Public Participation in Town Development

22
SARVAJANIK EDUCATION SOCIETY SARVAJANIK COLLEGE OF ENGINEERING & TECHNOLOGY SURAT affiliated with GUJARAT TECHNOLOGICAL UNIVERSITY AHMEDABAD P. G. CENTER IN CIVIL ENGINEERING DEPARTMENT Report entitled Public Participation in Town DevelopmentIn the partial fulfilment of the requirement for the award of degree of MASTER OF ENGINEERING (CIVIL) TOWN AND COUNTRY PLANNING – I SEMESTER – II Submitted under URBAN PLANNING TECHNIQUES & PRACTICE (2724801) By: Under the guidance of Prof. Himanshu J. Padhya Associate Professor in CED Prof. Sejal Bhagat Prof. Palak Shah Assistant Professor in CED (MARCH, 2015) Pathik Chaudhari (Enrolment No.140420748011) M. E. CIVIL (TCP) – I Semester – II

description

Graduate report for subject :URBAN PLANNING TECHNIQUES & PRACTICECourse : Town & Country Planning(Post Graduation)

Transcript of Public Participation in Town Development

  • SARVAJANIK EDUCATION SOCIETY

    SARVAJANIK COLLEGE OF ENGINEERING & TECHNOLOGY

    SURAT affiliated with

    GUJARAT TECHNOLOGICAL UNIVERSITY

    AHMEDABAD

    P. G. CENTER IN

    CIVIL ENGINEERING DEPARTMENT

    Report entitled

    Public Participation in Town Development

    In the partial fulfilment of the requirement for the award of degree of

    MASTER OF ENGINEERING (CIVIL) TOWN AND COUNTRY PLANNING I

    SEMESTER II

    Submitted under

    URBAN PLANNING TECHNIQUES & PRACTICE (2724801)

    By:

    Under the guidance of

    Prof. Himanshu J. Padhya

    Associate Professor in CED

    Prof. Sejal Bhagat

    Prof. Palak Shah

    Assistant Professor in CED

    (MARCH, 2015)

    Pathik Chaudhari (Enrolment No.140420748011)

    M. E. CIVIL (TCP) I Semester II

  • Department of Civil Engineering

    SARVAJANIK COLLEGE OF ENGINEERING AND TECHNOLOGY,

    SURAT

    (2014-15)

    Declaration

    I hereby declare that the work being presented in this Graduate Report entitled Public

    Participation in Town Development by Pathik Chaudhari M., of Semester II, ME Civil (Town & Country

    Planning) - I bearing Enrolment No: 140420748011 submitted to the Civil Engineering Department at

    Sarvajanik College of Engineering and Technology, Surat; is an authentic record of my own work carried

    out during the period of odd semester 2014-2015 under the supervision of Prof. Himanshu J. Padhya and

    Prof. Sejal Bhagat.

    Neither the source there in, nor the content of the seminar report have been copied or

    downloaded from any other source directly. I understand that my result grades would be revoked if later

    it is found to be so.

    ______________________

    Pathik M. Chaudhari

    (140420748011)

  • Department of Civil Engineering

    SARVAJANIK COLLEGE OF ENGINEERING AND TECHNOLOGY,

    SURAT

    (2014-15)

    Certificate

    This is to certify that Graduate Report entitled Public Participation in Town Development is presented

    and report is submitted by Pathik M. Chuadhri of Second Semester for partial fulfilment of requirement

    for the degree of MASTER OF ENGINEERING IN (CIVIL) TOWN & COUNTRY PLANNING of Sarvajanik College

    of Engineering and Technology, Surat during the academic year 2014-2015.

