Public Service Company (PNM) Blackwater Synchronous ... Blackwater Synchronous Condenser Outage...
Transcript of Public Service Company (PNM) Blackwater Synchronous ... Blackwater Synchronous Condenser Outage...
Public Service Company (PNM) Blackwater Synchronous
Condenser Outage Remedial Action Scheme Overview
Malati Chaudhary (PNM Transmission Planning)
Thomas Duane (PNM Transmission Planning)
Daniel Marquis (PNM System Protection)
February 27th, 2019
Outline
2
• Eastern New Mexico system
• Overview of RAS Scheme, Purpose and
Classification
• Studies assessing RAS performance
• RAS Design, Operational Control and Monitoring,
and Functional Testing
• Operating procedures for RAS unavailability
• NERC CIP Compliance
• Conclusion
4
Overview of Eastern NM System
• 216 mile 345 kV line from BA to Blackwater (BB line) is located in an area of NM with very large wind generation potential.
292 MW, Type 3
90 MW, Type 1 200 MW, Type 3
297 MW, Type 4
Grady Wind 200 MW, Type 4, 2019
Blackwater HVDC, 200 MW
Synchronous Condenser, 170 MVA, 2019
Short circuit MVA requirement at Broadview and at Blackwater
5
• Low short circuit conditions exist at the far eastern end of the line.
• Short circuit ratio of 1.6 MVA/MW is required for Broadview and
Grady windfarms at Broadview.
• Short circuit ratio of 2.1 MVA/MW is needed at Blackwater HVDC.
• A synchronous condenser is being installed to allow total generation
to be increased to 497 MW. Also allows for simultaneous operation
of Blackwater HVDC.
• Synchronous condenser is sized to provide 969 MVA of short circuit
MVA at Blackwater.
Purpose of RAS
6
What happens when Blackwater synchronous condenser is out of service?• Results in immediate reduction of short circuit MVA at Blackwater causing potential
HVDC control instability and inner current control instability of wind turbine
generators.
• Balance can be restored by reducing total power from inverter based equipment to
a level that can be supported by the available short circuit MVA without the
synchronous condenser.
Purpose:
• Mitigate control instability caused by the insufficient short circuit capacity when
synchronous condenser is out.
Purpose of RASContd.
7
Note: Insert graphic diagram showing operating points with and without synchronous condenser.
Classification of RAS
• Local Area Protection Scheme (LAPS) Generation subject to control instability is limited to Broadview and Grady
windfarms (497 MW) that feed radially into the Blackwater 345 kV station.
RAS can interrupt up to 697 MW of transfers between Broadview and Grady
windfarms and the Blackwater HVDC Converter.
HVDC Converter firm commitments are only 15 MW.
Cascading effects beyond eastern New Mexico are not expected.
RAS redundancy is more in line with Wide Area Protection Scheme.
8
Breaker level one-line diagram of Blackwater 345 kV Station and overview of RAS functionality
9
B B B
B
To Taiban 345 kVTo Blackwater HVDC
B
B
B B
Broadview KW SubstationGrady Windfarm
Broadview JN Substation
Broadview Western Interconnect
Broadview 345 kV Station
Blackwater 345 kV Station
These two breakers will be tripped to trip Grady windfarm when
transfer trip signal is sent by RAS for tripping Grady windfarm.
RAS will isolate these two breakers to isolate
Broadview station from Blackwater in case Grady is
not tripped.
