PVEng Vessel Engineering Ltd. 120 Randall Drive, Suite B Waterloo, FOntario, Canada N2V 1C6 Tel. 51...

2
Pressure Vessel Engineering Ltd. 120 Randall Drive, Suite B Waterloo, Ontario, Canada N2V 1C6 Tel. 519-880-9808 Fax 519-880-9810 [email protected] www.pveng.com PVEng Page 1 of 2 This document and any information contained herein are considered confidential and may not be used or disclosed except in accordance with any agreements made with or by PVEng. Introduction Identify company and full address; identify product and part number; list date completed and location of test. This report summarizes the results of the proof test completed for: Company: XXX Product: XXX Location: XXX Date: XXX Setup Identify set-up, indicate how system was displaced of air, identify how pressure was introduced, reference applicable photos / drawings / documents. The “Cooler Discharge Tube” was assembled with mating ISO 6162-1 caps on each end ¼” NPT ports were provided on each cap to allow for pressure line and air escape A calibrated gauge was plumbed in the pressure line to monitor pressure throughout the test. Water was introduced to the system to displace all air The end opposite the pressure connection was plugged to seal the system Pressure was incrementally raised until failure (see results below) Please refer to attached photos. Gauge (ASME VIII-1 UG-102) Identify gauge used including size, pressure range, calibration date and expiry. Provide gauge calibration report. Test Gauge # XXX 0 XXX psi Calibrated on XXX Calibration due XXX Please refer to attached gauge calibration document.

Transcript of PVEng Vessel Engineering Ltd. 120 Randall Drive, Suite B Waterloo, FOntario, Canada N2V 1C6 Tel. 51...

Page 1: PVEng Vessel Engineering Ltd. 120 Randall Drive, Suite B Waterloo, FOntario, Canada N2V 1C6 Tel. 51 9- 80 ax 5 19- 8 0 i nf o@pve g.c m

Pressure Vessel Engineering Ltd.120 Randall Drive, Suite B

Waterloo, Ontario, Canada

N2V 1C6

Tel. 519-880-9808

Fax 519-880-9810

[email protected]

www.pveng.com

PVEng

Page 1 of 2

This document and any information contained herein are considered confidential and may not be used or disclosed except in accordance with any agreements made with or by PVEng.

Introduction Identify company and full address; identify product and part number; list date completed and location of test.

This report summarizes the results of the proof test completed for: Company: XXX

Product: XXX Location: XXX Date: XXX Setup Identify set-up, indicate how system was displaced of air, identify how pressure was introduced, reference applicable photos / drawings / documents.

The “Cooler Discharge Tube” was assembled with mating ISO 6162-1 caps on each end

¼” NPT ports were provided on each cap to allow for pressure line and air escape

A calibrated gauge was plumbed in the pressure line to monitor pressure throughout the test.

Water was introduced to the system to displace all air

The end opposite the pressure connection was plugged to seal the system

Pressure was incrementally raised until failure (see results below) Please refer to attached photos.

Gauge (ASME VIII-1 UG-102) Identify gauge used including size, pressure range, calibration date and expiry. Provide gauge calibration report.

Test Gauge # XXX 0 – XXX psi Calibrated on XXX Calibration due XXX Please refer to attached gauge calibration document.

Page 2: PVEng Vessel Engineering Ltd. 120 Randall Drive, Suite B Waterloo, FOntario, Canada N2V 1C6 Tel. 51 9- 80 ax 5 19- 8 0 i nf o@pve g.c m

Pressure Vessel Engineering Ltd.120 Randall Drive, Suite B

Waterloo, Ontario, Canada

N2V 1C6

Tel. 519-880-9808

Fax 519-880-9810

[email protected]

www.pveng.com

PVEng

Page 2 of 2

This document and any information contained herein are considered confidential and may not be used or disclosed except in accordance with any agreements made with or by PVEng.

Results (ASME VIII-1 UG-101) Indicate hold time, results, add comments if any.

Pressure (psi)

Duration (min)

Comments Result

50 0.5 Initial pressure No leak found

75 0.5 No leak found

100 0.5 No leak found

125 0.5 No leak found

150 0.5 No leak found

175 0.5 No leak found

200 0.5 No leak found

225 10 No leak found

270 10 No leak found

300 7 Leak witnessed after 7 min Leak found

*Test was completed at ambient temperature. Summarize results

A leak was witnessed at 300 psi after 7 minutes holding time.

Local failure was witnessed at the head opposite the spigot side.

Last pressure with no leak witnessed was 260 psi Witnesses Have all parties involved sign and date the report.

This test was conducted in the presence of an authorized inspector on XXX. Completed by ___________________________ XXX XXX (Customers Company) Witnessed by ___________________________ ______________________________ XXX Authorized Inspector National Board Number