    Prof. Sejal Bhagat Prof. Himanshu J. Padhya

    Assistant Professor Associate Professor & Head

    Civil Engineering Department Civil Engineering Department

    External Examiner

    Date: ______________

    Place: ______________

  • Public Participation In Town Development Pathik Chaudhari (140420748011)

    Graduate Report in UPTP M.E. Sem-II (TCP)-2015 SCET

    1 | P a g e

    INDEX

    1. INTRODUCTION -------------------------------------------------------------------------------------------------------- 3

    1.1 MAJOR CONSIDERATIONS ------------------------------------------------------------------------------------------------- 4

    2. POINT OF ENTRY FOR PUBLIC INPUT ----------------------------------------------------------------------------- 5

    2.1 THE PLANNING PROCESS: IDEALIZED CONCEPT ------------------------------------------------------------------------- 5

    2.2 POINTS OF ENTRY FOR INITIAL PARTICIPATION -------------------------------------------------------------------------- 5

    3. IMPORTANCE OF PUBLIC PARTICIPATION ---------------------------------------------------------------------- 7

    4.1 A BETTER DECISION ------------------------------------------------------------------------------------------------------- 7

    4.2 STRONGER DEMOCRACY -------------------------------------------------------------------------------------------------- 8

    4. PREPARING FOR PUBLIC PARTICIPATION ----------------------------------------------------------------------- 9

    4.1 CREATING A PARTICIPATION STRATEGY ---------------------------------------------------------------------------------- 9

    5. RECOMMENDATIONS ----------------------------------------------------------------------------------------------- 10

    5.1 ESTABLISHING PURPOSES FOR PUBLIC PARTICIPATION EFFORTS ----------------------------------------------------- 10

    5.2 IDENTIFYING THE PUBLICS PERSPECTIVE ------------------------------------------------------------------------------- 11

    5.3 TIMING AND APPROACHES TO PUBLIC PARTICIPATION ---------------------------------------------------------------- 11

    5.4 IDENTIFYING CITIZEN PREFERENCES AND SATISFACTION LEVELS. ------------------------------------------------------ 11

    5.5 DECIDING HOW TO INCORPORATE INFORMATION INTO DECISION-MAKING ----------------------------------------- 12

    5.6 PROVIDING FEEDBACK TO THE PUBLIC ON HOW THEIR INPUT HAS BEEN USED --------------------------------------- 12

    6. CASE STUDY: SURAT CITY SOLID WASTE COLLECTION SYSTEM ------------------------------------------ 13

    6.1 OBJECTIVES FOR AN INNOVATIVE & MODERN SOLID WASTE MANAGEMENT: -------------------------------------- 13

    6.2 THE NEW AND MODERN APPROACH TO THE SOLID WASTE MANAGEMENT ----------------------------------------- 13

    6.3 PRESENT STATUS: --------------------------------------------------------------------------------------------------------- 14

  • Public Participation In Town Development Pathik Chaudhari (140420748011)

    Graduate Report in UPTP M.E. Sem-II (TCP)-2015 SCET

    2 | P a g e

    6.4 PRIMARY COLLECTION THROUGH DOOR-TO-DOOR GARBAGE COLLECTION ----------------------------------------- 15

    6.5 BENEFITS FROM THE PROJECT-------------------------------------------------------------------------------------------- 16

    7. CONCLUSION ---------------------------------------------------------------------------------------------------------- 17

    POTENTIAL BENEFITS OF PUBLIC PARTNERSHIPS: --------------------------------------------------------------------------- 17

    POTENTIAL RISKS OF PUBLIC PRIVATE PARTNERSHIPS: --------------------------------------------------------------------- 18

    REFERENCES ----------------------------------------------------------------------------------------------------------------- 19

    Table 1 Present status of Surat SWM system source : SMC website(2015) ........................... 15

  • Public Participation In Town Development Pathik Chaudhari (140420748011)

    Graduate Report in UPTP M.E. Sem-II (TCP)-2015 SCET

    3 | P a g e

    1. Introduction

    Building on access roads, waterways and unauthorized places had remained one of the

    major problems confronting city and town managers over the years.

    The situation is more disturbing in major cities where private land developers have

    consistently ignored laid down drawings and plans and continue to build haphazardly, resulting

    in near slums in urban residential areas.

    It has also been said that lack of capacity on the part of the Town and Country Planning

    Department to enforce laws and regulations on area and site planning schemes, as well as the

    inability of city authorities to control physical developments in their areas have compounded

    the problem. Traditional authorities and landowners have also been blamed for intentionally

    allocating waterways and reserved areas to private developers for their own selfish interest.

    However, one could equally put the blame on the current town and country planning

    regulations and systems in the country, which is centrally controlled and does not give

    opportunity to the stakeholders in the communities to participate in the development of

    planning schemes in their areas.