RAS will trip these two breakers to trip HVDC
GCB
RAS will sense the status of Generator
Circuit Breaker (GCB) to determine the status of synchronous condenser
Generator Step Up Transformer362/17.5/12.47 kV
PNMWesternInterconnect
33 mile
RAS scheme
10
Total MW flow from Broadview and Grady Windfarm at
Broadview>297 MW
MW Transfer from Blackwater HVDC > 17 MW**
Synchronous Condenser Out of Service
Trip signal sent to Pattern Energy for Tripping Grady Windfarm
Both Grady Breaker Statuses “Open”
30 Cycle
15 Cycle
Trip Broadview Tie at Blackwater
Trip Blackwater HVDC Converter
30 Cycle
15 Cycle
10 Cycle
10 Sec
10 Cycle
10 Sec
Curtailment Active Signal to Power Operations (for
PNM), GridForce (for Pattern)
Blackwater SynCon RAS Simplified LogicPROPOSED
Revision Date: 2019-Feb-04
BOTH RAS Controller Relays Out Of Service
Curtailment Active Signal to GridForce (for Pattern Curtailment Action)RAS Alarm to PNM Power Ops (for PNM Curtailment Action)
NOT GateAND Gate
KEY: Pickup Delay Dropout
Delay
If output is low, input must remain high continuously for a period equal to pickup delay before output goes high.If output is high, input must remain low continuously for a period equal to dropout delay before output goes low.
RAS schemeContd.
11
• Tripping Grady will reduce the power injection from Broadview to 297 MW.
• If the trip confirmation signal is not received within 30 cycles, then the tie to Broadview
switchyard is opened at Blackwater.
Note:
• PSCAD studies are currently underway to provide a better understanding of the inverter based
controls at Blackwater under insufficient short circuit MVA and may indicate that operating
time frames can be relaxed at a future date, however, overall coordination should not change.
Study to assess performance of the RAS
12
• Positive Sequence Power Flow and stability programs do not adequately demonstrate
control system operations under insufficient short circuit MVA conditions. The study is
used primarily to ensure that RAS does not create adverse effects on the
interconnected system.
Scenario Cases
• Scenario 1: 1000 MW of wind generation connected in eastern New Mexico with the
Blackwater HVDC transferring 17 MW to SPP (east)
• Scenario 2: 750 MW of wind generation connected in eastern New Mexico with 497
MW of wind generation coming from Broadview and with the Blackwater HVDC
transferring 200 MW from SPP to WECC (west)
Contingency• Trip of the Blackwater synchronous condenser.
Study to assess performance of the RASContd.
Scenario 1: Power flow response when tripping Grady within 30 cycles
13
Study to assess performance of the RASContd.
Scenario 1: Voltage response when tripping Grady within 30 cycles
14
Study to assess performance of the RASContd.
Scenario 1: Power flow response when isolating Broadview station after 30 cycles instead of tripping Grady
15
Study to assess performance of the RASContd.
Scenario 1: Voltage response when isolating Broadview station after 30 cycles instead of tripping Grady
16
Study to assess performance of the RASContd.
Scenario 2: Power flow response when tripping Grady within 30 cycles
17
Study to assess performance of the RASContd.
Scenario 2: Voltage response when tripping Grady within 30 cycles
18
Study to assess performance of the RASContd.
Scenario 2: Power flow response when isolating Broadview station after 30 cycles instead of tripping Grady
19
Study to assess performance of the RASContd.
Scenario 2: Voltage response when isolating Broadview station after 30 cycles instead of tripping Grady
20
21
Coordination with other RAS and Protection Scheme
• Other Protection System (Most Likely Candidates) Reactor insertion relay system Automatic Reactor Switching Scheme
• No interactions were found between the proposed RAS and other RAS and protection scheme.
Impact to the WECC power gridIf RAS operates as designed:• Could cause slight frequency decline in the western grid, however, declines will be well within
the range of normal generation and transmission disturbances and should not present any
unique problems locally or to the western grid.
If RAS fails to operate as designed:• Could produce oscillations due to inner current control instability of wind turbine generators
and Blackwater HVDC control instability.
• Control instability that could lead to the shut down of Broadview and Grady wind turbines
and Blackwater HVDC.
• The oscillations will be local to the radial transmission system between BA and Blackwater.
22
RAS Design.
Redundancy
• The RAS is designed to ensure failure is a non-credible event by using redundant
system 1 and system 2.
• Failure of any single relay will not interfere with ability of other redundant relay to
detect RAS trigger conditions and to initiate transfer trip and trip signals.
• There is no credible common mode of failure, including CT and VT secondaries.
• RAS will be continuously armed with no means of completely disarming via SCADA.
• If both systems become unavailable, automatic curtailment or alarms are sent via
SCADA.
