Purple Line Extensionmedia.metro.net/.../presentation_purpleline_2015... · Constellation ....
Transcript of Purple Line Extensionmedia.metro.net/.../presentation_purpleline_2015... · Constellation ....
![Page 1: Purple Line Extensionmedia.metro.net/.../presentation_purpleline_2015... · Constellation . Westwood/UCLA Westwood/VA Hospital . Pre-Construction Activities . Current - 2016 2015](https://reader034.fdocuments.in/reader034/viewer/2022050719/5f32b0077c45c5451b2e5af2/html5/thumbnails/1.jpg)
Purple Line Extension Section 1 Construction Community Meeting September 17, 2015
![Page 2: Purple Line Extensionmedia.metro.net/.../presentation_purpleline_2015... · Constellation . Westwood/UCLA Westwood/VA Hospital . Pre-Construction Activities . Current - 2016 2015](https://reader034.fdocuments.in/reader034/viewer/2022050719/5f32b0077c45c5451b2e5af2/html5/thumbnails/2.jpg)
Agenda
2
• Section 2 and 3 Update
• Construction Update
• Eat, Shop, Play Highlights
• Doing Business With Metro
• Business Interruption Fund
• Break Out Q&A
![Page 3: Purple Line Extensionmedia.metro.net/.../presentation_purpleline_2015... · Constellation . Westwood/UCLA Westwood/VA Hospital . Pre-Construction Activities . Current - 2016 2015](https://reader034.fdocuments.in/reader034/viewer/2022050719/5f32b0077c45c5451b2e5af2/html5/thumbnails/3.jpg)
Purple Line Extension Project Alignment
3
![Page 4: Purple Line Extensionmedia.metro.net/.../presentation_purpleline_2015... · Constellation . Westwood/UCLA Westwood/VA Hospital . Pre-Construction Activities . Current - 2016 2015](https://reader034.fdocuments.in/reader034/viewer/2022050719/5f32b0077c45c5451b2e5af2/html5/thumbnails/4.jpg)
Section 2 and 3 Status
Under Construction Forecasted Schedule
Section 1 Section 2 Section 3
Length 3.9 Miles 2.55 Miles 2.48 Miles
New Stations Wilshire/La Brea
Wilshire/Fairfax
Wilshire/La Cienega
Wilshire/Rodeo
Century City/
Constellation
Westwood/UCLA
Westwood/VA
Hospital
Pre-Construction Activities Current - 2016 2015 - 2018 2025 - 2027
Construction 2015 - 2023 2019 - 2026 2027 - 2035
Operations 2024 2026 2035 4
![Page 5: Purple Line Extensionmedia.metro.net/.../presentation_purpleline_2015... · Constellation . Westwood/UCLA Westwood/VA Hospital . Pre-Construction Activities . Current - 2016 2015](https://reader034.fdocuments.in/reader034/viewer/2022050719/5f32b0077c45c5451b2e5af2/html5/thumbnails/5.jpg)
PLE Section 1 Alignment
5
![Page 6: Purple Line Extensionmedia.metro.net/.../presentation_purpleline_2015... · Constellation . Westwood/UCLA Westwood/VA Hospital . Pre-Construction Activities . Current - 2016 2015](https://reader034.fdocuments.in/reader034/viewer/2022050719/5f32b0077c45c5451b2e5af2/html5/thumbnails/6.jpg)
Purple Line Maintenance Facility
6
Butterfield Property
590 S Santa Fe Avenue
• Located in Arts District downtown, near 6th St Bridge
• Building demolition completed
• Environmental review of property – Department of Toxic Substance
Control (DTSC) conducting public comment period now through October 7th on draft removal action work plan for site.
– For more information contact DTSC Project Manager Jessy Fierro at [email protected] , 818-717-6563
![Page 7: Purple Line Extensionmedia.metro.net/.../presentation_purpleline_2015... · Constellation . Westwood/UCLA Westwood/VA Hospital . Pre-Construction Activities . Current - 2016 2015](https://reader034.fdocuments.in/reader034/viewer/2022050719/5f32b0077c45c5451b2e5af2/html5/thumbnails/7.jpg)
Tie-in at Western Station
7
Pothole Work (Underground Utility Investigation) •September 14 thru October 9th
– Wilshire between Manhattan Place and Western
– Daytime: 9:00am to 3:30pm
Acquire Buildings/Abatement – Properties anticipated to be acquired by October 2015
– Demo will follow in spring 2016
Example of utility work at Fairfax
Rendering of AUR Work
![Page 8: Purple Line Extensionmedia.metro.net/.../presentation_purpleline_2015... · Constellation . Westwood/UCLA Westwood/VA Hospital . Pre-Construction Activities . Current - 2016 2015](https://reader034.fdocuments.in/reader034/viewer/2022050719/5f32b0077c45c5451b2e5af2/html5/thumbnails/8.jpg)
Crenshaw Yard Staging Site Wilshire/Crenshaw
• Used throughout Section 1 utility relocation and construction
• Mitigation efforts and maintenance:
– “Right Turn Only” signs at Lorraine Gate
– “No Metro Contractor Parking on City Street” signs
– Noise awareness training
– Nightly noise readings
– Maintenance inside and outside of yard
8 Signage at the Crenshaw Yard
![Page 9: Purple Line Extensionmedia.metro.net/.../presentation_purpleline_2015... · Constellation . Westwood/UCLA Westwood/VA Hospital . Pre-Construction Activities . Current - 2016 2015](https://reader034.fdocuments.in/reader034/viewer/2022050719/5f32b0077c45c5451b2e5af2/html5/thumbnails/9.jpg)
La Brea Station
Rendering shows length of the La Brea underground station box on Wilshire Blvd from Orange Dr to Detroit St
9
![Page 10: Purple Line Extensionmedia.metro.net/.../presentation_purpleline_2015... · Constellation . Westwood/UCLA Westwood/VA Hospital . Pre-Construction Activities . Current - 2016 2015](https://reader034.fdocuments.in/reader034/viewer/2022050719/5f32b0077c45c5451b2e5af2/html5/thumbnails/10.jpg)
