Pwalugu Multi-Purpose Dam Project Stakeholder Consultative … MPD... · 2019-04-24 · www. v r a...
Transcript of Pwalugu Multi-Purpose Dam Project Stakeholder Consultative … MPD... · 2019-04-24 · www. v r a...
Pwalugu Multi-Purpose Dam ProjectStakeholder Consultative Meeting
Accra
April 24, 2019
w w w . v r a . c o m
w w w . v r a . c o m
➢ Background of the Pwalugu Project
➢ Project Description
➢ Current Status of the Project
➢ Project Benefits
➢ Project Impacts and mitigations
➢ Project Organisation
➢ Way Forward
Outline
w w w . v r a . c o m
➢ In 2013, VRA received funding from Agence Francaisede Development to undertake Feasibility Study, anEnvironmental & Social Impact Assessment (ESIA) anda Resettlement Action Plan (RAP);
➢ ESIA was completed in 2016 and feasibility study in2018;
➢ Subsequently GoG has decided to proceed with theproject and therefore VRA has initiatedimplementation of the project;
➢ This project is in line with VRA’s objective of ensuringdevelopment in a sustainable manner and itsmandate to develop the hydro resources of the VoltaBasin.
Background
w w w . v r a . c o m
➢ The Project will comprise the following:
▪ A dam with maximum reservoir area of 350 km2 and full supply level of 165m
▪ A 60 MW power house with two (2) turbines
▪ A 20 metre high weir with primary and secondary canals for a 20,000 hectare irrigation scheme
▪ 15km overhead transmission line
▪ Resettlement of project affected persons
▪ Estimated cost of dam, powerhouse and weir isabout $300m. Cost of irrigation scheme andresettlement will be known after completion ofon-going studies.
Project Description
w w w . v r a . c o m
➢ Six (6) project alternatives were assessed;➢ Reservoir elevation reduced from 170m to
165m to reduce environmental and socialimpact as well as cost.
➢ The current project design strikes the bestbalance among the project benefits ofhydropower, flood control, irrigation and theenvironmental & social impact;
➢ Construction will take about 3.5 years afteraward of contract (at the end of the year).
Project Description
w w w . v r a . c o m
Dam and Power House
w w w . v r a . c o m
IRRIGATIONAREA
DAM SITE
THE RESERVOIR AREA
Dam, Reservoir and Irrigation Areas
w w w . v r a . c o m
➢ The contractor has submitted technical and commercialproposal. Proposal is in four (4) volumes covering EPCcontract, employers requirement, technical specification& technical proposal. VRA has assembled a teamcomprising specialists in dam studies/safety, hydrology,hydro operations, HSE, EPC contracts and supported byits external consultant, Tractebel Engineering.
➢ Revision of ESIA and associated RAP for reduced damheight. EPA will then organise stakeholder consultationsbefore issuing a permit;
➢ The engineering study for the irrigation has beencompleted. An institutional study is being conducted byGIDA to ensure its sustainability will be completed inMay 2019;
Current Status
w w w . v r a . c o m
➢ Irrigation scheme, the largest in the country,will boost agricultural production and formbasis for agro industries, including revival ofPwalugu tomato factory;
➢ Potential to produce 117,000 tons of rice and49,000 tons of maize and reduce import by 16%& 32% respectively. Other crops that willbenefit from increased production includeonion, tomatoes, sweet potato, sweet pepperand watermelon.
➢ Potential for smaller irrigation schemes aroundthe reservoir, fish farming, which will improvelivelihoods and create jobs upstream of dam.
Project Benefits
w w w . v r a . c o m
➢ Hydropower will increase renewable energycapacity and enhance Ghana’s climate changecommitment of 10% renewable by 2030 underthe United Nations Framework for ClimateChange;
➢ Power will be supplied to NEDCo and willimprove quality of supply/voltages;
➢ Dam will reduce the frequency of floodsdownstream. An emergency preparedness andresponse plan will be prepared to managefloods.
Project Benefits
w w w . v r a . c o m
➢ Resettlement of some households within andoutside the forest reserve. The exact area tobe affected and the number of people will beknown after revision of ESIA;
➢ Reservoir will also cover part of thesurrounding forest reserve;
➢ Areas outside the forest reserves will also beaffected.
➢ Land acquisition for dam and reservoir area
Project Impacts
w w w . v r a . c o m
➢ Resettlement will done to international standardwhich requires the following:▪ Involuntary resettlement should be avoided if
possible▪ Full and fair compensation for lost assets▪ Should be conceived as improving the livelihoods of
affected people and implemented accordingly▪ Affected people should be consulted and involved in
resettlement planning
➢ Details of the resettlement will be known afterthe revision of the ESIA/RAP, and will involveextensive consultation with national, region,district and traditional authorities as well asaffected persons and civil society groups.
Mitigating Project Impacts
w w w . v r a . c o m
Project Organisation
➢ The Pwalugu Development Committee,comprising the Office of the Vice President,Ministries of Finance, Energy, Agriculture andAttorney General, will provide overall guidanceto the project;
➢ VRA will manage the project activities through a dedicated Project Secretariat;
➢ A broader stakeholder consultative group atnational, regional & district levels will also becreated to ensure all stakeholders are adequatelyinformed on the progress of the project andmake input into project implementation.
w w w . v r a . c o m
Way Forward
➢ National Stakeholder meeting and Inauguration ofProject Development Committee (PDC) - April 24;
➢ Conclude discussions with Contractor for the Dam,Power House and Weir by end of July 2019;
➢ Revise of ESIA/prepare EMP – timing to be knownafter meeting with EPA on April 25;
➢ Start of consultations on land acquisition andresettlement;
➢ Target is to conclude all preparatory activities by theend of the year for start of construction early nextyear (dry season).
w w w . v r a . c o m
Power Economics
+
+
w w w . v r a . c o m
END OF PRESENTATION