    Traditional rulers, landlords, developers and other opinion leaders, who have vital

    information, which are needed for proper planning, are denied the opportunity to make

    meaningful contributions before area and site planning schemes are prepared for the

    community. As a result, most of the stakeholders, especially chiefs and landowners see these

    plans as "foreign" and thereby disregard them and go ahead to either design their own plans or

    begin to demarcate lands anyhow.

    Others who even decide to use the planning schemes designed by the town and country

    planning to allocate plots to developers, often do not understand the interpretations in the plans

    and the reasons why certain areas should not be allocated.

    Thus, the current planning approach has alienated the very people, who owned the land

    and, therefore, denied them the proper management and control of the land, resulting in the

    confused state cities and towns find themselves.

    The Department has started engaging in discussions with relevant bodies to change

    some of its laws and regulations to enable it to involve all stakeholders in land to participate in

    planning schemes in all communities in the country.

    Under the new system, chiefs, landowners, developers, identifiable groups and all other

    opinion leaders would be engaged in all town planning processes and a committee comprising

  • Public Participation In Town Development Pathik Chaudhari (140420748011)

    Graduate Report in UPTP M.E. Sem-II (TCP)-2015 SCET

    4 | P a g e

    the stakeholders and other technical experts constituted to ensure the implementation of

    approved schemes.

    This will enable the people to own the schemes and protect them in order to prevent

    others from encroaching on unauthorized areas. Although the idea had eluded the town and

    city planners for quite some time, it is considered as a welcoming change.

    1.1 Major Considerations

    Specific planning approaches designed to balance the trade-off between technical

    demands and public involvement can only be developed on a case-by-case basis. There are two

    broad corners, however, which arise from previous experience and which address this basic

    trade-off, which must be considered in the attempt to form any general approach to

    participatory planning.

    First, public participation should not be viewed as an adjunct to planning, but rather as an

    inherent and continuous element of the planning process.

    Second, to assure that public input will have an impact upon decision-making, it must produce

    results in a form that can be utilized by planners as an integral part of ongoing data analysis.

    Taken together, the two major considerations concern in eliciting effective public

    participation; that is, to identify appropriate mechanisms of participation, and to effectively

    link these mechanisms to the planning process.

  • Public Participation In Town Development Pathik Chaudhari (140420748011)

    Graduate Report in UPTP M.E. Sem-II (TCP)-2015 SCET

    5 | P a g e

    2. Point Of Entry For Public Input

    2.1 The Planning Process: Idealized Concept

    Figure shows the regional economic development planning process as an idealized

    concept. It is considered as idealized because the steps in the process are represented in a

    strictly sequential order.

    Figure 1 Steps in Planning Process Cycle

    The model shown contains eight specific steps within the planning process cycle. A

    review of these steps will reveal a basic sequential logic to the process. Models based upon the

    same essential logic but containing a greater or lesser number of specific steps might be equally

    valid, as might be variations on the names of each of the steps. Critical to a rational planning

    process, however, is the basic pattern of a continuous iterative framework. The planning cycle

    shown is two to three years in duration; the process is continuous, so that as one cycle reaches

    its end, the succeeding cycle has been initiated.

    2.2 Points of Entry for Initial Participation

    The selection of points of entry is guided by the rational, iterative nature of the

    planning process. The adjustment and refinement that takes place among the steps diminishes

    the importance of the sequential nature of the process. This suggests that public input can be

  • Public Participation In Town Development Pathik Chaudhari (140420748011)

    Graduate Report in UPTP M.E. Sem-II (TCP)-2015 SCET

    6 | P a g e

    effective and useful even if not a direct component of the decision-making associated with each

    step.

    The nature of the first step away from conventional, centralized planning and the lack

    of necessity for public involvement at every planning ster suggest that there two points

    appropriate for the initial entry of public participation in the regional planning process:

    formulation of goals (step one) and comparative assessment of options (step five).

    In the initial stages of goal formulation, when the planner collects data to enhance his

    perception of the regions development problems and to conceptualize potential solutions,

    public input can provide valuable information not included in the physical and economic data

    normally utilized by the planner. At this stage, the planner should have a definite understanding

    of the general concerns of the public so that the formulation of goals, and each subsequent step,

    benefits from valid interpretation of the regions development needs. It is important that data

    from participatory efforts be collected early enough in the planning cycle to provide planners

    with an accurate orientation to the regions needs which can be utilized in setting appropriate

    directions for planning activities.

