Public Spending Code Quality Assurance Report 2016 Cork … · 2018-03-13 · Cork County Council-...
Transcript of Public Spending Code Quality Assurance Report 2016 Cork … · 2018-03-13 · Cork County Council-...
Public Spending Code Quality Assurance Report 2016
Cork County Council
For submission to the National Oversight and Audit Commission in compliance with the Public Spending Code.
Cork County Council- Public Spending Code Quality Assurance Report 2016
2
Cork County Council- Public Spending Code Quality Assurance Report 2016
3
Cork County Council- Public Spending Code Quality Assurance Report 2016
4
Cork County Council- Public Spending Code Quality Assurance Report 2016
5
Contents
Introduction 7
Step 1 - Project Inventory 8
Step 2 – Summary Information of Procurement >10m Euro 15
Step 3 – Public Spending Code Checklists 16
Step 4 – In depth project checks 30
Step 5 – Summary Report 57
Cork County Council- Public Spending Code Quality Assurance Report 2016
6
Cork County Council- Public Spending Code Quality Assurance Report 2016
7
Introduction
Cork County Council has completed this Quality Assurance Report as part of its on-going Public Spending Code compliance.
The Public Spending Code aims to ensure that the state achieves value for money in the use of all public funds. This
Quality Assurance Report gauges whether Cork County Council meets these aims.
This Quality Assurance process contains 5 steps
1. An inventory of projects/programmes at the different stages of the Project Life Cycle
2. Online publication of procurement information relative to projects in excess of 10million Euro. Specifically those in
progress or completed in the year under review.
3. Complete checklist relative to different Capital and Current expenditure programs stages
4. In-depth check on a number of projects/programmes 5. Summary Report
Cork County Council- Public Spending Code Quality Assurance Report 2016
8
Step 1 - Project/Programme Inventory
This inventory reflects all of Cork County Councils Capital and Current Expenditure based Programmes/Projects in excess
of >€500,000 for the reporting period.
Please note the following
CCC’s Annual Capital Programme, Annual Budget and AFS informs this inventory
No new Current (Revenue) Expenditure projects are under development or have ended in this reporting period.
All Current (Revenue) expenditure includes pay.
Certain current Revenue and Capital projects are aggregates of numerous smaller projects or multiyear projects
(denoted by asterisk). These are included in the inventory because the overall project exceeds >500,000 euro even
though some spending falls outside the reporting period.
The inventory excludes Water Capital projects as IW oversees same (albeit with CCC as an agent).
Cork County Council- Public Spending Code Quality Assurance Report 2016
9
Cork County Council Expenditure being considered Expenditure being incurred >.5m Expenditure recently ended >.5m
Current >.5m Cap. Grt >.5m Cap. Proj <5m Cap. Proj 5-20m Cap. Proj >20m Current >.5m€
Cap.Grt Scheme Cap. Proj>.5m
Current >.5m€
Cap.Grt Scheme Cap. Proj>.5m
LIHAF works A-Housing & Building € 27,333,330
Single House Acquisitions 2017-2019* A-Housing & Building € 25,000,000
RAS Programme A-Housing & Building € 5,163,199 € 8,880,119
Energy Efficiency NSW 2016-2018* A-Housing & Building € 13,000,000
Clonakilty (Beechgrove) Social Housing A-Housing & Building € 11,864,318
Carrigaline (Kilnagleary) Social Housing A-Housing & Building € 9,829,700
LA Housing Units Maintenance and Improvement A-Housing & Building € 7,934,047
Ballincollig (Poulavone) Social Housing A-Housing & Building € 7,735,000
Ballincollig (Town Centre) Turnkey 30 units (Phase 1) A-Housing & Building € 7,735,000
Bantry Turnkey Housing A-Housing & Building € 6,268,000
Housing Grant Service A-Housing & Building € 5,616,791 € 5,616,791
Housing Capital Programme Support A-Housing & Building € 5,422,489
Cobh Carrignafoy Social Housing A-Housing & Building € 5,131,824
Cobh Turnkey - College Manor A-Housing & Building € 5,131,824.00
Kanturk (Greenane) Part V Affordable (Phase 2) A-Housing & Building € 5,082,000
Passage West Social HousingTurnkey A-Housing & Building € 4,670,000.00
Dunmanway Kearneys Field A-Housing & Building € 4,528,000
Voluntary Housing Scheme A-Housing & Building € 4,428,751
Disabled Person Grant Improvements (on CCC houses) (2016-2018) A-Housing & Building € 4,000,000
Repossessed Houses A-Housing & Building € 3,750,000
Capital Assistance Scheme Renovations Sheltered Housing 2016-2018* A-Housing & Building € 3,590,448
Kanturk Bluepool Infill Scheme A-Housing & Building € 3,182,000
Housing Assessment, Allocation & Transfer Service A-Housing & Building € 514,083 € 2,216,547
Housing Loans A-Housing & Building € 2,563,245
Fermoy Duntahane Social Housing A-Housing & Building € 2,268,125
Courtmacsharry Social Housing A-Housing & Building € 2,000,000
Bantry (Convent Site) Housing A-Housing & Building € 2,000,000
Housing Rent & TP Service A-Housing & Building € 1,946,811
Hazelwood/Glanmire Improvement Scheme A-Housing & Building € 1,900,000
Cloyne (Spittal) Phase 2 A-Housing & Building € 1,859,000
Mortgage to Rent Scheme A-Housing & Building € 1,800,000
Macroom (Masseytown) Social Housing (Phase 2) A-Housing & Building € 1,467,954
Rosscarbery CAS Townlands A-Housing & Building € 1,331,018
Void Refurbishment Programme 2016-18* A-Housing & Building € 1,220,000
Bandon CAS 9 units A-Housing & Building € 1,115,014.00
Macroom (Masseytown) Social Housing (Phase 1) A-Housing & Building € 1,100,000.00
Cork County Council- Public Spending Code Quality Assurance Report 2016
10
Cork County Council Expenditure being considered Expenditure being incurred >.5m Expenditure recently ended >.5m
Current >.5m Cap. Grt >.5m Cap. Proj <5m Cap. Proj 5-20m Cap. Proj >20m Current >.5m€
Cap.Grt Scheme Cap. Proj>.5m
Current >.5m€
Cap.Grt Scheme Cap. Proj>.5m
Mitchelstown Stag Park A-Housing & Building € 1,068,000
Ordinary Social Housing Scheme AIB 10 Properties A-Housing & Building € 1,058,500.00
Part V Housing South A-Housing & Building € 1,050,000
Sleaveen East Housing Scheme A-Housing & Building € 1,037,500
Fermoy (Oliver Plunkett Hill) Social Housing A-Housing & Building € 1,000,000
Bandon (Gagganstown) Part V Affordable 3,5,7,8 A-Housing & Building € 719,688
Ballydineen Halting Site A-Housing & Building € 710,000
