Puesta Del Sol II Progress and Update Report May, June, & July, 2000

description

Puesta Del Sol II. Progress and Update Report May, June, & July, 2000. Side View. Top View. The Stainless Steel Ladder $2,100 US. Guards uniforms & security. Uniform Hat Days.......Rafael Nights.....Tolentino Sundays.. Rafael Tolentino Luis. - PowerPoint PPT Presentation

Transcript of Puesta Del Sol II

Page 1: Puesta Del Sol II

Puesta Del Sol II

Progress and Update Report

May, June, & July, 2000

Page 2: Puesta Del Sol II

The Stainless Steel Ladder $2,100 US

Side View Top View

Page 3: Puesta Del Sol II

Guards uniforms & security

Uniform Hat Days.......Rafael Nights.....Tolentino Sundays..

Rafael

Tolentino

Luis

Page 4: Puesta Del Sol II

No Glass Containers

Page 5: Puesta Del Sol II

Pool Maintenance

Pressure wash monthly

Ordered 5 new lightsOrdered tile to fix

small damaged tilesTo regrout in

September

Page 6: Puesta Del Sol II

Wind Turbines

Installed 4 Wind Turbines on sewer vents

Act as wind powered extractors creating a negative pressure on sewer vents

Reduce odor on windy days in the condos

Page 7: Puesta Del Sol II

AC Leak on Roof.....7 South

Page 8: Puesta Del Sol II

Leaking roof 7 North

Old leak coming through AC plumbing

Fiberglassed panels on roof and side

To do similar work on South side to prevent future leak

Page 9: Puesta Del Sol II

Attic Tour...TV....OTIS

Page 10: Puesta Del Sol II

Water Meters ......16 installed

Page 11: Puesta Del Sol II

Spiral Stairs to be repainted

Page 12: Puesta Del Sol II

The Box on the side

Page 13: Puesta Del Sol II

September 16 to 23....closed

POOL AREA regrout pool replace pool lights replace glass install barrier I and II install Jacuzzi pump rewire pool room

BUILDING• clean cistern• replumb water pump• elevator, tile floor. paint

shaft. & cable repairs• paint spiral stairs• general cleaning &

painting