    The second appropriate point to introduce public participation is strep five, the

    comparative assessment of project options. By this stage, enough of the basic technical

    planning work has been performed by the staff of the planning authority for specific project

    options to be submitted to the public. The range of choices presented for public response in any

    community or within any sector will be relatively narrow and well-defined. Clearly defined

    choices are essential to obtaining useful direct public input, especially in the initial phases of

    popular participation in the planning process. Since the nature of the public input will be

    focused upon specific project options, it can be easily integrated into the planning process by

    a planning staff lacking extensive experience with public participation.

  • Public Participation In Town Development Pathik Chaudhari (140420748011)

    Graduate Report in UPTP M.E. Sem-II (TCP)-2015 SCET

    7 | P a g e

    3. Importance of public participation

    Public participation in making decisions is vital. It brings benefits in making an

    individual decision and also for democracy more generally. It uses the knowledge, skills and

    enthusiasm of the public to help make the decision and recognizes that the public have a

    significant role to play.

    It is also a moral duty. Public authorities work for the public. To do so in a way that the

    public want and to ensure that they know what the public needs, they must involve the public

    when they make decisions. Each person has a stake in protecting and enhancing the

    environment and citizens know the needs of their communities through work, play and travel.

    That is why public involvement is a central part of sustainable development policies. Solutions

    to achieve economic, social and environmental improvements at the same time will only be

    found if everyone is involved and if the discussion is open so that new ideas and approaches

    can be considered.

    4.1 A Better Decision

    Public participation can lead to better decisions. That is, decisions that better meet the

    needs of more people, decisions that last longer and decisions that have more validity. Better

    decisions will lead to improvements in everyones quality of life. By considering the issue as

    widely as possible, improvements in social conditions, the economy and the environment can

    occur at the same time.

    There is no secret to this. Involving more people in the process uses a wider range of

    experiences. It brings in more points of view and uses knowledge about local conditions that

    might not be widely known. If the decision takes account of this wider range of experience and

    views, it is more likely to be right since more issues have been considered and more risks

    evaluated.

    Public participation does not guarantee that everyone will be happy with a decision

    since different groups of people will have different priorities and concerns. But involving the

    public at an early stage in the decision-making process, and finding ways for their views to be

    heard and taken into account, helps to build consensus. It means that concerns can often be met

    early in a planning process, when changes may be easier to make, rather than late in the process

    when even small changes may cost both time and money.

    In addition, by being involved in the process, the public is exposed to the whole range

    of factors which may influence a decision. Even if people do not agree with the final decision,

    they are more likely to understand why it was made.

  • Public Participation In Town Development Pathik Chaudhari (140420748011)

    Graduate Report in UPTP M.E. Sem-II (TCP)-2015 SCET

    8 | P a g e

    4.2 Stronger Democracy

    In the longer term, public participation can improve democracy. Again, this is no secret.

    Regular public participation shows people that they are valued and that their views are

    important. These exercises build trust and confidence in the authority undertaking the exercise

    and demonstrate to the public that change is possible. Individuals and community groups can

    become more active and more responsible for their environment and quality of life. People can

    feel more part of a community and authorities can make better relationships with these

    communities which continue after the decision has been taken. Participation exercises can build

    confidence to undertake other initiatives, help give the public the skills to do so and generate

    enough enthusiasm to complete the initiative.

  • Public Participation In Town Development Pathik Chaudhari (140420748011)

    Graduate Report in UPTP M.E. Sem-II (TCP)-2015 SCET

    9 | P a g e

    4. Preparing for public participation

    In general, public participation should be undertaken when people are affected by the

    decision. They should be involved even when it is uncertain what they will say or when they

    may oppose the proposal.

    4.1 Creating a participation strategy

    The most obvious starting point for preparing a strategy for a participation exercise are

    the existing legal requirements. In many countries, the law sets a framework for public

    participation exercises. Good practice goes beyond these minimum requirements and even

    where there is no legal framework in place, it is still possible to organise effective public

    participation exercises. The participation exercise must be open and honest to encourage trust

    and show that the decision is fair. Giving the impression that the decision has already been

    made is very damaging to the process. The public will not participate if they think that the

    decision has already been made.