La Brea Station Construction
LADWP Electrical Duct Bank Work • Currently underway on NE corner of Wilshire
and La Brea, 8pm to 6am, Sunday thru Thursday
• Anticipated completion date September 30th
Pothole Work (Underground Utility Investigation) • September 14 thru October 23rd • Orange Dr to Detroit St
• Daytime: 9:00am to 3:30pm • Nighttime: 8:00pm to 6:00am
Sewer/Storm Drain • October 4 thru Oct 25 • Nightime: 8:00pm to 6:00am
10
LADWP Electrical Duct bank Work
![Page 11: Purple Line Extensionmedia.metro.net/.../presentation_purpleline_2015... · Constellation . Westwood/UCLA Westwood/VA Hospital . Pre-Construction Activities . Current - 2016 2015](https://reader034.fdocuments.in/reader034/viewer/2022050719/5f32b0077c45c5451b2e5af2/html5/thumbnails/11.jpg)
• Completed demolition of former Metro Customer Service Center, Blockbuster and Lawrence of La Brea buildings
• Sound wall construction underway • Daytime operation: 7am to 4pm
• Work began August 28th and will continue until October 29th
• Sound wall will be 20 feet high
La Brea Station North La Brea Staging Yard
11
Demolition of Buildings at N La Brea Staging Yard
Construction of Noise Barrier around yard
![Page 12: Purple Line Extensionmedia.metro.net/.../presentation_purpleline_2015... · Constellation . Westwood/UCLA Westwood/VA Hospital . Pre-Construction Activities . Current - 2016 2015](https://reader034.fdocuments.in/reader034/viewer/2022050719/5f32b0077c45c5451b2e5af2/html5/thumbnails/12.jpg)
• Demolition of former Bank of America Property Completed
• Metro acquired adjacent property on the southeast corner of Wilshire/Detroit end of August.
– Abatement activities underway
– 7am-4pm, Monday thru Friday
– Demolition of buildings anticipated to begin in October
• Future South La Brea Staging Yard – Sound wall construction anticipated to begin in
October.
La Brea Station South La Brea Staging Yard
12
![Page 13: Purple Line Extensionmedia.metro.net/.../presentation_purpleline_2015... · Constellation . Westwood/UCLA Westwood/VA Hospital . Pre-Construction Activities . Current - 2016 2015](https://reader034.fdocuments.in/reader034/viewer/2022050719/5f32b0077c45c5451b2e5af2/html5/thumbnails/13.jpg)
• Demolition of former Bank of America Property completed
• Metro acquired adjacent property on the southeast corner of Wilshire/Detroit end of August.
La Brea Station South La Brea Staging Yard
13
Demolition of Buildings at S La Brea Staging Yard
Abatement work currently underway at former business buildings on SE corner of Wilshire/ Detroit
![Page 14: Purple Line Extensionmedia.metro.net/.../presentation_purpleline_2015... · Constellation . Westwood/UCLA Westwood/VA Hospital . Pre-Construction Activities . Current - 2016 2015](https://reader034.fdocuments.in/reader034/viewer/2022050719/5f32b0077c45c5451b2e5af2/html5/thumbnails/14.jpg)
La Brea Station Mitigation
14
Noise Blankets during nighttime Ductbank work at NE corner of Wilshire and La Brea
Design of Sound Wall for N/S La Brea yards
Crenshaw Staging Yard Maintenance
![Page 15: Purple Line Extensionmedia.metro.net/.../presentation_purpleline_2015... · Constellation . Westwood/UCLA Westwood/VA Hospital . Pre-Construction Activities . Current - 2016 2015](https://reader034.fdocuments.in/reader034/viewer/2022050719/5f32b0077c45c5451b2e5af2/html5/thumbnails/15.jpg)
La Brea Tree Removal
• La Brea Tree removal begins end of September
• 16 trees will be removed in medians
• 6 Sidewalk Trees removed and relocated
– 4 Trees relocated to Crenshaw Staging Yard
– 2 Trees relocated to LAPD Wilshire Division
• Trees posted for removal May 9, 2015
• Board of Public Works approved Tree removal plan July 22, 2015
• Tree removal schedule
– Fairfax: summer 2016
– La Cienega: late 2016
• End of project trees will be replaced 2:1
15
Trees being removed at median located on Wilshire between La Brea and Detroit
![Page 16: Purple Line Extensionmedia.metro.net/.../presentation_purpleline_2015... · Constellation . Westwood/UCLA Westwood/VA Hospital . Pre-Construction Activities . Current - 2016 2015](https://reader034.fdocuments.in/reader034/viewer/2022050719/5f32b0077c45c5451b2e5af2/html5/thumbnails/16.jpg)
La Brea Median Removal
16
Median on Wilshire between Sycamore and La Brea
Median on Wilshire between La Brea and Detroit
October 2015
• 3 medians removed on Wilshire between Sycamore and Cloverdale
• Medians returned after project completion with landscape
• Work required to reconfigure Wilshire to 2 lanes in each direction for pile drilling operations
Median on Wilshire between Detroit and Cloverdale
![Page 17: Purple Line Extensionmedia.metro.net/.../presentation_purpleline_2015... · Constellation . Westwood/UCLA Westwood/VA Hospital . Pre-Construction Activities . Current - 2016 2015](https://reader034.fdocuments.in/reader034/viewer/2022050719/5f32b0077c45c5451b2e5af2/html5/thumbnails/17.jpg)
La Brea Station Pile Installation
17
November 2015 through Summer 2016*
• First major construction activity of subway at La Brea.