Youghal St Francis Court A-Housing & Building € 631,738
Youghal The Estuary A-Housing & Building € 625,346
Cloyne (Spittal) Phase 1 5 units A-Housing & Building € 620,000.00
Housing Comm Dev Support A-Housing & Building € 611,115
The Nest Part V Affordable No 1,2,4 A-Housing & Building € 565,000
N28 Cork Ringaskiddy (TII) B-Road Transportation and Safety £ 40,900,000
Local Roads - Maintenance & Improvement B-Road Transportation and Safety € 39,211,762
Reg Roads - Maintenance & Improvement B-Road Transportation and Safety € 16,458,909
N22 Ballyvourney Macroom (TII) Site Investigation and Land purchase B-Road Transportation and Safety € 8,320,000 € 8,320,000
Plant and Machinery Purchase B-Road Transportation and Safety € 7,216,117
Public Lighting operations B-Road Transportation and Safety € 526,465 € 5,690,594
Carrigaline Western Relief Road B-Road Transportation and Safety € 6,150,000
Clogher Cross Water dyke realigment B-Road Transportation and Safety € 6,050,000
N20 Buttevant Streets (TII) B-Road Transportation and Safety € 6,000,000.00
N73 Annakisha South Realignment (TII) B-Road Transportation and Safety € 5,100,000
N72 Carrig to Ballygriffin Realignment (TII) B-Road Transportation and Safety € 3,500,000.00
Castletownbere Traffic Management Plan B-Road Transportation and Safety € 3,200,000
N71 - School Link Road B-Road Transportation and Safety € 3,020,000
Carrigrohane Land Purchase B-Road Transportation and Safety € 3,000,000.00
Car Parking operations B-Road Transportation and Safety € 2,915,244
Public Lighting Improvement (2016-2018)* B-Road Transportation and Safety € 2,800,000
Non National Road LED Retrofit B-Road Transportation and Safety € 2,800,000
Agency and Recoupable Services B-Road Transportation and Safety € 2,315,213
Lehenaghmore Road Design & Interim Works B-Road Transportation and Safety € 2,060,000
Cork Science and Innovation Park Access Road Works B-Road Transportation and Safety € 2,000,000
Killeagh Village Pavement Strengthening B-Road Transportation and Safety € 1,945,398.00
Support to Roads Capital Prog B-Road Transportation and Safety € 1,932,303
Carrigaline Green Route Phase 2 B-Road Transportation and Safety € 1,905,000
Clarkes/Moneygourney Road Improvement Scheme B-Road Transportation and Safety € 1,630,000
Public Lighting Development (2016-2018)* B-Road Transportation and Safety € 1,550,000
Dunkettle Junction Re design B-Road Transportation and Safety € 1,500,000
N71 - Clonakilty town Overlay B-Road Transportation and Safety € 1,438,272.00
Cork County Council- Public Spending Code Quality Assurance Report 2016
11
Cork County Council Expenditure being considered Expenditure being incurred >.5m Expenditure recently ended >.5m
Current >.5m Cap. Grt >.5m Cap. Proj <5m Cap. Proj 5-20m Cap. Proj >20m Current >.5m€
Cap.Grt Scheme Cap. Proj>.5m
Current >.5m€
Cap.Grt Scheme Cap. Proj>.5m
N22 Lissarda Village Pave Ren B-Road Transportation and Safety € 1,361,927
National Secondary Road - Maintenance & Improvement B-Road Transportation and Safety € 1,334,319
Midleton Road Drainage Works B-Road Transportation and Safety € 1,254,932
National Primary Road - Maintenance & Improvement B-Road Transportation and Safety € 1,147,526
N72 Balygriffin Overlay B-Road Transportation and Safety € 1,050,000.00
N72 Templenoe Overlay Scheme B-Road Transportation and Safety € 1,050,000
Safety Works in Yards & Depots* B-Road Transportation and Safety € 1,050,000.00
Bantry Culvert B-Road Transportation and Safety € 1,050,000
Ballybrack Cycle Track - Phase 2 & 3 B-Road Transportation and Safety € 900,000
Kanturk Access Road B-Road Transportation and Safety € 880,625
Douglas Village Improvements B-Road Transportation and Safety € 840,000
Little Island Junction Upgrade B-Road Transportation and Safety € 840,000
N72 Killetra Pavement Strengthening (TII) B-Road Transportation and Safety € 800,000.00
N22 - Macroom Streets Pavement improvement B-Road Transportation and Safety € 764,936.00
Road Safety Promotion/Educate B-Road Transportation and Safety € 751,794
N20 - Mallow (Annabella) Roundabout Works B-Road Transportation and Safety € 730,010
Carrigaline Ferney Rd. B-Road Transportation and Safety € 720,000
Traffic Management Improvement B-Road Transportation and Safety € 675,841
Midleton (Broomfield) Road Works B-Road Transportation and Safety € 630,000
Leemount X Junction Upgrade B-Road Transportation and Safety € 628,000
Donnybrook Cross & Bus Stop B-Road Transportation and Safety € 600,000
N71 Newmills Realignment (TII) B-Road Transportation and Safety € 500,000
N71 Owenahincha Newmills realignment B-Road Transportation and Safety € 500,000
Lower Lee Flood Relief Scheme C-Water Services £ 40,000,000
Water Supply C-Water Services € 1,771,502 € 21,157,105
Skibbereen Flood Relief Scheme C-Water Services € 12,500,000
Glashaboy River (Glanmire/Sallybrook) Flood Relief Scheme C-Water Services € 9,000,000
Douglas River Flood Relief Scheme (Including Togher) C-Water Services € 9,000,000
Waste Water Treatment C-Water Services € 540,629 € 7,460,849
Agency & Recoupable Services C-Water Services € 645,883 € 1,747,581
Youghal Coastal Protection Works C-Water Services € 2,000,000
Local Authority Water C-Water Services € 508,487 € 1,334,276
Public Convenience Operations C-Water Services € 1,432,029
Group Schemes Administration C-Water Services € 1,311,797
Midleton Flood Relief Scheme C-Water Services € 1,250,000
Pluvial Flood Relief Measures C-Water Services € 900,000
Dursey Cable Car (2016-2018) C-Water Services € 650,000
Water Capital Programme Support C-Water Services € 527,916
Sheeps Head Sea Wall Rehabilitation Project C-Water Services € 502,000.00
Cork County Council- Public Spending Code Quality Assurance Report 2016
12
Cork County Council Expenditure being considered Expenditure being incurred >.5m Expenditure recently ended >.5m
Current >.5m Cap. Grt >.5m Cap. Proj <5m Cap. Proj 5-20m Cap. Proj >20m Current >.5m€
Cap.Grt Scheme Cap. Proj>.5m
Current >.5m€
Cap.Grt Scheme Cap. Proj>.5m
Crookstown Flood Relief Scheme C-Water Services € 500,000
Economic Development & Promotion D-Development Management € 1,744,961 € 7,240,704
Commercial & Enterprise Function D-Development Management € 3,647,699 € 1,791,914
Mallow Business Growth Hub D-Development Management € 1,255,000
Tourism Development & Promotion D-Development Management € 1,161,892
