2EP6-230 Waterproofing for foudation and Wall for W2 (West Wall) 5 12-Jan-16 17-Jan-16

PANEL 7PANEL 7 23 31-Dec-15 26-Jan-16

M8J4S-QR-U2EP7-120 Reinfocement Fixing for W1(East Wall) 4 31-Dec-15 04-Jan-16

M8J4S-QR-U2EP7-130 Formworks for W1(East Wall) 2 04-Jan-16 05-Jan-16

M8J4S-QR-U2EP7-140 Concreting for W1(East Wall) 1 06-Jan-16 06-Jan-16

M8J4S-QR-U2EP7-150 Deshuttering for W1(East Wall) 1 07-Jan-16 07-Jan-16

M8J4S-QR-U2EP7-160 Curing for W1(East Wall) 7 09-Jan-16 16-Jan-16

M8J4S-QR-U2EP7-170 Waterproofing for foudation and Wall for W1(East Wall) 5 17-Jan-16 21-Jan-16

M8J4S-QR-U2EP7-180 Reinfocement Fixing for W2 (West Wall) 4 05-Jan-16 09-Jan-16

M8J4S-QR-U2EP7-190 Formworks for W2 (West Wall) 2 09-Jan-16 10-Jan-16

M8J4S-QR-U2EP7-200 Concreting for W2 (West Wall) 1 11-Jan-16 11-Jan-16

M8J4S-QR-U2EP7-210 Deshuttering for W2 (West Wall) 1 12-Jan-16 12-Jan-16

M8J4S-QR-U2EP7-220 Curing for W2 (West Wall) 7 13-Jan-16 20-Jan-16

M8J4S-QR-U2EP7-230 Waterproofing for foudation and Wall for W2 (West Wall) 5 21-Jan-16 26-Jan-16

BACKFILLING BEHIND WALLBACKFILLING BEHIND WALL 10 12-Dec-15 22-Dec-15

M8J4S-QR-U2EW-100 Bacfilling behind the Wall 1 5 12-Dec-15 16-Dec-15

M8J4S-QR-U2EW-110 Bacfilling behind the Wall 2 5 17-Dec-15 22-Dec-15

Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun2015 2016

PROJECT: DESIGN & CONSTRUCT NEW ORBITAL HIGHWAY & TRUCK ROUTE (P023) -CONTRACT 2: ORBITAL HIGHWAY SALWA ROAD TO NORTH RELIEF ROADINTERNAL TARGET PROGRAMME OF WORKS

GREEN LINE TUNNEL PROGRAMME

Remaining Level of EffortActual Level of Effort

Actual WorkRemaining Work

Critical Remaining ...Milestone

Page 19 of 19 TASK filter: Q-RAIL GREEN LINE.© Oracle Corporation