• Length of pile installation will be on Wilshire from Orange Dr. to Detroit St.
• Pile installation includes:
– Rig to construct 95ft (L) deep hole on 7 center to center spacing
– Crane lifting 95Ft (L) , 24 Inch H-piles into holes
– 1-2 piles per day, 390 piles total
– Drilling, pile installation and backfilled concrete completed same day
• All work occurs behind a k-rail.
• Operation anticipated to take approximately 4-6 months on each side of the street.
• Typical works hours 7am-11pm.
• Wilshire will be reduced to two lanes each way during construction.
*dates subject to change
![Page 18: Purple Line Extensionmedia.metro.net/.../presentation_purpleline_2015... · Constellation . Westwood/UCLA Westwood/VA Hospital . Pre-Construction Activities . Current - 2016 2015](https://reader034.fdocuments.in/reader034/viewer/2022050719/5f32b0077c45c5451b2e5af2/html5/thumbnails/18.jpg)
La Brea Station Pile Installation
18
• Wilshire Reconfiguration, Cloverdale to Mansfield
• 2 lane westbound Wilshire, 2 lanes eastbound Wilshire
• No medians, no parking on Wilshire
![Page 19: Purple Line Extensionmedia.metro.net/.../presentation_purpleline_2015... · Constellation . Westwood/UCLA Westwood/VA Hospital . Pre-Construction Activities . Current - 2016 2015](https://reader034.fdocuments.in/reader034/viewer/2022050719/5f32b0077c45c5451b2e5af2/html5/thumbnails/19.jpg)
La Brea Station Pile Installation
19
![Page 20: Purple Line Extensionmedia.metro.net/.../presentation_purpleline_2015... · Constellation . Westwood/UCLA Westwood/VA Hospital . Pre-Construction Activities . Current - 2016 2015](https://reader034.fdocuments.in/reader034/viewer/2022050719/5f32b0077c45c5451b2e5af2/html5/thumbnails/20.jpg)
La Brea Station Decking Layout
20
• Green: Hard closures at Highland and La Brea
• 7 full weeks OR • 16 weekends
• Purple: Hard closure at La Brea and Detroit
• 3 weekends, Detroit to La Brea
• 3 weekends, La Brea intersection
*Dates subject to change
![Page 21: Purple Line Extensionmedia.metro.net/.../presentation_purpleline_2015... · Constellation . Westwood/UCLA Westwood/VA Hospital . Pre-Construction Activities . Current - 2016 2015](https://reader034.fdocuments.in/reader034/viewer/2022050719/5f32b0077c45c5451b2e5af2/html5/thumbnails/21.jpg)
La Brea Station Decking Options
Decking • Construction of a concrete deck, curb to curb on Wilshire, between
Orange Dr and Detroit St.
• After concrete panels are installed, traffic can travel over the surface while the station is constructed underground.
• Will follow pile operations; anticipated spring 2016
Option 1* • 7 week full closure of Wilshire, from Highland and La Brea
– 7 days a week, 7am-11pm above deck, 11pm-7am below deck
– 15 Nights of work
• 6 weekend closures La Brea to Detroit
– 9pm Friday thru 6am Monday, work continuous
Option 2* • Approximately 22 weekend closures
– 9pm Friday thru 6am Monday, work continuous
– 66 Nights of work
21 Have a preferred option? Send comments to [email protected], Subject: Decking Options
*Dates subject to change
![Page 22: Purple Line Extensionmedia.metro.net/.../presentation_purpleline_2015... · Constellation . Westwood/UCLA Westwood/VA Hospital . Pre-Construction Activities . Current - 2016 2015](https://reader034.fdocuments.in/reader034/viewer/2022050719/5f32b0077c45c5451b2e5af2/html5/thumbnails/22.jpg)
La Brea Station Decking
22
Early detours: South on Crenshaw, west on Olympic, north on La Brea Detour at hard closure: South on Highland, west on Olympic, north on La Brea
![Page 23: Purple Line Extensionmedia.metro.net/.../presentation_purpleline_2015... · Constellation . Westwood/UCLA Westwood/VA Hospital . Pre-Construction Activities . Current - 2016 2015](https://reader034.fdocuments.in/reader034/viewer/2022050719/5f32b0077c45c5451b2e5af2/html5/thumbnails/23.jpg)
La Brea Station Decking
23
• Work Area: Wilshire Blvd from Orange Dr to Detroit St Driveway Access Maintained to Businesses and Residents
![Page 24: Purple Line Extensionmedia.metro.net/.../presentation_purpleline_2015... · Constellation . Westwood/UCLA Westwood/VA Hospital . Pre-Construction Activities . Current - 2016 2015](https://reader034.fdocuments.in/reader034/viewer/2022050719/5f32b0077c45c5451b2e5af2/html5/thumbnails/24.jpg)
La Brea Station Decking Decking Photos from Crenshaw/LAX project
24
![Page 25: Purple Line Extensionmedia.metro.net/.../presentation_purpleline_2015... · Constellation . Westwood/UCLA Westwood/VA Hospital . Pre-Construction Activities . Current - 2016 2015](https://reader034.fdocuments.in/reader034/viewer/2022050719/5f32b0077c45c5451b2e5af2/html5/thumbnails/25.jpg)
La Brea Station Decking Community Outreach
25
• Marketing Campaign • Social Media: Facebook, Twitter • Advertising: Newspapers, radio • Media Coverage: Press Release, event • Business and resident outreach