Industrial & Commercial Facilities D-Development Management € 1,016,842
Clonakilty Fire Station D-Development Management € 990,000
Celtic Food Cluster D-Development Management € 948,658
Building Control Service D-Development Management € 916,246
Industrial Unit Development D-Development Management € 900,000
Unfinished Housing Estates D-Development Management € 510,703
Haulbowline Remediation E-Environmental Services € 37,010,959
Fire Service operation E-Environmental Services € 12,979,035
Development Management Service E-Environmental Services € 9,047,589
Recovery & Recycle Facility Operations E-Environmental Services € 6,429,347
Landfill Operation & Aftercare E-Environmental Services € 4,512,357
Burial Grounds Maintenance E-Environmental Services € 3,369,540
Forward Planning Service E-Environmental Services € 3,144,994
Youghal Landfill Capping E-Environmental Services € 3,100,000
Safety of Structures & Places E-Environmental Services € 2,162,508
Litter Management operations E-Environmental Services € 2,105,468
Water Quality,Air & Noise Pollution control service E-Environmental Services € 1,934,519
Street Cleaning operations E-Environmental Services € 1,818,546
Fire Prevention E-Environmental Services € 1,805,801
Waste Regs, Monitor & Enforcement service E-Environmental Services € 1,556,799
Kanturk Fire Station E-Environmental Services € 1,300,000
Macroom Fire Station E-Environmental Services € 1,100,000
Enforcement Service E-Environmental Services € 1,071,770
Civil Defence HQ E-Environmental Services € 900,000
Heritage & Conservation Service E-Environmental Services € 604,063
Fire Applicances purchase (3 no) E-Environmental Services € 506,087
Youghal Joint Burial Board E-Environmental Services € 500,000
Library & Archive operations F-Recreation and Amenity € 906,538 € 9,154,175
Dunmanway Swimming Pool F-Recreation and Amenity € 5,600,000.00
Outdoor Leisure Areas Operation F-Recreation and Amenity € 3,993,471
Community Grants F-Recreation and Amenity € 3,692,918 € 3,692,918
North Cork Arts Centre F-Recreation and Amenity € 3,500,000
Leisure Facilities Operation F-Recreation and Amenity € 2,632,388
Cork Harbour Greenway F-Recreation and Amenity € 2,000,000
Cork County Council- Public Spending Code Quality Assurance Report 2016
13
Cork County Council Expenditure being considered Expenditure being incurred >.5m Expenditure recently ended >.5m
Current >.5m Cap. Grt >.5m Cap. Proj <5m Cap. Proj 5-20m Cap. Proj >20m Current >.5m€
Cap.Grt Scheme Cap. Proj>.5m
Current >.5m€
Cap.Grt Scheme Cap. Proj>.5m
Blackwater River Blueway F-Recreation and Amenity € 2,000,000
Arts Programme Operation F-Recreation and Amenity € 1,789,323
Kinsale Library- development of Old Mill F-Recreation and Amenity € 1,700,000
Mallow Boardwalk F-Recreation and Amenity € 1,631,088
Bandon Public Realm improvements F-Recreation and Amenity € 1,500,000
Clonakilty Phase 1 Greenway F-Recreation and Amenity € 1,500,000
Midleton Town Centre Access and Enhancement Project Phase II F-Recreation and Amenity € 1,407,735
Camden Fort Meagher renovation F-Recreation and Amenity € 1,395,000
Youghal Eco Board Walk Project F-Recreation and Amenity € 1,200,000
Midleton Parking improvements F-Recreation and Amenity € 1,170,000.00
Skibbereen Public Realm F-Recreation and Amenity € 1,100,000
Mallow Public Realm F-Recreation and Amenity € 1,000,000
Cobh Lower Harbour Public Realm Works F-Recreation and Amenity € 1,000,000
Mallow Pedestrian Bridge F-Recreation and Amenity € 1,000,000
Kinsale Long Quay Carpark F-Recreation and Amenity € 900,000
Mobile Library purchase F-Recreation and Amenity € 750,000
Mallow new car park F-Recreation and Amenity € 600,000
Kinsale Short Quay Development F-Recreation and Amenity € 500,000
Dunmanway Town Square F-Recreation and Amenity € 500,000
Castletownbere Public Realm F-Recreation and Amenity € 500,000
Spike Island Renovation (2016-2018) F-Recreation and Amenity € 500,000
Veterinary Service G-Agriculture, Education, Health and Welfare € 3,308,477
Op & Maint of Piers & Harbours G-Agriculture, Education, Health and Welfare € 760,601
Rates Administration H-Miscellaneous Services € 19,153,982
Pensions & Lump Sum Costs H-Miscellaneous Services € 575,066 € 16,306,041
Profit/Loss Machinery Account H-Miscellaneous Services € 8,776,014
Agency & Recoupable Services H-Miscellaneous Services € 6,784,696
Corporate Building Costs H-Miscellaneous Services € 6,114,606
General Corporate Services H-Miscellaneous Services € 932,613 € 4,643,911
Corporate Affairs Overhead H-Miscellaneous Services € 932,613 € 4,643,911
ICT H-Miscellaneous Services € 820,086 € 4,372,418
Human Resources Function H-Miscellaneous Services € 3,749,508
Finance Function Overhead H-Miscellaneous Services € 839,299 € 2,647,252
Carrigrohane Recreation & Amenity lands H-Miscellaneous Services € 3,000,000
Local Reps and Civic Leadership H-Miscellaneous Services € 2,642,910
Motor Taxation service H-Miscellaneous Services € 2,516,816
Fermoy Weir H-Miscellaneous Services € 1,870,000
County Hall Motor Tax building H-Miscellaneous Services € 1,800,000.00
County Hall Teagasc building H-Miscellaneous Services € 1,800,000
Cork County Council- Public Spending Code Quality Assurance Report 2016
14
Cork County Council Expenditure being considered Expenditure being incurred >.5m Expenditure recently ended >.5m
Current >.5m Cap. Grt >.5m Cap. Proj <5m Cap. Proj 5-20m Cap. Proj >20m Current >.5m€
Cap.Grt Scheme Cap. Proj>.5m
Current >.5m€
Cap.Grt Scheme Cap. Proj>.5m
Area Office Overhead H-Miscellaneous Services € 1,111,474
Briery Gap Theatre Repair and Refurbishment. H-Miscellaneous Services € 1,000,000
ICT systems development H-Miscellaneous Services € 800,000
Profit/Loss Stores Account H-Miscellaneous Services € 793,108
Operation Morgue/Coroner Costs H-Miscellaneous Services € 592,797
Cobh PurchaseOld Town Hall H-Miscellaneous Services € 580,000
Financial ICT systems development H-Miscellaneous Services € 580,000
Franchise Costs H-Miscellaneous Services € 525,877
Totals
€ 21,869,124 € - € 54,884,860 € 39,284,824 € 80,900,000 € 326,803,532
€ 3,692,918 € 263,269,985
€ -
€ - € 42,315,944
Cork County Council- Public Spending Code Quality Assurance Report 2016
15
Step 2 – Summary Information on Website
As part of the Quality Assurance process Cork County Council has published summary information online of all procurement >€10million Euro.