    It can be difficult to build sufficient trust for the public to want to participate, especially

    in places where public participation is relatively new. The strategy might need to include a trust

    building phase with the public, NGOs and businesses or be part of a longer strategy for building

    a relationship between the authority and the public.

    The strategy must be honest about the level of public participation. An exercise which

    promises action on decisions that cannot be changed will undermine the publics trust. They

    are much less likely to participate in future exercises if this happens. In making the strategy,

    recognize that local circumstances can be different. A plan which worked well for one area

    might not work well somewhere else. If in doubt, find out what is required for the area

    concerned.

    Although making a strategy is vital, it should not be followed at all costs. Review

    progress against the plan regularly and consider whether changes need to be made to achieve

    the objective.To provide a clear focus for the process, someone should be appointed to act as

    the manager with overall responsibility. His or her role will be to make sure that:

    the process is properly prepared;

    the process is reviewed regularly to monitor progress;

    Preparing for public participation

    the process follows the timetable;

    the results are achieved; and

    Feedback is given so that lessons can be learnt.

  • 10 | P a g e

    5. Recommendations

    The Government should include the following considerations in designing their efforts:

    Purposes for involving the public;

    Assurances that they are getting the publics perspective rather than only that of a small number

    of highly vocal special interest groups;

    Approaches to eliciting public participation and the points in the planning-budgeting-performance

    management cycle those approaches are likely to be most effective;

    Information that the process will be incorporated into decision making;

    Communication to the public regarding how the information collected will be and was used; and

    Buy-in from top government officials.

    5.1 Establishing Purposes for Public Participation Efforts

    Articulating the purpose for conducting a public participation process is critical because

    the purpose becomes the foundation for deciding who to involve, how to select them, what

    activities they will be involved in, what information will be collected, and how the government

    will use the information. Consequently, determining the purpose should be the first step in

    designing a participation effort. Governments should not initiate public participation processes

    without establishing a tangible purpose or objectives, nor is it sufficient to create a public

    participation process simply because it is a best practice or because other governments have done

    so.

    Purposes may include one or more of the following, and, in addition, individual

    governments may identify other purposes for involving the public:

    To improve performance by better understanding what the public wants and expects from its

    government;

    To adjust services and service levels more closely to citizens preferences;

    To establish performance measures that incorporate the publics perspective;

    To differentiate among the expectations of a jurisdictions various demographic groups in policy

    and service design;

    To understand public priorities in planning, budgeting, and managing services. (Public priorities

    are particularly important in making budget decisions when revenues are not sufficient to continue

    to provide all services at their current levels);

  • Public Participation In Town Development Pathik Chaudhari (140420748011)

    Graduate Report in UPTP M.E. Sem-II (TCP)-2015 SCET

    11 | P a g e

    To establish long term strategies to provide for a fiscally sustainable future for the jurisdiction;

    To ensure that capital investment decisions, such as the location of infrastructure elements, are

    informed by public input;

    To provide information to the public about a governments services and results.

    5.2 Identifying the Publics Perspective

    Citizens are diverse. Not only do citizen viewpoints differ from those of government insiders, but

    from citizen to citizen. No single citizen or group of citizens is able to represent the views of all

    citizens. The best way to assure a broad perspective is to collect information in a variety of ways and

    from a variety of sources.

    5.3 Timing and Approaches to Public Participation

    Timing and approaches are related because approaches that work in one phase of planning, budgeting,

    and performance management may not be effective in other phases. For example, a community goal

    setting session would be very appropriate in assisting a government to establish priorities in

    developing a strategic plan or in the early stages of the budget process.

    General approaches and timing are listed below:

    5.4 Identifying citizen preferences and satisfaction levels.

    Such efforts should occur before a decision has been made, or to test various ideas and approaches.