• Meetings with local groups, leaders • Elected Official Briefings • Safety Presentations • School Presentations • Community Partnerships
I-405 Freeway Closure “Carmageddon”
![Page 26: Purple Line Extensionmedia.metro.net/.../presentation_purpleline_2015... · Constellation . Westwood/UCLA Westwood/VA Hospital . Pre-Construction Activities . Current - 2016 2015](https://reader034.fdocuments.in/reader034/viewer/2022050719/5f32b0077c45c5451b2e5af2/html5/thumbnails/26.jpg)
La Brea Station Decking Process of Determination
• August/September: Outreach started directly to businesses and residents, La Brea to Highland
• September 17-November 11: Outreach continues to businesses and residents
• November 12: Next Construction Community Meeting – Will make determination by this meeting
• If approved, November - March 2016: Contractor and Metro work to get approvals from
– City Council Member Ryu, CD4
– LA Department of Transportation
– LA Bureau of Engineering
– Board of Public Works
Have a preferred option? Send comments to [email protected], Subject: Decking Options
26
![Page 27: Purple Line Extensionmedia.metro.net/.../presentation_purpleline_2015... · Constellation . Westwood/UCLA Westwood/VA Hospital . Pre-Construction Activities . Current - 2016 2015](https://reader034.fdocuments.in/reader034/viewer/2022050719/5f32b0077c45c5451b2e5af2/html5/thumbnails/27.jpg)
Detours: Wilshire Full Closure
27
• LADOT approves all detour routes for each construction activity
• Will avoid local streets • Proposed detours
• South to Olympic • North to 3rd Street.
LADOT Dash Map
• Bus lines that use Wilshire between Fairfax and La Brea • Metro 720 • Metro 20 • LADOT Dash Fairfax • Antelope Valley Transit (AVT)
• No buses use 8th currently • DASH uses 6th
![Page 28: Purple Line Extensionmedia.metro.net/.../presentation_purpleline_2015... · Constellation . Westwood/UCLA Westwood/VA Hospital . Pre-Construction Activities . Current - 2016 2015](https://reader034.fdocuments.in/reader034/viewer/2022050719/5f32b0077c45c5451b2e5af2/html5/thumbnails/28.jpg)
Parking Utilization Study
• La Brea Utilization study completed
– Investigated from Highland to Ridgeley, 6th to 8th
• Station located in Miracle Mile
– High demand for parking on and off-street
– Several Preferred Parking Districts
• Examined parking utilization rate of existing parking spaces
• Determined initial additional spaces needed for Parking Management Plan
28
![Page 29: Purple Line Extensionmedia.metro.net/.../presentation_purpleline_2015... · Constellation . Westwood/UCLA Westwood/VA Hospital . Pre-Construction Activities . Current - 2016 2015](https://reader034.fdocuments.in/reader034/viewer/2022050719/5f32b0077c45c5451b2e5af2/html5/thumbnails/29.jpg)
Parking Relocation
Proposed Parking Replacement Plan
• Turn 2 way street into 1 way street
– Removes parallel parking on one side
– Replaces one side with angled parking
• Current prospects: Cloverdale and Ridgeley
• Will remain 2 way street up to public parking lots. After lots, northbound one way street from Wilshire to 6th
• Requires 2/3 approval by building owners/managers of both sides of each street
• Meeting with residents/owners August 20, 2015
• Overall opinion: NOT SUPPORTED
• Metro evaluating EIR for any further parking requirements
29
![Page 30: Purple Line Extensionmedia.metro.net/.../presentation_purpleline_2015... · Constellation . Westwood/UCLA Westwood/VA Hospital . Pre-Construction Activities . Current - 2016 2015](https://reader034.fdocuments.in/reader034/viewer/2022050719/5f32b0077c45c5451b2e5af2/html5/thumbnails/30.jpg)
Fairfax Station
Rendering shows length of the Fairfax underground station box on Wilshire Blvd from west of Fairfax to just west of Ogden Dr.
30
![Page 31: Purple Line Extensionmedia.metro.net/.../presentation_purpleline_2015... · Constellation . Westwood/UCLA Westwood/VA Hospital . Pre-Construction Activities . Current - 2016 2015](https://reader034.fdocuments.in/reader034/viewer/2022050719/5f32b0077c45c5451b2e5af2/html5/thumbnails/31.jpg)
Fairfax Station Construction
Metro Advanced Utility Relocation (AUR) Work
• Electrical, water and gas work continues
• Work Hours:
Day work:
o Monday thru Friday: 9am-3:30pm
o Saturday: 8am-6pm
Night work:
o Sunday thru Thursday: 8pm-6am
o Friday: 10pm-8am
31
Photos of recent AUR work for Fairfax Station
Photos of recent AUR work at Wilshire/Fairfax
![Page 32: Purple Line Extensionmedia.metro.net/.../presentation_purpleline_2015... · Constellation . Westwood/UCLA Westwood/VA Hospital . Pre-Construction Activities . Current - 2016 2015](https://reader034.fdocuments.in/reader034/viewer/2022050719/5f32b0077c45c5451b2e5af2/html5/thumbnails/32.jpg)
Fairfax Utility Relocation 2 Years *Schedule is subject to change. Updated as of July 2015.