The link below leads to the PSC section of the website.
https://www.corkcoco.ie/your-county-council/accessibility-maps-publications
The following projects and relevant information are included at time of publication. Available information is subject to project stage.
Haulbowline Island Remediation
River Ilen Drainage Scheme
N22 - Ballyvourney-Macroom Road
N28 – Cork- Ringaskiddy Road
Clonakilty Beechgrove Social Housing
Carrigaline Kilnagleary Social Housing
Lower Lee Flood Relief Scheme
Cork County Council- Public Spending Code Quality Assurance Report 2016
16
Step 3 – Public Spending Code Checklists
These checklists summarise CCC’s PSC compliance. No Current Programmes with expenditure > €500,000
commenced/finished during the reporting period. In –depth project checks informed the specific scores.
The Checklist scoring mechanism is as follows
I. Scope for significant improvements = a score of 1 II. Compliant but with some improvement necessary = a score of 2
III. Broadly compliant = a score of 3
In some cases fields are marked as N/A and information is included in the comment box
Checklist 1 – To be completed in respect of general obligations not specific to individual projects/programmes.
Check
list
Code
Question
Code
Question Self-Assessed
Compliance
Rating: 1 - 3
Comment/Action Required
1 1 Does the local authority ensure, on an on-
going basis, that appropriate people within the
authority and its agencies are aware of the
requirements of the Public Spending Code (incl.
through training)?
3 All Senior Management, budget holder and project staff
are now aware of PSC requirements. Reminders are
issued to staff on project documentation.
1 2 Has training on the Public Spending Code been
provided to relevant staff within the authority?
3 DPER provided in-depth briefings to appropriate CCC
staff in April 2016.
Cork County Council- Public Spending Code Quality Assurance Report 2016
17
Check
list
Code
Question
Code
Question Self-Assessed
Compliance
Rating: 1 - 3
Comment/Action Required
1 3 Has the Public Spending Code been adapted for
the type of project/programme that your local
authority is responsible for? i.e., have adapted
sectoral guidelines been developed?
2 Departments now incorporate PSC compliance into their
existing project management practice.
1 4 Has the local authority in its role as
Sanctioning Authority satisfied itself that
agencies that it funds comply with the Public
Spending Code?
NA This has not arisen as CCC does not fund external bodies
for>500k. However it will be included in any future
arrangement.
1 5 Have recommendations from previous QA
reports (incl. spot checks) been disseminated,
where appropriate, within the local authority
and to agencies?
3 Yes, particularly arising from Internal Audit and other
such Quality Reviews.
1 6 Have recommendations from previous QA
reports been acted upon?
3 Yes these are put in place where feasible
1 7 Has an annual Public Spending Code QA report
been certified by the local authority’s Chief
Executive, submitted to NOAC and published
on the authority’s website?
3
1 8 Was the required sample of
projects/programmes subjected to in-depth
checking as per step 4 of the QAP?
3
Cork County Council- Public Spending Code Quality Assurance Report 2016
18
Check
list
Code
Question
Code
Question Self-Assessed
Compliance
Rating: 1 - 3
Comment/Action Required
1 9 Is there a process in place to plan for ex post
evaluations/Post Project Reviews? Ex-post
evaluation is conducted after a certain period
has passed since target project completion
emphasising project effectiveness and
sustainability.
2 Post project review analysis depends on the complexity
of same and outcomes.
1 10 How many formal Post Project Review
evaluations have been completed in the year
under review? Have they been issued promptly
to the relevant stakeholders / published in a
timely manner?
2 This is not formally defined so not currently possible to
say. However these take place when requested by
Sanctioning Authorities.
1 11 Is there a process to follow up on the
recommendations of previous evaluations/Post
project reviews?
2 Depends on case by case
1 12 How have the recommendations of previous
evaluations / post project reviews informed
resource allocation decisions?
2 Depends on case by case
Cork County Council- Public Spending Code Quality Assurance Report 2016
19
Checklist 2 – To be completed in respect of capital projects/programmes & capital grant schemes that were under consideration in the past year. Checkli
st Code
Question
Code
Question Self-Assessed
Compliance
Rating: 1 - 3
Comment/Action Required
2 1 Was a preliminary appraisal undertaken for all
projects > €5m?
3 Yes, both to CCC’s internal standards and sanctioning
body standards.
2 2 Was an appropriate appraisal method used in
respect of capital projects or capital
programmes/grant schemes?
3 Yes, in co-ordination with sanctioning body standards
2 3 Was a CBA/CEA completed for all projects
exceeding €20m?
3 Yes, in co-ordination with sanctioning body standards
2 4 Was the appraisal process commenced at an
early stage to facilitate decision making? (i.e.
prior to the decision)
3 Yes, as per sanctioning body funding requirements
2 5 Was an Approval in Principle granted by the
Sanctioning Authority for all projects before
they entered the planning and design phase
(e.g. procurement)?
3 Yes, as per sanctioning body funding requirements
2 6 If a CBA/CEA was required was it submitted to
the relevant Department for their views?
3 Carried out by other bodies which then provide funding
to CCC.
2 7 Were the NDFA consulted for projects costing
more than €20m?
3 Carried out by other bodies which then provide funding
to CCC.
2 8 Were all projects that went forward for tender 3
Cork County Council- Public Spending Code Quality Assurance Report 2016
20
Checkli
st Code
Question
Code
Question Self-Assessed
Compliance
Rating: 1 - 3
Comment/Action Required
in line with the Approval in Principle and, if not,
was the detailed appraisal revisited and a fresh
Approval in Principle granted?
2 9 Was approval granted to proceed to tender? 3 Yes in all cases
2 10 Were procurement rules complied with? 3 Yes in all cases
2 11 Were State Aid rules checked for all supports? 3 Yes in all cases
2 12 Were the tenders received in line with the
Approval in Principle in terms of cost and what
is expected to be delivered?
3 Yes
2 13 Were performance indicators specified for each
project/programme that will allow for a robust
evaluation at a later date?
2 Where applicable and identifiable. CCC needs to apply
further indicators in certain project types in light of
greater understanding post DPER briefing. This
particularly applies to projects with qualitative
outcomes.
2 14 Have steps been put in place to gather
performance indicator data?
2 Yes subject to data availability
Cork County Council- Public Spending Code Quality Assurance Report 2016
21
Checklist 3 – To be completed in respect of new current expenditure under consideration in the past year.
Checklist
Code
Question
Code
Question Self-Assessed
Compliance
Rating: 1 - 3
Comment/Action Required
3 1 Were objectives clearly set out? 3 Yes
3 2 Are objectives measurable in quantitative
terms?
3 Yes
3 3 Was a business case, incorporating financial
and economic appraisal, prepared for new
current expenditure?