    Governments may solicit information for general purposes, such as strategic planning, or may solicit

    targeted information as input for specific projects, plans, or initiatives. Unless there is a compelling

    reason to target only certain segments, public involvement approaches should encourage all citizens

    to participate. In addition, governments should make involvement opportunities accessible to all

    citizens and hold meetings at various times to provide maximum participation. Local governments

    have used numerous mechanisms for eliciting public input. Common methods for soliciting

    information include the following:

    o Surveys, either in person or via mail, phone, or Internet.

    o Focus groups

    o Interviews

    o Comment (or point of service) cards

    o Public meetings, such as public hearings, Town Hall meetings, and community vision sessions

  • Public Participation In Town Development Pathik Chaudhari (140420748011)

    Graduate Report in UPTP M.E. Sem-II (TCP)-2015 SCET

    12 | P a g e

    5.5 Deciding how to incorporate information into decision-making

    Information derived from public involvement processes provides a critical perspective for making

    decisions in planning, budgeting, and management. However, such information should be

    considered along with expert knowledge and judgment (such as the engineering expertise

    necessary to build a bridge) and objective data (such as economic and demographic information,

    both of which are also critical to good decision making).

    5.6 Providing feedback to the public on how their input has been used

    Governments should systematically collect, maintain, monitor, and analyze information gained

    from public involvement activities, maintain contact information on individuals and groups that

    wish to be kept informed, and use multiple communication mechanisms to ensure that those

    involved or interested in the process are notified of opportunities for additional feedback and of

    decisions made based on the public involvement process. Most importantly, governments should

    explain how public involvement has made a difference in plans, budgets, and performance, and

    gather public feedback on how successful the process has been through the publics eyes.

  • Public Participation In Town Development Pathik Chaudhari (140420748011)

    Graduate Report in UPTP M.E. Sem-II (TCP)-2015 SCET

    13 | P a g e

    6. Case Study: Surat City Solid Waste Collection System

    6.1 Objectives for an innovative & modern Solid Waste Management:

    To devise a system of storage of waste and segregation of recyclable waste at source. To improve system of primary collection of waste. To devise more efficient system of day to day cleaning, conventionally and mechanically. To devise system to eliminate practices of throwing garbage on the road causing nuisance

    & health threat.

    To modernize the system of community waste storage & synchronize the system of primary collection as well as transportation of waste.

    To eliminate manual handling of waste and open transportation vehicles. To improve the system of transportation of waste by ensuring "handling waste only once". To construct four more semi close body transfer station to strengthen the existing primary

    collection-transportation and secondary transportation system.

    To reduce quantity of waste going to landfill site by adopting suitable technology. Land to be acquired for other landfill disposal site. To derive income from the processing of waste. To ensure safe disposal of waste including bio-medical wastes. To do institutional strengthening. To have public participation.

    6.2 The new and modern approach to the Solid Waste Management

    Integration of SWM with other activities viz. sewerage, water supply, health care,

    engineering departments, etc.

    Emphasis was laid on Complaint redressed system, Grievance redressed system, Litter

    prevention system,

    Slum Up gradation & Rehabilitation, Field work, Daily meeting in this regard, etc.

    Financial commitment: Equipment, Vehicles, communication.

    Involving citizens: Positive involvement, penalizing truants, creating public awareness.

  • Public Participation In Town Development Pathik Chaudhari (140420748011)

    Graduate Report in UPTP M.E. Sem-II (TCP)-2015 SCET

    14 | P a g e

    6.3 Present Status:

    Quantity of M.S.W. generation: 1575.000 M.T. (350 gpcd)

    Collection and transportation: 1499.440 M.T. per day (Average of 01/04/13 to 31/03/14)

    System of collection and transportation:

    a) Primary collection & its transportation:-

    - Sweeping during day time.

    - Container lifting.

    - Door to Door collection system.

    - Night scraping & brushing activity.

    - Hotel-Kitchen waste management

    - Society ANUDAN

    b) Secondary transportation:-

    Municipal Solid Waste collected through primary collection system reaches to the

    Semi closed body transfer station of the respective zone from where it is being sent to the

    Khajod Disposal transported through close body container in a mechanically compacted

    way.

    Name of Transfer station Zone

    Bhatar South west

    Katargam North & Central (Part)

    Varachha East

    Anjana South-East

    Pal West

    Bhestan South

  • Public Participation In Town Development Pathik Chaudhari (140420748011)

    Graduate Report in UPTP M.E. Sem-II (TCP)-2015 SCET

    15 | P a g e

    c) Disposal of M.S.W.:-

    M.S.W. transported from the transfer stations reaches to the final disposal site at

    Khajod whereat M.S.W. is dumped and levelled by the heavy machineries. Daily cover of

    soil is also laid on the levelled M.S.W. Out of total collection of garbage average 400 TPD

    garbage is sent to processing plant which is established on BOOT basis contract through

    PPP mode. This plant is in operation from September 2008. At present the plant is not in

    operation due to snapshot of financial condition of the PPP agency.