32
![Page 33: Purple Line Extensionmedia.metro.net/.../presentation_purpleline_2015... · Constellation . Westwood/UCLA Westwood/VA Hospital . Pre-Construction Activities . Current - 2016 2015](https://reader034.fdocuments.in/reader034/viewer/2022050719/5f32b0077c45c5451b2e5af2/html5/thumbnails/33.jpg)
Fairfax Station Mitigation
• Noisy activities re-scheduled from night to day work or to be completed by 11 p.m. Activities are monitored throughout each shift.
• Torch cutters used in place of traditional plate cutters.
• Sound blankets shifted and additional blankets added when needed.
• Low impact back up alarms installed on mobile equipment for night work.
• Battery powered (solar charged) lights eliminate noise from generators.
33 Photos of noise mitigation at Wilshire/Fairfax
![Page 34: Purple Line Extensionmedia.metro.net/.../presentation_purpleline_2015... · Constellation . Westwood/UCLA Westwood/VA Hospital . Pre-Construction Activities . Current - 2016 2015](https://reader034.fdocuments.in/reader034/viewer/2022050719/5f32b0077c45c5451b2e5af2/html5/thumbnails/34.jpg)
Fairfax Station Ogden Staging Yard
• Buildings on Wilshire at Ogden and Orange Grove have been abated.
• Future Ogden Staging Yard
Next Steps:
• Demo anticipated
end of October 2015
34 Buildings at 6010-6030 Wilshire
![Page 35: Purple Line Extensionmedia.metro.net/.../presentation_purpleline_2015... · Constellation . Westwood/UCLA Westwood/VA Hospital . Pre-Construction Activities . Current - 2016 2015](https://reader034.fdocuments.in/reader034/viewer/2022050719/5f32b0077c45c5451b2e5af2/html5/thumbnails/35.jpg)
Fairfax Station North Fairfax Staging Yard • North Fairfax Staging Yard
• Demolition of Marinello building
– Scheduled to begin Sept 21- October 19
– Work hours: 7am-4pm
• Temporary re-routing of the adjacent alley at Wilshire required
– Deliveries will be maintained to 99cent store
– Work hours: 9am-4pm
35
Johnnies
![Page 36: Purple Line Extensionmedia.metro.net/.../presentation_purpleline_2015... · Constellation . Westwood/UCLA Westwood/VA Hospital . Pre-Construction Activities . Current - 2016 2015](https://reader034.fdocuments.in/reader034/viewer/2022050719/5f32b0077c45c5451b2e5af2/html5/thumbnails/36.jpg)
Fairfax Station Fairfax Coordinated Construction Projects (FCCP)
Multiple construction projects are underway within a 3 block radius of Wilshire and Fairfax.
• Metro Purple Line Extension
• The Petersen Automotive Museum
• The Academy of Motion Pictures Arts and Science
• Alliance residential and commercial
The FCCP committee members meet every 2 months to discuss and review the specifics of local construction relating to timelines and coordinated traffic control as a continuing effort to reduce the impact on the community.
36
Buildings at 6010-6030 Wilshire
![Page 37: Purple Line Extensionmedia.metro.net/.../presentation_purpleline_2015... · Constellation . Westwood/UCLA Westwood/VA Hospital . Pre-Construction Activities . Current - 2016 2015](https://reader034.fdocuments.in/reader034/viewer/2022050719/5f32b0077c45c5451b2e5af2/html5/thumbnails/37.jpg)
La Cienega Station
Rendering shows length of the La Cienega underground station box on Wilshire Blvd from La Cienega to Tower Dr.
37
![Page 38: Purple Line Extensionmedia.metro.net/.../presentation_purpleline_2015... · Constellation . Westwood/UCLA Westwood/VA Hospital . Pre-Construction Activities . Current - 2016 2015](https://reader034.fdocuments.in/reader034/viewer/2022050719/5f32b0077c45c5451b2e5af2/html5/thumbnails/38.jpg)
La Cienega Station Construction
Metro Advanced Utility Relocation (AUR) Work
• Electrical, sewer and telecommunication work continues from La Cienega to San Vicente and on La Cienega north of Wilshire
Photo of recent AUR work for the La Cienega Station
38
![Page 39: Purple Line Extensionmedia.metro.net/.../presentation_purpleline_2015... · Constellation . Westwood/UCLA Westwood/VA Hospital . Pre-Construction Activities . Current - 2016 2015](https://reader034.fdocuments.in/reader034/viewer/2022050719/5f32b0077c45c5451b2e5af2/html5/thumbnails/39.jpg)
La Cienega Utility Relocation 30 Months *Schedule is subject to change. Last updated September 2015
39
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
AT&T
2017
Fiber
Gas
AT&T
Water, Sewer, Storm Drain and Power
Fiber
2014 2015 2016
![Page 40: Purple Line Extensionmedia.metro.net/.../presentation_purpleline_2015... · Constellation . Westwood/UCLA Westwood/VA Hospital . Pre-Construction Activities . Current - 2016 2015](https://reader034.fdocuments.in/reader034/viewer/2022050719/5f32b0077c45c5451b2e5af2/html5/thumbnails/40.jpg)
La Cienega Station What’s Next
April through December 2015
• AUR activities occur mostly during daytime hours.