NA Not applicable to relevant projects
3 4 Was an appropriate appraisal method used? NA Not applicable to relevant projects
3 5 Was an economic appraisal completed for all
projects exceeding €20m or an annual spend
of €5m over 4 years?
NA Not applicable to relevant projects
3 6 Did the business case include a section on
piloting?
NA Not applicable to relevant projects
3 7 Were pilots undertaken for new current
spending proposals involving total
expenditure of at least €20m over the
proposed duration of the programme and a
minimum annual expenditure of €5m?
NA Not applicable to relevant projects
3 8 Have the methodology and data collection
requirements for the pilot been agreed at the
NA Not applicable to relevant projects
Cork County Council- Public Spending Code Quality Assurance Report 2016
22
Checklist
Code
Question
Code
Question Self-Assessed
Compliance
Rating: 1 - 3
Comment/Action Required
outset of the scheme?
3 9 Was the pilot formally evaluated and
submitted for approval to the relevant
Department?
NA Not applicable to relevant projects
3 10 Has an assessment of likely demand for the
new scheme/scheme extension been
estimated based on empirical evidence?
NA No applicable projects
3 11 Was the required approval granted? 3 Yes where involving Sanctioning Authorities.
3 12 Has a sunset clause (as defined in section
B06, 4.2 of the Public Spending Code) been
set?
2 Applied where applicable
3 13 If outsourcing was involved were
procurement rules complied with?
3
3 14 Were performance indicators specified for
each new current expenditure proposal or
expansion of existing current expenditure
programme which will allow for a robust
evaluation at a later date?
2
3 15 Have steps been put in place to gather
performance indicator data?
2
Cork County Council- Public Spending Code Quality Assurance Report 2016
23
Checklist 4 – To be completed in respect of capital projects/programmes & capital grants schemes incurring expenditure
in the year under review.
Checklist
Code
Question
Code
Question Self-Assessed
Compliance
Rating: 1 - 3
Comment/Action Required
4 1 Was a contract signed and was it in line with
the Approval in Principle?
3
4 2 Did management boards/steering
committees meet regularly as agreed?
3
4 3 Were programme co-ordinators appointed to
co-ordinate implementation?
3
4 4 Were project managers, responsible for
delivery, appointed and were the project
managers at a suitably senior level for the
scale of the project?
3
4 5 Were monitoring reports prepared regularly,
showing implementation against plan,
budget, timescales and quality?
3
4 6 Did projects/programmes/grant schemes
keep within their financial budget and time
schedule?
2
4 7 Did budgets have to be adjusted? 3 Some renegotiation needed to take place to stay within
budget.
Cork County Council- Public Spending Code Quality Assurance Report 2016
24
Checklist
Code
Question
Code
Question Self-Assessed
Compliance
Rating: 1 - 3
Comment/Action Required
4 8 Were decisions on changes to budgets / time
schedules made promptly?
2 Some postponement whilst waiting for a decision.
4 9 Did circumstances ever warrant questioning
the viability of the project/programme/grant
scheme and the business case incl. CBA/CEA?
(exceeding budget, lack of progress, changes
in the environment, new evidence, etc.)
NA
4 10 If circumstances did warrant questioning the
viability of a project/programme/grant
scheme, was the project subjected to
adequate examination?
NA
4 11 If costs increased was approval received from
the Sanctioning Authority?
NA
4 12 Were any projects/programmes/grant
schemes terminated because of deviations
from the plan, the budget or because
circumstances in the environment changed
the need for the investment?
NA
Cork County Council- Public Spending Code Quality Assurance Report 2016
25
Checklist 5 – To be completed in respect of current expenditure programmes incurring expenditure in the year under
review.
Checklist
Code
Question
Code
Question Self-Assessed
Compliance
Rating: 1 - 3
Comment/Action Required
5 1 Are there clear objectives for all areas of
current expenditure?
3 Yes, as part of Budgeting and Business Planning Process
5 2 Are outputs well defined? 3 Yes including National Performance Indicators
5 3 Are outputs quantified on a regular basis? 3 Yes
5 4 Is there a method for monitoring efficiency on
an on-going basis?
2 Yes
5 5 Are outcomes well defined? 3
5 6 Are outcomes quantified on a regular basis? 2
5 7 Are unit costings compiled for performance
monitoring?
2
5 8 Are other data compiled to monitor
performance?
2
5 9 Is there a method for monitoring
effectiveness on an on-going basis?
2
5 10 Has the organisation engaged in any other
‘evaluation proofing’ of
programmes/projects?
2
Cork County Council- Public Spending Code Quality Assurance Report 2016
26
Checklist 6 – To be completed in respect of capital projects/programmes & capital grant schemes discontinued in the
year under review.
Checklist
Code
Question
Code
Question Self-Assessed
Compliance
Rating: 1 - 3
Comment/Action Required
6 1 How many post project reviews were
completed in the year under review?
2 Some Reviews take place but no specific register of
same
6 2 Was a post project review completed for all
projects/programmes exceeding €20m?
NA None completed in this expenditure bracket
6 3 Was a post project review completed for all
capital grant schemes where the scheme both
(1) had an annual value in excess of €30m
and (2) where scheme duration was five years
or more?
NA None completed in this expenditure bracket
6 4 Aside from projects over €20m and grant
schemes over €30m, was the requirement to
review 5% (Value) of all other projects
adhered to?
Yes
6 5 If sufficient time has not elapsed to allow for
a proper assessment, has a post project
review been scheduled for a future date?
No
6 6 Were lessons learned from post-project
reviews disseminated within the Sponsoring
2 Yes as part of post project review where required.
Cork County Council- Public Spending Code Quality Assurance Report 2016
27
Agency and to the Sanctioning Authority? (Or
other relevant bodies)
6 7 Were changes made to practices in light of
lessons learned from post-project reviews?
2 Depending on project. For example better initial project
briefs is a key outcome.
6 8 Were project reviews carried out by staffing
resources independent of project
implementation?
No
Cork County Council- Public Spending Code Quality Assurance Report 2016
28
Checklist 7 – To be completed in respect of current expenditure programmes that reached the end of their planned
timeframe during the year or were discontinued.
Checklist
Code
Question
Code
Question Self-Assessed
Compliance
Rating: 1 - 3
Comment/Action Required
7 1 Were reviews carried out of current
expenditure programmes that matured
during the year or were discontinued?
No
7 2 Did those reviews reach conclusions on
whether the programmes were efficient?
No
7 3 Did those reviews reach conclusions on
whether the programmes were effective?
No
7 4 Have the conclusions reached been taken into
account in related areas of expenditure?
NA
7 5 Were any programmes discontinued
following a review of a current expenditure
programme?
NA
7 6 Were reviews carried out by staffing
resources independent of project
implementation?
NA
7 7 Were changes made to the organisation’s
practices in light of lessons learned from
reviews?
NA
Cork County Council- Public Spending Code Quality Assurance Report 2016
29
Cork County Council- Public Spending Code Quality Assurance Report 2016
30
Step 4 - In-Depth Reviews
Introduction CCC has carried out an In-Depth Review of the following projects to provide assurance that Cork County Council Departments and Functions comply with the Public Spending Code.