• If transfer trip to Grady breakers at Broadview fails, the RAS ensures connected
inverter based generation is reduced by opening Broadview-Blackwater tie after a
short time delay.23
Detection
26
• The synchronous condenser RTU monitors the synchronous condenser status and
continuously provides positive confirmation via independent hardwire contacts to
PNM RAS controllers. Loss of positive confirmation signal results in controllers
concluding the condenser is offline.
• At Blackwater, the current and voltages are monitored from CTs and VTs with
independent secondaries, one analogue CT and VT per line to each controller.
• Applicable Breaker and MOD 52B statuses at Broadview are transmitted over direct
fiber using dedicated and redundant SEL-2506 relays.
TelecommunicationContd.
28
• All the communication is located within the Blackwater 345 kV station
except for the communications used to monitor and trip the Grady facility at
the Broadview switchyard.
• Communication paths to Broadview consist of direct fiber, with System 1
and System 2 fibers using separate and independent OPGW conductors.
• System utilizes equipment where critical components are protected and
communication paths are diverse providing at least 99.99% reliability in its
operational network.
• Non-deterministic communication systems are not deployed in the network.
• Communication maintenance technicians are on call 24 hours per day to
respond to network outages.
RAS Logic Controllers and Trip Circuits
29
• The logic controllers are two redundant and independent 411L1 relays,
each receiving separate inputs and sending separate outputs.
• Both System 1 and System 2 controllers directly trip corresponding coils
of all applicable breakers at Blackwater.
• At Broadview, System 1 directly trips trip coil 1 of applicable breakers and
System 2 directly trips trip coil 2 of applicable breakers.
RAS operational control and monitoring
• Relays and communication equipment have self diagnostics which alarm
through SCADA to power operations.
• SEL 2506 relays have channel monitoring and a hard wired relay failure
alarm. Their status is continuously monitored at Power Operations.
• Loss of signal from synchronous condenser results in arming of the RAS.
• RAS actions are monitored in full by the Power Operations EMS system
SCADA.
30
RAS Functional Testing (DRAFT)• Each set of relays can be taken out of service locally or via SCADA for maintenance or repair
without affecting the operation of the redundant relay scheme.
• Taking the controller relay out of service locally or by SCADA is accomplished by changing the
status of its dedicated 43CO relay maintenance switch to the Tagged position.
• Three separate tests will be carried for PNM portion of RAS:
Loss detection of synchronous condenser, and power curtailment for RAS out of service condition
Curtailment for loss of synchronous condenser online signal and if MW outputs are below specified
setpoints
Curtailment for loss of synchronous condenser online signal and if MW outputs are above specified
setpoints
• All the sensing relays, controllers, breaker trip circuits, and applicable communication paths
will be tested over any 5 year period.
31
Procedure during RAS unavailability
32
• If both controllers are out of service, an automatic power reduction in effect signal is sent to
both PNM system operations via SCADA and Pattern Energy via GridForce.
• The maximum wind generation will be curtailed to a level (297 MW) that can be supported
by the available short circuit MVA without synchronous condenser.
• The Blackwater HVDC output is maintained to no more than 17 MW in either direction.
• Repairs and/or replacements will be made as quickly as possible if there is a failure in one
part of the redundant RAS system making it non-redundant.
NERC CIP compliance• The performance of the RAS equipment at Blackwater station is not sensitive to NERC
CIP compliance because it does not use routable protocols for RAS related
communication.
• Engineering access complies with NERC CIP by following PNM’s standard NERC CIP
compliance design and protocols.
33
Conclusion
34
• No system performance issues were identified due to the addition and
operation of Blackwater Synchronous Condenser Outage RAS.
• The RAS design has full redundancy.
• The RAS is continuously armed and monitored for failure.
• No coordination issues were found with other RAS or protection schemes.
• NERC CIP compliance is not expected to have any negative impacts on RAS
functionality.
• RAS commissioning and functional testing will be preformed to ensure end-
to-end functionality.
Approval Request
35
• PNM is requesting approval of the proposed Blackwater Synchronous Condenser Outage Remedial Action Scheme.