    Table 1Present status of Surat SWM system source : SMC website(2015)

    6.4 Primary Collection through Door-to-Door Garbage Collection

    The door-to-door garbage collection was planned for the timely removal of waste at the

    source. Door-to-door collection of waste was introduced in four out of the seven zones of SMC

    with the help of private sector participation, however owing to the excellent performance of the

    private agencies; it was introduced in all the 7 zones of SMC. The practice of night scrapping and

    brushing of roads was done by SMC staff. Listed are the main features of the door-to-door services

    in SMC:

    Adopted PPP model - Service Contract the entire system of door-to-door garbage collection has been leveraged through 7 different private agencies.

    Period of concession/engagement 7 years based on the useful life of vehicle. Private Parties: There are seven different private agencies involved in door-to-

    door collection.

    Arrangement between parties in the PPP arrangement: The agencies are paid

    Tipping fee against door-to-door collection services. The private operator is

    responsible for the capital as well as the entire O&M expenses for the system during

    the concession period. Vehicles employed for garbage collection are monitored

    through Time-Place Movement Chart, under which vehicles have to move in

    accordance with the time schedule, area of coverage, and number of units allotted

    to each vehicle. Vehicles under door-to-door collection system are also monitored

    by the Vehicle Tracking System. Complaints of non-coverage of wards/spots are

    monitored at the ward level.

    Responsibility of the Private Agencies/Operators: The agencies employ and

    maintain their own garbage collection vehicles as per the requirement laid down by

    SMC. Garbage collected is unloaded at one of the six TS located within the

    Municipal area of SMC. The private operator bears the entire O&M cost of primary

    collection and collects almost 700 TPD of mixed waste from door-to-door

    collection from the different wards of Surat.

    Responsibility of the Municipal Body: The municipal body facilitated the private

    agencies with transfer stations for easy tipping of garbage. This has helped improve

    the trip time of the collection vehicles.

    Funds Infused by Private Party: The private agency brought in closed body vehicles for door-to-door garbage collection. Around Rs. 15 Cr. was spent by the agency for the purchase of 300 of closed type vehicles to carry out collection

    activity.

  • Public Participation In Town Development Pathik Chaudhari (140420748011)

    Graduate Report in UPTP M.E. Sem-II (TCP)-2015 SCET

    16 | P a g e

    Project Progress: Door-to-door collection of waste for all the zones was awarded

    to 7 agencies based on competitive bidding. The bidding process was done through

    eprocurement system where the agencies were selected based on their financial

    quotes. Agencies who quoted least were selected and entrusted the work.

    Tipping Fee: The agencies are paid tipping fee at a rate ranging between Rs. 570

    per metric ton to Rs. 1188 per metric ton of waste collected. The rates will be

    escalated after every 1 year during the procurement period.

    6.5 Benefits from the Project

    The coverage of SWM services increased to 97% in Surat, while door-to-door collection

    services increased to 92%. The practice of waste segregation has also been introduced with

    almost 17% of MSW generated being segregated presently. Waste segregation was not

    practiced before the implementation of the project,

    Overall improvement in the environment, as waste is now collected from the door step

    avoiding waste to be dispersed in the open. People have developed the habit of storing

    waste in domestic bins;

    Timely collection of waste from every house/shop on a daily basis;

    Reduction in the number of stray animals around containers spots;

    Reduction of odor and waste spillage nuisance as it is collected in closed containers/pickup

    vans involving less handling;

    Reduction in number of containers and container spots have resulted in curtailment of cost

    which were otherwise required for lifting of the containers;

    Cost curtailment on repairing and maintenance of containers and hydraulic dumper placers

    by SMC;

    Spare sweepers/workers are now engaged in carrying out sanitation work of new

    developing areas in the most effective manner;

    The old collection system of waste through open tractors has been curtailed;

    Due to the IEC activities being undertaken, it has helped in improving awareness amongst

    citizens. This has also helped in improving the cleanliness around the community

    containers;

    Revenue generation from collection of user-charge. SMC has been able to achieve 88%

    efficiency in the collection of user-charges from its citizens.