These reviews cover approx 15.6% of CCC’s total Capital Expenditure and 7.5% of Current Expenditure as an average for 2014-2016.
Review Area Current Expenditure
Capital Expenditure
Value
Buttevant Street Renovation
Complete (2017) €6,000,000
“Motor Tax” building renovations
Complete (2017) €1,800,000
Arts Programme Operation
Yes (Under Progress)
€1,789,000
Cork County Council- Public Spending Code Quality Assurance Report 2016
31
Programme or Project Information
Name Buttevant Street Renovation
Detail
This project involved the renovation and reconstruction of aspects of Buttevant’s street fabric including
road resurfacing
pavement rehabilitation
Street lighting
Concealed utilities
Responsible Body TII/Cork County Council
Current Status Completed
Start Date 2015
End Date 2017
Overall Cost 6 million Euro
Cork County Council- Public Spending Code Quality Assurance Report 2016
32
Section B - Step 1: Logic Model Mapping
As part of this In-Depth Check, CCC Performance and Governance Unit have completed a Programme Logic Model (PLM) for the Buttevant
Street Renovation.
Objectives: Urban renewal was the key objective and particularly to restore usability to this attractive streetscape. At the same time the high
traffic throughput necessitated road resurfacing. No alternative high level project objective was available considering the location of the
works. However, within this context, numerous design and engineering solutions were analysed to ascertain which was the most cost effective.
Objectives Inputs Activities Outputs Outcomes Urban Renewal
Resurfacing
Funding
Council Staff
Consultant Staff
Contractor Staff
Materials
Project Design and Risk
Assessment
Public Consultation
Archaeological investigation
Service
relocation/undergrounding
Pavement works
Re surfacing
Street furniture improvements
Improved Road surface
Improved Pavement
surfaces
New services where
required
Improved public realm
along Main Street
Improved urban
environment
Better road surface
More attractive to
investment
Cork County Council- Public Spending Code Quality Assurance Report 2016
33
Inputs: The primary input to the programme was the capital funding of €6 million which was provided for by TII contributing 2.75m euro and
CCC providing the funding balance. CCC staff provided project design and oversight whilst Arups Engineering consultants provided direct
supervision. The specific works were carried out by Priory Construction. Archaeological investigation work was contracted to Rubicon.
Activities: Project Activities included
Project Design and Risk Assessment
Public Consultation
Archaeological investigation
Service relocation/undergrounding
Pavement works
Re surfacing
Street furniture improvements
Outputs: Having carried out the identified activities using the inputs, the outputs of the project are for improved
Improved Road surface
Improved Pavement surfaces
New services where required
Improved public realm along Main Street
Outcomes: The envisaged project outcome was to improve the Main Streets public realm through better pedestrian facilities and a more
attractive environment. Similarly the improved road pavement has allowed for faster and easier vehicular transit through the town. Utilities
have also been undated where appropriate taking advantage of the road opening works.
Cork County Council- Public Spending Code Quality Assurance Report 2016
34
Section B - Step 2: Summary Timeline of Project/Programme
The following section tracks the Buttevant Street Renovation from inception to conclusion in terms of major project/programme milestones
June 2014 Part 8
November 2014 Project Tender
February 2015 Project Start
October 2016 Project Work Finalised
March 2017 Final Project Payments
Cork County Council- Public Spending Code Quality Assurance Report 2016
35
Section B - Step 3: Analysis of Key Documents
The following section reviews the key documentation relating to appraisal, analysis and evaluation for the Buttevant Street Renovation.
Project/Programme Key Documents
Title Details
Part 8 and Managers Report
Project Objectives
Relevant National Policy
Environmental Thresholds
Public Consultation Submissions
Project Recommendations
Monthly Progress Monitoring meetings -
Minutes
Public Consultation
Health and Safety
Archaeology
Project decisions
Traffic Management
Utility Liaison
Payments
Monthly formal progress report
Cork County Council- Public Spending Code Quality Assurance Report 2016
36
Key Document 1: Part 8 and Managers Report
The document is clearly laid out and includes the key scheme objectives. It also summarises key project thresholds including public
consultation, environmental and heritage assessment. However it makes little reference to actual project management and stage completion.
Nevertheless these items are included in the project contracts.
Key Document 2: Monthly Progress Monitoring meetings - Minutes
The monthly progress report meetings are clear with issue summaries and assigned roles as appropriate. However a statement at the start
would be desirable setting out the overall project status.
Key Document 3: Monthly formal progress report
Again this document clearly lays out the individual project issues (archaeology, Safety Audits, Utilities, Works). However again it does not have
an overall statement as to project status.
Cork County Council- Public Spending Code Quality Assurance Report 2016
37
Section B - Step 4: Data Audit
The following section details the data audit that was carried out for the Buttevant Street Renovation. It evaluates whether appropriate data is
available for the future evaluation of the project/programme.
Data Required Use Availability
Necessary Road repairs
Assess impact of improved
road surface in terms of
lower repair requests and
costs
Yes, held by TII/CCC as part
of Pavement Management
System.
Economic impacts Assess scheme impact on
town vitality
Planning Policy Unit to
assess at next Local Area
Plan review
Utility repairs
Assess impact of utility
works in terms of reducing
repair occurrence.
Available through CCC
“Road Opening Licence”
System.
Cork County Council- Public Spending Code Quality Assurance Report 2016
38
Data Availability and Proposed Next Steps
As per the table above, it should be feasible to construct a before and after snapshot of the projects success. However this project will require
several years to bed in particularly in terms of improving Buttevant’s economic performance.
Section B - Step 5: Key Evaluation Questions
The following section looks at the key evaluation questions for the Buttevant Street Renovation based on the findings from the previous
sections of this report.
Does the delivery of the project/programme comply with the standards set out in the Public Spending Code? (Appraisal Stage,
Implementation Stage and Post-Implementation Stage)
In terms of tenders the project phase complied with procurement guidelines and it was not necessary to omit any works in order to achieve
expected costs. Specific project goals and timelines are also in place. Finally, a post project review will be carried out to ascertain “lessons
learned” within the context of future such proposals.
Is the necessary data and information available such that the project/programme can be subjected to a full evaluation at a later date?
The project’s high levels goals are qualitative the improvements have been welcomed by Buttevant’s inhabitants. The contributory objectives
(constructions, improved drainage etc)
What improvements are recommended such that future processes and management are enhanced?
The project ran on budget but ran over initial timeframe as a much higher level of archaeological inspection was required than originally
anticipated. In particular the presence of several National monuments required both Ministerial consent and detailed excavation works. In
terms of future projects CCC considers that it is now in a better position to manage works in areas with a concentration of archaeology.