• Days and Hours o Monday thru Friday: 7am – 4pm
o Saturday or Sunday: 8am – 6pm
o Night Time Hours:
• 8pm – 6am or
• 1am – 9am
40
for La Cienega Station
![Page 41: Purple Line Extensionmedia.metro.net/.../presentation_purpleline_2015... · Constellation . Westwood/UCLA Westwood/VA Hospital . Pre-Construction Activities . Current - 2016 2015](https://reader034.fdocuments.in/reader034/viewer/2022050719/5f32b0077c45c5451b2e5af2/html5/thumbnails/41.jpg)
La Cienega Station Gale Staging Yard
• Recently acquired properties for future staging yard on Gale
• Abatement work at 111 N. Gale scheduled September 7- 18, 2105
– Work hours: 7am-3:30pm
41
![Page 42: Purple Line Extensionmedia.metro.net/.../presentation_purpleline_2015... · Constellation . Westwood/UCLA Westwood/VA Hospital . Pre-Construction Activities . Current - 2016 2015](https://reader034.fdocuments.in/reader034/viewer/2022050719/5f32b0077c45c5451b2e5af2/html5/thumbnails/42.jpg)
La Cienega Station What’s Next
• Future N La Cienega Staging Yard
• Abatement activities in progress for properties acquired
– Former Citibank
– Former Phoenix Restaurant
42
![Page 43: Purple Line Extensionmedia.metro.net/.../presentation_purpleline_2015... · Constellation . Westwood/UCLA Westwood/VA Hospital . Pre-Construction Activities . Current - 2016 2015](https://reader034.fdocuments.in/reader034/viewer/2022050719/5f32b0077c45c5451b2e5af2/html5/thumbnails/43.jpg)
Weekend Directional Closures Wilshire, La Cienega to San Vicente
43
• 7 weekends total
• September 11-12 complete!
• This weekend: Friday at 10pm through Sunday, Sept 20 at 6pm
• 5 more weekends through October 24, 2015
• Directional closures (either full EB or WB Wilshire), between La Cienega to San Vicente
• Days and Hours
o Start: Friday 10pm or 1am*
o End: Sunday by 6pm *start time depends on the Saban Theatre performance schedule
Detours: • EB Wilshire closed at La Cienega:
Detour NB La Cienega, SB San Vicente, EB Wilshire
• WB Wilshire: One lane open from San Vicente to La Cienega.
• NB San Vicente left turn to WB Wilshire: Closed
![Page 44: Purple Line Extensionmedia.metro.net/.../presentation_purpleline_2015... · Constellation . Westwood/UCLA Westwood/VA Hospital . Pre-Construction Activities . Current - 2016 2015](https://reader034.fdocuments.in/reader034/viewer/2022050719/5f32b0077c45c5451b2e5af2/html5/thumbnails/44.jpg)
44
Eat, Shop, Play Wilshire Lunch Meet-up at Hill Bar & Grill
• On September 1, we held our 2nd #espWilshire Lunch Meet-up at The Hill Bar & Grill, a locally-owned restaurant located diagonally across the street from the future La Cienega Station. 45 diners attended to show their support for EAT, SHOP, PLAY Wilshire.
– Address: 8442 Wilshire Blvd. Beverly Hills, CA 90211
– For more info visit: www.thehillbarandgrill.net
![Page 45: Purple Line Extensionmedia.metro.net/.../presentation_purpleline_2015... · Constellation . Westwood/UCLA Westwood/VA Hospital . Pre-Construction Activities . Current - 2016 2015](https://reader034.fdocuments.in/reader034/viewer/2022050719/5f32b0077c45c5451b2e5af2/html5/thumbnails/45.jpg)
45
Eat, Shop, Play Wilshire Vendor Day
Zimmer Children’s Museum
Vendor Day, Thursday, August 20th (Gateway Lobby) The Zimmer is designed for children 8 & under, this museum boasts hands-on exhibits and frequent family programs.
6505 Wilshire Blvd. , Los Angeles, 90048
More info: http://www.metro.net/service/discounts/esp-purple-line/zimmer-childrens-museum/
Dysonna City Art Gallery Vendor Day, Thursday, July 10th (Union Station) • Dysonna City Art Gallery presents new and experienced artist
from across the United States. All types of art are featured every month from abstract to figurative fine art to photography. The Gallery also has special events, painting classes and so much more.
• Address: 5373 Wilshire Blvd, Los Angeles, 90036 • More Info: http://www.metro.net/service/discounts/esp-purple-
line/dysonna-city-art-gallery/
![Page 46: Purple Line Extensionmedia.metro.net/.../presentation_purpleline_2015... · Constellation . Westwood/UCLA Westwood/VA Hospital . Pre-Construction Activities . Current - 2016 2015](https://reader034.fdocuments.in/reader034/viewer/2022050719/5f32b0077c45c5451b2e5af2/html5/thumbnails/46.jpg)
46
Eat, Shop, Play Wilshire Candela Taco Bar and Grill
Candela Taco Bar & Lounge serves over 15 types of tacos, entrees and delicious drinks. They also have Tango Night Tuesdays starting at 7 p.m. and $1 taco night every Wednesday. There’s also a private event space for up to 600 guests. Mention “Metro” or “Purple Line Extension” and receive 20% off an appetizer.
– Address: 831 South La Brea, Los Angeles, CA 90036
– For more info visit: http://www.metro.net/service/discounts/esp-purple-line/candela-taco-bar-lounge/
![Page 47: Purple Line Extensionmedia.metro.net/.../presentation_purpleline_2015... · Constellation . Westwood/UCLA Westwood/VA Hospital . Pre-Construction Activities . Current - 2016 2015](https://reader034.fdocuments.in/reader034/viewer/2022050719/5f32b0077c45c5451b2e5af2/html5/thumbnails/47.jpg)
47
Eat, Shop, Play Wilshire ESP Spotlight LACMA
GO METRO: and receive $2.00 discount on general admission Info: http://www.metro.net/service/discounts/esp-purple-line/lacma/
![Page 48: Purple Line Extensionmedia.metro.net/.../presentation_purpleline_2015... · Constellation . Westwood/UCLA Westwood/VA Hospital . Pre-Construction Activities . Current - 2016 2015](https://reader034.fdocuments.in/reader034/viewer/2022050719/5f32b0077c45c5451b2e5af2/html5/thumbnails/48.jpg)
48
Eat, Shop, Play Wilshire Speedy Computer Center
• Speedy Computer Center is a neighborhood computer center that provides on-site services, usually within 2 hours of your call or a technician can be sent to your home, office and or business. Rates in store and on-site are reasonable and most repairs are same day service, some even while you wait.