  • Public Participation In Town Development Pathik Chaudhari (140420748011)

    Graduate Report in UPTP M.E. Sem-II (TCP)-2015 SCET

    17 | P a g e

    7. Conclusion

    Potential Benefits of Public Partnerships:

    Exploring PPs as a way of introducing private sector technology and innovation in

    providing better public services through improved operational efficiency

    incentivizing the private sector to deliver projects on time and within budget

    Imposing budgetary certainty by setting present and the future costs of infrastructure

    projects over time

    Utilizing PPs as a way of developing local private sector capabilities through joint ventures

    with large international firms, as well as sub-contracting opportunities for local firms in

    areas such as civil works, electrical works, facilities management, security services,

    cleaning services, maintenance services

    Using PPs as a way of gradually exposing state owned enterprises and government to

    increasing levels of private sector participation (especially foreign) and structuring PPPs

    in a way so as to ensure transfer of skills leading to national champions that can run their

    own operations professionally and eventually export their competencies by bidding for

    projects/ joint ventures

    Creating diversification in the economy by making the country more competitive in terms

    of its facilitating infrastructure base as well as giving a boost to its business and industry

    associated with infrastructure development (such as construction, equipment, support

    services)

    supplementing limited public sector capacities to meet the growing demand for

    infrastructure development

    Extracting long-term value-for-money through appropriate risk transfer to the private

    sector over the life of the project from design/ construction to operations/ maintenance.

  • Public Participation In Town Development Pathik Chaudhari (140420748011)

    Graduate Report in UPTP M.E. Sem-II (TCP)-2015 SCET

    18 | P a g e

    Potential Risks of Public Private Partnerships:

    Development, bidding and ongoing costs in PPP projects are likely to be greater than for traditional government procurement processes - the government should therefore determine

    whether the greater costs involved are justified. A number of the PPP and implementation units

    around the world have developed methods for analysing these costs and looking at Value for

    Money.

    There is a cost attached to debt While private sector can make it easier to get finance, finance will only be available where the operating cash flows of the project company are expected

    to provide a return on investment (i.e., the cost has to be borne either by the customers or the

    government through subsidies, etc.)

    Some projects may be easier to finance than others (if there is proven technology involved and/ or the extent of the private sectors obligations and liability is clearly identifiable), some

    projects will generate revenue in local currency only (eg water projects) while others (eg ports and

    airports) will provide currency in dollar or other international currency and so constraints of local

    finance markets may have less impact.

    Some projects may be more politically or socially challenging to introduce and implement than others - particularly if there is an existing public sector workforce that fears being transferred

    to the private sector, if significant tariff increases are required to make the project viable, if there

    are significant land or resettlement issues, etc.

    There is no unlimited risk bearing private firms (and their lenders) will be cautious about accepting major risks beyond their control, such as exchange rate risks/risk of existing assets.

    If they bear these risks then their price for the service will reflect this. Private firms will also want

    to know that the rules of the game are to be respected by government as regards undertakings to

    increase tariffs/fair regulation, etc. Private sector will also expect a significant level of control over

    operations if it is to accept significant risks

    Private sector will do what it is paid to do and no more than that therefore incentives and performance requirements need to be clearly set out in the contract. Focus should be on

    performance requirements that are out-put based and relatively easy to monitor

    Government responsibility continues citizens will continue to hold government accountable for quality of utility services. Government will also need to retain sufficient expertise,

    whether the implementing agency and/ or via a regulatory body, to be able to understand the PPP

    arrangements, to carry out its own obligations under the PPP agreement and to monitor

    performance of the private sector and enforce its obligations

  • Public Participation In Town Development Pathik Chaudhari (140420748011)

    Graduate Report in UPTP M.E. Sem-II (TCP)-2015 SCET

    19 | P a g e

    References

    www.suratmunicipal.gov.in : SMC website

    Surat Solid Waste Management Project under JNNURM: City Report -Ministry of Urban Development

    Government of India

    www.worldbank.org/pppirc : public-private partnerships (PPPs) in infrastructure