Cork County Council- Public Spending Code Quality Assurance Report 2016
39
Section C: In-Depth Check Summary
The following section presents a summary of the findings of this In-Depth Check on the Buttevant Street Renovation Project
Summary of In-Depth Check
The Buttevant Street Renovation project involved the repair and replacement of pavement and roads in the town as well as other public realm
and utility improvements. This in turn would improve the streets permeability to both motorists and pedestrians whilst also providing a more
attractive environment for residents and businesses.
TII part funded the works as a Sanctioning Authority to the extent of 2.75m euro. CCC provided the funding balance.
In terms of project scoping an initial risk assessment identified the following key concerns.
Broken or Leaking mains/sewers
Unknown archaeological and heritage sites (Buttevant is a medieval town)
Whilst CCC oversaw the project, Consultant Engineers managed the works on a day to day basis. This working relationship was managed
through regular progress report meetings.
The project ran on budget but ran over initial timeframe as a much higher level of archaeological inspection was required than originally
anticipated. In particular the presence of several National monuments required both Ministerial consent and detailed excavation works.
The project outcome is considered as a success as the town is a more attractive environment and this should lead to improved economic and
social outcomes. This in-depth review considers that this capital project meets PSC criteria.
Cork County Council- Public Spending Code Quality Assurance Report 2016
40
Programme or Project Information
Name “Motor Tax” building renovations
Detail
This project involved the renovation and reconstruction of the old “Motor Tax building” on the County Hall
Campus. It is now used as a Community and Enterprise Public Office
Responsible Body Cork County Council
Current Status Completed
Start Date 2014
End Date 2017
Overall Cost 1.8 million Euro
Cork County Council- Public Spending Code Quality Assurance Report 2016
41
Section B - Step 1: Logic Model Mapping
As part of this In-Depth Check, CCC Performance and Governance Unit have completed a Programme Logic Model (PLM) for the “Motor Tax”
building renovations
Description of Programme Logic Model
Objectives Inputs Activities Outputs Outcomes Increased office
accommodation
Improved Energy
Efficiency
Cost effective
Refurbishment
Funding
Planning Permission
CCC Design Staff
Consultant Engineers
Contractors
Project Design and Risk
Assessment
Public Consultation/Planning
Permission
Surveys
Construction works
Fitting out
Finished building
On budget
No significant H&S
issues
Office space
Public Accessibility
Energy Efficiency
Lower costs vis a vis new
builds.
Cork County Council- Public Spending Code Quality Assurance Report 2016
42
Objectives: CCC has primary responsibility for community and economic development in the County. The current office accommodation in
County Hall was not suitable in the context of both size and public accessibility. CCC decided to renovate an existing disused building on the
campus (Motor Tax) for the purposes of office accommodation.
Inputs: CCC provided 1.8 million euro for the project and was the sole funding organization. CCC staff provided project design and supervision
in conjunction with consultant engineers.
Activities: Project Activities included
Project Design and Risk Assessment
Public Consultation/Planning Permission
Surveys
Construction works
Fitting out
Outputs: Having carried out the identified activities using the inputs, the outputs of the project are for improved
Office space
Public Accessibility
Energy Efficiency
Lower costs vis a vis new builds.
Outcomes: The envisaged project outcome was to provide a high quality office space whilst reusing an existing building with lower running
costs going forward. This was achieved although the project did run over initial schedules due to ongoing cost discussions with potential
contractors.
Cork County Council- Public Spending Code Quality Assurance Report 2016
43
Section B - Step 2: Summary Timeline of Project/Programme
The following section tracks the “Motor Tax” building renovations from inception to conclusion in terms of major project/programme milestones
June 14 Project Scoping
April 15 Planning Permission granted
November 15 Tender issued
June 16 Tender awarded
July 16 Construction commenced
April 17 Construction Complete
Cork County Council- Public Spending Code Quality Assurance Report 2016
44
Section B - Step 3: Analysis of Key Documents
The following section reviews the key documentation relating to appraisal, analysis and evaluation for the “Motor Tax” building renovations
Project/Programme Key Documents
Title Details
Monthly Progress Monitoring meetings -
Minutes
Health and Safety
Works Progress
Necessary Changes
Lessons Learned Review
Project Timeline
Stage Outcomes and alternative options
Lessons Learned
Key Document 1: Monthly Progress monitoring meetings - Minutes
The monthly progress report meetings are clear with issue summaries and assigned roles as appropriate. However a statement at the start
would be desirable setting out the overall project status.
Key Document 2: Lessons Learned Review
This is a very comprehensive document prepared by a Project Team member. It runs through the entire project highlighting reasons for time
delays (particularly related to tender document preparation and changed scope). The scope change was primarily due to an internal
Cork County Council- Public Spending Code Quality Assurance Report 2016
45
restructuring which resulted in changed office space requirements. The review concluded that this area should be better managed in future
and that a Project Execution Plan should be finalised early in a public works project for identifying the brief, communications and stakeholder
responsibility
Section B - Step 4: Data Audit
The following section details the data audit that was carried out for the “Motor Tax” building renovations. It evaluates whether appropriate data
is available for the future evaluation of the project/programme.
Data Required Use Availability
Office Space Accommodation Post Occupation Survey
Energy Efficiency Cost effectiveness Energy usage analysis
(Billing, metering)
Data Availability and Proposed Next Steps
As per the table above, it should be feasible to construct a before and after snapshot of the projects success.
Cork County Council- Public Spending Code Quality Assurance Report 2016
46
Section B - Step 5: Key Evaluation Questions
The following section looks at the key evaluation questions for the “Motor Tax” building renovations based on the findings from the previous
sections of this report.
Does the delivery of the project/programme comply with the standards set out in the Public Spending Code? (Appraisal Stage,
Implementation Stage and Post-Implementation Stage)
The appraisal stage was not documented as fully as it could have been and Steering Group meetings were informal. The tender stage ran over
schedule due to pre tender internal design changes and post tender cost negotiations. Nevertheless this process resulted in a project which
ran to budget and with a relatively straightforward construction period.
Is the necessary data and information available such that the project/programme can be subjected to a full evaluation at a later date?
Yes, as the main brief was to improve office space quantity and quality at a set construction and running cost.
What improvements are recommended such that future processes and management are enhanced?
A detailed project brief at the start would have facilitated the process through informing the design and tender phase. In the case of this
project the requirements changed somewhat at the outset to reflect a Directorate restructuring. This resulted in some design changes.
Cork County Council- Public Spending Code Quality Assurance Report 2016
47
Section C: In-Depth Check Summary
The following section presents a summary of the findings of this In-Depth Check on the “Motor Tax” Renovation Project
Summary of In-Depth Check
This project involves the renovation of a disused office building on the County Hall campus for use by the Local Enterprise Office/Community
Department. This renovation finished in mid Q2 2017 at a cost of 1.8million Euro.
The project goals were as follows
Return a building to active use
Bring more staff into the County Hall campus
Reduce payments on rent for off campus office accommodation.
Alternative accommodation off campus would still result in high rent payments and there was inadequate space in the County Hall building
itself for this Department. At the same time this service experiences a high quantity of public visits and this is facilitated by its location.