– Address: 5217 Wilshire Blvd, Los Angeles, CA 90036
– For more info visit: http://www.metro.net/service/discounts/esp-purple-line/speedy-computer-center/
![Page 49: Purple Line Extensionmedia.metro.net/.../presentation_purpleline_2015... · Constellation . Westwood/UCLA Westwood/VA Hospital . Pre-Construction Activities . Current - 2016 2015](https://reader034.fdocuments.in/reader034/viewer/2022050719/5f32b0077c45c5451b2e5af2/html5/thumbnails/49.jpg)
How To Do Business With Metro Workshop
September 17, 2015
![Page 50: Purple Line Extensionmedia.metro.net/.../presentation_purpleline_2015... · Constellation . Westwood/UCLA Westwood/VA Hospital . Pre-Construction Activities . Current - 2016 2015](https://reader034.fdocuments.in/reader034/viewer/2022050719/5f32b0077c45c5451b2e5af2/html5/thumbnails/50.jpg)
DEOD’s Responsibilities Administer and oversee Gather data & generate reports Publicize contract opportunities Provide training and resources Set DBE/SBE/DVBE goals Monitor compliance
![Page 51: Purple Line Extensionmedia.metro.net/.../presentation_purpleline_2015... · Constellation . Westwood/UCLA Westwood/VA Hospital . Pre-Construction Activities . Current - 2016 2015](https://reader034.fdocuments.in/reader034/viewer/2022050719/5f32b0077c45c5451b2e5af2/html5/thumbnails/51.jpg)
About Metro Multimodal transportation agency 1) Operator of buses and rail 2) Transportation planning and programming agency 3) Construction agency of mobility related building projects
![Page 52: Purple Line Extensionmedia.metro.net/.../presentation_purpleline_2015... · Constellation . Westwood/UCLA Westwood/VA Hospital . Pre-Construction Activities . Current - 2016 2015](https://reader034.fdocuments.in/reader034/viewer/2022050719/5f32b0077c45c5451b2e5af2/html5/thumbnails/52.jpg)
What does that Mean? Largest public works programs in the country Dozen of projects $30 to $40 Billion over 30 years Metro is changing the urban landscape
![Page 53: Purple Line Extensionmedia.metro.net/.../presentation_purpleline_2015... · Constellation . Westwood/UCLA Westwood/VA Hospital . Pre-Construction Activities . Current - 2016 2015](https://reader034.fdocuments.in/reader034/viewer/2022050719/5f32b0077c45c5451b2e5af2/html5/thumbnails/53.jpg)
Why is that Important? Metro needs contractors to: Design & build projects Service & maintain existing projects and infrastructure Metro needs a LOT of: Prime contractors Small Business Enterprises (SBEs)
![Page 54: Purple Line Extensionmedia.metro.net/.../presentation_purpleline_2015... · Constellation . Westwood/UCLA Westwood/VA Hospital . Pre-Construction Activities . Current - 2016 2015](https://reader034.fdocuments.in/reader034/viewer/2022050719/5f32b0077c45c5451b2e5af2/html5/thumbnails/54.jpg)
Metro’s Commitment to Small Businesses Long history of support Values and encourages participation of small businesses We need you DEOD’s role
![Page 55: Purple Line Extensionmedia.metro.net/.../presentation_purpleline_2015... · Constellation . Westwood/UCLA Westwood/VA Hospital . Pre-Construction Activities . Current - 2016 2015](https://reader034.fdocuments.in/reader034/viewer/2022050719/5f32b0077c45c5451b2e5af2/html5/thumbnails/55.jpg)
DEOD’s Resources & Information DEOD website
6 Steps to Doing Business with Metro Small Business Programs Events Calendar Fact Sheets Certification Application Current & Future Solicitations Useful Links Today’s Presentation
metro.net/connect
![Page 56: Purple Line Extensionmedia.metro.net/.../presentation_purpleline_2015... · Constellation . Westwood/UCLA Westwood/VA Hospital . Pre-Construction Activities . Current - 2016 2015](https://reader034.fdocuments.in/reader034/viewer/2022050719/5f32b0077c45c5451b2e5af2/html5/thumbnails/56.jpg)
![Page 57: Purple Line Extensionmedia.metro.net/.../presentation_purpleline_2015... · Constellation . Westwood/UCLA Westwood/VA Hospital . Pre-Construction Activities . Current - 2016 2015](https://reader034.fdocuments.in/reader034/viewer/2022050719/5f32b0077c45c5451b2e5af2/html5/thumbnails/57.jpg)
BIF Introduction
• Metro’s Goal: Help small “mom and pop” businesses continue to thrive throughout construction and post construction.