The initial project analysis confirmed that the best VFM outcome would result through renovation of the existing building as opposed to
demolition and rebuild. It is anticipated that approximately 600,000 Euro has been saved when comparing the former and latter.
CCC is entirely funding the project and has received full planning from Cork City Council. The project is directly managed by the Co.Architect
who reports directly to a Divisional Manager.
The project was tendered for in accordance with procurement guidelines and resulted in a contract in line with expected costs.
Cork County Council- Public Spending Code Quality Assurance Report 2016
48
Project management meetings between contractor and the Co. Architect occur at particular thresholds and in any case not longer than a
2week interval.
A post project review has concluded that it is viable to refurbish older buildings at a competitive cost vis a vis newer buildings whilst still
reaching high quality standards. However a detailed project scope may have reduced the time needed to design and tender for the proposal.
Assessment: This in-depth review considers that this capital project meets PSC criteria.
Cork County Council- Public Spending Code Quality Assurance Report 2016
49
Programme or Project Information
Name Arts Programme Operations
Detail
This project involves the promotion and support of Arts in Cork County including
Grants
Event Support
Bursaries
Art Procurement
Responsible Body Cork County Council
Current Status Underway
Start Date Ongoing
End Date Ongoing
Overall Cost 1.789 million Euro
Cork County Council- Public Spending Code Quality Assurance Report 2016
50
Section B - Step 1: Logic Model Mapping
As part of this In-Depth Check, CCC Performance and Governance Unit have completed a Programme Logic Model (PLM) for the Arts
Programme
Objectives:
Support development of Arts at a local level Support emerging and established creative artists in County Cork Develop new audiences for the Arts Foster and encourage excellence in the Arts Advocate for the local Arts sector on a local, national, and international level Support the Arts through provision of resources, services and communication of funding opportunities.
Inputs: The primary input to the programme is the Sections budget of 1.789 million and it’s assigned staff. The section also operates under
National Arts Plan which informs its strategic goals. This translates into the various grants and support schemes targeted at different aspects of
artistic endeavor in the county.
Activities:
Artists in schools Scheme Artist-in-Residence in the Community Music Education Scheme Music, Drama and Dance Programming
Cork County Council- Public Spending Code Quality Assurance Report 2016
51
Voluntary Arts Training Programme Community Based Arts Development Youth Arts Development. Bursary Schemes. Residency Projects. Commissioning. Film making support Purchase of work.
Outputs: Having carried out the identified activities using the inputs, the programme outputs are for
Artistic events of all types
Individual Arts works
Outcomes:
Greater participation in Arts at all levels
Increased Arts based tourism
Cork County Council- Public Spending Code Quality Assurance Report 2016
52
Section B - Step 2: Summary Timeline of Project/Programme
The Arts Office runs grant and bursary competitions and supports events throughout the year.
Section B - Step 3: Analysis of Key Documents
The following section reviews the key documentation relating to appraisal, analysis and evaluation for the “Arts Programme”
Project/Programme Key Documents
Title Details
Grant Award Summary
Candidates
Award amounts
Aims
Project Completion Summary for individual
projects
Project Outcome
Expense Items
Attendance/Success factor
Key Document 1: Grant Award Summary
This document outlines the grant award outlay for the relevant year. It is intended for Council Members and breaks down awards by Municipal
District. It is quite clear and helps to ensure an appropriate sectoral and geographic funding breakdown.
Key Document 2: Project Completion Summary:
Cork County Council- Public Spending Code Quality Assurance Report 2016
53
This document is prepared by applicants post project completion and is a requirement for funding drawdown. It requires them to detail the
attendance or other quantitative indicators associated with the project. This information is then collated into a database.
Section B - Step 4: Data Audit
The following section details the data audit that was carried out for the “Arts Programme”. It evaluates whether appropriate data is available for
the future evaluation of the project/programme.
Data Required Use Availability
Event Attendance Ensuring maximum VFM Post project review
submissions
Expenditure Cost effectiveness Post project review
submissions
Data Availability and Proposed Next Steps
The above information enables Arts staff to build a VFM picture relative to previous years and also highlight projects which are more likely to
require higher or lower funding amounts.
Cork County Council- Public Spending Code Quality Assurance Report 2016
54
Section B - Step 5: Key Evaluation Questions
The following section looks at the key evaluation questions for the “Arts Programme” based on findings from the previous sections of this report.
Does the delivery of the project/programme comply with the standards set out in the Public Spending Code? (Appraisal Stage,
Implementation Stage and Post-Implementation Stage)
The Programme is multi annual and spread across a wide range of grants and other bursaries. However each funding stream is periodically
reviewed and scoped in relation to new funding streams.
Is the necessary data and information available such that the project/programme can be subjected to a full evaluation at a later date?
Yes, each grant recipient must return data to the Arts Office prior to funding payment. This information is then collated and used to inform
later projects.
What improvements are recommended such that future processes and management are enhanced?
An online application system and database would greatly benefit this process. This is currently under consideration as part of the “Your
Council" Online platform rollout. Process mapping has already taken place to facilitate this.
Cork County Council- Public Spending Code Quality Assurance Report 2016
55
Section C: In-Depth Check Summary
Through its Arts programme CCC aims to achieve the following
Stimulating public interest in the Arts Promoting knowledge, appreciation, and promotion of the Arts Improving standards in the Arts
CCC also procures works and awards grants along the following themes
Bursary Schemes. Residency Projects. Commissioning including “% for Arts” scheme Purchase of work
In terms of Grant assistance CCC awards grants based on pre established artistic and financial requirements approved by Members and in keeping with the 2003 Arts Act. In practice a wide range of artistic works are funded including events, recitals, festivals and items from individuals.
All applications are assessed according to these criteria to ensure that a wide range of projects are promoted from an artistic and geographic viewpoint., The Arts office also aims to ensure that CCC funding does not duplicate alternative funding from other bodies. Post submission closure date the Arts Department issues a report to Members prior to any grant award. In this way CCC aims to reconcile both artistic integrity and effective use of public funding.
Artists and community groups must acknowledge CCC’s role in the promoting the event or works and cannot claim funding until the funded event or other item has been carried out. All grant awardees must then submit a completion report which aims to establish if the proposed goals were achieved including target audience, numbers attending events, key issues encountered and a breakdown of expenditure items. In this way the Arts Office is better able to advise and co-ordinate future applications as well as target future initiatives.
Cork County Council- Public Spending Code Quality Assurance Report 2016
56
Going forward, CCC is examining moving to an online application system which would further improve efficiency and public accessibility.
Assessment: it is considered that this service is carried out in line with PSC guidance.
Cork County Council- Public Spending Code Quality Assurance Report 2016
57
Step 5 – Summary Report Cork County Council considers that it complies with Public Spending Code requirements.
In terms of future progress CCC
Has set up a Procurement Unit
Includes PSC project appraisal as part of its Internal Audit scope in terms of Capital Project Assessment.
Intends setting up a project inventory for all Capital Projects specifically funded by CCC.