• Financial assistance to small “mom and pop” businesses directly impacted by Metro transit rail construction along three project areas: – Regional Connector, Little Tokyo area
– Crenshaw/LAX Transit Project
– Metro Purple Line Extension, Phase 1
![Page 58: Purple Line Extensionmedia.metro.net/.../presentation_purpleline_2015... · Constellation . Westwood/UCLA Westwood/VA Hospital . Pre-Construction Activities . Current - 2016 2015](https://reader034.fdocuments.in/reader034/viewer/2022050719/5f32b0077c45c5451b2e5af2/html5/thumbnails/58.jpg)
BIF Eligibility Requirements
• Small “mom and pop” business with 25 or fewer total employees
• Businesses located immediately adjacent to the rail corridor and directly impacted by Metro construction
• For-profit business or non-religious, non-profit
• Continuous operation for at least 2 years along the corridor
• Must be a solvent business
• Must be able to produce relevant financial records demonstrating a loss of business revenue directly related to period of Metro’s construction disruption
• Must be in good standing with all local, state and federal taxing and licensing authorities
• Must meet all technical qualifications as outlined in Metro’s BIF Administrative Guidelines
![Page 59: Purple Line Extensionmedia.metro.net/.../presentation_purpleline_2015... · Constellation . Westwood/UCLA Westwood/VA Hospital . Pre-Construction Activities . Current - 2016 2015](https://reader034.fdocuments.in/reader034/viewer/2022050719/5f32b0077c45c5451b2e5af2/html5/thumbnails/59.jpg)
BIF Financial Threshold
• Financial threshold: The lesser total of amount of $50,000 or 60% of annual business revenue losses per business – Maximum annual per business not to exceed
$50,0000
• Covered fixed operating expenses: Utilities, Insurance, Rent/Mortgage, Payroll and Others upon review
Note: Special provisions exists for commercial property owners
![Page 60: Purple Line Extensionmedia.metro.net/.../presentation_purpleline_2015... · Constellation . Westwood/UCLA Westwood/VA Hospital . Pre-Construction Activities . Current - 2016 2015](https://reader034.fdocuments.in/reader034/viewer/2022050719/5f32b0077c45c5451b2e5af2/html5/thumbnails/60.jpg)
BIF Program Resources
> BIF Program Materials • Factsheet (take one) • 4 Step Easy Guide
> BIF Application • Online
• Paper (per request to PCR) • In person
> BIF Business Advisors > BIF Workshop Series
• Date: Wednesday, October 14, 2015 • Time: 11:30am – 12:30pm • Location: 5200 Wilshire Apartments *Refer to Metro’s BIF Workshop schedule for additional locations, dates and times
![Page 61: Purple Line Extensionmedia.metro.net/.../presentation_purpleline_2015... · Constellation . Westwood/UCLA Westwood/VA Hospital . Pre-Construction Activities . Current - 2016 2015](https://reader034.fdocuments.in/reader034/viewer/2022050719/5f32b0077c45c5451b2e5af2/html5/thumbnails/61.jpg)
BIF Workshop Series
Purple Line Extension, Phase 1 Wednesday, October 14, 2015 11:30am-12:30pm 5200 Wilshire Apartments Los Angeles, CA 90036 Community Room, 3rd Floor **Street parking only Regional Connector, Little Tokyo area Tuesday, November 10, 2015 10:30am-11:30am Little Tokyo Branch Library, L.A. Public Library 203 S. Los Angeles Street Los Angeles, CA 90012
Crenshaw/LAX Transit Project Corridor Wednesday, September 30, 2015 4:00pm-5:00pm Metro’s Business Solution Center (Co-located at the L.A. Urban League) 3450 Mount Vernon Drive Los Angeles, CA 90008 Tuesday, October 27, 2015 10:30am-11:30am Inglewood City Hall Community Room A, 9th Floor One Manchester Blvd. Inglewood, CA 90301
For additional infomration and to RSVP, please email Adriana Hernandez at [email protected] or call (213) 922-2614.
![Page 62: Purple Line Extensionmedia.metro.net/.../presentation_purpleline_2015... · Constellation . Westwood/UCLA Westwood/VA Hospital . Pre-Construction Activities . Current - 2016 2015](https://reader034.fdocuments.in/reader034/viewer/2022050719/5f32b0077c45c5451b2e5af2/html5/thumbnails/62.jpg)
BIF Fund Administrator
Pacific Coast Regional, Small Business Development Corp. (PCR)
Angela Winston
Vice President & Program Manager
3255 Wilshire Blvd., Suite 1501
Los Angeles, CA 90010
(213)739-2999 ext. 223
www.pcrcorp.org
![Page 63: Purple Line Extensionmedia.metro.net/.../presentation_purpleline_2015... · Constellation . Westwood/UCLA Westwood/VA Hospital . Pre-Construction Activities . Current - 2016 2015](https://reader034.fdocuments.in/reader034/viewer/2022050719/5f32b0077c45c5451b2e5af2/html5/thumbnails/63.jpg)
Future Community Meetings
• Next Section 1 Community Meeting: November 12, 2015 at John Burroughs Middle School Auditorium, 600 S. McCadden Pl.
• Community Meetings held on the 3rd Thursday of every other month
(except November, which is the 2nd Thursday of the month due to Thanksgiving)
– Community Meeting location will rotate along the alignment
– Section 1 Advisory Group will meet as needed to discuss station specific issues. Meetings will be open to the public.
• Sign up for the newsletter to receive project updates!
63
![Page 64: Purple Line Extensionmedia.metro.net/.../presentation_purpleline_2015... · Constellation . Westwood/UCLA Westwood/VA Hospital . Pre-Construction Activities . Current - 2016 2015](https://reader034.fdocuments.in/reader034/viewer/2022050719/5f32b0077c45c5451b2e5af2/html5/thumbnails/64.jpg)
Stay in Touch
www.metro.net/purplelineext
twitter.com/purplelineext
facebook.com/purplelineext
213.922.6934
64